This solicitation package seeks proposals for the rehabilitation of the Salt River Visitor Contact Station at Salt River Bay in the U.S. Virgin Islands. The National Park Service is conducting this procurement as a total small business set-aside. Offerors must attend a mandatory pre-proposal conference and site visit on October 21, 2021 to be eligible for award. Proposals are due by 2:00 PM AST on November 8, 2021 in accordance with instructions in the solicitation. The work includes repairing and replacing building systems and features, upgrading accessibility, and other site improvements to rehabilitate the visitor contact station.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SALT RIVER BAY
NATIONAL HISTORICAL PARK &
ECOLOGICAL PRESERVE
CHRISTIANSTED, ST CROIX, USVI
REHABILITATE VISITOR CONTACT STATION
CHRI (SARI)
PMIS NO. 251127
PROJECT SPECIFICATIONS
VOLUME 1 OF 3
(DIVISIONS 1‐14)
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
August 2, 2021 Revised October 12, 2021
BLANK PAGE
CHRI (SARI) 251127
2 AUGUST 2021
00000 - 1
TABLE OF CONTENTS – VOL 1
TABLE OF CONTENTS
VOLUME 1 - DIVISIONS 1 THROUGH 14
VOLUME 2 - DIVISIONS 15 THROUGH 48
VOLUME 3 - APPENDICIES FOR SPECIFICATIONS AND REFERENCE
VOLUME 1
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 000107 - SEALS PAGE
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 011100 - SUMMARY OF WORK
SECTION 012601 - CONTRACT MOD PROCEDURES
SECTION 012700 - CONTRACT LINE ITEMS
SECTION 013100 - PROJECT MANAGEMENT & COORDINATION
SECTION 013216 - CONSTRUCTION SCHEDULE
SECTION 013323 - SUBMITTAL PROCEDURES
SECTION 013323 - SUBMITTAL LIST
SECTION 013513 22 - ARCHEOLOGICAL PROTECTION
SECTION 013523 - OWNER SAFETY REQUIREMENTS
SECTION 014000 - QUALITY REQUIREMENTS
SECTION 014000.A - ACCESSIBILITY INSPECTION REPORT FORM
SECTION 014000.B - ACCESSIBILITY INSPECTION REPORT FORM SAMPLE
STATEMENT OF STRUCTURAL TEST & SPECIAL INSPECTIONS
SECTION 014200 - REFERENCE STANDARDS
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
SECTION 015719 11 - INDOOR AIR QUALITY
SECTION 015719 12 - NOISE ACOUSTICS MANAGEMENT
SECTION 015723 – TEMPORARY STORM WATER POLLUTION PREVENTION
SECTION 016700 - PRODUCT REQUIREMENTS
SECTION 017340 - EXECUTION
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 017419.A - PROJECT WASTER MANAGEMENT PLAN WORKSHEET
SECTION 017419.B – STANDARD SOLID WASTE CONVERSIONS
SECTION 0174 19.C - NON HAZARDOUS SPECIAL WASTE DISPOSAL PERMIT APPLICATION
SECTION 017700 - CLOSEOUT PROCEDURES
SECTION 017823 - OPERATION AND MAINTENANCE DATA
SECTION 017900 - DEMONSTRATION AND TRAINING
SECTION 018113 – SUSTAINABILITY REQUIREMENTS FOR NON-LEEDTM PROJECTS
DIVISION 02 - EXISTING CONDITIONS
SECSECTION 024119 - SELECTIVE DEMOLITION
DIVISION 03 - CONCRETE
SECTION 033000 - CAST-IN-PLACE-CONCRETE
00000 - 2
DIVISION 04 - MASONRY
SECTION 042000 - UNIT MASONRY
SECTION 042200 - CONCRETE UNIT MASONRY
SECTION 044313.13 - ANCHORED STONE MASONRY VENEER
DIVISION 05 - METALS
SECTION 051200 - STRUCTURAL STEEL
SECTION 055000 - METAL FABRICATIONS
SECTION 057300 - DECORATIVE METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
SECTION 061000 - ROUGH CARPENTRY
SECTION 061053 - MISCELLANEOUS ROUGH CARPENTRY
SECTION 062013 - EXTERIOR FINISH CARPENTRY
SECTION 062023 - INTERIOR FINISH CARPENTRY
SECTION 064113 - WOOD-VENEER-FACED ARCHITECTURAL CABINETS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 071416 - COLD FLUID-APPLIED WATERPROOFING
SECTION 071600 - POLYMER MODIFIED CEMENT WATERPROOFING
SECTION 072100 - THERMAL INSULATION
SECTION 072600 - VAPOR RETARDERS
SECTION 075613 - FLUID-APPLIED MEMBRANE ROOFING
SECTION 076200 - SHEET METAL FLASHING AND TRIM
SECTION 077123 - MANUFACTURED GUTTERS
SECTION 077200 - ROOF ACCESSORIES
SECTION 078413 - PENETRATION FIRESTOPPING
SECTION 078443 - JOINT FIRESTOPPING
SECTION 079200 - JOINT SEALANTS
SECTION 079210 - FLUID APPLIED FLASHINGS
DIVISION 08 - OPENINGS
SECTION 081213 - HOLLOW METAL DOORS & FRAMES
SECTION 081416 - FLUSH WOOD DOORS
SECTION 083483 - FLOOR DOORS
SECTION 084113 - ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
SECTION 085113 - ALUMINUM WINDOWS
SECTION 087100 - DOOR HARDWARE
SECTION 088000 - GLAZING
SECTION 089119 - FIXED LOUVERS
00000 - 3
DIVISION 09 - FINISHES
SECTION 092216 - NON-STRUCTURAL METAL FRAMING
SECTION 092400 - CEMENT PLASTERING
SECTION 092900 - GYPSUM BOARD
SECTION 093013 - CERAMIC TILING
SECTION 099123 - INTERIOR PAINTING
SECTION 099300 - STAINING AND TRANSPARENT FINISHING
SECTION 099600 - HIGH-PERFORMANCE COATINGS
SECTION 099653 - ELASTOMERIC COATINGS
DIVISION 10 - SPECIALTIES
SECTION 101423.16 - ROOM-IDENTIFICATION PANEL SIGNAGE
SECTION 102800 - TOILET, BATH, AND LAUNDRY ACCESSORIES
SECTION 104300 - EMERGENCY AID SPECIALTIES
SECTION 104413 - FIRE PROTECTION CABINETS
SECTION 104416 - FIRE EXTINGUISHERS
SECTION 105116 – LOCKERS
SECTION 107500 – FLAGPOLES
DIVISION 11 - EQUIPMENT
SECTION 118129 - HORIZONTAL FALL PROTECTION
DIVISION 12 - FURNISHINGS
SECTION 122413 - ROLLER WINDOW SHADES
SECTION 123661.19 - QUARTZ AGGLOMERATE COUNTERTOPS
DIVISION 13 - SPECIAL CONSTRUCTION
SECTION 133100 - SHADECLOTH FABRICS
DIVISION 14 - CONVEYING EQUIPMENT
NOT APPLICABLE
END OF SECTION 00 00 00
000107 - 1
PROFESSIONAL SEALS
000107 – PROFESSIONAL SEALS
CIVIL ENGINEER:
John Prorock, PE
PE # 1711-E
Divisions:
024119, 221353, 311000, 312000, 312500, 321313, 321443, 333000, 334100
000107 - 2
PROFESSIONAL SEALS
LANDSCAPE ARCHITECT:
Kevin Vollnogle, PLA, ASLA License # 1637-LA Divisions: 329200, 329300
000107 - 3
PROFESSIONAL SEALS
ARCHITECT:
Aaron Bowman, AIA Registration # 1639-A Divisions: 01-32 Except where indicated as prepared by other design professionals below
000107 - 4
PROFESSIONAL SEALS
STRUCTURAL ENGINEER:
Dean W Ussery, PE
PE # 0-47138-1B
Divisions: 033000, 042200, 051200, 061000
000107 - 5
PROFESSIONAL SEALS
PLUMBING ENGINEER
MECHANICAL ENGINEER:
William Billard, PE
PE # USVI 0-51079-1B
Divisions: 22, 23
000107 - 6
PROFESSIONAL SEALS
ELECTRICAL ENGINEER:
Brian Bates, PE
PE # USVI 0-53283-1B
Divisions: 26, 27, 28
END OF SECTION 000107
011100 - 1
SUMMARY OF WORK
SECTION 011100 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of site.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Conduct of Operations
9. Work Restrictions.
10. Special Construction Requirements.
11. Geophysical Report.
12. Geotechnical Report.
13. Asbestos, Lead Based Paint, and Indoor Air Quality Report
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: This project will take place at the Salt River Bay National Historical Park and Ecological Preserve to the west of Christiansted on St Croix, USVI. Project will focus on the Visitor Contact Station site.
B. The Work consists of the following:
1. The Work includes renovation of the Visitor Contact Station, including demolition of the upper levels, rebuilding of the structures, renovations of the structure’s lower levels, and site utilities, site work for parking and installing a new drive and entrance.
2. Refer to Section 012700 – Contract Line Items for base bid and bid options for the project.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in 1 phase.
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this
011100 - 2
Contract with work performed under separate contracts.
B. Preceding Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.
1. None anticipated
C. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. None anticipated.
1.5 GOVERNMENT-FURNISHED MATERIALS
A. Government will furnish products indicated.
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.
3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.
4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into the Work.
B. Government-Furnished Products:
1. None anticipated.
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have use of the site for construction operations. Do not disturb portions of project site beyond areas in which the Work is indicated.
1. Limit site disturbance, as indicated on the drawings. If not indicated, earthwork and clearing of vegetation shall be limited, to 20 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; and 15 feet beyond main utility branch trenches.
B. Storage of Materials: Confine storage of materials to the construction line of Limit of Site Disturbance.
011100 - 3
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. Existing Protected Agave Plants are located out of the Limit of Site Disturbance but shall be protected.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state/territorial load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.7 PUBLIC USE OF SITE
A. The road within the limits of the project will be closed to the general public during construction.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will not occupy the premises during entire construction period. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing roads. Do not close or obstruct roads for extended periods of time without written permission from the Contracting Officer (CO).
B. New Buildings
011100 - 4
1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.
b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.
c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
1.9 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.10 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: None unless approved by the Contracting Officer.
2. Early Morning Hours: None unless approved by the contracting officer.
3. Hours for noisy equipment: 8:00 a.m. to 4:00 p.m.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
011100 - 5
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government, or others, unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: Outages during weekday working hours not to exceed 4 hours consecutively.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.12 GEOPHYSICAL REPORT
A. A geophysical report of the site and structures entitled Geophysical Report at the Salt River Bay National Historic Site and Ecological Preserve, St. Croix, USVI date January 7, 2021has been prepared by Manuel E. Candelario Cosme, MSCE, PE & Tanayshali Melendez, BSCE, both of Jaca & Sierra Testing Laboratory | Geotechnical Engineers.
B. This report is included in this specification package as Appendix A.
1.13 GEOTECHNICAL REPORT
A. A geotechnical report of the site and structures entitled Geotechnical Report at the Salt River Bay Historic Site, St. Croix, USVI date January 8, 2021has been prepared by Manuel E. Candelario Cosme, MSCE, PE & Manuel E. Porrata Arbona, MECE, EIT, both of Jaca & Sierra Testing Laboratory | Geotechnical Engineers.
B. This report is included in this specification package as Appendix B.
1.14 ASBESTOS, LEAD BASED PAINT, AND INDOOR AIR QUALITY REPORT
A. An asbestos, lead base paint and indoor air quality investigation report of the structures entitled Asbestos, LBP and Fungi Inspection Report at National Park Services, Salt River Bay National Park dated April 2021 has been performed by Maxcess Armantrading and prepared by Dr. John Verstraaten of Environmental Concepts, Inc.
011100 - 6
B. This report is included in this specification package as Appendix C.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
012601 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 012601 – CONTRACT MODIFICATION PROCEDURES
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
012601 - 2
CONTRACT MODIFICATION PROCEDURES
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
14 JULY 2021
012601 - 3
CONTRACT MODIFCATION PROCEDURES
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
012601 - 4
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
012601 - 5
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead ....................... 10% Profit ............................. 10%
012601 - 6
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
12 OCTOBER 2021
012700 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 0001 – Demolition of Existing Buildings A, B, C, D, E and I and Site Facilities
1. This item consists of the associated work with the demolition of existing Buildings A, B, C, D, E and I (refer to the Key Plan on the General sheets of the Contract Drawings) to the slabs and the demolition of the surrounding site facilities, courtyard elements and miscellaneous appurtenances as specified in the Contract Drawings with the exception of Buildings F and G. The work associated with the demolition of Buildings F and G is covered under a separate optional Contract Line Item below.
2. Measurement for payment will be per monthly progress and substantial completion.
3. Payment will be made at the contract price per lump sum price
B. Contract Line Item No. 0002 – Rehabilitation of Visitor Contact Station.
1. This item consists of the new construction of areas A (Visitor Contact Station), B (Concrete shade structure covering viewing & interpretive areas); D&E (educational spaces); associated utilities and site work; landscaping in the courtyard; repair and rehabilitation of existing structures; all finishes and interior casework; lighting and electrical work in the buildings and around the courtyard; HVAC and associated ductwork; rainwater catchment and piping to existing cisterns; plumbing systems and all associated fixtures and equipment. This item includes installation of piping stub-outs for future connections to Building F as follows: 1) Domestic water: install the 3/4" domestic water piping feed for Building F within the foundation of new Building A as specified and extend approximately 5-feet beyond the foundation of new Building A, stub and cap for future connection to Building F; 2) Sanitary:
install the 3” sanitary line for Building F within the foundation of new Building A as specified and extend approximately 5-feet beyond the foundation of new Building A, stub and cap for future connection to Building F.
012700 - 2
C. Contract Line Item No. 0003 – Construction of ABAAS Parking and Sidewalks
1. This item consists of civil and landscape work for new parking and sidewalks
D. Contract Line Item No. 0004 – Option A: Photovoltaic System
1. This item consists of a new photovoltaic system throughout the buildings.
E. Contract Line Item No. 0005 – Option B: Site Landscaping
1. This item consists of additional site landscaping adjacent to the buildings beyond the courtyard landscaping provided in Line Item No. 2.
F. Contract Line Item No. 0006 – Option C: Rehabilitation of Upper Parking Area
1. This item consists of the rehabilitation of the upper parking area, additional site demolition, additional parking, vehicular turnaround, and related site landscaping and rain garden area.
G. Contract Line Item No. 0007 – Option D: Rehabilitation of Lower Parking Area
1. This item consists of the rehabilitation of the lower parking area, stair and sidewalk leading up to the buildings, and the associated site and landscape work.
H. Contract Line Item No. 0008 – Option E: Rehabilitation of Driveway
1. This item consists of the rehabilitation of the existing drive, pulloffs, and the associated site and landscape work.
I. Contract Line Item No. 0009 – Option F: Construction of Entry Gate and alternate Signage
1. This item consists of the construction of a new entry gate and associated signage XXX repair and rehabilitation of existing structures
J. Contract Line Item No. 0010 – Option G: Construction of Mockup Panel
1. This item consists of construction of a project mockup panel for testing and material review for the Visitor Contact Station complex.
012700 - 3
K. Contract Line Item No. 0011 – Option H: Construction of Concrete Shade Structure at area C
1. This item consists of construction of the cast-in-place concrete shade structure frame and shade material system for area C.
L. Contract Line Item No. 0012 – Option I: Construction of Building for Area F
1. This item consists of the new construction of area F (Office and Maintenance Storage space) including all appurtenances; all finishes and interior casework; lighting and electrical work in the buildings; HVAC and associated ductwork; rainwater catchment and piping to existing cisterns; plumbing systems and all associated fixtures and equipment.
M. Contract Line Item No. 0013 – Option J: Radio Repeater System
1. This item consists of construction of a specified Radio Repeater for the project, including testing and materials for the Visitor Contact Station structure.
N. Contract Line Item No. 0014 – Option K: Cell Booster System
1. This item consists of construction of a specified Cell Booster System for the project, including testing and materials for the Visitor Contact Station structure.
O. Contract Line Item No. 0015 – Option L: Demolition of existing Buildings F and G
1. This item consists of the associated work with the demolition of existing Buildings F and G (refer to the Key Plan on the General sheets of the Contract Drawings) to the slabs and the demolition of the associated site facilities and miscellaneous appurtenances as specified in the Contract Drawings. All references to work associated with the demolition of Buildings F or G in the contract drawings or other contract documents shall be considered to be part of this Contract Line Item.
END OF SECTION 012700
013100- 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Requests for Information (RFIs).
5. NPS/DSC SharePoint Project Website.
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
013100- 2
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination
Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.
Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
013100- 3
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire- alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
013100- 4
8. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Contracting Officer (CO) will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.
If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Preparation Format: AutoCad.dwg, Version 2013, operating in Microsoft Windows operating system.
3. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
4. Contracting Officer (CO) will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the
Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre- Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. Hurricane Preparedness Plan
6. A list of Subcontractors for this project.
7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
9. Waste Management Plan.
10. Quality Control Plan.
11. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
12. Indoor Air Quality (IAQ) Management Plan.
13. Historic Preservation Treatment Plan.
013100- 5
14. Tropical Storm Response Plan (per Specification 013523)
15. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
E. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract
Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
013100- 6
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum.
All contract changes will be processed following the terms and conditions of the contract.
1.6 NPS/DSC SHAREPOINT PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website, or a similar internet-based project management website provided either by NPS or an NPS administered separate contract, for communication throughout the contract period. All references to “NPS/DSC SharePoint Project website”, or similar, in these specifications shall mean any such project management website provided either by NPS or an NPS administered separate contract.
B. NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Schedule of Values.
12. Drawing and specification document hosting, viewing, and updating.
13. Online document collaboration.
14. Reminder and tracking functions.
15. Archiving functions.
16. Notification of submittal and RFI statuses and current responsible party.
17. Permits and addendums
013100- 7
C. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website.
Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
D. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
E. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Schedule of Values
9. Payments to Contractor.
10. Payroll reports.
11. Contract time.
12. Liquidated damages.
13. Contractor Performance Evaluation.
14. Display of Hotline posters.
15. Notice to proceed.
16. Correspondence procedures.
17. NPS/DSC SharePoint Project website.
18. Acceptance/rejection of work.
19. Progress meetings.
20. Submittal procedures.
21. NPS Final Accessibility Inspection.
22. Environmental requirements.
23. Permit requirements.
24. As-constructed drawings/operation and maintenance…