Bid_Schedule_-_Fan_Coil_Replace.xlsx
XLSX spreadsheet 32 KB Posted
- Attached to
- Fan Coil Unit Replacement
- Solicitation number
- 140P6425B0004
About this file
The provided file is a Bid Schedule for a Fan Coil Unit Replacement project at the First Ladies National Historic Site in Canton, OH. The National Park Service (NPS) is seeking a small business contractor to replace multiple fan coil units throughout a six-story building, with an estimated project magnitude between $500,000 and $750,000. The solicitation (140P6425B0004) is a firm-fixed price contract anticipated to begin in June 2025, with Construction Wage Rate Requirements applicable to Stark County, OH.
The bid schedule includes a base bid for fan coil unit replacements on the 2nd, 3rd, 4th, and 6th floors, with an optional additional replacement for the 5th floor. The project is 100% set aside for small businesses under NAICS code 238220, with a size standard of $19 million. Potential bidders must have a Unique Entity Identifier (UEI) number and be registered and active in the System for Award Management (SAM). The point of contact is Craig D Bryant, Contracting Officer, who can be reached at craig_bryant@nps.gov or 330-468-2500 x6.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| First Ladies National Historic Site | |
| U.S. Department of Interior | |
| National Park Service |
PROJECT: Fan Coil Unit Replacement
BID SCHEDULE
Construction Items Unit Quantity Price/ Unit Subtotal
| Mobilization/Demobilization | ||||
| - Mob/Demob Costs | LS | 1 | $ - 0 | $ - 0 |
| Site Preparation, Demolition and all associated work/items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
| Fan Coil Unit Replacement (2nd, 3rd, 4th and 6th Floor) and all associated work/items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
Subtotal $ - 0
| Overhead | % | $ - 0 |
| Profit | % | $ - 0 |
| Bonds | % | $ - 0 |
Grand Total (Base Bid) $ - 0
| Option #1: Fan Coil Unit Replacement (5th Floor) and all associated work/items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
| Overhead | % | $ - 0 |
| Profit | % | $ - 0 |
| Bonds | % | $ - 0 |
Grand Total (Option #1) $ - 0
Grand Total (Base Bid + Option #1) $ - 0
Printed: &D &T &Z&F image1.png
File details come from the government source that posted it. Updated .