A06_DS_Attachment_02_Water_Points_Map_8-7-2025.pdf

PDF 749 KB Posted

Attached to
The Sugarloaf Multi-use Environmental Resilience R Federal contract opportunity
Solicitation number
140D0425R0119
Issued by
Department of the Interior Departmental Offices Interior Business Center

About this file

This document is an Exhibit O detailing specifications for two water points (FARP West and Hargrove) within a JMMU-designated area. Each water point requires identical infrastructure: 1 well, 1 elevated water tank (5K gallons), and 1 open top tank (34'x12', 80K gallons). Specific construction and installation requirements include:

Key installation details include a 100 GPM industrial well with heated pump house, 30' gates, a windsock with light, 1,000 linear feet of 8-foot wildlife fencing with a lockable gate, and 12-inch cement stabilized road base access around the tanks. Additional notes mandate specific safety measures such as installing a ladder inside the tank that does not extend above tank walls, removing trees within the fenced area, and adding aviation balls to power lines. The document is version updated on 8/6/2025 at 0730, with precise technical specifications for tank dimensions, concrete wall heights, and site preparation requirements.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JMMU

EXHIBIT O – Water Points FARP West Water Point:

1X Well 1X Elevated Water Tank 5K Gallons 1X open top tank 34’x 12’. 80K gallons

Hargrove Water Point:

1X Well 1X Elevated Water Tank 5K Gallons 1X open top tank 34’x 12’. 80K gallons

Elevated 5k gallon water tank

Hargrove Water Point

30’ gates

H 34’ Dia,12’ tall (80K Gallons) Semi buried concrete tank. Wall 48” above ground.

14R PV 15573 56798

Windsock w/ light

Install a new industrial well with minimum 100gpm yield with pump house with heat

Version updated 8/6/2025 @ 0730

NOTE: a ladder to be installed in the tank not to extend above top of tank walls to prevent snagging hazard. Add 2 more AVN Balls towards JMMU. Remove all trees within the fenced area

EX

H

IB

IT

O

W at er P oi nt s

12-inches Cement Stabilized Road Base access around tank

1,000 LF of 8-foot-tall wildlife fencing w/lockable gate. All soil between fence and road base to be cement stabilized

34’ Dia,12’ tall (80K Gallons) Semi buried concrete tank. Wall 48” above ground.

14R PV 18875 67497

12-inches Cement Stabilized Road Base access around tank

FARP West Water Point Elevated 5k gallon water tank

30’ gates

Windsock w/ light

Install New Well 100 GPM flow rate & Pumphouse with heat

NOTE: shore power to pumphouse. Pricing for dominion to install 6x aviation balls on powerline.

Remove all trees within the fenced area. Remove tall tree on berm to the southwest of the tank. a ladder to be installed in the tank not to extend above top of tank walls to prevent snagging hazard.

1,000 LF of 8-foot-tall wildlife fencing w/lockable gate. All soil between fence and road base to be cement stabilized

Version updated 8/6/2025 @ 0730

EXHIBIT O – Water Points