This is a bid form for the City of Norcross, Georgia's Downtown Norcross Parking Improvements project located at 65 Lawrenceville Street. The project encompasses parking and pedestrian facilities surrounding Norcross City Hall, including grading, storm drainage, paving, sidewalks, ADA improvements, retaining walls, landscaping, lighting, and associated site improvements. The bid form itemizes approximately 57 line items across multiple categories: civil general site items (demolition, earthwork, temporary protection measures), site work hardscape items (retaining walls, stairs, railings, site amenities, landscape, and stormwater infrastructure), roadway paving and pavement marking (asphalt paving, concrete curb and gutter, sidewalks, and specialized paving options), and electrical appurtenances (utility poles, light fixtures, and conduits). Key quantities include 1,153 square yards of concrete demolition, 2,949 square yards of asphalt demolition, 4,162 square yards of asphalt paving, 4,634 square feet of sidewalk, 9,865 square feet of driveable brick pavers, and 7,632 square feet of permeable pavers. Sealed bids must be submitted by 11:00 a.m. on September 28, 2026, in two printed copies and one electronic copy to the City of Norcross Public Works Department. A non-mandatory pre-bid meeting with optional site visit will be held on August 26, 2026, at 11:00 a.m. Questions must be submitted by email by 5:00 p.m. on September 7, 2026. All work must be completed within 315 calendar days following issuance of the Notice to Proceed.
The bid form requires contractors to complete the Schedule of Items for each stage of construction and provide total costs for each item, with bid prices including all direct, indirect, administrative, and incidental costs necessary to complete the work. Contractors are responsible for verifying all quantities, and all extended costs, subtotals, and the base bid must be calculated correctly. The base bid shall include all work shown on the drawings and described in the specifications, whether or not specifically listed as a separate bid item. The form indicates that all unit cost and extended cost fields are currently blank, requiring bidders to complete pricing information. No information regarding set-asides, incumbent contractors, funding sources, or total project budget is provided in this bid form document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID FORM
| NOTE TO CONTRACTOR: Complete the Schedule of Items for each stage of construction and provide a total cost for each item. Bid prices shall include all direct, indirect, administrative, and incidental costs necessary to complete the Work in accordance with the Contract Documents. Quantities shown are for bidding purposes only; the Contractor is responsible for verifying all quantities. Verify that all Extended Costs, Subtotals, and the Base Bid are calculated correctly. The Base Bid shall include all Work shown on the Drawings and described in the Specifications, whether or not specifically listed as a separate bid item. | |||||
| DOWNTOWN NORCROSS PARKING IMPROVEMENTS | |||||
| Item Number | Description | Quantity | Unit | Unit Cost | Total Extended Cost |
| Civil General Site Items | |||||
| 1 | General Requirements and Mobilization | 1 | LS | $ - 0 | |
| 2 | Traffic Control | 1 | LS | $ - 0 | |
| 3 | Demolition and removal- Concrete | 1153 | SY | $ - 0 | |
| 4 | Demolition and removal- Asphalt | 2,949 | SY | $ - 0 | |
| 5 | Demolition and removal - Curb and Gutter | 1673 | LF | $ - 0 | |
| 6 | Demolition and removal - storm pipe | 645 | LF | $ - 0 | |
| 7 | Demolition and removal - storm structures | 13 | EA | $ - 0 | |
| 8 | Demolition and salvage - site amenities | 1 | LS | $ - 0 | |
| 9 | Clearing | 2.18 | AC | $ - 0 | |
| 6 | Earthwork | 1200 | CY | $ - 0 | |
| 9 | Haul in | 650 | CY | $ - 0 | |
| 10 | Haul off | 0 | CY | $ - 0 | |
| 7 | Temporary Construction Fence | 400 | LF | $ - 0 | |
| 8 | Temporary Sediment trap w outlet protection | 13 | EA | $ - 0 | |
| 8 | Tree Protection Fence | 1025 | LF | $ - 0 | |
| 9 | additional Tree Protection measures per plans | 1 | EA | $ - 0 | |
| 9 | Silt Fence (per single row) | 1165 | LF | $ - 0 | |
| 10 | Construction Exit | 1 | EA | $ - 0 | |
| 11 | Temporary Grassing,Mulching, Dust Control (DS1/DS2/Du) | 1.68 | AC | $ - 0 | |
| 12 | Stone Outlet protection | 1 | EA | $ - 0 | |
| 13 | Inlet Protection and retrofit | 1 | EA | $ - 0 | |
| SUBTOTAL FOR CIVIL SITE ITEMS | $ - 0 | ||||
| Site Work | |||||
| Hardscape Items | |||||
| 14 | CIP Concrete Retaining Wall | 2300 | SF | $ - 0 | |
| 15 | Concrete Stairs - 12" tread & 6" riser | 85 | SF | $ - 0 | |
| 16 | Steel pipe handrails | 30 | LF | $ - 0 | |
| 17 | decorative railing on walls | 503 | LF | $ - 0 | |
| Site Amenities | |||||
| 18 | Project sign (temporary sign w project information) | 1 | LS | $ - 0 | |
| 19 | removable bollards | 17 | EA | $ - 0 | |
| 20 | concrete wheelstops | 31 | EA | $ - 0 | |
| 21 | ADA parking signage | 3 | EA | $ - 0 | |
| 22 | Park Bench | 2 | EA | $ - 0 | |
| 23 | Outdoor tables with seating and shade umbrellas | 4 | EA | $ - 0 | |
| 24 | Tree grate with frame and tree guard | 6 | EA | $ - 0 | |
| 25 | 40' flagpole assembly | 1 | EA | $ - 0 | |
| 24 | Pond gate | 1 | EA | $ - 0 | |
| Landscape | |||||
| 25 | Automated, in-ground irrigation system | 1 | EA | $ - 0 | |
| 26 | Replacement trees (6" cal.) from Select Trees | 8 | EA | $ - 0 | |
| 27 | Replacement trees (4" cal.) from Select Trees | 13 | EA | $ - 0 | |
| 28 | Replacement trees (3" cal.) | 28 | EA | $ - 0 | |
| 29 | Replacement trees (8' ht.) | 15 | EA | $ - 0 | |
| 30 | Shrubs and groundcover (3 Gal. or ht based per plans) | 299 | EA | $ - 0 | |
| 31 | Shrubs (7-10 gal) | 13 | EA | $ - 0 | |
| 32 | Ornamental Grasses/Perennials (1 Gal.) | 1802 | EA | $ - 0 | |
| 33 | Sod Installed | 9107 | SF | $ - 0 | |
| 33 | Bioretention media mix | 215 | CY | $ - 0 | |
| 34 | Deeproot Silvacell 1X units with soil media | 126 | EA | $ - 0 | |
| Stormwater | |||||
| 35 | 24" RCP pipe | 409 | LF | $ - 0 | |
| 36 | 18" RCP pipe | 635 | LF | $ - 0 | |
| 37 | 8" N-12 HDPE pipe drainline and accessories | 140 | LF | $ - 0 | |
| 36 | 8"-15" drain inlet | 10 | EA | $ - 0 | |
| 37 | Duratrench 6" trench drain | 66 | LF | $ - 0 | |
| 38 | Duratrench 12" trueradius slot drain | 67 | LF | $ - 0 | |
| 37 | Stormwater manhole/ catch basin | 5 | EA | $ - 0 | |
| 38 | Stormwater drop inlet | 7 | EA | $ - 0 | |
| 39 | doghouse/existing Storm structure connection | 3 | EA | $ - 0 | |
| 40 | Outlet control structure | 1 | EA | $ - 0 | |
| 41 | Water Quality structure | 2 | EA | $ - 0 | |
| 42 | 8" perforated PVC underdrain + cleanouts | 100 | LF | $ - 0 | |
| SUBTOTAL FOR SITE WORK | $ - 0 | ||||
| Line # | Description | Quantity | Unit | Unit Cost | TOTAL |
| Roadway | |||||
| Paving & Pavement Marking | |||||
| 43 | Asphalt Paving | 4162 | SY | $ - 0 | |
| 44 | Pavement Marking, Wheelstops, Signs | 1 | LS | $ - 0 | |
| Concrete Paving/Curb | |||||
| 45 | 24" Concrete Curb and Gutter | 2250 | LF | $ - 0 | |
| 46 | ADA curb ramps | 600 | SF | $ - 0 | |
| 46 | Driveable concrete paving and ribbon curbing | 250 | SY | $ - 0 | |
| 47 | 4" Sidewalk | 4634 | SF | $ - 0 | |
| Specialized Paving | |||||
| 48 | Driveable Brick pavers | 9865 | SF | $ - 0 | |
| 49 | 12"x12" pavers in brick plaza | 18 | EA | $ - 0 | |
| 50 | Permeable pavers | 7632 | SF | $ - 0 | |
| 51 | Bioretention island curbing additional depth | 165 | LF | $ - 0 | |
| SUBTOTAL FOR ROADWAY | $ - 0 | ||||
| Electrical | |||||
| Appurtenances | |||||
| 52 | Relocated power /utility pole | 3 | EA | $ - 0 | |
| 53 | New /reused Acorn light poles+fixtures | 14 | EA | $ - 0 | |
| 54 | New parking lot light poles+fixtures | 4 | EA | $ - 0 | |
| 55 | New parking lot light fixture mounted on utility pole | 4 | EA | $ - 0 | |
| 56 | New bollard lighting | 12 | EA | $ - 0 | |
| 57 | Low Voltage lighting system | 1 | EA | $ - 0 | |
| 57 | 2" PVC power conduits | 500 | LF | $ - 0 | |
| SUBTOTAL FOR ELECTRICAL | $ - 0 | ||||
| TOTAL PROJECT COST (BASE BID): | $ - 0 |