This is a Section F (Deliveries or Performance) document from SLAC National Accelerator Laboratory's supply chain management records for a federal contract opportunity. The document outlines a single line item for demolition and removal services at the MSS Yard facility.

The base scope of work requires the contractor to perform complete demo and removal of buildings B308 and B311 located at the MSS Yard, including the retired synchronous condenser and all related equipment. Performance is scheduled to commence upon Notice of Award, with project completion required no later than December 2026. The contract document is marked as DRAFT and is based on SLAC-SCM-GEN-032 (Rev. 06/04/12). No pricing information, set-asides, small business requirements, or specific response dates are provided in this deliverables section.

View the file

Other files

File Type Posted
B2_07.2_Subcontractor_Form_IIPP_052121_DRAFT.pdf PDF
B2_08.0_Section_K_(Rep_and_Certs)_DRAFT.pdf PDF
B2_02_Section_B_(Supplies_or_Services_and_Price_Costs)_DRAFT.pdf PDF
B2_00_RFP_Cover_DRAFT.pdf PDF
B2_03.3_SLAC BIO Adopted Codes and Standards (Updated 01012025)_DRAFT.pdf PDF
B2_05.1_Fixed_Price_Construction_March2024_DRAFT.pdf PDF
B2_09.2_Section_L_Attachment_B_SLAC_Question&Answer_Log_(RFI)_DRAFT.pdf PDF
B2_07.5_SubcontractorFormSQF_DRAFT.pdf PDF
B2_10_Section_M_Evaluation_Methodology_DRAFT.pdf PDF
B2_05.0_Section_G_(General_TsCs)_DRAFT.pdf PDF
B2_07.8_Construction_Subcontracts_Final_Release_DRAFT.pdf PDF
B2_07.7_Final_Inspection_Report_DRAFT.pdf PDF
B2_08.1_Reps_and_Certs_Supplement_DRAFT.pdf PDF
B2_07.1_DBA_WD_CA20260018_7.14.26_Mod_06_DRAFT.pdf PDF
B2_07.4_SF1413_DRAFT.pdf PDF
B2_07.3_Work_Classification_Form_367094_DRAFT.pdf PDF
B2_09.0_Section_L_Instruction_to_Offerors_DRAFT.pdf PDF
B2_09.1_Section_L_Attachment_A_Proposal_Breakdown_Sheet_DRAFT.pdf PDF
B2_01_Section_A_(Subcontract_Form)_DRAFT.pdf PDF
B2_03.0_Section_C_(Specifications_SOW)_DRAFT.pdf PDF
B2_03.1_SOW_RPC WP1 Demolition_R3_DRAFT.pdf PDF
B2_07.6_NTP_Submittal_Checklist_061424_DRAFT.pdf PDF
B2_07.0_Section_J_(List_of_Attachments)_DRAFT.pdf PDF
B2_06_Section_H_(Special TsCs)_DRAFT.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLAC NATIONAL ACCELERATOR LABORATORY • 2575 SAND HILL ROAD • MENLO PARK • CALIFORNIA • 94025 • USA

Operated by Stanford University for the U.S. Department of Energy

SECTION F (REV. 06/04/12) SLAC-SCM-GEN-032 PAGE 1 OF 1

SUPPLY CHAIN MANAGEMENT

Section F – Deliveries or Performance

Period of Performance

ITEM

NO.

SUPPLIES/SERVICES FROM TO

Base Scope:

Demo and removal of MSS Yard buildings B308 and B311, retired synchronous condenser, and related equipment.

Notice of

Award

Project completion no later than (NLT) December 2026. DRAFT

File details come from the government source that posted it. Updated .