B08_Solicitation_Attachment_7_Bid_Sheet__8_17_26_(1_pg).pdf
PDF 92 KB Posted
- Attached to
- St. Marks NWR Aucilla Tram Road Bridge DB
- Solicitation number
- 140FC126Q0044
- Issued by
- Not on record
About this file
This is a Schedule of Items for a design-build contract dated 17 August 2026 for design and construction services related to the Aucilla Tram Bridge Deck, Water Control Structure Boards, and Guardrails at St. Marks National Wildlife Refuge.
The contract includes seven line items (CLINs) covering pre-construction and design services, plus construction services. CLINs 100-106 comprise the design phase: Permitting/Permits (CLIN 100), Geotechnical Investigation if required (CLIN 101), Topographic Survey if required (CLIN 102), 35% Schematic Design Services (CLIN 103), 65% Design Development Services (CLIN 104), 95% Construction Documents Services (CLIN 105), and 100% Construction Documents Services (CLIN 106). All design items are priced as lump sum. CLIN 400 covers Construction Services as a firm-fixed price lump sum that includes all labor, materials, equipment, supervision, subcontracting, testing, temporary work, bonding, overhead, profit, and other costs necessary to construct and deliver the proposed approach. Offerors must provide detailed pricing and cost element breakdowns for each CLIN down to the sub-item level in the Scope of Work, including labor, materials, equipment, competitive subcontractor quotes, overhead, bonding, and profit. All CLINs require pricing entries; if a CLIN is not separately priced or is included in another CLIN, offerors must enter $0.00 and identify where costs are included. Blank entries may result in proposal rejection. Design development after contract award does not reopen or modify the firm-fixed construction price except through written contract modification by the Contracting Officer.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
17 August 2026
Design-Build Services for Aucilla Tram Bridge Deck, Water Control Structure Boards, and Guardrails at St. Marks National Wildlife Refuge
Item # Description Unit Amount
100 Permitting/Permits, if applicable Lump Sum $___________
101 Geotechnical Investigation, if required by Lump Sum $___________ Proposed technical approach
102 Topographic Survey, if required by Lump Sum $___________ Proposed technical approach
103 35% Schematic Design Services Lump Sum $___________
104 65% Design Development Services Lump Sum $___________
105 95% Construction Documents Services Lump Sum $___________
106 100% Construction Documents Services Lump Sum $___________
SUBTOTAL CLINS (100-106) $___________
400 Construction Services Lump Sum $___________
TOTAL AMOUNT (All CLINS 100-106 and 400) $___________
CLIN 400 NOTE: Offerors shall submit a firm-fixed price for Construction Services with their proposal. The price shall include all labor, materials, equipment, supervision, subcontracting, testing, temporary work, bonding, overhead, profit, and other costs necessary to construct and deliver the proposed technical approach in accordance with the Statement of Work. Design development after award does not reopen or modify the awarded firm-fixed price except through a written contract modification issued by the Contracting Officer.
Provide pricing and cost element break downs for each of the items listed, down to the sub item level in the Scope of Work, in enough detail to allow adequate price analysis. This could include, but is not limited to, labor, materials, equipment, competitive subcontractor quotes, overhead, bonding and profit.
Offerors shall enter a price for every CLIN. If a CLIN is not separately priced, is included in another CLIN, or is not required for the proposed technical approach, enter $0.00 and identify where the associated cost is included. Blank entries may result in rejection of the proposal.
File details come from the government source that posted it. Updated .