B09_SA_Amendment_5_Additional_Q_A.pdf

PDF 85 KB Posted

Attached to
The Sugarloaf Multi-use Environmental Resilience R Federal contract opportunity
Solicitation number
140D0425R0119
Issued by
Department of the Interior Departmental Offices Interior Business Center

About this file

This document is an Additional Q&A for Solicitation 140D0425R0055, titled "Fort Cavazos Range Repair," dated 04/08/2025. The Q&A addresses two specific technical questions related to the project: first, the amperage of RLM lights along heating blankets for MATs 2 and 8, which is confirmed to be 5.10 amps for both thermals and lights; second, a clarification that all RLM work on Jack Mountain must be performed during a mandatory shut down. The document provides direct, concise answers to these technical inquiries, which appear to be part of the ongoing solicitation process for a range repair project at Fort Cavazos.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: 140D0425R0055 Project Name: Fort Cavazos Range Repair

Date: 04/08/2025

Additional Q&A

What is the amperage on the RLM lights along the heating blankets for MATs 2 and 8?

ANS: The amp load is 5.10 amps for the thermals and the lights.

Does all the RLM work on Jack Mountain need to be performed during mandatory shut down?

ANS: Yes.