This memorandum outlines adjustments made to construction bid documents for the Rehabilitate the Tuolumne Meadows Campground project. Numerous campsite layouts and amenities were modified to accommodate existing site conditions like trees and topography. Trail alignments were updated based on GPS data. Signage and civil features like parking and drainage were also adjusted. Specification sections and details were revised based on a final geotechnical report. The solicitation seeks bids to rehabilitate the Tuolumne Meadows Campground in Yosemite National Park to enhance the visitor experience. The National Park Service is the contracting agency. The deadline to submit bids in response to solicitation number 140P2021R0082 was not provided.

View the file

Other files

File Type Posted
B09_Amend_0003_ConstructionClause_0003.pdf PDF
B09_Amend_0003_Attach_5B2_PSP_Vol_II_PriceSched_0003.xlsx XLSX spreadsheet
Sol_140P2021R0082_Amd_0003.pdf PDF
B09_Amend_0003_Sol_140P2021R0082_Responses_to_Questions_0003.pdf PDF
B09_Amend_02_Attach_1C_YOSE-229677_Technical_Bid_Specs_Div_22-27_0002.pdf PDF
B09_Amend_02_Attach_3B_20376009-Rev0-Otak_Tuolumne_Meadows_CG_Geotech-08032021_0002.pdf PDF
B09_Amend_02_Attach_1D_02_YOSE-229677_Technical_Bid_Specs_Div_31-33_0002.pdf PDF
B09_Amend_02_Attach_2E_YOSE-229677_Bid_Docs_Utilities_Volume_3_0002.pdf PDF
B09_Amend_02_Attach_2D_YOSE-229677_Bid_Docs_080321_Structural_Architecture_MEP_Volume_5_0002.pdf PDF
B09_Amend_02_Attach_2B_YOSE-229677_Bid_Docs_Grading_Alignment_Details_Signage_Soil_Prep_Volume_4_0002.pdf PDF
B09_Amend_02_Attach_2A_YOSE-229677_Bid_Docs_Gen_TESC-Demo-Volume_1_0002.pdf PDF
B09_Amend_02_Attach_1A_YOSE-229677_Bid_Specs_Cover_TOC_Div_01_0002.pdf PDF
B09_Amend_0002_Sol_140P2021R0082_AttendLog-Rspns_to_Ques-Extd_RspDate_0002.pdf PDF
B09_Amend_02_Attach_4_WageDetermination_CA20210018_20210723_0002.pdf PDF
B09_Amend_02_Attach_1B_YOSE-229677_Technical_Bid_Specs_Div_02-13_0002.pdf PDF
B09_Amend_02_Attach_2C_YOSE-229677_Bid_Docs_Site-Plans-Volume_2_0002.pdf PDF
Sol_140P2021R0082_Amd_0002.pdf PDF
Attach_2E_YOSE-229677_Construction_Drawings_070121_Utilities_Volume_3_rev_0001.pdf PDF
Sol_140P2021R0082_Amd_0001.pdf PDF
B08_Solit_Attach_2A_YOSE-229677_Construction_Drawings_070121_Gen_TESC-Demo-Volume_1.pdf PDF
B08_Solit_Attach_3A_YOSE_229677_Hazardous_Materials_Report.pdf PDF
Sol_140P2021R0082.pdf PDF
B08_Solit_Attach_5B2_PSP_Vol_II_PriceSched_Draft.xlsx XLSX spreadsheet
B08_Solit_Attach_2E_YOSE-229677_Construction_Drawings_070121_Utilities_Volume_3.pdf PDF
B08_Solit_ConstructionClauseTemplate_REQD.pdf PDF
B08_Solit_Attach_1B_YOSE-229677_Techincal_Specs_Div_31-33.pdf PDF
B08_Solit_Attach_1A_YOSE-229677_Division_01_Specs.pdf PDF
B08_Solit_Attach_2C_YOSE-229677_Construction_Drawings_070121_Site-Plans-Volume_2.pdf PDF
B08_Solit_Attach_2D_YOSE-229677_Construction_Drawings_070121_Structural_Architecture_MEP_Volume_5.pdf PDF
B08_Solit_Attach_5B3_PSP_Vol_II_GenRefs.doc DOC document
B08_Solit_Attach_2B_YOSE-229677_Construction_Drawings_070121_Grading_Alignment_Details_Signage_Soil_Prep_Volume_4.pdf PDF
B08_Solit_Attach_5B1_PSP_Vol_II_SF24-16d_BidBonds.pdf PDF
B08_Solit_Attach_5A1_PSP_Vol_I_ProjExp.docx DOCX document
B08_Solit_Attach_3B_YOSE_229677_Geotechnical_Draft_070121.pdf PDF
B08_Solit_Attach_1C_YOSE-229677_Technical_Specs_Div_02-13.pdf PDF
A16_JOFOC_BrandName_YOSE_229677_Over150k_REQD.pdf PDF
B08_Solit_Attach_5A2_PSP_Vol_I_PastPerf.docx DOCX document
B08_Solit_Attach_4_Wage_Determination_CA20200018_070821.pdf PDF
B08_Solit_Attach_5B4_PSP_Vol_II_SubKPlanForm.doc DOC document
B08_Solit_Attach_1D_YOSE-229677_Technical_Specs_Div_22-27.pdf PDF
B08_Solit_Attach_5A_PSP_Cover.rtf RTF text file
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

n:\cs\contract\yose\140p2021r0082 - yose 229677 - tuolumme meadows campground\amend 2 docs\yose-229677 bid document adjustments memo_21_0804.docx

Memorandum

To: Rehabilitate the Tuolumne Meadows Campground Project Team

From: Keith Bates, Otak, Inc.

Copies: Project Team

Date: August 4, 2021

Subject: Construction Document Package Adjustments

Project No.: YOSE 229677

This memorandum is a general list of adjustments made to the Tuolumne Meadows Rehabilitation project bid documents since the project was initially advertised. This list may not include all items that may have been modified within the bid document package.

Many of the campsite adjustments were made to accommodate existing site conditions (primarily trees/boulders). In addition, after seeing the drainage patterns during the heavy storm, campsite amenity locations were adjusted within the proposed campsite areas. There were also a few campsites where the amenities were rearranged to preserve existing views of the surrounding natural environment.

LOOP A

Removed site A42 (existing A57) and reconfigured site A44 (existing A59) due to existing topography constraints and new Loop A alignment

Made A46 (existing A73) an accessible site Moved parking spur for A47 (existing A69) due to existing constraints and adjusted from ABA to standard site Removed A70 (new BP site next to existing A75) due to existing natural resource and added a new BP campsite between A58 and A61 (existing A84) Adjusted furnishing layout for existing sites A6, A10, A11, A13, A17, A19, A37, A41, A46, A55, A56, A58, A61, A62, A68, & A78 - Campsite area adjustments due to existing conditions.

• Note: Loop A campsites have been renumbered and therefore new campsite numbers have changed. Therefore, all new campsite numbers listed here may differ from the newly submitted plans but existing numbers remain the same.

LOOP H

Adjusted south walk-in sites due to existing conditions and to reduce potential tree removal Adjusted sites H1-H6 due to Loop H drive realignment

Subject Click here to enter a date n:\cs\contract\yose\140p2021r0082 - yose 229677 - tuolumme meadows campground\amend 2 docs\yose-229677 bid document adjustments

LOOP B

Adjusted layout of site B21 due to existing boulders Changed existing sites B47-B49 to ‘Significant Fill’

LOOP C

Adjusted layout of site C14 (existing C10) due to existing conditions Changed existing site C62 to ‘Significant Cut’ Changed existing site C65 to ‘Grading Modifications’

GROUP CAMP

Moved Group Campsite F to existing location

LOOP D

Adjusted proposed layout of sites D9, D8, D13, & D14 due to existing conditions Changed existing site D3 ‘Grading Modifications’

LOOP E

Changed E5 to ‘Grading Modifications’ Realigned access drive for sites E15-E18 to match existing Adjusted layout of site E8 due to boulders Adjusted sites E11, E16, & E18 due to existing feature conflicts

LOOP F

Adjusted furnishing and stair layouts of existing sites F5 - Campsite area adjustments due to existing conditions.

Relocated accessible parking at Mission 66 RR 3078 and show site F10 as ‘Grading Modifications’

LOOP G

Updated campsite numbering to match existing locations and numbers Changed sites G5, G11 and G22 to ‘Significant Cut’

Adjusted furnishing layouts of existing sites G9, G13, G15, and G16 - Campsite area adjustments due to existing conditions.

Adjusted parking spur alignments of existing sites G10 and G17 due to existing topographic conditions and tree locations n:\cs\contract\yose\140p2021r0082 - yose 229677 - tuolumme meadows campground\amend 2 docs\yose-229677 bid document adjustments

ABA Sites

Added and reconfigured accessible campsite surface areas

Trail Adjustments

GPS tracking of the existing trails led to new decisions on existing trails to keep and improve as well as more accurate alignments for all trails shown in the plans. Some trails were removed to eliminate duplication of circulation and maintain the integrity of the campsite

Removed Loop D accessible trail Removed Loop B crushed rock trail Updated alignment of shore front trail (compacted earth) Updated alignment of accessible trail from Loop A to Danah Campfire (crushed rock with binder) Updated alignment of trail from Dana Campfire to Loop H walk-ins (compacted earth) Updated alignment of trail from Dana Campfire to Group Camp (compacted earth) Updated alignment of trail from registration office to current construction staging area

(compacted earth) Updated alignment of trail from Loop B to Group Camp (compacted earth)

Signage

• Added signs to be relocated as a separate table on the sign inventory table

• Relocated/added information signs:

o Info board by kiosk o Info board by restroom #3022 – move closer to path o ‘Danah Campfire Circle / Elizabeth Lake’ sign by kiosk

Added note to inventory sheet (C9.14) “New sign #2 and relocated sign RL-3 shall be installed on the same post” o Info board by restroom #3076 o Backpackers Camp Info Boards o Info boards at all other existing restrooms o Added MUTCD signs that were already on the base to the inventory and gave them a number (one-way and do not enter signs) o Added parking signs for group camp campsite’s designated parking areas o Added ‘One Way’ and ‘Do Not Enter’ signs to sites A9 – A13 loop

Civil - Site

• Added stop lines and “STOP” lettering, and additional pavement marking arrows at kiosk to align with current pavement markings

• Removed stop sign near kiosk

• Added removable bollards at old Loop A road alignment (multiple locations) o Reference plans in hands notes - sheet C2.14 n:\cs\contract\yose\140p2021r0082 - yose 229677 - tuolumme meadows campground\amend 2 docs\yose-229677 bid document adjustments

• Included accessible parking stall across from Kiosk

• Showed new pavement where we are removing existing kiosk / at grading limits

• Shifted parking at restroom #3022 to avoid manhole

• Shifted parking for restroom #3077 so parking shares an edge with the existing sidewalk

• Loop H Drive Realignment at intersection with Loop A Drive

• Adjusted parking and circulation at Group Camp to save existing trees

• Rotated dumpsters so a garbage truck can more easily access

• Added dumpster location improvements to existing dumpster location in Loop C.

• Added dumpster location improvements to existing dumpster location between Loop E and Loop

F.

Utilities

• Shifted water spigot at restroom #3022 to avoid tree

• Revised spigot location at site D21 to improve access

• Provided culvert extension near site B32-B34

• Revised spigot location across from site E11 – move to north / west side of road [bollard not needed]

• Revised spigot location between sites E6-E18 due to existing site conditions

• Removed existing culvert near site F1 – label on demo plans

• Relocated spigot at Dana Campfire to be south of trail for improved access

• Added Culvert 15 extensions (between sites B30 and B34)

• Added water appurtenance callouts for water spigot at restroom #3024

• Added water appurtenance callouts for water spigot at Bid Option 1: Loop H new restroom

• Added water appurtenance callouts for water spigot at Bid Option 2: Group Camp new restroom

• Added sizes of existing water lines at water tie-in locations

• Revised callouts from crosses to tees on sheets C4.12 and C4.15

• Revised size of water tees on sheets C4.8, C4.13, C4.16, C4.21, C4.24

• Revised quantity of gate valves on sheet C4.17

Other

• Added landscape edging by Danah Campfire along compacted earth trail

• Added detail for curb ramp

• Added “DO NOT BLOCK” sign to gate detail

• Adjusted and added minor elements to the pre-manufactured building details on sheets C8.9-

C8.12

• Revised depth of pavement section on Detail 1, sheet C8.1 to 4” HMA over 5” Class 2 aggregate base per final geotechnical report recommendation.

• Gauge of insulated locator wire on Detail 6, sheet C8.2 n:\cs\contract\yose\140p2021r0082 - yose 229677 - tuolumme meadows campground\amend 2 docs\yose-229677 bid document adjustments

• Revised depth of pipe bedding under and above pipe in Detail 1, sheet C8.2 per final geotechnical report recommendation.

Final Geotechnical Report is now included in the Project Specifications appendix.

Project Specifications:

Modifications to the Project Specification sections, may include but are not limited to:

• Division 01 - 01 10 00, 01 57 23, 01 74 19, Submittal List, Closeout-Operations & Maintenance Form

• 13 34 23

• 32 15 00

• 32 15 43

• 32 17 00