This document provides details on a federal solicitation opportunity from the National Park Service to stabilize and rehabilitate the Birth Home of Martin Luther King Jr. in Atlanta, Georgia. The solicitation number is 140P2023R0070 and seeks to restore the historic property, which is listed on the National Register of Historic Places. The National Park Service is the issuing agency and the work location is within the Martin Luther King Jr. National Historical Park. No further specifics on pricing, response dates, or award timing are included in this brief overview of the opportunity.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents (TOC) | NPS DSC Division 1 Specifications | 101321 page 1 of 4
NPS DSC Division 1 Specifications Table of Contents
National Park Service (NPS) - Denver Service Center (DSC) | 10-13-21
Table of Contents (TOC)
DIVISION 1 – GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 32 16 Construction Schedule
01 32 33 Photographic Documentation
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 35 25 Explosives – NOT USED
01 35 91 Historic Preservation Treatment Procedures
01 40 00 Quality Requirements
01 40 00.1 NPS Universal Design Accessibility Scoping Form
01 40 00.2 Statement of Structural Tests and Special Inspections
01 42 00 Reference Standards
01 50 00 Temporary Facilities and Controls
01 57 19.11 Indoor Air Quality (IAQ) Management
01 57 19.12 Noise and Acoustics Management
01 57 23 Under-an-Acre Pollution Prevention (UPP)
01 67 00 Product Requirements
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance (O&M) Data
01 79 00 Demonstration & Training
01 91 14 Total Building Commissioning
DIVISION 02 -- EXISTING CONDITIONS
02 22 50 Selective Demolition in Historic Structures
02 41 00 Site Demolition
02 80 00 Asbestos Remediation
02 83 00 Lead Remediation
02 85 00 Mold Remediation
DIVISION 03 -- CONCRETE
03 01 00 Concrete Cleaning
03 03 30 Historic Pebbledash Stair Repair.
03 10 00 Concrete Forming and Accessories
03 20 00 Concrete Reinforcing
03 30 00 Cast-In-Place Concrete
Table of Contents (TOC) | NPS DSC Division 1 Specifications | 101321 page 2 of 4
DIVISION 04 -- MASONRY
04 01 20 – Brick Masonry Cleaning
04 05 13 – Masonry Mortaring
04 0523 - Masonry Grouting
04 22 00 – Concrete Unit Masonry
04 90 00 - Brick Masonry Repairs
DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
06 10 00 - Rough Carpentry
06 20 00 - Finish Carpentry
06 47 00 - Wood Louver Restoration
DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
07 17 16 - Bentonite Composite Sheet Waterproofing
07 21 00 - Batt Insulation
07 21 26 - Blown Insulation
07 26 16 - Crawlspace Vapor Retarders
07 46 23 - Wood Siding and Shingles
DIVISION 08 -- OPENINGS
08 01 20 - Wood Door and FrameRestoration
08 14 16 - Flush Wood Doors
08 31 00 - Access Doors and Panels
08 56 95 - Interior Storm Window Inserts
08 91 00 - Metal Louvers
08 95 40 - Historic Window Restoration
DIVISION 09 -- FINISHES
09 20 00 – Plaster Repairs and Conservation
09 21 16 - Gypsum Board Assemblies
09 24 00 – Cement Plastering
09 9100 – Interior Painting
09 9500 – Wallcoverings
09 9600 – High Performance Coatings
DIVISION 10 -- SPECIALTIES
10 8223 – Interior Grilles
DIVISION 11 -- EQUIPMENT
11 81 29 - Facility Fall Protection
DIVISION 12 – FURNISHINGS -NOT USED
DIVISION 13 -- SPECIAL CONSTRUCTION -NOT USED
DIVISION 14 -- CONVEYING EQUIPMENT -NOT USED
DIVISION 21 -- FIRE SUPPRESSION
21 00 10 – Fire Suppression General
21 00 90 – Fire Suppression Performance Verification
21 30 00 – Fire Suppression Systems
Table of Contents (TOC) | NPS DSC Division 1 Specifications | 101321 page 3 of 4
DIVISION 22 -- PLUMBING -NOT USED
DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 00 10 – HVAC General
23 00 90 – HVAC Performance Verification
23 00 95 – Testing, Adjusting and Balancing
23 10 00 – Piping, Valves and Accessories
23 25 00 – HVAC Insulation
23 60 00 – Equipment
23 70 00 – Air Distribution
23 80 00 – Automatic Temperature Controls
DIVISION 25 -- INTEGRATED AUTOMATION -NOT USED
DIVISION 26 -- ELECTRICAL
26 00 10 – Electrical General
26 00 90 – Electrical Performance Verification
26 05 19 – Building Wire and Cable, 600 Volt
26 05 26 – Grounding
26 05 29 – Supporting Devices
26 05 33 – Raceways
26 05 73.13 – Short Circuit Studies
26 05 73.16– Coordination Studies
26 05 73.19 – Arc-Flash Hazard Analysis
26 09 23 – Lighting Control Devices
26 13 00 – Boxes
26 14 80 – Connections to Meters and Equipment
26 24 16 – Panelboards
26 27 26 – Wiring Devices
26 28 16 – Circuit and Motor Disconnects
26 40 20– Service Entrance
26 47 50 – Overcurrent Protective Devices
26 47 60 – Individual Circuit Breakers
DIVISION 27 -- COMMUNICATIONS -NOT USED
DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY
28 30 10 – Fire Detection and Alarm General
28 30 90– Fire Detection and Alarm Performance
28 31 00 – Fire Alarm System
DIVISION 31 -- EARTHWORK
31 10 00 – Site Clearing
31 22 00 – Grading
31 23 17– Excavating and Backfilling
31 23 33 – Trenching and Backfilling
DIVISION 32 -- EXTERIOR IMPROVEMENTS
32 14 13 – Precast Concrete Unit Paving
32 31 80 – Wood Fencing
32 92 23 – Sodding
Table of Contents (TOC) | NPS DSC Division 1 Specifications | 101321 page 4 of 4
32 93 00 – Planting
DIVISION 33 -- UTILITIES
33 40 00 – Storm Drainage Utilities
DIVISION 34 -- TRANSPORTATION -NOT USED
DIVISION 40 -- PROCESS INTEGRATION -NOT USED
DIVISION 46 -- WATER AND WASTEWATER EQUIPMENT -NOT USED
APPENDICES
Appendix A – Hazardous Materials Survey prepared by Schweiger Environmental, LLC and dated March 10, 2022.
Appendix B - Wallpaper Conditions Assessment Report with Recommendations prepared by Jablonski Building Conservation, Inc and dated March 10, 2021.
MALU 257817 01 11 00 - 1
051121 SUMMARY OF WORK
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21
MALU 257817
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Under Other Contracts
3. Government-Furnished Materials
4. Contractor Use of Site
5. Public Use of Site
6. Occupancy Requirements for Buildings
7. Conduct of Operations
8. Work Restrictions
9. Special Construction Requirements
10. Soils Investigation Report
11. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location:
Martin Luther King, Jr. Birth Home
Martin Luther King, Jr. National Historical Park
501 Auburn Avenue
Atlanta, Georgia 30312
B. The Work consists of:
1. Exterior Improvements to the building envelope to include exterior siding and trim repairs, window rehabilitation, miscellaneous exterior door repairs, brick masonry cleaning and repair, porch floor, railing and ceiling repairs and exterior painting.
a. See the Hazardous Materials Survey and sections 028000 Asbestos Remediation, 028300 Lead Remediation and 028500 Mold Remediation for treatment requirements for items identified in the survey as hazardous material.
b. Note that the window restoration is primarily focused on the exterior faces of sash and trim. The exterior face only will be stripped of paint. The interior finish is to be protected and retained. In some cases, where a portion of a component requires replacement, bare wood will be present on the interior. These areas of bare wood will require spot priming and inpainting to match the existing interior window finish as part of the Base Bid.
MALU 257817 01 11 00 - 2
2. Integration of new systems to include a new mechanical system, electrical system, fire protection system and fire alarm system. Electrical work will require replacement of the existing exterior weatherhead with an underground electrical feed. The house is transitioning from a single phase to a three-phase system which will require coordination with Georgia Power for the installation of four new electrical poles between the Birth
Home location and Boulevard and a pad transformer to be located in the Gift Shop rear yard.
a. The electrical wiring and wiring for the fire alarm system will be replaced and will require strategic removal of plaster for access. See the Specification 02 4100
Selective Demolition for the process of probing at the plaster finish to establish the most minimal amount of plaster removal required for the replacement of this writing,
3. Interior work will include the repair to any plaster that is disturbed in the course of installing the new systems. The existing wallpaper is to be removed and replaced with replicated patterns.
a. The area with head height in the crawlspace is to be enlarged for new mechanical and fire protection equipment.
b. A mechanical room will be constructed in the attic.
4. Structurally, the brick masonry foundation walls and piers will be repointed. New CMU piers and 4 x 4 posts are to be added. New shear walls are to be added within the crawlspace. In the attic, connections will be strengthened. The existing kickers will be removed to maximize space in the mechanical room. The mid-span of the roof rafters will be supplementally supported with the new mechanical walls and a strongback beam.
5. There are two Bid Options as indicated in the B series sheets of the Construction Drawings.
1) Bid Option #1: The removal and replacement of the Gift Shop Retaining Wall
2) Bid Option #2 includes interior painting of all previously painted interior finishes.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this
Contract with work performed under separate contracts.
1. There is a potential project proposed for the replacement of the Fire Suppression systems at adjacent properties, 497 and 503 Auburn Avenue. This project is not yet funded and construction dates are not yet established. NPS will inform the Contractor if this construction project will occur during the construction duration of this project.
B. Preceding Work: Government plans to award separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.
1. 503 Auburn Fire Suppression Replacement: A separate contract will be awarded to for the adjacent structure, 503 Auburn Avenue. The shared driveway between the MLK Birth
Home and 503 Auburn Avenue will be impacted when fire suppression lines are routed to the existing vault in the driveway.
MALU 257817 01 11 00 - 3
2. MLK Birth Home Lift Replacement: A separate contract will be awarded to for the replacement of the lift at the rear of the building.
3. The status of these projects will be reviewed at the Pre-Bid Conference.
C. Concurrent Work: Government will award separate contract(s) for the following construction operations in the vicinity of the Project site. Some coordination by the Contractor will be required simultaneously with work under this Contract.
1. Fire Station HVAC Replacement: A separate contract will be awarded to for the replacement of the HVAC system at the Historic Fire Station No. 9 at 39 Boulevard NE.
2. Fire Station Elevator Replacement: A separate contract will be awarded to for the replacement of an elevator at the Historic Fire Station No. 9 at 39 Boulevard NE.
3. Potential impacts of this concurrent work include coordinating access to the 3-phase power pole at the corner of Boulevard and Auburn Avenue and access to the parking area behind the fire station for staging or Contractor parking.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
1. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
2. The project will be closed to the public during construction. It is desired that when feasible, public access be provided to the front porch for visitors to take photos.
3. NPS staff will require access to the interiors on occasion.
B. Storage of Materials: Confine storage of materials to the paved area at the rear of house until construction commences in these areas. There are a limited number of parking spaces at an adjacent property, 515 Auburn Avenue. There is also storage or parking space behind the Historic
Fire Station No. 6 at 39 Boulevard NE.
C. Parking: Confine contractor parking to parking area behind the Historic Fire Station No. 6 at 39
Boulevard NE. Off-site parking will be required.
D. Stockpiling: Confine stockpiling to identified storage areas.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
MALU 257817 01 11 00 - 4
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
J. Interior furnishings: NPS will be responsible for removing all furnishings and collections items from the house prior to commencement of work. Ceiling mounted , historic light fixture will remain in place. The Contractor will be responsible for protecting the historic light fixtures throughout the duration of construction.
1.5 PUBLIC USE OF SITE
A. The building will be closed to the public during construction. Access to the front porch is desired when construction activities allow safe access.
B. Contractor shall conduct his operations to ensure the least inconvenience to public. Lane closures may be permitted, when required, upon specific approval of Contracting Officer for a maximum of 2 calendar days.
1.6 OCCUPANCY REQUIREMENTS FOR BUILDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will visit the premises occasionally, with exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not
MALU 257817 01 11 00 - 5
to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.
1.7 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 calendar days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
D. The Contractor is expected to keep a neat and orderly job site as indicated in Section 01 7340
Execution. The Contractor is required to schedule a meeting with the Contracting Officer and
Park staff to review the appropriate cleaning processes for the interiors of interpreted rooms.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:30 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Notify the Contracting Officer at least 3 calendar days in advance to obtain approval and any applicable restrictions if weekend work is desired.
2. Early Morning Hours: Early morning hours are not permissible.
3. Hours for Noisy Construction Activities: Noisy Construction Activities must be kept to a minimum. These activities should be scheduled for the afternoon.
4. The Contractor should coordinate his schedule so that no work activities conflict with annual MLK holiday programs and activities. MLK Day is observed the third Monday each January.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
MALU 257817 01 11 00 - 6
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than three calendar days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Utility outages should not exceed 4 hours.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within
25 feet of entrances, operable windows, or outdoor air intakes.
E. Museum Fire Protection: Refer to the NPS Museum Handbook, Part 1, Chapter 9: Museum Fire
Protection for additional guidance on temporary fire protection during the work. National Park
Service - Museum Management Program (nps.gov)
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using
Project Website.
B. NPS will provide a list of any programs that may impact the Contractors use of site.
1.10 ADDITIONAL REPORTS
A. The report Hazardous Materials Survey prepared by Schweiger Environmental, LLC and dated
March 10, 2022 is attached as Appendix A to this Specification. Note that Specification Sections
028000 Asbestos Remediation, 028300 Lead Remediation and 028500 Mold Remediation outline the requirements for hazardous material remediation.
B. The report Wallpaper Conditions Assessment Report with Recommendations prepared by
Jablonski Building Conservation, Inc and dated March 10, 2021 is attached as an Appendix B to this Specification.
C. In case of conflict between report and drawings or specifications, drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
MALU 257817 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
MALU 257817
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
MALU 257817 01 26 01 - 2
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
MALU 257817 01 26 01 - 3
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized
MALU 257817 01 26 01 - 4
by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
MALU 257817 01 26 01 - 5
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit…………………...10%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
MALU 257817 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
MALU 257817 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
MALU 257817
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 01 Site Improvements
1. This item consists of selective demolition of site features to include removal of the designated pecan tree, fencing, erosion control, and minor excavation and grading of the site as indicated in the drawings.
2. Measurement for payment will be for work in place to include selective demolition of paving, removal of trees, repairs of existing retaining walls, construction of new retaining walls, fencing, preparation of staging areas and finish grading as indicated on the drawings.
Tree protection, excavation and erosion control measures and protection of historic fabric are to be maintained throughout construction. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item Number 002 Site Paving Improvements
1. This item consists of site paving improvements including a new driveway, portions of the rear driveway, repair to the existing hexagonal paved walks, repairs to the existing front stair as indicated in the drawings.
2. Measurement for payment will be for work in place to include the removal, salvage and reinstallation of the existing interpretive panel, salvage of undamaged hexagonal pavers, new subbases for hexagonal paver walks, and sawcutting the driveway as indicated on the drawings. Reinstallation of salvaged hexagonal pavers, installation of new pavers where missing, new concrete drive and portions of the plaza, and dutchman repairs of the existing stair. A new concrete side stair, new driveway, curb at driveway and plaza areas. New
MALU 257817 01 27 00 - 2
concrete pads for mechanical units at rear of Gift Shop are included. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item Number 003 Site Drainage Improvements
1. This item consists of site drainage improvements including the tie-in of downspouts at
Birth Home and adjacent properties as indicated in the drawings.
2. Measurement for payment will be for work in place to include minor excavation for routing of subsurface drainage including the foundation drains, installation of new cast iron downspout boots, installation of new cleanouts at each downspout tie-in, piping towards the street, installation of grated flumes at the sidewalk. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item Number 004 Selective Demolition
1. This item consists of selective demolition related to systems replacement and wallcovering replacement.
2. Measurement for payment will be for work in place including the removal of abandoned mechanical systems, fire protection systems, fire alarm systems and electrical systems as indicated in the drawings. Selective demolition includes the strategic removal of any plaster removed to facilitate installation of the new systems and the removal of existing wallcoverings and hazardous material abatement. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.\
E. Contract Line Item Number 005 Foundation and Structural Repairs
1. This item consists of structural work within the crawlspace, attic and underpinning of the perimeter walls.
2. Measurement for payment will be for work in place including the excavation of soils as indicated on the drawing, related shoring, bracing, installation of new piers, beams, pilasters, underpinning of existing hearths, piers and perimeter walls at the crawlspace and basement level where noted on the drawings. In the attic, work includes the removal of existing collar ties and kickers, bracing, installation of new sistered framing at attic floor, new collar ties, cripple walls, beams, reinforcing at the kitchen chimney. Perimeter foundation walls require underpinning. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
F. Contract Line Item Number 006 Exterior Envelope Repairs
1. This item consists of exterior envelope repairs.
2. Measurement for payment will be for work in place including the repairs to exterior siding, exterior trim and the front porch framing, railing and ceiling repairs. Brick masonry repairs at the foundation walls – exterior and interior faces, and the chimneys are included.
Window rehabilitation, screen repairs, and louver rehabilitation are included. Exterior painting is included. Provide all labor, equipment, materials and incidentals required to complete the work.
MALU 257817 01 27 00 - 3
3. Payment will be made at the contract lump sum price.
G. Contract Line Item Number 007 Installation of Electrical System
1. This item consists of the installation of a new electrical system including site level electrical to extend 3 phase infrastructure from Boulevard to site.
2. Measurement for payment will be for work in place including installation of new electrical panels, disconnects and feeders. Rewiring of all outlets, light switches and light fixtures are included. A new underground electrical service from the street to the house is included.
Coordination with Georgia Power for the installation of new 3-phase power poles from
Boulevard and a pad transformer are included, but the cost incurred by Georgia Power will be paid directly by the NPS. The contractor will provide the pad for the pad transformer and the trenching from nearest pole to pad transformer. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
H. Contract Line Item Number 008 Installation of Mechanical System
1. This item consists of the installation of a new mechanical system.
2. Measurement for payment will be for work in place including installation of new variable refrigerant flow (VRF) mechanical system with a Dedicated Outdoor Air system. . All associated units, thermostats, controls and ductwork is included. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
I. Contract Line Item Number 009 Installation of Fire Suppression System
1. This item consists of the installation of a new Pre-Action Fire Suppression system.
2. Measurement for payment will be for work in place including installation of new pre-action, dry pipe fire suppression system. An independent dry-pipe system serves the exterior of the building. New piping, sprinkler heads, drains and valves are included. A new alarm bell and fire department connection are included. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
J. Contract Line Item Number 010 Installation of Fire Alarm System
1. This item consists of the installation of a new Fire Alarm system.
2. Measurement for payment will be for work in place including installation of a new fire alarm system including wiring, control panels, heat detectors, smoke alarms and horn strobe devices. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
K. Contract Line Item Number 011 Interior Repairs and Wallpaper Replacement
1. This item consists of all work occurring in the interior spaces.
2. Measurement for payment will be for work in place including repairs of any plaster removed to facilitate the installation of new systems. Replacement of all wallcoverings at walls and ceilings with custom replicated wallcoverings are included. Work in the
MALU 257817 01 27 00 - 4
crawlspace and attic to create the mechanical spaces and any structural reinforcements called for these spaces is included. Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
L. Contract Line Item Number 012 Commissioning
1. This item consists of commissioning of new systems.
2. Measurement for payment will include costs for updating project requirements, the
Contractors Commissioning plan, Submittals, developing the Systems Manual, training, Construction process activities, as described in American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHREA) 0-2005, paragraph. 7.Provide all labor, equipment, materials and incidentals required to complete the work.
3. Payment will be made at the contract lump sum price.
M. Option A - Gift Shop Retaining Wall Replacement
1. Contract Line Item Number 013 - Gift Shop Retaining Wall Replacement
N. This item consists of removal of the full extent of the Gift Shop retaining wall including section along the alley/drive, the section facing Auburn Avenue and the section between the Gift Shop and MLK Birth Home. The existing stairs will remain in place and must be protected. The existing interpretive panel is removed and reinstalled with newly constructed retaining wall.
a. Measurement for payment: Payment includes select site demolition of existing wall, excavation, shoring, reconstruction of a new cmu wall with parge coating and cast concrete cap.. Provide all labor, equipment, materials and incidentals required to complete the work.
b. Payment will be made at the contract lump sum price.
O. Option B - Interior Painting
1. Contract Line Item Number 014 – Interior Painting
a. This item consists of surface preparation and interior painting of all previously painted surfaces in the Birth Home interior. New paint colors will match the existing color palette exactly. Drawdowns and mock-ups will be required. The existing interpretive panel is removed and reinstalled with newly constructed retaining wall.
b. Measurement for payment: Payment includes paint preparation, application of new painted coating to interior wood trim, interior wood doors, interior stair and railings interior wood sash, interior wood frames, plaster wall and ceilings where scheduled in the drawings. . Provide all labor, equipment, materials and incidentals required to complete the work.
c. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
MALU 257817 01 31 00 - 1
012721 PROJECT MANAGEMENT AND COORDINATION
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
MALU 257817
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
4. Section 01 91 14 "Total Building Commissioning" for coordinating the work with Owner’s
Commissioning Authority.
1.2 DEFINITIONS
A. Agency with Jurisdiction: An Agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.
B. Construction Permits – Contractor Provided: Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service. Examples of typical Contractor Provided
Permits are: National Pollutant Discharge Elimination System (NPDES) Construction Permit
(ground disturbance), dewatering permit, permit for work in a roadway (with traffic management plan), temporary utility tap permit, etc.
MALU 257817 01 31 00 - 2
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination
Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems. Indicate any historic fabric such
MALU 257817 01 31 00 - 3
as plaster or wood trim to be removed for installation of new work. See Section 02
4100 Selective Demolition for more requirements.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 millimeters) but no larger than 30 by
40 inches (750 by 1000 millimeters).
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, mechanical, plumbing, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4.…