This document contains a past performance questionnaire for a contractor bidding on the solicitation for YOSE 229677 to rehabilitate the Tuolumne Meadows Campground. The questionnaire collects information on the contractor's performance on a previous relevant contract, including ratings in quality, schedule, cost control, management, small business subcontracting, and regulatory compliance. References are asked to provide comments supporting ratings, with comments on exceptional, marginal, and unsatisfactory performance being most helpful. The completed questionnaire should be returned by a specified date and time to the contracting officer and contract specialist listed from the National Park Service Denver Service Center.

View the file

Other files

File Type Posted
B09_Amend_0003_ConstructionClause_0003.pdf PDF
B09_Amend_0003_Attach_5B2_PSP_Vol_II_PriceSched_0003.xlsx XLSX spreadsheet
Sol_140P2021R0082_Amd_0003.pdf PDF
B09_Amend_0003_Sol_140P2021R0082_Responses_to_Questions_0003.pdf PDF
B09_Amend_02_Attach_2F_YOSE-229677_Bid_Document_Adjustments_Memo_20100804_0002.pdf PDF
B09_Amend_02_Attach_1C_YOSE-229677_Technical_Bid_Specs_Div_22-27_0002.pdf PDF
B09_Amend_02_Attach_3B_20376009-Rev0-Otak_Tuolumne_Meadows_CG_Geotech-08032021_0002.pdf PDF
B09_Amend_02_Attach_1D_02_YOSE-229677_Technical_Bid_Specs_Div_31-33_0002.pdf PDF
B09_Amend_02_Attach_2E_YOSE-229677_Bid_Docs_Utilities_Volume_3_0002.pdf PDF
B09_Amend_02_Attach_2D_YOSE-229677_Bid_Docs_080321_Structural_Architecture_MEP_Volume_5_0002.pdf PDF
B09_Amend_02_Attach_2B_YOSE-229677_Bid_Docs_Grading_Alignment_Details_Signage_Soil_Prep_Volume_4_0002.pdf PDF
B09_Amend_02_Attach_2A_YOSE-229677_Bid_Docs_Gen_TESC-Demo-Volume_1_0002.pdf PDF
B09_Amend_02_Attach_1A_YOSE-229677_Bid_Specs_Cover_TOC_Div_01_0002.pdf PDF
B09_Amend_0002_Sol_140P2021R0082_AttendLog-Rspns_to_Ques-Extd_RspDate_0002.pdf PDF
B09_Amend_02_Attach_4_WageDetermination_CA20210018_20210723_0002.pdf PDF
B09_Amend_02_Attach_1B_YOSE-229677_Technical_Bid_Specs_Div_02-13_0002.pdf PDF
B09_Amend_02_Attach_2C_YOSE-229677_Bid_Docs_Site-Plans-Volume_2_0002.pdf PDF
Sol_140P2021R0082_Amd_0002.pdf PDF
Attach_2E_YOSE-229677_Construction_Drawings_070121_Utilities_Volume_3_rev_0001.pdf PDF
Sol_140P2021R0082_Amd_0001.pdf PDF
B08_Solit_Attach_2A_YOSE-229677_Construction_Drawings_070121_Gen_TESC-Demo-Volume_1.pdf PDF
B08_Solit_Attach_3A_YOSE_229677_Hazardous_Materials_Report.pdf PDF
Sol_140P2021R0082.pdf PDF
B08_Solit_Attach_5B2_PSP_Vol_II_PriceSched_Draft.xlsx XLSX spreadsheet
B08_Solit_Attach_2E_YOSE-229677_Construction_Drawings_070121_Utilities_Volume_3.pdf PDF
B08_Solit_ConstructionClauseTemplate_REQD.pdf PDF
B08_Solit_Attach_1B_YOSE-229677_Techincal_Specs_Div_31-33.pdf PDF
B08_Solit_Attach_1A_YOSE-229677_Division_01_Specs.pdf PDF
B08_Solit_Attach_2C_YOSE-229677_Construction_Drawings_070121_Site-Plans-Volume_2.pdf PDF
B08_Solit_Attach_2D_YOSE-229677_Construction_Drawings_070121_Structural_Architecture_MEP_Volume_5.pdf PDF
B08_Solit_Attach_5B3_PSP_Vol_II_GenRefs.doc DOC document
B08_Solit_Attach_2B_YOSE-229677_Construction_Drawings_070121_Grading_Alignment_Details_Signage_Soil_Prep_Volume_4.pdf PDF
B08_Solit_Attach_5B1_PSP_Vol_II_SF24-16d_BidBonds.pdf PDF
B08_Solit_Attach_5A1_PSP_Vol_I_ProjExp.docx DOCX document
B08_Solit_Attach_3B_YOSE_229677_Geotechnical_Draft_070121.pdf PDF
B08_Solit_Attach_1C_YOSE-229677_Technical_Specs_Div_02-13.pdf PDF
A16_JOFOC_BrandName_YOSE_229677_Over150k_REQD.pdf PDF
B08_Solit_Attach_4_Wage_Determination_CA20200018_070821.pdf PDF
B08_Solit_Attach_5B4_PSP_Vol_II_SubKPlanForm.doc DOC document
B08_Solit_Attach_1D_YOSE-229677_Technical_Specs_Div_22-27.pdf PDF
B08_Solit_Attach_5A_PSP_Cover.rtf RTF text file
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS: Offeror to complete Sections A and B and transmit questionnaire to reference.

Reference to complete Sections C and D and transmit back to Contracting Officer listed in section E.

A. CONTRACTOR INFORMATION

Company Name

Street Address

City

State

Zip Code

DUNS Number

Point of Contact

B. CONTRACT INFORMATION

Project Title

Contract Number

Contract Type

Awarded Contract Price

Current / Final Price

Contract Award Date

Contract Completion Date

Period of Performance

Project Location

Client / Owner

Brief description of the contract & work effort:

C. REFERENCE:

Name

Position / Title

Organization

Phone Number

Email Address

Signature

Date

D. EVALUATION

Rating
Definition
Exceptional
Performance met contractual requirements and exceeded many to the owner’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance met contractual requirements and exceeded some to the owner’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance met contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance did not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Evaluation Area
Rating

Quality

Quality of workmanship (including subcontractors)?
Choose an item.
Quality of and adherence to quality control plan?
Choose an item.
Quality of informational and technical submittals?
Choose an item.
Overall Quality Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Schedule (& Time Management)

Met project schedule milestones?
Choose an item.
Responded to owner requests in a timely manner?
Choose an item.
Informational and technical submittals submitted timely?
Choose an item.
Promptly addressed scheduling issues?
Choose an item.
Overall Schedule (& Time Management) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Cost Control

Addressed differing & unforeseen site conditions so as to minimize additional costs?
Choose an item.
Provided fair and reasonable pricing for contract modifications?
Choose an item.
Submitted accurate and complete invoices?
Choose an item.
Promptly paid subcontractors and suppliers?
Choose an item.
Overall Cost Control Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Management

General oversight by project manager and superintendent?
Choose an item.
Coordination with and control of subcontractors?
Choose an item.
Avoidance of accidents & safety violations?
Choose an item.
Addressed location factors (especially remote locations)?
Choose an item.
Maintained good working relationship with owner representatives?
Choose an item.
Demonstrated flexibility, innovativeness and cooperation in resolving potential problems?
Choose an item.
Overall Management Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Small Business Subcontracting (& Labor Standards)

Met regulatory and contractual labor standards?
Choose an item.
Successfully contracted with small and socio-economically disadvantaged businesses?
Choose an item.
Quality and adherence to applicable subcontracting plans?
Choose an item.
Overall Small Business Subcontracting (& Labor Standards) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of excellent, marginal, & unsatisfactory are especially helpful.):

Regulatory Compliance

Met building and life safety codes?
Choose an item.
Overall Regulatory Compliance Rating
Choose an item.
Overall Recommendation:
Given what I know today about the contractor's ability to perform in accordance with the contract’s most significant requirements, I would recommend them for similar contracts:
Choose an item.
Overall Comments:

E. RETURN:

Return by
Time / Date
eMail Subject Description
YOSE 229677 – Rehab Tuolumne Meadows Campground-PPQ Submission
Name
CO: Natasha DiPietro / CS: Kevin Ralston
Title
Contracting Officer / Contract Specialist
Organization
National Park Service – Denver Service Center