B2_03.1_SOW_RPC WP1 Demolition_R3_DRAFT.pdf
PDF 386 KB Posted
- Solicitation number
- SLAC_RFP_367094
- Issued by
-
Department of Energy Office of Science
About this file
This is a Statement of Work (SOW) for demolition and disassembly activities supporting a reactive power compensation and power factor correction project at SLAC National Accelerator Laboratory in Menlo Park, California.
The scope of Work Package 1 requires the subcontractor to demolish metal buildings B308 and B311, remove a non-operational 110,000-pound synchronous condenser, and disconnect associated electrical equipment, cabling, and wiring located in the Master Substation (MSS) Yard. All work must be performed within an active substation yard under escort by SLAC employees and coordinated with the assigned Construction Manager. The subcontractor must furnish all labor, materials, tools, equipment, and temporary construction power. Demolished materials must be disassembled into convenient sizes and separated into SLAC-provided bins for metal, wire, and breakage for salvage removal, with Class II concrete and soil materials placed in designated bins for SLAC waste management. A critical constraint limits vehicle and crane operations to a 20-foot width by 11-foot height clearance zone due to 230kV overhead power lines. The existing ground grid must be preserved with any unavoidable impacts coordinated in advance.
Key deliverables include a schedule of major work activities, work plans for high-risk critical activities, Job Hazard Analysis, daily safety tailgates, verification of existing conditions with red-lined drawings, project close-out inspections, and completion of SLAC's punch list. The subcontractor must demonstrate experience in self-performed demolition work, successful execution of past projects with established partner relationships, and prior experience working in operational critical facilities such as main substations. The performance period spans six weeks from October 12 to November 20, 2026, with RFP release on August 14, 2026, proposal due September 3, 2026, and contract award anticipated September 25, 2026.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for the
Reactive Power Compensation Power Factor Correction
Work Package 1 - Demolition at
SLAC National Accelerator Laboratory
July 15, 2026
Document Title: Statement of Work for the Reactive Power Compensation Power Factor Correction Work Package 1 Demolition
SLAC-I-708-905-023 Page 2 of 9
Document Approval:
Originator: Anuneet Krishna – Plant Engineering Manager, Subject Matter Expert
• Content/Format • SME Input • Actionable • Complete/Accurate
Reviewer: Oleksandr Martynchuk, Design Manager
Verification Planning • Scope Alignment • Design Manager
Reviewer: Boris Ilinets – Senior Electrical Engineer, Subject Matter Expert
• Content/Format • SME Input • Actionable • Complete/Accurate • Verification Planning • Scope Alignment
Reviewer: Tim Carnes – Construction Manager
• Facts • Details • Concepts
Reviewer: Victor Longa – Electrical Operations Planning
• Facts • Details • Concepts
Reviewer: Amy Ancheta – Division Director of Engineering, F&O
• Clarity • Organization • Adherence to Project Processes • Quality Assurance Requirements
Approver: Lori Shewchuk – Project Manager
• Final Authorization
Informed Parties Notified on July 15, 2026
Tracy Ng – CUIR Project Director
Brendan Curran – Director, Facilities & Operations
Revision History
Revision Date Released Description of Change
R3 July 15, 2026 Revisions to Sections 4, 6 and 7 to reflect scope changes and reductions, updated schedule, and disposal responsibilities.
R2 June 19, 2026 Revisions to Section 4 – 6., 7, & 8, Section 4.1, C & D, and Section 6 Preliminary Schedule for additional RFP clarifications.
R1 May 8, 2026 Addition of clarifications to disposal and disassembly instructions; see section Deliverables item 4.
R0 March 26, 2026 Original Release.
SLAC-I-708-905-023 Page 3 of 9
Table of Contents 1 Introduction and Overview 2 Purpose 3 Location 4 Scope of Work
4.1 Disassembly and Removal ...................................................... Error! Bookmark not defined.
4.2 System to Remain
5 Qualifications 6 Project Preliminary Schedule for Subcontracted Work 7 Deliverables
SLAC-I-708-905-023 Page 4 of 9
Acronyms BIO Building Inspection Office
BM/AM Building Manager/Area Manager
CM Construction Manager
LOTO Log Out Tag Out
LV Low Voltage
MV Medium Voltage
OSHA Occupational Safety and Health Administration
RFP Request for Proposal
SOW Statement of Work
TTO Transition to Operations
ZVV Zero Voltage Verification
SLAC-I-708-905-023 Page 5 of 9
1 Introduction and Overview SLAC receives power at its Master Substation (MSS) from a PG&E 230kV transmission line via two 230kV/12.47kV stepdown transformers. SLAC identifies that its AC power system encounters power factor issues at the point of connection (POC) with PG&E, where the power factor strays outside the contractual range (0.97 lag to 0.99 lead). This deviation stems from various factors, including reactive power imbalances, capacitive or inductive loads, etc. Consequently, suboptimal power factor conditions can result in increased power losses, reduced system efficiency, and involve potential penalties imposed by PG&E.
To address this challenge, SLAC plans to implement power factor correction measures through the installation of two switched power factor correction (PFC) systems – one on 12.47 kV Bus-1 and another on 12.47kV Bus-2 at the Master Substation (MSS). These PFC units will dynamically improve reactive power flow, compensating for system reactive power demand, and maintaining the overall power factor within the required range. Enhancing power factor correction in this manner will optimize energy utilization, reduce system losses, and ensure continued compliance with PG&E contractual requirements.
2 Purpose Prior to the installation of the new power factor correction equipment, it is necessary to demolish existing buildings (B308 and B311) with equipment inside them to create adequate space within the MSS Yard.
This Statement of Work outlines the scope for the demolition, disassembly, and removal of existing assets, including metal buildings B308 and B311, a non-operational synchronous condenser, and the associated electrical equipment and cabling and wiring serving the condenser. All identified buildings and equipment are located in the SLAC MSS Yard.
The intent of this document is to also provide the Subcontractor with a basic insight into the type and magnitude of the project, safety compliance issues, and technical and project management requirements.
3 Location Perform onsite support work outlined in this SOW at SLAC National Accelerator Laboratory, 2575 Sand Hill Road, Menlo Park, San Mateo County, 94025, California, at the specified location.
SLAC-I-708-905-023 Page 6 of 9
Figure 1. B016 and the Master Substation Yard
4 Scope of Work
1. The Subcontractor shall furnish all labor, materials, tools, equipment, and incidentals necessary to perform and complete the work indicated in this SOW.
2. This SOW defines the intended outcomes of the work, identifies applicable reference standards, and provides relevant technical requirements. All work shall be performed in accordance with applicable industry standards, codes, and SLAC requirements.
3. All work shall be performed within an active substation yard. Subcontractor personnel shall be escorted at all times by a SLAC employee, typically a High Voltage Electrician or a qualified Construction Manager. The subcontractor shall coordinate all activities with the assigned Construction Manager.
4. The Subcontractor shall provide all “temporary construction power” for the execution of the work.
1. ee
B308 & B311
SLAC-I-708-905-023 Page 7 of 9
4.1 System to Remain
A. Existing Ground grid – maintain and preserve the ground grid; any unavoidable impacts shall be coordinated with SLAC in advance.
5 Qualifications
1. Subcontractor shall be capable of successful project outcomes and demonstrate their experience in self-performed work and partnering with sub-tier firms.
2. Subcontractor shall demonstrate key personnel have experience from successful execution of past projects and current relationships with partners.
3. Subcontractor shall demonstrate they and their sub-tiers have experience working in an operational critical facility, such as a main substation.
6 Project Preliminary Schedule for Subcontracted Work
Key Activities Planned Completion Date Procurement Activities
Request for Proposal August 14, 2026 Proposal due September 3, 2026 Evaluations & Reviews September 8, 2026 Final Clarifications and BAFO September 15, 2026 Award PO September 25, 2026 Kick-off 3 days after Award Schedule 3 days after Kick-Off WPC and NTP 10 days after Award
Construction Subcontract Performance Period - 6 weeks October 12 – November 20, 2026 SLAC Inspections Ongoing throughout demolition Close Out November 30, 2026
7 Deliverables
SLAC-I-708-905-023 Page 8 of 9
1. Schedule and Work Planning & Controls
a. Provide a schedule of major work activities
b. Provide work plans for high-risk critical activities
c. Provide Job Hazard Analysis (JHA)
d. Complete Daily Safety Tailgates
2. Execution
a. The Subcontractor shall verify existing conditions prior to the start of work.
b. The Subcontractor shall identify any ambiguity in the drawings and work with SLAC
SMEs to verify existing conditions. These gaps shall be resolved via RFI’s and captured as red-lines on the field drawing set.
c. Work shall be coordinated with the CM and with SLAC HV electricians.
d. A Red-lined drawing set shall be available in the field.
e. Subcontractor is to conduct daily safety tailgate meetings prior to start of work
3. Project Acceptance
a. Perform project close-out inspections and provide documentation as required by the contract.
b. Complete the project close-out punch list provided by SLAC.
4. Demo Disposal Clarifications:
a. Synchronous Condenser’s Weight approximation: 110,000 lbs.
b. The building and equipment materials are to be disassembled into pieces/convenient sizes and separated into SLAC provided bins (for metal, wire, and “breakage”) and removed for salvage by SLAC. GC activities shall be coordinated with the CM and SLAC Salvage.
c. The removed Class II concrete and soil materials are to be placed in SLAC provided bins and disposed of by SLAC. GC activities shall be coordinated with the CM and SLAC Waste Management.
d. Due to the clearance limitations from the 230kV overhead power lines in the MSS yard, large/tall vehicles and cranes cannot be used. A 20’ wide by 11’ high “stay within” limit is defined to maintain the proper distance from the energized components.
References
1. RPC PFC WP1 Drawings
DWG # SHEET # DISCIPLINE TITLE
GENERAL
B016S-G00-0087 G0.0 COVER SHEET
B016S-G00-0088 G0.0 GENERAL NOTES
ELECTRICAL
B016S-E00-0089 E0.0 ELECTRICAL ELECTRICAL SYMBOLS &
ABBREVIATIONS
SLAC-I-708-905-023 Page 9 of 9
B016S-E00-0090 E0.0 ELECTRICAL ELECTRICAL GENERAL NOTES
B016S-E00-0091 E0.1 ELECTRICAL ELECTRICAL LAYOUT PLAN -
DEMOLITION
B016S-E00-0092 E0.7 ELECTRICAL ELECTRICAL PHOTO DETAILS
#1 - DEMOLITION
B016S-E00-0093 E0.7 ELECTRICAL ELECTRICAL PHOTO DETAILS
#2 - DEMOLITION
B016S-E00-0094 E0.7 ELECTRICAL ELECTRICAL ONE-LINE
DIAGRAM #1 - DEMOLITION
B016S-E00-0095 E0.7 ELECTRICAL ELECTRICAL ONE-LINE
DIAGRAM #2 - DEMOLITION
CIVIL/STRUCTURAL
B016S-C01-0096 C0.1 CIVIL CIVIL DEMOLITION PLAN
2. Division 1 and Technical Specifications
3. Division 1
4. Division 26 – Electrical
5. BIO authorized Standards & Codes
6. SLAC ES&H Manual including SLAC Enhanced Rigor Work Planning and Control Procedure, Chapter 2
7. Construction Safety Requirements Manual (SLAC-I-730-0A23L-003-R004)
| 1 Introduction and Overview |
| 2 Purpose |
| 3 Location |
| 4 Scope of Work |
| 4.1 System to Remain |
| 5 Qualifications |
| 6 Project Preliminary Schedule for Subcontracted Work |
| 7 Deliverables |