B08-W912PF26RA011_ATT D_BIDSHEET.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Design-Bid-Build (DBB) Repair of Storm Sewer Water and Sanitary Sewer Systems, Caserma Miotto, Longare, Vicenza, Italy.
Solicitation number
W912PF26RA011
Issued by

About this file

This is a Direct Cost Bid Sheet (Attachment D) for a Design-Bid-Build construction solicitation (W912PF26RA011) for repair of storm and sanitary sewer systems at Caserma Miotto in Longare, Vicenza, Italy. Offerors must complete all blue-shaded fields with prices proposed in Euros (EUR).

Part 1 requires offerors to provide direct costs only (labor, materials, equipment) for each definable feature of work without including profit, overhead, or bond costs. The bid sheet covers CLIN 0001 (Base: Storm Water System Repairs including lamination tanks, retaining walls, temporary fencing, TOC, wellpoint system, sewer lines, natural ditch, concrete channel, two lift stations, and first flush system); CLIN 0002 (Base: Sanitary Sewer Lines Repairs); CLIN 0003 (Option 1: Asbestos Water Pipe Removal and Disposal at 100 linear meters across three time periods); CLIN 0004 (Option 2: Reinstallation of Existing Sport Field Synthetic Turf); CLIN 0005 (Option 3: Repair of Landslides Areas); and CLIN 0006 (Option 4: Sedimentation Pond Installation). Part 2 requires unburdened daily rates for four Key Personnel positions—Project Manager, Quality Control Manager, Site Safety & Health Officer, and Site Superintendent—each estimated at 1,010 days. Offerors must then transfer direct costs from Part 1 to the SF 1442 schedule with all applicable indirect costs, overheads, and profit applied for final fully burdened total pricing by CLIN or unit price for CLIN 0003.

View the file

Other files

File Type Posted
B08-W912PF26RA011_ATT11_VINCA_APPROVAL.zip ZIP file
B08-W912PF26RA011_AMD0003_SF30_20260821.pdf PDF
B08-W912PF26RA011_AMD0003_CONFORMED_20260821.pdf PDF
B08-W912PF26RA011_ATT08_THIRD_PARTY_AGENCY_PKGS.zip ZIP file
B08-W912PF26RA011_ATT09_MOU_LICENSES.zip ZIP file
B08-W912PF26RA011_ATT10_MODULO MU19 SIGNED.pdf PDF
B08-W912PF26RA011_AMD0002_SF30_20260819.pdf PDF
B08-W912PF26RA011_ATT03_SOW_SEWER_100.zip ZIP file
B08-W912PF26RA011_AMD0002_CONFORMED_20260819.pdf PDF
B08-W912PF26RA011_ATT01_SOW_REV01_20260818.pdf PDF
B08-W912PF26RA011_ATT07_PPI LOG_20260819.pdf PDF
B08-W912PF26RA011_ATT D_BIDSHEET_REV01.xlsx XLSX spreadsheet
B08-W912PF26RA011_ATT04-05_SOW_STORM_100.zip ZIP file
B08-W912PF26RA011_AMD0001_CONFORMED_20260810.pdf PDF
B08-W912PF26RA011_AMD0001_SF30_20260810.pdf PDF
B08-W912PF26RA011_ATT06_THIRD_PARTY_AGENCY_DOCS.zip ZIP file
B08-W912PF26RA011_ATT07_PPI LOG_20260810.pdf PDF
B08-W912PF26RA011_ATT F_SITE VISIT_PHOTOS.pdf PDF
B08-W912PF26RA011_ATT E_SITE VISIT_ROUTE.pdf PDF
B08-W912PF26RA011_ATT C_PPQ_AMD01.pdf PDF
B08-W912PF26RA011_ATT G_SITE VISIT_ATTENDANCE_Redacted.pdf PDF
B08-W912PF26RA011_ATT B_EXPERIENCE.docx DOCX document
B08-W912PF26RA011_ATT05_SOW_STORM_2.zip ZIP file
B08-W912PF26RA011_ATT02_SOW_GENERAL.zip ZIP file
B08-W912PF26RA011_ATT04_SOW_STORM_1.zip ZIP file
B08-W912PF26RA011_ATT03_SOW_SEWER.zip ZIP file
B08-W912PF26RA011_20260729.pdf PDF
B08-W912PF26RA011_ATT01_SOW_20260629.pdf PDF
B08-W912PF26RA011_ATT C_PPQ.pdf PDF
B08-W912PF26RA011_ATT A_PPI.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Sheet

DBB STORM & SANITARY SEWER REPAIR

CASERMA MIOTTO

W912PF26RA011 ATTACHMENT D

DIRECT COST BID SHEET

OFFEROR NAME:

INSTRUCTIONS TO OFFERORS
1Offerors must complete all blue shaded fields. Prices must be proposed in Euros (€).
2Part 1 Direct Costs: Provide the Direct Cost only (e.g., labor, materials, equipment) for each Definable Feature of Work. Do not include profit, home office overhead, field office overhead, or bond costs in this section.
3Part 2 Key Personnel Rates: Provide the unburdened daily rate for the identified Key Personnel. This rate is evaluated for reasonableness but is not included in the Total Evaluated Price (TEP) for tradeoff purposes.
4SF 1442 Total Pricing: Offerors shall take the direct costs from Part 1, apply all applicable indirect costs, overheads, and profit, and enter the final, fully burdened total price for each CLIN (0001, 0002, 0004-0006) directly onto the SF 1442 schedule. For CLIN 0003 (SLINs 0003AA, 0003AB, 0003AC), enter the fully burdened Unit Price.

PART 1: DIRECT COSTS FOR DEFINABLE FEATURES OF WORK

(Note: Provide Direct Costs ONLY in this section. Do not include overhead or profit)

CLINDescription / Definable Feature of WorkQtyUnitUnit Price (€)Cost Sum (€)
0001BASE: Storm Water System Repairs
Laminiation Tanks and Various Structural Works1JobN/A€ - 0
Retaining Walls and Temporary Perimeter Fence1JobN/A€ - 0
TOC1JobN/A€ - 0
Wellpoint System1JobN/A€ - 0
Storm Sewer Line Site Civil/Mechanical Utilities1JobN/A€ - 0
Natural Ditch1JobN/A€ - 0
Concrete Channel & Motor Pool1JobN/A€ - 0
Lift Station #11JobN/A€ - 0
Lift Station #21JobN/A€ - 0
1st Flush System1JobN/A€ - 0
CLIN 0001 Total Direct Cost€ - 0

0002 BASE: Sanitary Sewer Lines Repairs 1 Job N/A € - 0

0003OPTION #1: Asbestos Water Pipe Removal and Disposal
0003AAAsbestos Removal (if exercised Days 1 - 365)100LM€ - 0
0003ABAsbestos Removal (if exercised Days 366 - 730)100LM€ - 0
0003ACAsbestos Removal (if exercised Days 731 - Completion )100LM€ - 0
CLIN 0003 Total Direct Cost€ - 0
0004OPTION #2: Reinstallation of Existing Sport Field
Synthetic Turf Sportfield1JobN/A€ - 0
Polisportiva Longare Works1JobN/A€ - 0
CLIN 0004 Total Direct Cost€ - 0
0005OPTION #3: Repair of Landslides Areas
Naturalistic Sliding Interventions1JobN/A€ - 0
Landscaping Mitigation Works1JobN/A€ - 0
CLIN 0005 Total Direct Cost€ - 0

0006 OPTION #4: Sedimentation Pond Installation 1 Job N/A € - 0

PART 2: KEY PERSONNEL UNBURDENED DAILY RATES

(Note: These rates must be unburdened base daily rates).

Key Personnel RoleEstimated QtyUnitUnburdened Daily Rate (€)
Project Manager1010Day€ - 0
Quality Control Manager (QCM)1010Day€ - 0
Site Safety & Health Officer (SSHO)1010Day€ - 0
Site Superintendent1010Day€ - 0