Bidder Questions and Answers_updated 3.27.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
DMV HQ Replacement of Chiller #2
Solicitation number
S-73000-00016059
Issued by
Marion County, Oregon

About this file

This is a Bidder Questions and Answers document for the Oregon Department of Transportation's DMV Headquarters Chiller #2 replacement project in Salem, Marion County. The project involves replacement of a 140-ton Trane chiller with a new 140-ton Daikin unit, along with installation of two new chilled water pumps with variable frequency drives (VFDs), an air separator, a pot feeder, rooftop curbs, and a main rooftop electrical disconnect. A non-mandatory site visit was scheduled for March 24, 2026 at 1:30 PM, following the mandatory pre-bid conference on March 17, 2026. Bidders submitted 14 questions between March 17-24, 2026, addressing equipment specifications, installation methods, storage requirements, and operational parameters. Key clarifications provided include confirmation that the new chiller unit should be stored at the contractor's yard rather than on-site, that both chilled water pumps should operate independently in a lead-lag rotation capable of individual operation, that welded piping is preferred over Victaulic installation methods, and that the new air separator may be installed outside if properly insulated with heat trays. VFD brand preferences were specified as ABB or Snyder Electric or approved equal, and a substitution request for an alternative chiller unit was denied based on efficiency requirements.

The procurement includes specifications requiring new mechanical units to be 20 percent more efficient than Oregon Energy Efficiency Specialty Code minimums and to weigh equal to or less than replaced units. All work must comply with Oregon prevailing wage rates for Marion County (BOLI Region 3) and State Buy America requirements for steel, iron, coatings, and manufactured products. Bid submission through OregonBuys was required by April 2, 2026, with project commencement no earlier than October 1, 2026 and substantial completion by November 24, 2026. Liquidated damages are assessed at $600 per calendar day for delays beyond the substantial completion date. The project is funded from State sources, with the cost estimate for bonding purposes ranging from $100,000 to $300,000. Required insurance includes Commercial General Liability of $1,000,000 per occurrence and $2,000,000 annual aggregate, plus Commercial Automobile Liability of $1,000,000 per occurrence. Award will be made to the lowest responsive bid from a responsible bidder, subject to a five-calendar-day protest period.

View the file

Other files

File Type Posted
00016059_Exh 5 to Sample Contract_Specifications.doc DOC document
00016059_Sample PI Contract.docx DOCX document
00016059_ITB.docx DOCX document
DMV_HQ_Structural _for information only.pdf PDF
00016059_Bid tab.xlsx XLSX spreadsheet
Pre bid sign in~2.pdf PDF
Existing unit model no_for information only.docx DOCX document
Mechanical Drawings - for information only.pdf PDF
00016059_Add 1.docx DOCX document
Daikin partial specifications_for information only.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Salem DMV Headquarters Chiller #2 F8246701033 S-73000-00016059
Bidders Questions
NumberDate ReceivedQuestionAnswer
13/18/26Can another site visit be performed?Yes, scheduled for 3/24/26 @ 1:30 PM Non mandatory
23/18/26Are there existing mechanical, electrical, and structural plans for the building?Provided what was available.
33/18/26Under the Project Description, it states that the contractor is required to store chiller on-site until installation. Does ODOT want the new chiller sitting on-site until the installation or did they mean they wanted it stored off-site and delivered on-site the day of the crane pick?Unit to be stored at contractors yard, not on construction site. See Addendum 1.
43/17/26Substitution Request for unit DB Model ACDS150ARBSDenied based on efficiency
53/17/26How many pumps are to be replaced?2 pumps to replace
63/19/26Will the specifications for the chilled water pumps to be replaced be released? Motor horsepower is available, but specs on flow rate, etc. would be very helpful.See page 10 of the drawings, chilled water pump 5 and 6
73/19/26Is the intent to install two new chilled water pumps with one in standby or to replace the hot water pump with a chilled water pump? It was unclear on the walk if the hot water pump would remain in service.intent is to install two new chilled water pumps to replace existing with VFD's and not touch the hot water circuit.
83/19/26Is there a preferred VFD brand (ABB, Allen Bradley, etc.) for use in the control system?Abb or Snyder electric or equal
93/19/26Will the complete model number of the existing Trane chiller be made available to verify weight constraints? The nameplate on the unit was not clear during the walk.See question 11
103/19/26Is there a preferred piping installation method? It appears some of the installation on the previous project was Victaulic rather than a welded install.Welded is preferred but any method that achieves required results is acceptable.
113/19/26Is there an equipment schedule that lists the model number and weight of the Trane chiller being replaced?Model information provided.
1219-MarI pulled Daikin info I could from web, but do not have access to exact model mechanical specs.See specifications provided
133/24/26Can the new air separator be installed outside by the new chiller?Yes, but it needs to be insulated and include heat trays.
143/24/26Do both chilled water pumps operate simultaneously, or do they operate in a lead/lag rotation?Independently, either pump needs to be able to make flow

File details come from the government source that posted it. Updated .