BL7 Energy and Water Monthly Report template.docx

DOCX document 108 KB Posted

Attached to
Amendment 0003 Full Maintenance Services Contract San Antonio, Pearsall, and New Federal Courthouse
Solicitation number
47PH0221R0004
Issued by

View the file

Other files

File Type Posted
SF30 Solicitation Amendment 47PH0221R0004 0003 2021 04 16.pdf PDF
San Antonio_Pearsall FM Spec 2021 04 15.pdf PDF
Changes to Solicitation 47PH0221R0004 Amendment 0002.pdf PDF
EXHIBIT C.1 Building Information Sheet_TX0501 San Antonio Federal Building_revised.pdf PDF
SF30 Solicitation Amendment 47PH0221R0004 0002 2021 04 15.pdf PDF
EXHIBIT C.1 Building Information Sheet_TX0503 AA Spears Judge Training Center_revised.pdf PDF
8 SA PROCUREMENT QUESTIONS ANSWERS.pdf PDF
9. Solicitation 47PH0221R0004 Pre-Proposal Conference Slides San Antonio & Pearsall.pptx.pdf PDF
3. RIVISED Figure B-3 Pricing of Services 47PH0221R0004.xlsx XLSX spreadsheet
5. SAN ANTONIO SITE VISIT SIGN IN SHEET 1.jpg JPG image
2. US Courthouse Commissioning Inspection Schedule.pdf PDF
4. SECOND SA SITE VISIT PHOTOS Zip File.zip ZIP file
7. Experience Worksheet - 47PH0221R0004 San Antonio Pearsall (1).pdf PDF
5. Second SAN ANTONIO SITE VISIT SIGN IN SHEET 2.jpg JPG image
10. SF30 Solicitation Amendment 47PH0221R0004 0001.pdf PDF
6. Changes to Solicitation 47PH0221R0004.pdf PDF
1. UPDATED Figure L-1 Combined Management Plan.xlsx XLSX spreadsheet
OM Photos 4-2-21-20210412T211125Z-001.zip ZIP file
Exhibit C3 Recycle Solid Water Trash Report.pdf PDF
ATTACHMENT 2 SF98 Request Wage Determination Bexar and Frio Counties New San Antonio Buy.pdf PDF
Exhibit BL3 - TX0501HS FED BLDG INFO SHEET.pdf PDF
Exhibit BL3 - TX398ZZ NEW USCH INFO SHEET (Data not Complete at this time).pdf PDF
Exhibit BL3 - TX0231ZZ PEARSALL BLDG INFO SHEET.pdf PDF
Figure L 1 Combined Management Plan.xlsx XLSX spreadsheet
Exhibit C4 - GSA Form 3638 Pest Control Work and Inspection Report.pdf PDF
BL6 WORK ORDERS SA PEAR Jan 1 2018 thru Nov 1 2020 No PMs.pdf PDF
Exhibit M10- PV Service Schedule V5.pdf PDF
BL2 TX0164ZZ GARCIA INVENTORY.pdf PDF
BL2 TX0503HS SPEARS INVENTORY.pdf PDF
Exhibit M5 - Smart Buildings.pdf PDF
Exhibit M3 - Environmental Sustainable Products.pdf PDF
ATTACHMENT 1 Mechanical CBA PMI IOEU July 2020.pdf PDF
Figure B 3 Pricing of Services.xlsx .xlsx XLSX spreadsheet
EXHIBIT C.1 BLDG INFO SHEET - Hipolito Garcia Federal Courthouse - TX0164ZZ.pdf PDF
Exhibit M9 - 2018 GSA PM Guide FINAL.pdf PDF
Exhibit BL3 - TX0503HS SPEARS BLDG INFO SHEET (To be Disposed).pdf PDF
ATTACHMENT 3 WD 2015 5291 Rev 16 date 12 21 2020 Frio County.pdf PDF
EXHIBIT C.1 BLDG INFO SHEET_Federal Parking Garage - TX0441ZZ.pdf PDF
Figure B 1 Contractors Staffing Declaration.xlsx XLSX spreadsheet
Exhibit BL3 - TX0502HS WOODS BLDG INFO SHEET (To be Disposed).pdf PDF
ATTACHMENT 1 Custodial CBA PMI LIUNA July 2020 Fully Executed FINAL.pdf PDF
EXHIBIT C.1 BLDG INFO SHEET - US Courthouse San Antonio - TX0398ZZ.pdf PDF
EXHIBIT C.1 BLDG INFO SHEET - Pearsall Federal Post Office Building - TX0231ZZ.pdf PDF
ATTACHMENT 3 WD 2015 5253 Rev 12 date 12 21 2020 Bexar County.pdf PDF
Exhibit BL3 - TX0164ZZ GARCIA BLDG INFO SHEET.pdf PDF
BL2 TX0441ZZ FED GARAGE INVENTORY.pdf PDF
EXHIBIT C.1 BLDG INFO SHEET - AA Spears Judge Training Center - TX0503HS.pdf PDF
EXHIBIT C.1 BLDG INFO SHEET - J Woods Federal Courthouse - TX0502HS.pdf PDF
Exhibit M6 - Water Treatment .pdf PDF
BL1 Fire Extinguisher Report SA and Pearsall.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 65 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BL7

Energy and Water Efficiency Monthly Report

1.0 General: This energy and water efficiency report is to be completed per the requirements of section 5.6, Energy & Water Efficiency, of the O&M services contract. The Contractor shall use this report template and submit completed reports as part of the monthly report to the Facility Manager.

2.0 Energy and Water Efficiency Reporting Template. The Contractor shall use this template to complete the energy and water efficiency report sections for “Contract Information” and “Contractor Reporting Elements.” The GSA Property Manager shall complete the section “GSA Review and Response Elements.”

Contract Information Contract Number:

Report Prepared by:

Building Information Building Number: (if the building is part of a combined facility use the facility level data) Building Name:

Building gross square foot:

Energy Technology & Analytic Tools Available at this Building:

Advanced Meters: yes/no
GSA Link: yes/no
Renewable Energy Systems: yes/no (describe)
Most Recent Energy Audit: yes/no (date)

Annual Performance Target (To be filled out by in conjunction with the regional energy coordinator and the facility manager at the beginning of the Contractor’s performance period and 1 year thereafter until the end of contract)

Energy
Water
TARGET Annual Usage
XX,XXX BTU/GSF
X.X Gal./GSF
TARGET Annual Usage Variance
+ / - 5% of target BTU/GSF
+ / - 5% of target Gallon/GSF
ACTUAL Annual Usage
XX,XXX BTU/GSF
X.X Gal./GSF
Actual Usage is Within Target Variance (Yes/No)?
Yes / No
Yes / No
ACTUAL Annual Usage, Previous Year
XX,XXX BTU/GSF
X.X Gal./GSF
Actual Usage is Improving Relative to Previous Year (Yes/No)?
Yes / No
Yes / No

If actual energy or water usage is not within target variance, please provide narrative justification:

If actual energy or water usage is not improving relative to previous year, please provide justification:

Monthly Utility Bill Reporting (To be filled out monthly)

Actual Usage for

Difference Between This Year & Previous Year

Purchased Utility
Recommended Reporting Unit
Current Billing Cycle Ending Month a
Current Billing Cycle
Same Month Previous Year
Actual Units
Percentage Difference
Electricity
kWh
Electric Demand
Peak kW
Natural Gas
100 Cubic Feetb (Therms)
Steam
MLB / mmBTU
Chilled Water
Ton-Hours

Other Energy c

Total Energy Usage mmBTU d

Domestic Water
Gallons e

a. Current cycle ending month refers to the most recent month in which data is available. EUAS and utility invoices are typically not available until 45 days after the month’s end. E.g. June data is available around August 15th.

b. EUAS data is reported in cubic feet. 100 cubic feet = 1 CCF = 1 Therm

c. Other energy can refer to biomass or other purchased utilities that should add to show total building energy consumption

d. Total mmBTU = (3,413 X kWh + 1.031 X 100 Cubic Feet + 1,000,000 X MLB + 12,000 X Ton-Hours ) / 1,000,000

e. Water is sometimes billed on quarterly (3 month) intervals. If water is billed quarterly, use the total quarterly value from the most recent quarter available.

Renewable Energy Production (If applicable, to be filled out monthly)

Energy Output

Difference Between This Year & Previous Year

System
Recommended Reporting Unit
Current Month
Current Month
Same Month Previous Year
Actual Units
Percentage Difference
Solar Photovoltaic
kWh
Solar Hot Water
mmBTU
Wind
kWh
Geothermal
mmBTU
Other
Other

Discussion & Analysis (If applicable, to be filled out monthly)

Are there any significant (>15%) increases energy or water usage?
No:
Yes:

If yes, what is the cause?

Are there any significant decreases or improvements energy or water usage?
No:
Yes:

If yes, what is the cause? Is it something that can be replicated across additional GSA buildings?

Are there any significant changes in renewable energy production?
No:
Yes:

If yes, what is the cause?

Please describe any planned adjustments to operations or physical changes to the building (by the Contractor, a project, or at the request of tenants) since the last report that may result in improved energy or water efficiency.

Please describe any planned adjustments to operations or changes made to the building (by the Contractor, a project, or at the request of tenants) since the last report that may result in increased energy or water usage.

Were planned adjustments from the last report implemented?

Advanced Meter Analysis (To be filled out monthly. If advanced meters are not available for this building, skip to next section.)

Electric Demand Profile (example)

Electric Sub-Meter Demand Profile (example)

Steam Demand Profile
Gas Demand Profile
Chilled Water Demand Profile
Domestic Water Demand Profile (example)

System & Efficiency Checks (To be filled out monthly)

Are advanced meters functioning properly (i.e. are any meters not communicating or reporting data or reporting faulty data)?

Yes

No

Malfunctioning meters reported to regional metering point of contact?

Is GSA Link functioning and are Sparks being addressed?

Yes

No

Malfunctioning GSA Link reported to regional point of contact?

Are space temperatures set at 72 degrees F. +/- 2 degrees F. for heating mode?

Yes

No

If no, are there plans to adjust temperatures to the desired range?

Are space temperatures set at 75 degrees F. +/- 3 degrees F. for cooling mode?

Yes

No

If no, are there plans to adjust temperatures to the desired range?

Are the night and weekend set back temperatures set to no more than 550 in the winter and no less than 900 in the summer?

Yes

No

If no, are the night/weekend setback temperatures at the level that promotes maximum energy savings without disrupting comfort?

Are holiday schedules verified for upcoming holidays?

Yes

No

If no, are there plans to verify or add holiday schedules?

Is the optimum start/stop sequence programmed into the building automation system?

Yes

No

If no, are there plans to implement optimum start/stop?

Is there a chilled water reset programmed into the chiller controls?

Yes

No

If chilled water reset schedule is available, but not in use, is there a plan to implement it?

Is there a hot water reset programmed into the boiler controls?

Yes

No

If a hot water reset schedule is available, but not in use, is there a plan to implement it?

Are the AHU schedules correctly programmed into the BAS and for the shortest possible time to maintain temperatures for the spaces served?

Yes

No

Comments

Are AHUs currently allowed to cycle off near the end of the day so building temperatures can “coast”?

Yes

No

Comments

Are computer room temperature set points at 78 degrees or higher, and are overtime utilities being collected for this space?

Yes

No

Comments

If applicable, have steam traps been inspected internally and, if needed, rebuilt prior to the heating season?

Yes

No

If no, are there plans to inspect and rebuild steam traps?

If applicable, have boiler efficiency tests been scheduled and performed in October - November?

Yes

No

If no, are there plans to schedule tests?

Have advanced meters and/or leak detection sensors been checked for signs of water leaks?

Yes

No

Comments

If applicable, have cooling towers been checked for signs of leaks or excessive drift?

Yes

No

If no, are there plans inspect cooling towers?

GSA Review & Concurrence

GSA1. GSA Reviewing Official:

GSA2. Date Reviewed:

GSA3. Comments:

image1.png image2.png image3.png

File details come from the government source that posted it. Updated .