This is a solicitation for a construction project to rehabilitate the Tuolumne Meadows Campground in Yosemite National Park to enhance the visitor experience. The scope of work includes removing and disposing of asbestos-containing materials, lead-based paint, and other lead-containing materials. It also involves removing tiles, wainscoting, and windows; setting aside window glass for reinstallation; and rehabilitating utilities and restrooms. The contractor must comply with EPA, OSHA, and other regulations for hazardous materials abatement and lead safety. Submittals, work plans, monitoring, training, and disposal documentation are required.

View the file

Other files

File Type Posted
B09_Amend_0003_ConstructionClause_0003.pdf PDF
B09_Amend_0003_Attach_5B2_PSP_Vol_II_PriceSched_0003.xlsx XLSX spreadsheet
Sol_140P2021R0082_Amd_0003.pdf PDF
B09_Amend_0003_Sol_140P2021R0082_Responses_to_Questions_0003.pdf PDF
B09_Amend_02_Attach_2F_YOSE-229677_Bid_Document_Adjustments_Memo_20100804_0002.pdf PDF
B09_Amend_02_Attach_1C_YOSE-229677_Technical_Bid_Specs_Div_22-27_0002.pdf PDF
B09_Amend_02_Attach_3B_20376009-Rev0-Otak_Tuolumne_Meadows_CG_Geotech-08032021_0002.pdf PDF
B09_Amend_02_Attach_1D_02_YOSE-229677_Technical_Bid_Specs_Div_31-33_0002.pdf PDF
B09_Amend_02_Attach_2E_YOSE-229677_Bid_Docs_Utilities_Volume_3_0002.pdf PDF
B09_Amend_02_Attach_2D_YOSE-229677_Bid_Docs_080321_Structural_Architecture_MEP_Volume_5_0002.pdf PDF
B09_Amend_02_Attach_2B_YOSE-229677_Bid_Docs_Grading_Alignment_Details_Signage_Soil_Prep_Volume_4_0002.pdf PDF
B09_Amend_02_Attach_2A_YOSE-229677_Bid_Docs_Gen_TESC-Demo-Volume_1_0002.pdf PDF
B09_Amend_02_Attach_1A_YOSE-229677_Bid_Specs_Cover_TOC_Div_01_0002.pdf PDF
B09_Amend_0002_Sol_140P2021R0082_AttendLog-Rspns_to_Ques-Extd_RspDate_0002.pdf PDF
B09_Amend_02_Attach_4_WageDetermination_CA20210018_20210723_0002.pdf PDF
B09_Amend_02_Attach_2C_YOSE-229677_Bid_Docs_Site-Plans-Volume_2_0002.pdf PDF
Sol_140P2021R0082_Amd_0002.pdf PDF
Attach_2E_YOSE-229677_Construction_Drawings_070121_Utilities_Volume_3_rev_0001.pdf PDF
Sol_140P2021R0082_Amd_0001.pdf PDF
B08_Solit_Attach_2A_YOSE-229677_Construction_Drawings_070121_Gen_TESC-Demo-Volume_1.pdf PDF
B08_Solit_Attach_3A_YOSE_229677_Hazardous_Materials_Report.pdf PDF
Sol_140P2021R0082.pdf PDF
B08_Solit_Attach_5B2_PSP_Vol_II_PriceSched_Draft.xlsx XLSX spreadsheet
B08_Solit_Attach_2E_YOSE-229677_Construction_Drawings_070121_Utilities_Volume_3.pdf PDF
B08_Solit_ConstructionClauseTemplate_REQD.pdf PDF
B08_Solit_Attach_1B_YOSE-229677_Techincal_Specs_Div_31-33.pdf PDF
B08_Solit_Attach_1A_YOSE-229677_Division_01_Specs.pdf PDF
B08_Solit_Attach_2C_YOSE-229677_Construction_Drawings_070121_Site-Plans-Volume_2.pdf PDF
B08_Solit_Attach_2D_YOSE-229677_Construction_Drawings_070121_Structural_Architecture_MEP_Volume_5.pdf PDF
B08_Solit_Attach_5B3_PSP_Vol_II_GenRefs.doc DOC document
B08_Solit_Attach_2B_YOSE-229677_Construction_Drawings_070121_Grading_Alignment_Details_Signage_Soil_Prep_Volume_4.pdf PDF
B08_Solit_Attach_5B1_PSP_Vol_II_SF24-16d_BidBonds.pdf PDF
B08_Solit_Attach_5A1_PSP_Vol_I_ProjExp.docx DOCX document
B08_Solit_Attach_3B_YOSE_229677_Geotechnical_Draft_070121.pdf PDF
B08_Solit_Attach_1C_YOSE-229677_Technical_Specs_Div_02-13.pdf PDF
A16_JOFOC_BrandName_YOSE_229677_Over150k_REQD.pdf PDF
B08_Solit_Attach_5A2_PSP_Vol_I_PastPerf.docx DOCX document
B08_Solit_Attach_4_Wage_Determination_CA20200018_070821.pdf PDF
B08_Solit_Attach_5B4_PSP_Vol_II_SubKPlanForm.doc DOC document
B08_Solit_Attach_1D_YOSE-229677_Technical_Specs_Div_22-27.pdf PDF
B08_Solit_Attach_5A_PSP_Cover.rtf RTF text file
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YOSE - 229677 02 41 13 - 1

6/2/21 SITE SELECTIVE

DEMOLITION

SECTION 02 41 13 – SITE SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Sawcutting and removal or recycling of existing asphalt concrete pavement.

2. Sawcutting and removal or recycling of existing cement concrete walkways.

3. Abandonment of existing water lines.

4. Removal and salvage of existing site features to include:

a. Gravel roadway material

b. Gravel campsite material

c. Boulders

d. Dumpsters

e. Campsite ID signs

f. Stone paving at restrooms

g. Riprap

5. Demolition, removal, and disposal of the following items:

a. Traffic signs

b. Picnic tables

c. Fire rings

d. Food storage lockers

e. Kiosk

f. Information board

g. Water spigots

h. Culvert

i. Sewer and water utilities

j. Benches at Dana Campfire Circle

k. Pedestrian railing at Dana Campfire Circle

B. Related Sections include the following:

1. Section 01 57 23 – Temporary Storm Water Pollution Prevention

2. Section 31 10 00 – Site Clearing

3. Section 31 20 00 – Earth Moving

4. Section 31 25 00 – Erosion and Sediment Controls

1.2 DEFINITIONS

A. Remove: Remove and legally dispose of items except those indicated by the Contracting Officer (CO) to be salvaged, reused, reinstalled, or to remain on Park property in a location approved of by the CO.

YOSE - 229677 02 41 13 - 2

DEMOLITION

B. Remove and Store for Reinstallation: Remove items indicated; clean, service, and otherwise prepare items for reuse; store and protect against damage. Reinstall items in locations indicated in the plans and specifications or as directed by the CO.

C. Existing to Remain: Protect items identified to remain against damage and soiling during demolition. When permitted by the CO, items may be removed to a suitable, protected storage location during demolition and then cleaned and reinstalled in their original locations.

D. Abandon: Abandon items indicated. Leave items in place and abandon as specified.

1.3 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, salvaged, or otherwise indicated to remain on the Park property, demolished materials shall become the Contractor’s property and shall be removed and legally disposed of at the Contractor’s expense.

B. Materials for removal and reinstallation:

1. The following materials shall be removed, cleaned, and prepared for reinstallation at the project site as indicated in the plans and specifications.

a. Gravel roadway material

b. Gravel campsite material

c. Boulders

d. Dumpsters

e. Stone paving at restrooms

f. Riprap

C. Materials to remove and provide to Park:

1. The following materials shall be removed, cleaned, and provided to the Park.

a. Campsite ID signs

D. Materials for removal and disposal:

1. The following materials shall be removed from the site and legally disposed of.

a. Traffic signs

b. Picnic tables

c. Fire rings

d. Food storage lockers

e. Kiosk

f. Information board

g. Water spigots

h. Culvert

i. Sewer and water utilities

j. Benches at Dana Campfire Circle

k. Pedestrian railing at Dana Campfire Circle

YOSE - 229677 02 41 13 - 3

DEMOLITION

1.4 QUALITY ASSURANCE

A. Comply with the local noise ordinances regarding hours of operations and allowable noise levels.

Monitor vibrations generated by the demolition activities and received by the existing structures in the immediate vicinity of the project.

1.5 SCHEDULING

A. Notify the Contracting Officer 48 hours prior to beginning demolition work.

B. Contractor shall coordinate underground utility location prior to beginning demolition work.

Contractor is responsible for verifying location of underground utilities.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 UTILITY SERVICES

A. Utility requirements: Locate, identify, disconnect, and seal or cap off indicated utility services where indicated.

1. Arrange to shut off indicated utilities with utility companies.

3.2 PREPARATION

A. Install erosion and sediment control measures, as specified in Section 31 25 00 – Erosion and Sediment Controls, prior to demolition.

B. Install site protection fencing, as specified in Section 01 50 00 – Temporary Facilities & Controls, prior to demolition.

C. Conduct demolition operations and remove debris to ensure minimum interference with roads, driveways, and other adjacent occupied and used facilities.

1. Do not close or obstruct roads, or other adjacent occupied or used facilities without permission from the CO and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways.

D. Conduct demolition operations to prevent injury to people and damage to facilities to remain.

Ensure safe passage of people around demolition area.

1. Erect temporary protection, such as walks, fences, and railings, where required by Contracting Officer.

2. Protect existing improvements, appurtenances, and landscaping to remain.

YOSE - 229677 02 41 13 - 4

DEMOLITION

3. Erect protective fencing around drip line of individual trees or around perimeter drip line of groups of trees to remain according to requirements specified in Section 31 10 00 – Site Clearing.

4. A vertical sawcut shall be made between any existing pavement that is to remain and the portion to be removed. Where sawcutting is required, the sawcut shall be a minimum of 3 inches deep. When the existing pavement is more than 3 inches thick, the portion below 3 inches may be broken after the sawcut is made.

3.3 POLLUTION CONTROLS

A. Use water mist, temporary enclosures, and other suitable methods to limit the spread of dust and dirt. Comply with governing environmental protection regulations.

1. Do not create hazardous or objectionable conditions, such as ice, flooding, and pollution, when using water.

2. The Contractor shall be responsible for ensuring that special precautions are undertaken during sawcutting operations. No concrete (asphalt or cement) or concrete by-products are to be discharged into any storm drain or surface water. Sawcutting operations will increase the pH of water, therefore filtering is not acceptable.

B. Remove and transport debris in a manner that will prevent spillage on site improvements or public roads.

3.4 DEMOLITION

A. Filling Below-Grade Areas: Completely fill below-grade areas and voids resulting from demolition of existing surfaces and construction shown on the plans with soil materials according to requirements specified in Section 31 20 00 – Earth Moving.

B. Damages: Promptly repair damage to adjacent facilities caused by demolition operations.

3.5 ABANDONED WATER LINES

A. Abandoned water mains shall be plugged and sealed watertight by means of a ductile iron plug or cap, or by permanently sealing with a minimum of 8-inch thick bulkhead constructed of Class B or a commercial mix concrete.

B. The concrete cover shall provide a minimum of 6 inches cover around the outside of the pipe and shall extend a minimum of 6 inches in each direction from the end of the pipe.

C. All existing valves that will have pressure on one side and an abandoned main on the other side shall be closed with a ductile iron plug and blocked with reaction backing on the side where the main has been abandoned.

D. A portion of the abandoned pipe shall be removed to allow clearance for plugging and backing.

YOSE - 229677 02 41 13 - 5

DEMOLITION

3.6 DISPOSAL AND RECYCLING OF DEMOLISHED MATERIALS

A. Promptly dispose of or recycle demolished materials: If recycling requires additional time to accomplish, provide for orderly storage of materials. Comply with the waste management requirements in Division 01.

B. Transport demolished materials off Park property and legally dispose or recycle material.

END OF SECTION 02 41 13

YOSE - 229677 02 41 19 - 1

SELECTIVE DEMOLITION

SECTION 02 41 19 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Salvage of existing items to be reused or recycled.

B. Related Requirements:

1. Section 017329 "Cutting and Patching" for cutting and patching procedures.

2. Section 02 42 96 - Historic Removal and Dismantling

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner, including plaques, items from era of original construction (bottles, etc.).

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.3 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site and review all building types .

1. Inspect and discuss condition of construction to be selectively demolished.

2. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

3. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

4. Review areas where existing construction is to remain and requires protection.

1.4 INFORMATIONAL SUBMITTALS

A. Predemolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by salvage and demolition operations. Comply with Section 01 32 33 "Photographic Documentation." Submit before Work begins.

YOSE - 229677 02 41 19 - 2

1.5 FIELD CONDITIONS

A. Notify CO of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

B. Hazardous Materials: Present in buildings and structures to be selectively demolished. Hazardous materials specifications address all hazardous materials which were found to be present. A report on the presence of hazardous materials is included in the spec Appendix for review and use.

Examine hazardous material specifications and report to become aware of locations where hazardous materials are present.

1. Do not disturb hazardous materials or items suspected of containing hazardous materials except under procedures specified elsewhere in the Contract Documents.

C. Historic Areas: Demolition and hauling equipment and other materials shall be of sizes that clear surfaces within historic spaces, areas, rooms, and openings, including temporary protection, by

12 inches or more.

1. Refer to 02 42 96 Historic Removal and Dismantling for removal and salvage of historic materials.

D. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

B. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs or video .

1. Inventory and record the condition of items to be removed and salvaged.

2. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

YOSE - 229677 02 41 19 - 3

3.2 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping.

Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

4. Dispose of demolished items and materials promptly. Comply with requirements in

Section 01 74 19 "Construction Waste Management and Disposal."

B. Work in Historic Areas: Selective demolition shall be done in a manner to protect existing to remain historic finishes, elements and fixtures.

C. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

3.3 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete with reinforcement: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete without reinforcement: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

C. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.

D. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

3.4 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site

YOSE - 229677 02 41 19 - 4

1. Do not allow demolished materials to accumulate on-site.

2. Comply with requirements specified in Section 01 74 19 "Construction Waste

Management and Disposal."

END OF SECTION 02 41 19

YOSE - 229677 02 42 96 - 1

HISTORIC REMOVAL AND

DISMANTLING

SECTION 02 42 96 - HISTORIC REMOVAL AND DISMANTLING

1.1 SUMMARY

A. Section Includes:

1. Historic treatment procedures for removal and dismantling work for designated historic spaces, areas, rooms, and surfaces and the following specific work:

a. Removal and dismantling of indicated portions of building or structure and debris hauling.

b. Salvage of existing items to be reused.

B. Related Requirements:

1. Section 01 35 91 "Historic Treatment Procedures" for general historic treatment requirements.

1.2 PRECONSTRUCTION MEETINGS

A. Preconstruction Conference(s): Conduct conference(s) at Project site for each building type. .

1. Review minutes of Preliminary Historic Treatment Conference that pertain to removal and dismantling procedures and protection of historic areas and surfaces.

2. Review list of items indicated to be salvaged.

3. Verify qualifications of personnel assigned to perform removal and dismantling.

4. Inspect and discuss condition of each construction type to be removed or dismantled.

5. Review requirements of other work that depends on condition of substrates exposed by removal and dismantling work.

6. Review methods and procedures related to removal and dismantling work, including, but not limited to, the following:

a. Historic removal and dismantling specialist's personnel, equipment, and facilities needed to make progress and avoid delays.

b. Materials, material application, sequencing, tolerances, and required clearances.

c. Fire prevention.

1.3 INFORMATIONAL SUBMITTALS

A. List of Items Indicated To Be Salvaged: Prepare a list of items indicated on Drawings to be salvaged for Owner's use or for reinstallation. Submit 15 days before preconstruction conference.

B. Inventory of Salvaged Items: After removal or dismantling Work is complete, submit a list of items that have been salvaged.

YOSE - 229677 02 42 96 - 2

1. Include item description, item condition, number of items if more than one of a type, and tag number. Include photo of item in original location.

2. As work proceeds, include on the inventory items that were indicated to be salvaged and items of historic importance discovered during the work. Document reasons, if any, why an item indicated to be salvaged was not salvaged.

1.4 QUALITY ASSURANCE

A. Removal and Dismantling Historic Treatment Program: Prepare a written, detailed description of materials, methods, equipment, and sequence of operations to be used for each phase of removal and dismantling work, including protection of surrounding and substrate materials and Project site.

1.5 MOCKUPS

A. Prepare mockups of specific historic removal and dismantling procedures specified in this Section to demonstrate aesthetic effects and to set quality standards for materials and execution.

1. Typical Removal Work, Large-Scale Mockups: As indicated on Drawings, remove typical tile flooring and FRP wainscot in Building A or C and roofing and beams in Building E, F, G or H.

2. Approval of mockups does not constitute approval of deviations from the Contract

Documents contained in mockups unless CO specifically approves such deviations in writing.

1.6 FIELD CONDITIONS

A. Notify CO of discrepancies between existing conditions and Drawings before proceeding with removal and dismantling work.

B. Hazardous Materials:

1. Hazardous materials are present in construction affected by removal and dismantling work.

Examine hazardous materials specification sections and the hazardous material report in the specification appendix to become aware of locations where hazardous materials are present.

a. Hazardous material work to be completed as specified in Section 028101 Offsite

Transportation and Disposal, Section 028213 Asbestos Abatement, Section 028313

Removal and Disposal of Materials Containing Lead, and Section 108119 Rodent

Control. .

b. Do not disturb hazardous materials or items suspected of containing hazardous materials, except under procedures specified in hazardous materials specification sections.

c. If unanticipated asbestos is suspected, stop work in the area of potential hazard, shut off fans and other air handlers ventilating the area, and rope off area until the questionable material is identified. Resume work in the area of concern after safe working conditions are verified.

YOSE - 229677 02 42 96 - 3

C. Storage or sale of removed or dismantled items on-site is not permitted unless otherwise indicated.

PART 2 - PRODUCTS - (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Preparation for Removal and Dismantling: Examine construction to be removed or dismantled to determine best methods to safely and effectively perform removal and dismantling work.

Examine adjacent work to determine what protective measures are necessary. Make explorations, probes, and inquiries as necessary to determine condition of construction to be removed or dismantled and location of utilities and services to remain that may be hidden by construction that is to be removed or dismantled.

1. Verify that affected utilities are disconnected and capped.

2. Inventory and record the condition of items to be removed and dismantled for reinstallation or salvage. Enter this information on the inventory of salvaged items.

3. Before removal or dismantling of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

B. Perform surveys as the Work progresses to detect hazards resulting from historic removal and dismantling procedures.

3.2 HISTORIC REMOVAL AND DISMANTLING

A. General: Have removal and dismantling work performed by a qualified historic removal and dismantling specialist. Ensure that historic removal and dismantling specialist's field supervisors are present when removal and dismantling work begins and during its progress.

B. Comply with requirements in Section 01 35 91 "Historic Preservation Treatment Procedures" for identifying and storing historic items.

C. Perform work according to the historic treatment program and approved mockup(s).

1. Perform removal and dismantling to the limits indicated.

2. Provide supports or reinforcement for existing construction that becomes temporarily weakened by removal and dismantling work, until the Project Work is completed unless otherwise indicated.

3. Perform cutting by hand or with small power tools as permitted by CO wherever possible.

Cut holes and slots neatly to size required, with minimum disturbance of adjacent work.

4. Do not operate air compressors inside building unless approved by CO in each case.

5. Dispose of removed and dismantled items off-site unless indicated to be salvaged or reinstalled.

YOSE - 229677 02 42 96 - 4

D. Unacceptable Equipment: Keep equipment that is not permitted for historic removal or dismantling work away from the vicinity where such work is being performed.

E. Removing and Dismantling Items on or Near Historic Surfaces:

1. Use only dismantling equipment and procedures within 12 inches of historic surface.

Protect historic surface from contact with or damage by tools.

2. Wherever possible, unfasten items in the opposite order from which they were installed.

3. Support each item as it becomes loosened to prevent stress and damage to the historic surface.

4. Dismantle anchorages.

F. Concrete Floor Surface:

1. Remove floor surfaces, fill, and topping as indicated on Drawings.

2. Use dismantling methods when removing floor surfaces 12 inches or less away from historic walls.

3. Take away material to a uniform surface at the indicated level.

END OF SECTION 02 42 96

02 81 01 - 1

YOSE – 229677 OFFSITE TRANSPORTATION AND DISPOSAL

SECTION 02 81 01 – OFFSITE TRANSPORTATION AND DISPOSAL

1.1 SUMMARY

A. This Section includes requirements for offsite transportation and disposal of wastes generated during rehabilitation of utilities and the rehabilitation of the restrooms at Tuolumne Meadows Campground in Yosemite National Park (YOSE) located off Tioga Pass Road in Yosemite Valley, California (Project Site or Property).

B. The Contractor shall be responsible for sampling, analysis, and characterization of waste materials to be shipped off-site for disposal or recycling as required by the Treatment Storage and/or Disposal Facility and the applicable environmental regulations.

C. It shall be the Contractor’s sole responsibility to obtain temporary EPA Hazardous Waste ID number(s) and/or California State EPA Hazardous Waste ID number(s) on behalf of the NPS for hazardous waste materials generated and removed from the site(s) during execution of this project.

The Contracting Officer will identify appropriate NPS individuals to sign the required paperwork as the generator signatory for the project.

D. Off-site recycling and disposal facilities shall be approved by the Contracting Officer prior to off-site transportation of materials.

E. Transportation of materials shall comply with legal load restrictions of the U.S. Department of Transportation (DOT) and the California Department of Transportation (Caltrans).

1.2 RELATED SPECIFICATIONS

A. Section 01 74 19: Construction Waste Management and Disposal

B. Section 02 82 13: Asbestos Abatement

C. Section 02 83 13: Removal and Disposal of Materials Containing Lead

1.3 SUBMITTALS

A. The Contractor shall include as a component of the Waste Management Plan (described in Section 01 74 19 “Construction Waste Management and Disposal") a description of planned means and methods for transporting and disposing of all waste materials removed or generated during the Project.

B. Permit profile of the Treatment Storage and/or Disposal Facility.

02 81 01 - 2

C. The Contractor shall provide original and/or carbon copies of all Bills of Lading and Manifests for all transported waste material loads from the site with all required generator, transporter, and waste disposal facility receipt/transfer signatures included. These documents shall be provided to the Contracting Officer at a minimum on a weekly basis and be accompanied by a detailed electronic waste tracking sheet. The waste tracking sheet shall be cumulative and updated on a weekly basis. This document shall provide the following:

1. Cumulative load numbers for each shipment,

2. A description of the waste material being shipped for disposal,

3. Company transporting the waste material,

4. Estimated waste volumes for each shipment,

5. Certified weight slips for each shipment,

6. The disposal facility of record for each waste stream, and

7. The specific Manifest or Bill of Lading specific identifier number for the load being shipped for disposal.

D. At the conclusion of the project, all waste disposal information collected shall be submitted to the Contracting Officer as an electronic deliverable package as part of the required project closeout record documentation. Payments to the Contractor for waste transportation disposal fees will not be approved until completed disposal tracking documents, as described above, are received by the Contracting Office.

1.4 WASTE CONTAINERS

A. The Contractor shall provide waste containers specific to the individual waste to be handled.

1.5 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.6 TRANSPORTATION OF WASTES

A. The Contractor shall be responsible for transportation of all wastes generated during the Project that cannot be salvaged, re-used, or recycled. This includes materials generated by final site cleanup activities and the dismantling of the temporary facilities and controls.

B. The Contractor shall be responsible for coordinating the number and schedule of vehicles required for off-site transportation of waste materials generated during execution of the Project.

C. The Contractor shall be responsible to inspect the transportation vehicles before and after loading to ensure compliance with all local, State, and Federal regulations for the safe transport of wastes from the Site to the receiving facility. The Contractor shall provide the necessary labor and materials to ensure all trucks and containers are covered prior to departure.

02 81 01 - 3

D. Liquid waste shall not be shipped to the waste disposal facility unless the disposal facility has the capability to solidify the wastes before disposal. If the waste facility cannot accept liquid wastes, all wastes shall pass the paint filter test prior to shipment.

E. The Contractor shall insure that the transporters arriving at the site for loading do not cause undue congestion to local roadways, and shall stage trucks either within the perimeter of the site or at an off-site staging area approved by the Contracting Officer.

F. The Contractor's transporters shall proceed directly from the site to a designated staging area or the designated off-site receiving facility. Temporary staging or storage of material shall only be allowed at designated staging areas approved by the Contracting Officer.

G. The Contractor shall originate, maintain, and provide the Contracting Officer with a copy of each executed Bill of Lading for all loads shipped off-site. In addition, the Contractor shall provide the Contracting Officer documentation and records verifying receipt of each truck load by the receiving facility. Such documentation shall indicate the actual weight of each load shipped.

H. Transporters shall proceed from the site along traffic routes established by the Contractor and approved by the Contracting Officer. Transporters shall call back weights after each load and modify loads accordingly. The Contractor shall ensure that trucks leaving the site are within appropriate weight limitations for the local roads along the designated route.

I. Weight measurements for materials transported to recycling and disposal facilities shall be determined by scales certified in accordance with federal, state, and local regulations and requirements.

1.7 DISPOSAL OF WASTES

A. The Contractor shall be responsible for the proper disposal of all solid and liquid wastes that are generated during execution of the Project in conformance with all Federal, State, and local regulations and requirements. Proper disposal requires that the facility accepting the waste be a state licensed disposal/recycling facility that is approved for acceptance of the waste based on the results of the characterization testing and analysis.

B. The disposal facilities shall be approved by the Contracting Officer prior to the transporting of waste. The Contractor shall not change facilities without prior written consent of the Contracting Officer.

C. Obtain temporary EPA ID number(s) and/or State of California ID numbers(s) on behalf of the NPS, as directed by the Contracting Officer, for hazardous waste generated during execution of this Project.

02 81 01 - 4

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 02 81 01

02 82 13 - 1

YOSE – 229677 ASBESTOS ABATEMENT

SECTION 02 82 13 – ASBESTOS ABATEMENT

1.1 DESCRIPTION

A. The work of this section consists of the asbestos abatement tasks during rehabilitation of utilities and the rehabilitation of the restrooms at Tuolumne Meadows Campground in Yosemite National Park (YOSE) located off Tioga Pass Road in Yosemite Valley, California (Project Site or Property). Scope items and requirements for asbestos management are presented below.

B. The estimated quantities of the asbestos-containing material (ACM) to be removed are provided in the Summary Table D.1 below.

C. The Contractor shall take all necessary reasonable measures to control air and water pollution by any material or equipment used during asbestos abatement.

D. Identified and Presumed locations of ACM:

1. Identified materials are described in the Summary Tables D.1, below.

2. All identified friable ACM are to be abated under full containment. In addition, the glass from the windows is to be removed, cleaned, and set aside for re-installation at a later phase of the project.

Table D.1 – YOSE – Tuolumne Meadows Campground Restrooms – ACM to be Abated

E. The Abatement Contractor shall be responsible for the collection and analysis of personnel exposure samples for asbestos and other constituents in accordance with the Occupational Safety and Health Administration (OSHA) regulations.

F. If suspect ACM is encountered in wall or ceiling interiors in unanticipated locations, the unforeseen condition will be documented and described, including the location, and the extent and the quantity of suspect ACM, and any immediate actions taken for safety or housekeeping purposes. This information will be provided to the Industrial Hygienist and the National Park Service (NPS) technical representative.

Building: Material: Estimated Quantity:

Restroom 3076 Friable asbestos-containing window caulking 14 windows each

Restroom 3077 Friable asbestos-containing window caulking

14 windows each

Restroom 3078 Friable asbestos-containing window caulking

14 windows each

Restroom 3079 Friable asbestos-containing window caulking

14 windows each

02 82 13 - 2

G. Any ACMs of the nature shown or described, but not specifically called out or shown in the plans, but which are reasonably implied and necessary for a complete and satisfactory removal job shall be included without additional cost to the Government.

H. Applicable training shall be provided by the Contractor prior to personnel performing abatement as required by applicable regulation 29 CFR 1926.1101 (asbestos). All persons conducting asbestos abatement work shall receive compliant training per Title 40 of the CFR – Protection of the Environment.

I. Two hours of asbestos awareness training shall be provided to applicable NPS personnel and subcontractors working in the project facilities that contain ACM that reasonably can be expected to be impacted as part of this Work.

J. Third party asbestos abatement oversight will be provided by an independent consultant contracted under the General Construction Contractor. Third party oversight by the third party Industrial Hygienist will be coordinated with the NPS Project Manager to provide project surveillance, perimeter and clearance air sampling, and visual inspections. The clearance air samples will be analyzed using Phase Contrast Microscopy (PCM) in accordance with applicable regulations. The contractor will be certified in all appropriate asbestos disciplines under California State Law. All work and material shall be subject to visual inspection by the Industrial Hygienist (IH). The Contractor shall provide reasonable and necessary facilities for such observation and shall render the necessary assistance to permit the representative to carry out all phases of observation. When required by the IH, the Contractor shall take down or uncover portions of the finished work. If the work thus exposed is unsatisfactory, all cost and expenses of exposing, removing, re-testing, replacing and restoring shall be borne by the Abatement Contractor. Any omission or failure on the part of the IH to disapprove or reject any inferior or defective work or material shall not be construed to be an acceptance of any such work or materials. The Abatement Contractor shall remove at its own expense any defective work or material rejected by the IH and shall rebuild or replace the same without extra charge to the Government. All re-testing of an area for a failed clearance shall be at the Abatement Contractor's expense.

K. Contractors and employees should be prepared to comply with the OSHA Fall Protection Standard 29 CFR 1926 Subpart M while working at heights. In the event scaffolding is utilized during the prep or removal process, OSHA Standard 29 CFR 1926 Subpart L will apply.

L. The Abatement Contractor shall be responsible for the clean-up and testing of any area contaminated due to Abatement Contractor negligence at no additional cost to the NPS.

1.2 REFERENCES AND RELATED SPECIFICATIONS

A. All work under this contract shall be done in strict accordance with all applicable Federal, State, and Local regulations, standards and codes governing asbestos abatement and other trade work done in conjunction with the abatement. The most recent edition of any relevant regulation, 02 82 13 - 3 standard, document or code shall be in effect. Where conflict among the requirements or with these specifications exists, the most stringent requirements shall be utilized.

B. Section 02 81 01: Offsite Transportation and Disposal

C. Landmark Environmental, Inc. Hazardous Materials Assessment, Historical Restrooms and Contact Station at Tuolumne Meadows Campground, Yosemite National Park, California.

Landmark Project No. 20061.001.001, dated 9/9/2020.

D. American Society of Safety Engineers (ASSE), ASSE/SAFE Z9.2 Fundamentals Governing the Design and Operation of Local Exhaust Ventilation Systems, 2012.

E. Underwriters Laboratories (UL), UL Standard for Safety High-Efficiency Particulate, Air Filter Units, UL 586, 2009; reprint 2017.

F. US Occupational Safety and Health Administration (OSHA), 29 CFR 1910.1001, General Industry Standards for Asbestos.

G. OSHA, 29 CFR 1926.1101, Construction Industry Standards for Asbestos.

H. OSHA, 29 CFR 1926.62 Lead.

I. OSHA, 29 CFR 1910.134, Respiratory Protection.

J. OSHA, 29 CFR 1910.145, Accident Prevention.

K. OSHA, 29 CFR 1910.2, Medical Records.

L. OSHA, 29 CFR 1910.38, Emergency/Fire Prevention Programs.

M. OSHA, 29 CFR 1910.1200, Hazard Communication.

N. US Environmental Protection Agency (EPA), 40 CFR 61 Sub. A, General Provisions.

O. EPA, 40 CFR 61 Sub. B.

P. US Department of Transportation (USDOT) 49 CFR 171 and 172.

Q. National Institute for Occupational Safety and Health (NIOSH), Certified Equipment List.

R. NIOSH, Occupational Exposure Sampling Strategy 77-173.

S. NIOSH, Guide to Industrial Respiratory Protection, 87-116.

T. State of California, Department of Industrial Relations, Division of Occupational Safety and Health (DOSH), 8 CCR 1529 – Asbestos.

U. DOSH, 8 CCR 1544 – Respiratory Protection.

02 82 13 - 4

V. DOSH, 8 CCR 1509 – Injury & Illness Prevent Program.

W. DOSH, 8 CCR 3204 – Access to Employee Exposure and Medical Records.

X. DOSH, 8 CCR 3221 – Fire Prevention Plan.

Y. DOSH, 8 CCR 5194 – Hazard Communication Standard.

Z. State of California, Department of Toxic Substances Control (DTSC), California Code of Regulations (CCR), Title 22, Division 4.5 – Environmental Health Standard for the Management of Hazardous Waste.

1.3 DEFINITIONS AND ACRONYMS

A. Asbestos: Includes chrysotile, amosite, crocidolite, tremolite asbestos, anthophyllite asbestos, actinolite asbestos, and any of these minerals that have been chemically treated and/or altered.

Asbestos includes PACM, as defined below.

B. Asbestos-Containing Material (ACM): Any material containing more than 1% asbestos.

C. Asbestos-Containing Waste Material (ACWM): Any material which is, or is suspected of being, a material contaminated with an ACM which is to be removed from a Regulated Area for disposal.

D. Asbestos Debris: Pieces of ACM that can be identified by color, texture, or composition (i.e., dust), if the dust is determined by an accredited inspector to be ACM.

E. Authorized Person: Any person authorized by the employer and required by work duties to be present in Regulated Areas.

F. Class I Asbestos Work: Activities involving the removal of ACM that is a thermal system insulation or a surfacing material.

G. Class II Asbestos Work: Activities involving the removal of ACM which is not thermal system insulation or surfacing material. This includes, but is not limited to, the removal of asbestos-containing wallboard systems with ACM drywall joint compound, sheet vinyl flooring, floor tile and sheeting, roofing and siding shingles, and construction mastics.

H. Critical Barrier: One or more layers of plastic sealed over all openings into a Regulated Area or any other similarly placed physical barrier sufficient to prevent airborne asbestos in a Regulated Area from migrating into an adjacent area.

I. Competent Person: The Abatement Contractor's employee who is: 1) capable of identifying existing asbestos in the workplace; 2) who has the authority to take prompt corrective measures to eliminate them; and 3) who is trained and accredited as defined in 29 CFR 1926.1101 and 29 CFR 1926.62. The duties of the Competent Person include, but are not limited to, the following:

controlling entry to and exit from the asbestos Regulated Area, supervising any employee

02 82 13 - 5 exposure monitoring required by the standards, ensuring that all employees working within a Regulated Area wear the appropriate personal protective equipment and are trained in the use of appropriate methods of exposure control and decontamination, and ensuring that engineering controls in use are functioning properly.

J. Disposal Bag: A properly labeled 6-mil. thick, leak-tight polyethylene bag used for containerizing and/or transporting asbestos waste to the disposal site.

K. Disturbance: Activities that disrupt the matrix of ACM or PACM, crumble or pulverize ACM or PACM, or generate visible debris from ACM or PACM. Disturbance includes cutting away small amounts of ACM and PACM, no greater than the amount which can be contained in one standard sized glove bag or waste bag in order to access a building component. Maximum glove bag or waste bag size referred to herein is 60-inches in length and width.

L. Friable Asbestos Material: Material that contains more than 1.0% asbestos by weight and that can be crumbled, pulverized, or reduced to powder by hand pressure when dry.

M. HEPA Filter: A High Efficiency Particulate Air (HEPA) filter capable of trapping and retaining 99.97% of all mono-dispersed particles (e.g., asbestos fibers) of 0.3-microns in diameter.

N. Industrial Hygiene: An area of specialization in the field of industrial safety and health that is concerned with predicting, recognizing, assessing, controlling, and preventing environmental stressors in the workplace that can lead to sickness, disease, or other forms of impaired health.

O. Industrial Hygienist: A person having a college or university degree(s) in engineering, chemistry, physics, medicine, or related physical or biological sciences who, by virtue of special studies and training, has acquired competence in industrial hygiene.

P. Intact: ACM that has not crumbled, been pulverized, or otherwise deteriorated so that the asbestos is no longer likely to be bound with its matrix.

Q. Negative Initial Exposure Assessment: An assessment by an industrial hygienist which demonstrates that employee exposure during an operation is expected to be consistently below the permissible exposure limit (PEL) for representative 8-hour time-weighted average (TWA) samples and 30-minute excursion limit (EL) samples.

R. Non-Friable Asbestos Material: Material that contains more than 1.0% asbestos by weight and that cannot be crumbled, pulverized, or reduced to a powder by hand pressure when dry.

S. Personal Monitoring: Sampling of the asbestos fiber concentrations within the breathing zone of an employee.

T. PACM: Presumed Asbestos-Containing Material means thermal system insulation and surfacing material found in buildings constructed no later than 1980.

02 82 13 - 6

U. Regulated Work Area: An area established by the abatement contractor to demarcate areas where Class I, II, and III asbestos work is conducted, and any adjoining area where debris and waste from such asbestos work accumulate, and a Regulated Work Area within which airborne concentrations of asbestos, exceed or there is a reasonable possibility they may exceed, the permissible exposure limit.

V. Removal: All operations where ACM and/or PACM are removed or stripped from structures or substrates, includes demolition operations.

W. Renovation: Modifying of any existing structure, or portion thereof.

X. Surfactant: A chemical wetting agent added to water to improve wetting and penetration into a substrate.

Y. Time Weighted Average (TWA): The average concentration of a contaminant in air during a specific time-period.

Z. Visible Emissions: Any emissions containing particulate asbestos material that are visually detectable without the aid of instruments.

1.4 SPECIAL CONSTRUCTION REQUIREMENTS

A. Special Historic Preservation Requirements: The site structures are National Historic Landmarks.

Protection of these national treasures extend not just to the structures at large, but to the original materials which still comprise the building fabric and contribute to its historic integrity. Original materials which will be affected by this work have been identified in the contract documents and where practicable, have been called out for salvage and reuse. The Contractor shall take extreme care in the salvage and reuse of these materials so noted. Careless demolition practices are not acceptable.

1.5 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.6 CONSTRUCTION MATERIALS

A. The Government will not furnish any materials for this project.

1.7 SALVAGED MATERIALS

A. Excess salvaged materials not reinstalled in the project remain the property of the Government.

02 82 13 - 7

B. Stockpile material within the rooms where the materials are recovered for reuse. If more space is required, coordinate storage location with Contracting Officer.

1.8 PROJECT SUBMITTAL REQUIREMENTS

A. Pre-Project Submittals:

1. Proof that required Federal, State, and local permits, have been obtained.

2. Proof of asbestos-specific insurance demonstrating both liability and pollution coverage.

Policy shall name the NPS as an additional insured and shall include a waiver of subrogation. Policy limits shall be a minimum of two million dollars ($2,000,000).

B. Health and Safety Related Submittals: The Contractor shall submit to the Contracting Officer for review an Asbestos-Specific Health and Safety Program including, but not limited to: a Respiratory Protection Program, a Medical Surveillance Program, and an Accident Prevention Program. Additional health and safety related submittals required are:

1. The Contractor shall submit the resume and copies of professional registrations/certifications for the Contractor's employee who will act as the Competent Person for the project. The Competent Person must meet the qualifications and have the training and certifications defined by OSHA.

2. Proof that all employees have passed appropriate medical examinations required by OSHA.

3. Certification that all employees have been instructed on the hazards of asbestos exposure, use and fitting of respirators and protective dress, use of showers, regulated work area entry and exit procedures, work methods, and protective measures.

4. Certification that each employee has been properly fitted with a specified respirator.

5. If rental equipment is to be used in the regulated work area or to transport asbestos contaminated waste, provide notice to rental agency stating intended use of equipment, with copy to the Industrial Hygienist.

6. For each type of training session, the Contractor shall submit a proposed outline of the subjects to be covered to the Industrial Hygienist for approval. The training shall not be conducted until the outline is approved.

7. Copies of attendance records and certificates for each employee for all asbestos training as required by this Section.

8. Copies of current physicians written medical opinions for all employee’s subject to medical surveillance requirements defined in OSHA respiratory Protection Standards.

C. Asbestos Abatement Project Plan: Develop and submit to the Contracting Officer for review a written Asbestos Abatement Project Plan. This plan should meet the requirements of a Project Design and be prepared by a certified Project Designer. The plan will be job-specific and list the work procedures to be used during the removal of asbestos from the identified buildings. This work plan shall include, but not be limited to:

1. Construction schedule in sufficient detail for the Contracting Officer to determine the duration and level of effort required for the project.

2. Description, accompanied by sketches to scale, of decontamination enclosure systems.

3. Description of asbestos waste handling procedures. Include name and address of waste disposal site; name, address, and telephone number of entity who will transport asbestos waste; and, a sample of transport manifest to be used to identify quantity of waste removed and accepted by disposal site.

02 82 13 - 8

D. Asbestos-Related Project Submittals – Ongoing Requirements

1. Results of all worker exposure assessment air samples shall be made available to applicable personnel per OSHA 29 CFR 1926.1101, and shall also be submitted to the Industrial Hygienist or a designated on-site representative within 24-hours of sample collection.

Submittals shall include sample collection logs and laboratory analysis sheets.

2. After every disposal operation, provide copies of transport manifests, disposal receipts, and chain of custody forms for all asbestos waste materials removed from the site. Chain-of-custody form shall include date, address of pickup site, name and address of Contractor, names of persons responsible for pickup, name and address of disposal site, quantity of asbestos waste, and type of containers used. The form shall be signed by the Contractor, the Contracting Officer, disposal site operator, and hauler if a private hauler is employed.

E. Close-out Report: Prepare a close-out report with the following items:

1. Description of removal activities performed during the project.

2. Pre- and post- work photographs.

3. Description and results of all occupational and environmental sampling.

4. Description and results of third party final clearance activities.

5. Results of waste characterization sampling.

6. Copies of all ACWM manifest documents shall be completed and signed by the

Contracting Officer, the Contractor, the Transporter, and the Disposal facility.

1.9 QUALITY ASSURANCE

A. Qualifications: Workers shall be fully qualified and experienced in the techniques of abatement, handling and disposal of ACMs and meet the requirements as set forth by OSHA and the EPA.

B. Regulatory Requirements:

1. Comply all regulatory standards. A listing can be found in section 1.2.

2. Notify all responsible state and local agencies in writing at least 10 days before removal work begins. Obtain all required permits before work begins. The Contractor shall be responsible for obtaining all necessary permits and certifications of personnel in conjunction with asbestos removal, hauling, and disposition and provide timely notification of such actions as may be required by Federal, state, regional and local authorities. Fees and/or charges for these permits shall be included in the Contractor's bid price. Provide copies of all obtained permits to the Industrial Hygienist.

3. Dispose of asbestos waste at an authorized landfill site in accordance with requirements of NESHAP and applicable state and local guidelines and regulations.

1.10 RECORD KEEPING

A. Daily Project Log: The Site Supervisor must maintain a Daily Project Log. The Daily Project Log must be used each day of the project to document the following information.

1. Date.

02 82 13 - 9

2. Name of Supervisor.

3. Name of Industrial Hygienist monitoring the regulated work area (if applicable).

4. Manometer data (if applicable)

5. Number of workers on site.

6. Equipment utilized.

7. Brief description of daily work activities.

8. Listing of any non-compliance noted, emergencies, stop work orders (with detailed explanation), and descriptions of any other significant events.

1.11 PROJECT CONDITIONS

A. Maintain existing emergency exits and building emergency equipment, such as fire alarms, fire hose equipment, and emergency lighting devices, in operating order.

B. Do not damage existing building materials which are not associated with the work or regulated work area.