This document provides instructions for submitting proposals in response to a solicitation for construction services. The solicitation is to stabilize and rehabilitate the birth home of Martin Luther King Jr. located in the Martin Luther King Jr. National Historical Park in Atlanta, Georgia. Proposals are due no later than the date and time specified in Block 13.a of the SF1442 form included in the solicitation. Offerors must submit their proposals in two separate volumes electronically via email, with technical proposals in Volume I and pricing information in Volume II. Volume I is to include information on the offeror's experience on similar past projects, technical approach, management approach, and past performance references. Key personnel proposed, such as the project manager, superintendent, quality control manager and safety manager, must also be identified in the technical proposal.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 1/4/23
Document No.
140P2023R0070
Document Title MALU 318172 Stabilize and Rehabilitate the Birth Home
(2) To the successful offeror upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the proposal as accepted.
(c) The amount of the proposal guarantee shall be 20% percent of the total proposal price or $3,000,000 whichever is less.
(d) If the successful offeror, upon acceptance of its proposal by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the offeror, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the offeror is liable for any cost of acquiring the work that exceeds the amount of its proposal, and the proposal guarantee is available to offset the difference.
(End of provision)
52.233-2 SERVICE OF PROTEST DEPARTMENT OF THE INTERIOR (SEPT 2006) (DEVIATION)
(JUL 1996)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from John Babcock.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the
GAO.
(c) A copy of the protest served on the Contracting Officer shall be simultaneously furnished by the protester to the Department of the Interior Assistant Solicitor, Acquisitions and Intellectual Property, 1849 C Street, NW, Room 6511, Washington, DC 20240.
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/content/regulations
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— April 11, Tuesday at 1:30PM ET
(c) Participants will meet at— https://acquisition.gov/far/current/html/Subpart%2033_1.html#wp1088681 http://www.acquisition.gov/content/regulations https://acquisition.gov/far/current/html/52_233_240.html#wp1113365 https://acquisition.gov/far/current/html/52_233_240.html#wp1113375
Document No.
140P2023R0070
Document Title MALU 318172 Stabilize and Rehabilitate the Birth Home
Martin Luther King, Jr. NHP in Atlanta, GA (End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the provision.
(b) The use in this solicitation of any Department of Interior Acquisition Regulation (48 CFR Chapter 14) provision with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.
(End of provision)
INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION –
COMPETITIVE SOURCE SELECTION
A. GENERAL
1. Submit, at a minimum, an offer that conforms to the solicitation documents. By submission of an offer, the offeror unconditionally assents to the terms and conditions in this solicitation and in any solicitation attachments. Proposals offering alternative stipulations to the requirements of this solicitation will NOT be considered or accepted.
2. In accordance with FAR 36.209, all firms, prime contractors or subconsultants, involved in developing the design or specifications for this construction solicitation are not eligible and prohibited from receiving any part of this construction award. Proposals from or containing firms under these circumstances will not be considered for award.
B. QUESTIONS
Pre-proposal questions shall be submitted a minimum of 14 days prior to the due date and time for proposals. Submit questions only though email to both of the following:
Contracting Officer, John Babcock, john_babcock@nps.gov
Contract Specialist, Julia Sullivan, Julia_sullivan@nps.gov
C. OFFER DUE DATE AND LOCATION
1. To be considered for award, proposals must be received no later than the date and time noted in Block 13.a of the SF1442 contained in this solicitation. Offerors are responsible for confirming their proposals are received by the due date and time.
D. SUBMISSION REQUIREMENTS
mailto:john_babcock@nps.gov mailto:Julia_sullivan@nsp.gov
Document No.
140P2023R0070
Document Title MALU 318172 Stabilize and Rehabilitate the Birth Home
1. Proposals shall be submitted via email. Proposals submitted via any means other than email shall not be accepted.
2. Proposals shall be sent to all of the following:
a. Contracting Officer, John Babcock, john_babcock@nps.gov.
b. Contract Specialist, Julia Sullivan, Julia_sullivan@nsp.gov.
c. CS_DSC_Proposal_Submission@nps.gov
3. Title subject line for all proposal submissions shall contain the solicitation number, Park-PMIS, and number of total emails, per the following example:
Subj: 140P2023R0070, MALU 318172, email 1 of 3
4. Submit proposals in separate VOLUMES (I and II) in the FORMATS specified, containing CONTENTS required. Each volume shall be submitted in separate email attachments.
5. Size limits:
a. Each email shall be no larger than 30 MB
6. Offerors shall verify receipt of proposals.
E. VOLUME I, TECHNICAL PROPOSAL – FORMAT, ORGANIZATION, CONTENTS
1. FORMAT: Submit (1) one electronic copy. No hard copies shall be submitted.
2. ORGANIZATION: Include folders and files for electronic formats named as follows:
FACTOR 1 – EXPERIENCE
FACTOR 2 – TECHNICAL APPROACH AND SCHEDULE
FACTOR 3 – MANAGEMENT APPROACH
FACTOR 4 – PAST PERFORMANCE
3. CONTENTS:
FACTOR 1 –EXPERIENCE
Subfactor 1A – Project Experience: Submit the attached "Project Experience" form addressing specific ASPECTS below for up to 5 relevant projects completed in the last 7 years. Submit separate forms for each project. Key Trades, if evaluated, are subject to substitution requirements in Section H of this solicitation and resulting contract. NOTE: Submit the same project information for Past Performance (Factor #4) as submitted under this factor.
Subfactor 1B – Key Personnel Submit resumes for key personnel as identified in this solicitation at Section H and listed below. All personnel proposed are subject to substitution requirements contained in this solicitation. There is no preprinted form for this submittal. Key personnel, include Project Manager, Superintendent, Quality Control Supervisor, and Safety Manager
Key Personnel include the following:
1. Project Manager
2. Project Superintendent
3. Quality Control Manager
4. Safety Manager*
*Project Superintendent and Safety Manager can be same person
FACTOR 2 – TECHNICAL APPROACH AND SCHEDULE
mailto:john_babcock@nps.gov mailto:Julia_sullivan@nsp.gov mailto:CS_DSC_Proposal_Submission@nps.gov