This document contains specifications for temporary facilities and controls for a construction project at the Martin Luther King, Jr. National Historical Park in Atlanta, Georgia. The specifications outline requirements for temporary facilities such as field offices, storage sheds, and toilets. They also cover equipment needs including fire extinguishers, heating and air conditioning units, and dust control mats. Material requirements are identified for pavement, fencing, barrier tape, wood enclosure fences, gypsum board, and polyethylene sheeting. Execution details cover installation requirements and relocation of temporary facilities as construction progresses.

View the file

Other files

File Type Posted
B09_Q_A_Amendment_08_0008.pdf PDF
Sol_140P2023R0070_Amd_0008.pdf PDF
Sol_140P2023R0070_Amd_0007.pdf PDF
B09_Amendment07_Attachment_SF1442_Pg1_Solit_140P2023R0070_MALU_318172_0007.pdf PDF
B09_Solicitation_Amendment00006_-_Attachment_10_-_Proposed_Equals_0006.doc DOC document
B09_Q_A_Amendment_06_0006.pdf PDF
B09_Solicitation_Amendment00006_Page32_Clauses_0006.pdf PDF
Sol_140P2023R0070_Amd_0006.pdf PDF
B09_Solicitation_Amendment00006_-_Attach_11_-_HazardousMaterials_0006.doc DOC document
B09_Solicitation_Amendment00006_Attachment_04_Solit_Vol_I_Project_Experience_Questionnaire_0006.docx DOCX document
B11_MALU318172_PreBid_20230411_FINAL_0005.pptx PPTX presentation
Sol_140P2023R0070_Amd_0005.pdf PDF
B09_Amendment05_Attachment_SF1442_Pg1_Solit_140P2023R0070_MALU_318172_0005.pdf PDF
B09_Amendment05_PreBid_SignInSheet_MALU318172_0005.jpeg JPEG file
Sol_140P2023R0070_Amd_0004.pdf PDF
B09_Amendment_03_Attachment_Pages_45_46_47_from_B08_Solit_Clauses_Construction_0003.pdf PDF
B09_Amendment_03_Attachment_01_35_92_COLLECTION_MOVE_AND_STORAGE_PROCEDURES_AND_ATTACHMENTS_0003.pdf PDF
Sol_140P2023R0070_Amd_0003.pdf PDF
B08_Solit_140P2023R0070_MALU_318172_REQD_3_21_0002.pdf PDF
Sol_140P2023R0070_Amd_0002.pdf PDF
Sol_140P2023R0070_Amd_0001.pdf PDF
B08_Solit_Attach_03_Construction_Wage_Decision_GA20230039.pdf PDF
B08_Solit_Clauses_Construction_Final_3_21_23_doc.pdf PDF
B08_Solit__Attach_02_Drawings.pdf PDF
B08_Solit_PSP_Vol_II_Solit_Attach_09_SubKPlanForm.doc DOC document
B08_Solit_PSP_Vol_II_Solit_Attach_07_GenRefs_doc.pdf PDF
B08_Solit_PSP_Vol_II_Solit_Attach_08_BidBond.pdf PDF
B08_Solit_PSP_Vol_I_Solit_Attach_05_PastPerf_REQD.docx DOCX document
B08_Solit_PSP_Vol_I_Solit_Attach_04_Exp_REQD.pdf PDF
B08_Solit_PSP_Vol_I_Solit_Attach_06_Price_Schedule.pdf PDF
B08_Solit_Attach_01_Specifications.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MALU 257817 01 26 01 - 2

012721 CONTRACT MODIFICATION PROCEDURES

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare pdring Cross-Out pdring Oval

MALU 257817 01 50 00 - 2

012721 TEMPORARY FACILITIES AND CONTROLS

3. Noise and Acoustics Management

4. Environmental Management

5. Construction Waste Management

1.5 PROJECT CONDITIONS

A. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before NPS acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Temporary materials may be new or used, but must be adequate in capacity for required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

B. Pavement: Comply with Division 32 [Section "Asphalt Paving."] [Section "Concrete Paving."]

[pavement Sections.]

C. Chain-Link Fencing: Minimum 2 inch (50 millimeters), 0.148 inch (3.76 millimeters) thick, galvanized steel, chain-link fabric fencing; minimum 6 feet (1.8 millimeter) high with galvanized steel pipe posts; minimum 2-3/8 inch (60 millimeters) OD (outside diameter) line posts and 2-7/8 inch (73 millimeters) OD corner and pull posts, with 1-5/8 inch (42 millimeters) OD top rails

D. Barrier Tape: Yellow tape Imprinted with "CAUTION: CONSTRUCTION AREA," manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.

E. Wood Enclosure Fence: Plywood, 8 feet (2.4 millimeters) high, framed with four 2 by 4 inch (50 by 100 millimeters) rails, with preservative-treated wood posts spaced not more than 8 feet (2.4 millimeters) apart.

F. Gypsum Board: Minimum 1/2 inch (12.7 millimeters) thick by 48 inches (1219 millimeters) wide by maximum available lengths; regular-type panels with tapered edges. Comply with ASTM C

36/C 36M.

G. Polyethylene Sheet: Reinforced, fire-resistive sheet, 10 mil (0.25-millimeter) minimum thickness, with flame-spread rating of 15 or less per ASTM E 84 and passing NFPA 701 Test Method 2.

H. Dust-Control Adhesive-Surface Walk-off Mats: Provide mats minimum 36 by 60 inches (914 by

1624 millimeters).

2.2 TEMPORARY FACILITIES

A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

pdring Cross-Out

Oval

MALU 257817 01 50 00 - 3

012721 TEMPORARY FACILITIES AND CONTROLS

1. Prefabricated, job built, or a mobile unit; excellent condition, structurally sound, non-flammable exterior construction, weather tight, minimum 300 square feet.

2. Operable windows and security screens, adjustable ventilation.

3. Restroom (minimum of lavatory and toilet, with exhaust fan if room is windowless).

4. Air conditioner and heater.

5. Interior partition with lockable door to divide office

6. Paneling or freshly painted walls, acoustical tile or painted ceilings, and resilient flooring.

7. Two exterior doors with dead bolts keyed from outside,

8. Minimum 20-square-foot landing and steps at each exterior door.

B. Storage and Fabrication Sheds: Temporary weather tight sheds or other covered facilities for storage of materials subject to weather damage. Number and size of structures shall be subject to

Contracting Officer's approval.

C. Toilets: Sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible, sturdy enclosures with privacy locks.

1. Provide separate toilet facilities for men and women.

2.3 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

B. Heating, Ventilation, and Air Conditioning (HVAC) Equipment: Unless Contracting Officer authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

2. Heating Units: Listed and labeled for type of fuel being consumed, by a testing agency acceptable to agency(ies) with jurisdiction, and marked for intended use.

3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with Minimum Efficiency Reporting

Value (MERV) of 8 at each return air grille in system and remove at end of construction.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance and as directed by the Contracting Officer.

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

Cross-Out

MALU_Specs_Birth Home_ Addendum 1
MALU_Specs_Birth Home_ Addendum 13
MALU_Specs_Birth Home_ Addendum 125
MALU_Specs_Birth Home_ Addendum 126

File details come from the government source that posted it. Updated .