2. US Courthouse Commissioning Inspection Schedule.pdf
PDF 72 KB Posted
- Attached to
- Amendment 0003 Full Maintenance Services Contract San Antonio, Pearsall, and New Federal Courthouse
- Solicitation number
- 47PH0221R0004
View the file
Other files
Show 40 more
Latest 50 of 65 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Courthouse Commissioning/Inspection Schedule for
New US Courthouse, TX0398ZZ, 214 W. Nueva St., San Antonio, TX
*The below dates are tentative and are subject to change.
Meeting Duration Start Finish
CXa Commissioning
CXa Functional Testing - CEP 5 10/1/21 10/7/21
CXa Functional Testing – Penthouse B 5 10/6/21 10/14/21
CXa Functional Testing – Penthouse A/B 5 10/15/21 10/21/21
CXa Functional Testing – Penthouse D 5 10/22/21 10/25/21
CXa BAS Functional Testing 5 11/03/21 11/09/21
Contractor Commissioning Punch
Contractor Punch for Commissioning - CEP 5 10/06/21 10/14/21
Contractor Punch for Commissioning – Penthouse B 5 10/15/21 10/21/21
Contractor Punch for Commissioning – Penthouse A/B
5 10/22/21 10/28/21
Contractor Punch for Commissioning – Penthouse D 5 10/29/21 11/04/21
CMa Final Commissioning
CMa Final Commissioning & Signoff - CEP 3 10/15/21 10/19/21
CMa Final Commissioning & Signoff – Penthouse B 3 10/22/21 10/26/21
CMa Final Commissioning & Signoff – Penthouse A/B
3 10/29/21 11/02/21
CMa Final Commissioning & Signoff – Penthouse D 3 11/05/21 11/09/21
Final Inspections & Signoffs
Plumbing Final Inspections & Signoff 10 04/29/21 05/12/21
Fire Protection Inspections & Signoff 10 06/09/21 06/22/21
Life Safety Inspections & Signoff 10 09/22/21 10/05/21
Test & Commission Fire Alarm System 10 10/01/21 10/14/21
Electrical Final Inspections & Signoff 15 10/01/21 10/21/21
Project Closeout
AHU Final Approval & Signoff 2 10/15/21 10/18/21
GSA Networked BAS Review 10 11/10/21 11/23/21
Final Inspection & Owner Punch 20 11/12/21 12/13/21
Initiate Warranty Period (FYI) 0 12/23/21
Punchlist Completion Verification & Signoff 30 12/24/21 01/22/22