This is Section L (Instructions to Offerors) from RFP 367094 for Reactive Power Compensation Power Factor Correction Work Package 1 – Demolition at SLAC National Accelerator Laboratory, a federally funded construction project operated by Stanford University for the U.S. Department of Energy.

SLAC intends to award one Firm Fixed Price subcontract without discussions, though reserves the right to conduct discussions if deemed necessary. To be eligible, offerors must be registered in good standing (non-debarred) with the System for Award Management (SAM), registered in the University's procurement system, and maintain a current Safety Qualification Form valid through the award date. Proposals must remain valid for 90 days from the due date and be submitted electronically in searchable PDF format with a maximum of 30 pages for both Volume I (Technical Proposal) and Volume II (Price Proposal). The technical proposal must include: project approach and work elements; assumptions and clarifications; sub-tier/trade partner information; preliminary safety plan addressing hoisting, rigging, lead abatement, and demolition; environmental compliance history for the past three years with all violation notices; OSHA 300 logs if Experience Modification Rate exceeds 1.0; proposed schedule with interdependencies; project management methodologies; key personnel qualifications and resumes (Project Manager 50%, Project Superintendent 100% onsite, Safety Representative minimum 25% and onsite for high-risk activities); current California contractor's license; statement confirming no convictions involving government contracts; and documentation of a local San Francisco Bay Area office established for a minimum of three years. The price proposal must include completed RFP Sections A and B with firm-fixed prices, bonding letter from primary surety, current Dun and Bradstreet Report, audited financial statements (if D&B SER score exceeds 6), price breakdown using the Proposal Breakdown Sheet, and completed Sections H, J, and K. All proprietary/confidential information must be marked accordingly. The point of contact is Senior Subcontract Administrator Doreen Agbayani at doreena@slac.stanford.edu. Late proposals will not be considered, and errors must be identified within three business days of the due date for corrections. All questions must be submitted in writing using the SLAC RFI Question and Answer Log before the proposal deadline.

View the file

Other files

File Type Posted
B2_04_Section_F_(Deliveries_Performance)_DRAFT.pdf PDF
B2_07.2_Subcontractor_Form_IIPP_052121_DRAFT.pdf PDF
B2_08.0_Section_K_(Rep_and_Certs)_DRAFT.pdf PDF
B2_02_Section_B_(Supplies_or_Services_and_Price_Costs)_DRAFT.pdf PDF
B2_00_RFP_Cover_DRAFT.pdf PDF
B2_03.3_SLAC BIO Adopted Codes and Standards (Updated 01012025)_DRAFT.pdf PDF
B2_07.1_DBA_WD_CA20260018_7.14.26_Mod_06_DRAFT.pdf PDF
B2_07.4_SF1413_DRAFT.pdf PDF
B2_07.3_Work_Classification_Form_367094_DRAFT.pdf PDF
B2_09.1_Section_L_Attachment_A_Proposal_Breakdown_Sheet_DRAFT.pdf PDF
B2_01_Section_A_(Subcontract_Form)_DRAFT.pdf PDF
B2_03.0_Section_C_(Specifications_SOW)_DRAFT.pdf PDF
B2_03.1_SOW_RPC WP1 Demolition_R3_DRAFT.pdf PDF
B2_05.1_Fixed_Price_Construction_March2024_DRAFT.pdf PDF
B2_09.2_Section_L_Attachment_B_SLAC_Question&Answer_Log_(RFI)_DRAFT.pdf PDF
B2_07.5_SubcontractorFormSQF_DRAFT.pdf PDF
B2_10_Section_M_Evaluation_Methodology_DRAFT.pdf PDF
B2_05.0_Section_G_(General_TsCs)_DRAFT.pdf PDF
B2_07.8_Construction_Subcontracts_Final_Release_DRAFT.pdf PDF
B2_07.7_Final_Inspection_Report_DRAFT.pdf PDF
B2_08.1_Reps_and_Certs_Supplement_DRAFT.pdf PDF
B2_07.6_NTP_Submittal_Checklist_061424_DRAFT.pdf PDF
B2_07.0_Section_J_(List_of_Attachments)_DRAFT.pdf PDF
B2_06_Section_H_(Special TsCs)_DRAFT.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLY CHAIN MANAGEMENT

Section L – Instructions to Offerors

RFP 367094

Reactive Power Compensation Power Factor Correction Work Package 1 - DEMOLITION

1. GENERAL INFORMATION

Section L – Instructions to Offerors provides general guidance for preparing proposals as well as specific instructions on the format and content of the proposal. The Offeror's proposal must include all data and information requested by the ITO and must be submitted in accordance with these instructions. The proposal shall be compliant with the requirements as stated in the Statement of Work (SOW) and Technical Specifications. Non-conformance with the instructions provided in this ITO may result in an unfavorable proposal evaluation.

SLAC intends to award without discussions with respective Offerors. SLAC, however, reserves the right to conduct discussions if deemed in its best interest.

The evaluation process and method are described in Section M – Evaluation Factors for Award.

For an Offeror to be eligible for a subcontract award with SLAC, the Offeror shall:

• Be registered in good standing (non-debarred) with the System for Award Management (SAM), the Official U.S. Government system that consolidated the capabilities of CCR/FedReg, ORCA, and EPLS. There is NO fee to register for this site.

Entities may register at no cost directly at the SAM website: http://www.SAM.GOV

• Be registered in the University’s procurement system of record:

https://suppliers.slac.stanford.edu/become-slac-supplier

• Have a current Safety Qualification Form approved and valid through the award date of this RFP.

SLAC anticipates awarding one Firm Fixed Price subcontract.

PLEASE NOTE: That SLAC National Accelerator Laboratory is operated by Stanford University for the U.S. Department of Energy (DOE) making this a federally funded construction project. As such, the Offeror is being made aware of, in addition to other required labor postings, the DOE WH Publication 1321, which can be found on the following website:

https://www.dol.gov/sites/dolgov/files/WHD/legacy/files/fedprojc.pdf http://www.sam.gov/ https://suppliers.slac.stanford.edu/become-slac-supplier https://www.dol.gov/sites/dolgov/files/WHD/legacy/files/fedprojc.pdf

1.1 PROPOSAL SUBMITTAL INFORMATION

POINT OF CONTACT: The Senior Subcontract Administrator, Doreen Agbayani, is the sole point of contact for this acquisition. Address any questions or concerns you may have, in writing, to the Senior Subcontract Administrator via email: doreena@slac.stanford.edu. All exchanges of source selection information between the University and Offerors will be controlled by the Senior Subcontract Administrator.

MARKING OF PROPRIETARY/CONFIDENTIAL INFORMATION: Offerors shall properly mark and identify with a restrictive legend or information markings on pages of the proposal that contain Proprietary/confidential information.

Proposals must be valid for Ninety (90) days from the proposal due date. The Offeror shall make a clear statement in its proposal cover letter utilizing the following language. “The undersigned agrees that this offer is valid for Ninety days, and to furnish any or all items upon which prices are offered at the price set opposite each item, delivered via email, within the time specified in the schedule.” Proposals shall be addressed to the Senior Subcontract Administrator:

SLAC National Accelerator Laboratory 2575 Sand Hill Road, Building 041 Menlo Park, California 94025 Attention: Doreen Agbayani

2. PREPARATION OF PROPOSALS: Proposals shall be submitted, in searchable PDF, on the forms furnished or copies thereof, and must be manually signed if erasures or other changes appear on the forms; the person signing the proposal must initial each erasure or change.

2.1 VOLUME I – TECHNICAL PROPOSAL

The Volume I Technical Proposal must contain the following information, but NOT contain any pricing information. All pricing information shall be submitted in Volume II Price Proposal.

Cover Sheet The cover sheet should include:

• Title: Reactive Power Compensation Power Factor Correction Work Package 1 -

DEMOLITION

• Volume I - Technical Proposal,

• Date of submission, mailto:doreena@slac.stanford.edu

• General Subcontractor Name, and

• Contact information.

Factor 1 – Technical Approach

• Sub-factor 1.1, Project Approach: Submit a narrative with your approach to complete the scope of work described in the SOW.

• Sub-factor 1.2, Project Work Elements: Describe the general approach to execute project work elements, including: coordination and communication with SLAC project personnel; pre-mobilization activities, demolition, lead abatement; removal of Synchronous Condenser out of Master Substation Yard; separation of materials identified for salvage and waste disposal; and demobilization.

• Sub-factor 1.3, Assumptions: Provide a list of project-specific assumptions and clarifications made in preparation of your proposal to supplement the information contained in SLAC project statement of work (SOW), drawings and specifications.

• Sub-factor 1.4, Sub-tier or Trade Partners: Provide a list of sub-tier or trade partner subcontractors intended to be used on the project. Describe their roles and responsibilities in the demolition activities.

Factor 2 – Safety

• Sub-factor 2.1, Safety Plan: Submit a preliminary safety plan to address key high consequence activities including but not limited to hoisting and rigging, lead abatement, general demolition, to meet the SOW deliverables.

• Sub-factor 2.2 Describe how you plan to implement your on-site ES&H program for the project.

• Sub-factor 2.3 Provide background information on their environmental regulatory compliance status and enforcement history for the past 3 years. Offeror shall include all notices of violation stemming from environmental non-compliance and the supporting documentation, including fines incurred and explanation of how the violations were addressed.

• Sub-factor 2.4 Submit form SLAC-I-730-0A21J-027-R010, Construction Subcontractor Safety Qualification Form (SQF) for the Offeror’s company which shows evidence of your overall safety record. If your Experience Modification Rate (EMR) is greater than 1.0, Offeror shall include OSHA 300 logs for self-performed work, for the past three years, and statements if there have been any fatalities or serious injuries. Offerors with a current SLAC approved SQF that remains valid at the time of proposal submission are not required to resubmit the SQF; however, the Offeror shall state that the approved SQF is on file with SLAC.

Factor 3 – Schedule

• Submit a proposed schedule with the bid proposal. For all activities provide the proposed start and end dates. Interdependencies shall be included.

Factor 4 – Project Management & Experience

• Sub-factor 4.1 Describe your team’s proposed methodologies for providing comprehensive project management services and project team coordination, and providing prompt, effective and safe demolition services.

• Sub-factor 4.2 Submit a written summary of Offeror’s Key Personnel (including sub-tier contractors), identifying the proposed Project Manager 50%, Project Superintendent 100% onsite, and Safety Representative minimum 25% and onsite for high-risk activities.

The summary must include the following:

o Their qualifications for the identified role.

o The percentage of time each role will be assigned to the project and time dedicated to being on-site.

o Specific examples of previous relevant projects that they supported.

o A copy of their resume.

Factor 5 – Statement of Qualifications The Offeror shall provide the following:

• Sub-factor 5.1 A current and valid California contractor’s license appropriate to Offeror’s trade.

• Sub-factor 5.2 A written statement regarding the following:

o Neither the Offeror’s firm, nor any of its owners or officers have been convicted of a crime involving the awarding of the contract of a government (U.S. Federal, State, and City) construction project, or the bidding or performance of a government contract.

o Offeror must identify a local office in the San Francisco Bay Area that has been established a minimum of three years. The San Francisco Bay Area is defined as the following 10 counties: Santa Clara, San Mateo, San Francisco, Alameda, Contra Costa, Marin, Napa, Sonoma, Solano and Santa Cruz Counties.

o Experience in contracts with DOE’s National Laboratories, the Department of Energy (DOE), the Department of Defense (DOD) and/or a federal facility are preferred but not required.

2.2 VOLUME II – PRICE PROPOSAL

Cover Sheet The cover sheet should include:

• Title: Reactive Power Compensation Power Factor Correction Work Package 1 -

DEMOLITION

• Volume II – Price Proposal,

• Date of submission,

• General Subcontractor Name, and

• Contact information.

Clearly stamp all company financial documents as “Business Sensitive” if applicable, on any included documents.

Business Documentation Financial information is required from the General Contractor only. Offeror shall provide:

• Provide letter from primary surety firm confirming bonding capability for this project, maximum bonding capability for a single project and total bonding capability.

• Provide current Dun and Bradstreet Report.

• If the Dun and Bradstreet SER score is greater than 6, or if the Offeror does not participate in Dun and Bradstreet, provide three most current years of audited financial statements. Financial statements are not required with a SER score of 6 or below. SLAC has access to Dun and Bradstreet reports.

• Offeror’s proposal must communicate acceptance to the SLAC Terms and Conditions, as indicated in the solicitation, including all attachments, and documents incorporated by reference. Requested exceptions to any of the solicitation documents must be communicated at the time of the proposal submission. Note that any exceptions to the SLAC Terms and Conditions will require SLAC Legal approval.

Price The Offeror is required to provide the following contract documentation:

• Submit RFP Section A (completed and signed form), acknowledgement of issued solicitation amendments.

• Submit RFP Section B with firm-fixed prices for each line item. All subcontract value totals to be provided in Section B, unless noted.

• Submit a price breakdown for each proposed firm-fixed-price item using Section L, Attachment A, Proposal Breakdown Sheet. The total must match the total price listed in Subcontract Section B (Supplies or Services and Price/Costs).

Contract Documentation

• Section H, (Special Terms and Conditions) completed with Key Personnel.

• Section J, (IIPP Form) shall be completed and signed.

• Section J, (Small Business Subcontracting Plan) shall be completed and signed.

• Section K, (Representations & Certifications) shall be completed and signed.

3. METHOD OF TRANSMISSION/ORGANIZATION/NUMBER OF COPIES/PAGE LIMITS:

Proposals must be submitted electronically in searchable PDF, as indicated in this Section L.

The Offeror shall prepare the proposal as set forth in the Proposal Organization Table. The titles and contents of the volumes shall be as defined in this table, all of which shall be within the required page limits as specified. The contents of each proposal volume are described in the ITO paragraph as noted in the table below.

Proposal Organization Table:

Volume ITO Section Volume Title Electronic Copies Page Limit

I 2.1 Technical Proposal 1 30 II 2.2 Price Proposal 1 30

4. LATE PROPOSALS AND MODIFICATIONS:

Late Proposals will not be considered. Errors in Proposals must be identified No Later Than 3 business days after the proposal due date for corrections to be considered.

5. WITHDRAWALS OF PROPOSALS:

Proposals may be withdrawn by email, addressed as instructed for the proposal, and must be received from the Offerors prior to award.

6. RFP AMENDMENTS:

The right is reserved, as the interests of SLAC may require, to revise or amend the solicitation documents and drawings prior to the due date set for submission of proposals.

Such revisions and amendments, if any, will be announced on an “Amendment of Solicitation/Subcontract Modification” form. Copies of such amendments may be issued and will be furnished to all prospective Offerors. If the revisions and amendments are of a nature which requires material changes in quantities or proposal prices or both, the date set for submission of proposals may be postponed by such number of days, as in the opinion of SLAC will enable the Offerors to develop their proposals. In such case, the Amendment of Solicitation/Subcontract Modification form will include an announcement of the new due date for receipt of proposals.

7. EXPLANATION TO OFFERORS:

Any explanation desired by an Offeror regarding the meaning or interpretation of the Request for Proposal, drawings, specifications, etc., must be requested in writing using the SLAC RFI’s to Owner Question and Answer Log (Attachment A) and with sufficient time allowed for a reply to reach the Offeror before the due date for submission of proposals.

Oral clarification of requirements or instructions provided by SLAC before the award of the Subcontract will not be binding. Questions containing Offeror’s non-proprietary information and corresponding clarifications will be shared with all Offerors.

8. TAXES:

The Offeror may consult the provisions on taxes that are provided throughout the General Terms and Conditions and to the California State Board of Equalization Regulations relating to sales of machinery and equipment for delivery under construction contracts with the United States government. However, responsibility for determination of the applicability of California State Board of Equalization Regulations shall rest solely with the Offeror, and no representation or guarantee either expressed or implied is made by the Government or SLAC hereunder as to the application thereof. SLAC will not reimburse Offeror for taxes as a separate line item.

9. SPECIFIED PRODUCT AVAILABILITY:

Where the Technical Specifications, Statement of Work, or Drawings list a specific product, the Offerors may assume that the product is commercially available; however, availability within the required performance period may require payment, by the successful Subcontractor at no additional cost to SLAC, of premiums for expediting production or shipment. The Offerors are cautioned to confirm not only product prices, but costs associated with timely acquisition of the product as required to meet performance period requirements. The Offerors are required to notify the University Senior Subcontract Administrator prior to the proposal due date of any obvious product unavailability.

10. SPECIFIED PRODUCT OR METHOD COMPATIBILITY:

Where the Technical Specifications, Statement of Work, or Drawings list a specific product or method, the Offerors may assume that the product or method is compatible with other requirements of the Subcontract. The Offerors are required to notify the University Senior Subcontract Administrator prior to the date set for receipt of proposals of any obvious incompatibility between a specified product or method and other requirements of the Subcontract.

11. EXCEPTIONS TO SLAC’S STANDARD TERMS AND CONDITIONS, PROVISIONS, AND/OR

CLAUSES: Offeror must identify any exceptions to SLAC terms and conditions or exceptions to any other element of the requirements that are a part of this RFP, with their proposal. SLAC will not entertain any exceptions not identified in the proposal submission. Exceptions taken may be cause for rejection of a proposal. Inclusion of any assumptions, clarifications, exclusions, or conditions may be cause for rejection of the proposal as non-responsive.

Attachments in Section L

Attachment A - SLAC Question & Answer Log

Attachment B – Proposal Breakdown