This is a Statement of Work (SOW) for Design-Build Services for the Aucilla Tram Road Bridge and Water Control Structure (WCS) Access Improvements at St. Marks National Wildlife Refuge in Florida. The U.S. Fish and Wildlife Service (USFWS) seeks a design-builder to provide permanent, safe access to stop-log boards and water control retaining devices; replace existing stop-log boards and retention components; alter the cantilevered bridge deck and/or extend the WCS operating face as necessary; and replace deficient bridge rail and traffic-safety features. The current configuration requires personnel to crawl beneath the bridge and enter water to operate the boards, creating safety hazards including exposure to flow and alligators.
The design-builder must provide all professional and construction services including field verification, structural evaluation, nondestructive investigation, design, technical specifications, construction cost and schedule estimates, permit support, fabrication, installation, testing, training, and closeout. The contract is firm-fixed-price, with design milestones requiring 35% schematic design submittal within 60 calendar days of design notice to proceed (NTP), 65% design development submittal within 120 days, 95% construction documents within 160 days, and 100% final documents within 190 days. Construction must achieve substantial completion within 240 calendar days and final completion within 270 days after construction NTP. The design must accommodate a 96-inch-wide government truck, replace timber stop-logs with heavy-duty aluminum suitable for brackish water, implement a positive corrosion-resistant retention system operable from above, and replace bridge guardrails with low-maintenance corrosion-resistant systems. The solution must enable operation by two trained refuge employees without water entry, crawling beneath the bridge, or reliance on portable equipment requiring recurring transport and assembly. The design-builder is responsible for obtaining permits and environmental compliance, maintaining structural integrity of existing bridge and WCS concrete, and conducting an operational demonstration verifying all stop-log boards and retaining devices can be released, removed, installed, and secured from above using furnished tools or permanent lifting assistance.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
St. Marks National Wildlife Refuge Aucilla Tram Road Bridge / WCS Access Improvements 1 of 19 Draft Revised August 2026
STATEMENT OF WORK for
DESIGN-BUILD SERVICES for Aucilla Tram Road Bridge and Water Control Structure Access
Improvements at the
St. Marks National Wildlife Refuge, Florida (Approximately 30.14093, -84.13868)
REVISION – SEPTEMBER 3, 2026
1. GENERAL INFORMATION
a. The U.S. Fish and Wildlife Service (USFWS) requests Design-Build Services to:
(1) provide permanent, safe, and practical access from the bridge deck or an integral permanent operating platform to all stop-log boards and retaining devices;
(2) replace the existing stop-log boards and associated retention and lifting components; (3) alter the cantilevered bridge deck and/or extend the water control structure (WCS) operating face as necessary; and (4) replace deficient bridge rail and related traffic-safety features. Specific requirements are listed in Section 5.
b. This project addresses the Aucilla Tram Road Bridge and the existing WCS at St.
Marks National Wildlife Refuge. The WCS controls water levels between two habitat impoundments using removable stop-log boards. The boards are located beneath the north-side bridge-deck overhang and are retained within existing concrete guide slots using small wood wedges. The current configuration requires Refuge personnel to crawl beneath the bridge and enter water to release, remove, install, and secure the boards, creating hazards that include flow and alligator exposure. The completed work shall provide permanent access from above to all stop-log boards and all retaining devices without requiring personnel to enter the water or crawl beneath the bridge. Routine operation shall not depend on transporting, assembling, disassembling, and storing a portable davit, hoist, temporary platform, or similar equipment.
c. Provide all professional and construction services necessary to complete this project, including field verification, structural evaluation, nondestructive investigation as needed, design, technical specifications, construction cost and schedule estimates, permit support, fabrication, installation, testing, training, and closeout. Existing bridge plans, inspection information, and photographs are provided. A full topographic survey and geotechnical investigation are not anticipated unless the selected design requires foundation, substructure, or other subsurface work. Any proposed full survey or geotechnical investigation shall be supported by written technical justification and authorized by the Contracting Officer before performance.
Aucilla Tram Road Bridge / WCS Access Improvements 2 of 19
d. Location: See Appendix A for driving directions to St. Marks NWR and the project site.
2. DESIGN SERVICES
a. General Requirements
i. The Contractor shall incorporate constructability, site accessibility, worker and public safety, durability, operations and maintenance, environmental and permitting impacts, economy of scale, life-cycle cost, and budget requirements into the design. The completed solution shall be permanent, straightforward to operate, low-maintenance, and capable of routine operation by no more than two trained Refuge employees. It shall provide access to every stop-log board and its retaining device. Permanently installed or integral manual lifting assistance may be used. Primary reliance on portable equipment requiring recurring transport, assembly, disassembly, or off-site storage is not acceptable unless specifically approved in writing by the Government after the Contractor demonstrates that the approach provides an operationally superior, lower-maintenance solution. Maintain the structural integrity and load-carrying capacity of the existing bridge and WCS. Wildlife and habitat protection, both during and after construction, shall be a design factor.
ii. Basis of Design: Design in accordance with all applicable Federal, State, and Local codes and regulations (latest edition at the time of contract award) with the following establishing the minimum requirements:
iii. Key Personnel: The key personnel specified in this contract are essential to work performance. At least 30 days prior to the Contractor voluntarily diverting any of the specified individuals to other programs or contracts the Contractor shall notify the Contracting Officer and shall submit a justification for the diversion or replacement and a request to replace the individual. The request must identify the proposed replacement and provide an explanation of how the replacement's skills, experience, and credentials meet or exceed the requirements of the contract. If the employee of the Contractor is terminated for cause or separates from the contractor voluntarily with less than thirty days’ notice, the Contractor shall provide the maximum notice practicable under the circumstances. The Contractor shall not divert, replace, or announce any such change to key personnel without the written consent of the Contracting Officer. The contract will be modified to add or delete key personnel as necessary to reflect the agreement of the parties.
iv. Site/Topographic Survey: Existing plans and inspection information shall be used as the design baseline, supplemented by field measurements sufficient to verify bridge-deck geometry, WCS geometry, guardrail locations, and site access. A full topographic survey is not anticipated. If the selected design requires a survey, the Contractor shall submit written technical justification and obtain Contracting Officer authorization before performing it. Any required survey shall be prepared by a Registered Land Surveyor licensed in Florida, incorporated into the drawings as an Existing Conditions sheet, and included with the 35% Documents.
v. Geotechnical Investigation: A geotechnical investigation is not anticipated because the project is intended to retain the existing bridge foundations, substructure, and WCS concrete structure. If the selected design
Aucilla Tram Road Bridge / WCS Access Improvements 3 of 19 introduces new foundations, changes foundation loading, or otherwise requires subsurface data, the Contractor shall submit written technical justification and obtain Contracting Officer authorization before performing the investigation. Any authorized investigation shall be performed by an independent testing laboratory, and the report shall be prepared and sealed by a Registered Geotechnical Engineer licensed in Florida and included with the 35% Documents.
vi. Existing Conditions Verification and Nondestructive Investigation: Before the 35% submittal, field-verify the bridge-deck thickness and overhang, exterior tee-beam location, guardrail anchorage, WCS geometry, number and dimensions of all stop-log boards, concrete guide-slot geometry, wood-wedge locations, and operating clearances. Use ground-penetrating radar, a cover meter, or other appropriate nondestructive methods wherever deck cutting, drilling, coring, or new anchorage is proposed. Do not rely solely on nominal dimensions.
vii. Buried electrical-power and internet lines are known to exist within the Lighthouse Road right-of-way; exact locations are unknown. The Design- Builder shall verify utility locations before excavation, drilling, anchoring, or other potentially conflicting work.
viii. Operational Design Basis: The design shall address both required operating functions: (1) releasing and re-securing the stop-log retaining devices, and (2) removing, installing, and manipulating every stop-log board. The design shall account for board binding due to debris, marine growth, sediment, or differential water pressure and shall provide safe mechanical advantages where needed.
ix. Drawing Standards:
1. Furnish full, complete, accurate and coordinated architectural, civil engineering, structural engineering, mechanical engineering, electrical engineering, and landscape architectural working drawings and schedules.
2. All drawings shall be prepared using an AutoCAD software product capable of providing electronic files in .dwg and .pdf formats. As part of the final submittal, provide all drawing files (.dwg & .pdf). Include all associated files such as .ctb, .stb, .pc3, and .pmp files as well as all referenced files attached to and corresponding to each final .dwg file. Adobe .pdf files of each .dwg file shall be submitted as electronic files at the final submittal
3. General: Ensure that drafting and lettering on all drawings is done clearly and to a scale that promotes accurate communication of the subject information.
4. Sheet size: 11” X 17” (ANSI B) or 17" X 22" (ANSI C) with 1-inch borders.
5. Lettering size: 1/8" (actual size) minimum height.
6. Minimum scale of floor plans: 1/8"=1"-0".
7. Title Blocks: The Design-Builder shall use a generic USFWS
Cover Sheet and Title Block for their sheet sizes. Company and project team information can be presented as desired on the generic sheets.
Aucilla Tram Road Bridge / WCS Access Improvements 4 of 19
8. Index to drawings: on first sheet (Title Sheet).
9. Location/Vicinity map: On first sheet (Title Sheet).
10. Project Number: Place FWS furnished Project Number on each drawing sheet in the appropriate place in each title block.
11. Asset Numbers, Work Order Numbers, etc: Place FWS furnished asset numbers and other data on the Title Sheet as directed by FWS Project Manager.
12. Graphic Scale: All drawings shall have a graphic scale in both English and Metric units for all scales used on that sheet.
13. Arrange all categories of drawings, i.e.; A-1, A-2, A-3; M-1, M-2, M-3, etc. so that individual buildings and their respective plans, sections, details, etc. within that category are grouped together in such a way that they can easily be separated or removed from the drawings. Do not mix one building’s details with another.
x. Specification Standards:
1. Specifications shall be written specifically for this project. Provide downloadable files, containing all specification sections with the final Contract Document submittal. Note: Copy the specifications onto a USB drive as a single document (file) and copy each section as a separate document (file). Adobe .PDF files of each specification section shall be submitted on compact disks at the final submittal. If a proprietary software program is used, the final specification submittal shall be exported to Microsoft Word for inclusion with the 95% and As-Built drawings.
2. FWS will provide Division 1 specifications.
3. References to “Owner” shall be changed to “Government”.
4. References to “Architect” or “Engineer” shall be changed to “Contracting Officer or their representative”.
xi. Firm-Fixed Price and Cost Control: The total design-build price, including construction, is established at contract award and is firm-fixed. The Design-Builder shall complete the design and construction within the awarded price and shall not cumulatively price mutually exclusive technical approaches.
1. With the 35% Schematic Design submittal, the Design-Builder shall provide one construction cost estimate reconciling the current design to the awarded construction price. The estimate shall identify major quantities, subcontracted work, assumptions, and any material cost risks.
2. If the estimate indicates that the design may exceed the awarded price, the Design-Builder shall promptly notify the Contracting Officer and revise the design as necessary to remain within the awarded price while continuing to satisfy all contract requirements. Government review of the estimate does not modify the firm-fixed contract price.
xii. Construction Schedule Estimate: The Design-Builder shall provide an estimated construction schedule and is responsible for:
Aucilla Tram Road Bridge / WCS Access Improvements 5 of 19
1. Verify Refuge closure dates with the Refuge Manager.
2. Identify items or services that require a long lead time greater than three weeks.
3. Identify any construction activities that may start early such as sitework, foundation, etc. that will expedite the overall period of performance.
xiii. Design Calculations: Submit final PE stamped calculations supporting all applicable design elements, including:
1. Structural analysis of the existing bridge deck, cantilevered overhang, guardrail anchorage, and any new WCS guide frame, sill, brackets, or anchors.
2. Hydraulic loading and sealing calculations for new stop logs, guides, or WCS extensions; confirmation that existing water-level-control elevations and clear flow area are maintained; and other calculations directed by the FWS Engineering Project Manager.
xiv. NEPA/Permit Responsibility: The Design-Builder shall obtain and pay for permits, licenses, and inspection fees necessary for the awarded technical approach, as refined during design. FWS will assist with compliance under the National Environmental Policy Act (NEPA) only. The design shall minimize work in the water, disturbance of the channel and wetlands, and impacts to listed species and habitat. The Environmental Permit Plan shall identify confirmed requirements, assumptions, contingencies, responsible personnel, agency contacts, and the anticipated permit schedule associated with the awarded technical approach. The project site is on U.S. Government land and is exempt from County or City building permits.
1. No hydraulic study is anticipated when the selected design maintains the existing WCS opening, control elevations, flow path, and water-level-management function. If the selected design changes any of those conditions, the Design-Builder shall identify and perform the necessary hydraulic analysis and permit coordination.
xv. Design-Build Milestone Schedule and Period of Performance
1. Design Milestones: The Design-Builder shall complete the design phases by the following deadlines, measured in calendar days after issuance of the Design Notice to Proceed (NTP-Design):
a. 35% Schematic Design Submittal: 60 calendar days after NTP-Design.
b. 65% Design Development Submittal: 120 calendar days after NTP-Design.
c. 95% Construction Documents Submittal: 160 calendar days after NTP-Design.
d. 100% Final Construction Documents Submittal: 190 calendar days after NTP-Design.
2. Construction NTP and Completion: Following Government acceptance of the 100% Final Construction Documents, the
Aucilla Tram Road Bridge / WCS Access Improvements 6 of 19
Contracting Officer will issue the Construction Notice to Proceed (NTP-Construction). The Design-Builder shall:
a. Start construction upon issuance of NTP-Construction.
b. Achieve Substantial Completion within 240 calendar days after NTP-Construction.
c. Achieve Final Completion within 270 calendar days after NTP-Construction, including testing, cleanup, punch-list work, and closeout activities.
3. Design Process
a. Design Review Meetings: Periodically meet with FWS representatives to review the design and discuss and resolve issues. These meetings may be TEAMS calls or onsite. Meeting times and locations shall be as agreed to by Design-Builder and FWS, but generally there will be a minimum of two on–site project meetings; 1) Pre-proposal, and 2) Schematic Design (35%) Review Meeting. The Design Development (65%) and Construction Document (95%) review meetings may be TEAMS conference calls.
i. Meeting minutes shall be kept and distributed in draft by the Design- Builder within 72 hours of the meeting to the FWS Contracting Officer’s Representative, the FWS Contracting Officer, the FWS Refuge Manager, and any Design-Builder consultants or subcontractors for review. The Design-Builder shall make any necessary corrections and return them to the FWS Contracting Officer’s Representative. After acceptance by the FWS Contracting Officer’s Representative, the meeting minutes shall be redistributed in final form to the same group named above. The final minutes shall become part of the official contract file.
b. Design Kickoff Meeting: A Design Kick-Off meeting will be held as a conference call; however, if the Design-Builder that is awarded this contract does not attend the onsite pre-bid meeting, this Design Kick-off meeting will be held onsite. The time and date of this meeting will be mutually agreed upon by the Refuge Manager, the Design-Builder, the FWS Engineering Project Manager and the FWS Contract Officer. The purpose of the meeting will be to review the Contract requirements, review the design requirements and process, discuss the existing conditions, and start the schematic or conceptual design process. Meeting minutes shall be kept and distributed by the Design-Builder contractor within 72 hours of the meeting.
The final minutes shall become part of the official contract file.
c. Schematic Design (SD) 35%: Validate and develop the technical approach included in the awarded proposal. The Design-Builder may evaluate reasonable design refinements necessary to satisfy the performance requirements, including refinements involving deck modification, WCS-guide extension, or a coordinated hybrid. The Design-Builder remains responsible for delivering a compliant solution within the awarded firm-fixed price. Any materially different Government-directed change to the awarded technical approach shall be addressed through written direction from the Contracting Officer. Prepare and submit the 35% package for Government review and conduct the onsite design review meeting.
i. Deliverables: Two sets of the following items shall be present and submitted to the FWS Project Manager 21 calendar days prior to this design review meeting. One set shall be mailed to the Refuge, and one
Aucilla Tram Road Bridge / WCS Access Improvements 7 of 19 set shall be mailed to the FWS PM/COR. Addresses to be provided prior to submittal. Note that failure to fulfill this list of elements may delay payment for the 35% phase until all documents are received.
1. Sealed copies of the Geotechnical Report, if one was completed.
2. Stamped/signed site topographic survey, if one was completed.
3. Record copy of the previous meeting’s accepted minutes.
4. Draft Specifications or at a minimum Specifications Table of Contents showing all sections that will be utilized.
5. Design Narrative with Calculations
6. Environmental Permit Plan. Identify the permits and agency coordination applicable to the awarded technical approach, as refined during schematic design. Identify confirmed requirements, assumptions, responsible personnel, agency contacts, anticipated schedule, and assistance required from FWS.
7. Technical Approach Validation Memorandum. Document how the awarded technical approach, including any proposed refinements, satisfies the structural, operational, hydraulic, environmental, safety, durability, maintenance, constructability, schedule, and firm-fixed-price requirements. Include concept-level plans, sections, principal dimensions, and the basis for advancing the approach into Design Development.
8. Dimensioned Operational Access Study showing how Refuge personnel will reach, release, lift, lower, reinstall, and secure every stop-log board and retaining device from above with simple tools.
Show guardrail configuration, operator position, tools or installed lifting assistance, clearances, and security provisions.
9. Preliminary manufacturer data for proposed aluminum stop logs, guide systems, seals, lifting hardware, and top-operated retention components.
d. Design Development (DD) 65%: Fully define and develop the awarded technical approach, as validated and refined during the 35% review, and incorporate all Government comments. At the end of Design Development, the bridge modification, WCS access arrangement, stop-log and retention system, guardrail system, structural details, operating method, and permit path shall be sufficiently defined for the Government to understand the complete solution.
i. Deliverables: Two sets of the following items shall be present and submitted to the FWS Project Manager 21 calendar days prior to this design review meeting. One set shall be mailed to the Refuge, and one set shall be mailed to the FWS PM/COR. Addresses to be provided prior to submittal. Note that failure to fulfill this list of elements may delay acceptance and payment for the 65% phase until all documents are received.
1. Coordinated Construction Documents developed to the 65% phase and reflecting the awarded technical approach, as validated and refined during the 35% review.
Aucilla Tram Road Bridge / WCS Access Improvements 8 of 19
2. Record copy of the previous meeting’s accepted minutes.
3. Draft Specifications with submittal register
4. Design Narrative with Calculations
5. Evidence of environmental permit(s) submitted
e. Construction Documents (CD) 95%: Develop drawings and technical specifications that fully describe the work to be constructed and that are suitable for Government review and completion of the final construction documents, incorporating Government DD review comments. Prepare and submit a Construction Document submittal for Government review and comment. Submit all drawings, specifications, engineering calculations, and other required data to the Contracting Officer’s Representative for distribution to the Refuge Manager and the Contracting Officer for review. The Government will require a maximum of 21 business days for review of these documents. During this phase of Government Review, the plans will be analyzed for constructability and for safety/code issues identified by the Government. Additional Revision and submittal may be required due to an incomplete submittal or Safety-mandated revision. Additional submittals will not be separately paid for by the Government and will be at the Design- Builder’s cost. Additional submittals are part of the contract scope.
1. Deliverables: Two sets of the following items shall be present and submitted to the FWS Project Manager 21 calendar days prior to this design review meeting. One set shall be mailed to the Refuge, and one set shall be mailed to the FWS PM/COR. Addresses to be provided prior to submittal. Note that failure to fulfill this list of elements may delay a construction NTP and payment for the 95% phase until all documents are received and accepted by the Contracting Officer as fulfilling the design phase.
a. Coordinated Construction Documents, drawings, specifications, developed to the 95% phase: these documents shall be checked for accuracy and shall be stamped by the design professionals responsible for the work.
b. Printed Documents: Provide stamped blackline sets of drawings and copies of written specifications
c. Electronic Documents: Provide a link to download all design data and files
d. Record copy of the accepted minutes from the previous meeting
e. Design Narrative with calculations
f. Drawings and written specifications for construction. The drawings and specifications shall be coordinated with all contract documents prior to submission.
g. The Government will provide review comments within 21 days of receipt of the 95% Construction Document package. The Design-Builder shall incorporate the accepted comments into the 100% Final Construction Documents. After Government acceptance of the 100%
Aucilla Tram Road Bridge / WCS Access Improvements 9 of 19
Final Construction Documents, the Design-Builder shall provide two stamped sets of drawings and specifications marked “FOR CONSTRUCTION.”
h. After Government acceptance of these documents, no changes will be allowed without written Contracting Officer approval.
f. Final Construction Documents (CD) 100%: Develop drawings and technical specifications that fully describe the work to be constructed and that are suitable for construction following Government acceptance. Incorporate Government review comments from previous phase. Prepare and submit a Construction Document submittal for Government review and comment. Submit all drawings, specifications, Engineering calculations and other required data to the FWS Engineering Project Manager for distribution to the Refuge and Contracting Officer for review. The Government will require a maximum of 21 days for review of these documents. During this phase of Government Review, the plans will be analyzed for constructability and for safety/code issues identified by the Government.
Additional Revision and submittal may be required due to an incomplete submittal or Safety-mandated revision. Additional submittals will not be separately paid for by the Government and will be at the Design-Builder’s cost. Additional submittals are part of the contract scope.
i. Deliverables: Three sets of the following items shall be present and submitted to the FWS Project Manager 21 calendar days prior to this design review meeting. Two sets shall be mailed to the Refuge, and one set shall be mailed to the FWS PM/COR. Addresses to be provided prior to submittal. Note that failure to fulfill this list of elements may delay payment for the 100% phase until all documents are received and accepted by the Contracting Officer as fulfilling the design phase.
1. Coordinated Construction Documents, drawings, specifications, developed to the 100% phase. These documents shall be checked for accuracy and stamped by the design professionals responsible for the work.
a. Printed Documents: Provide stamped blackline sets of drawings. Provide copies of written specifications.
b. Electronic Documents: Provide electronic documents containing all design data and files.
2. Record copy of the previous meeting’s accepted minutes.
3. Final approved and signed environmental permit(s).
4. Final design Narrative with Calculations
5. Drawings and written specifications (with submittal register) for construction. The drawings and specifications shall be coordinated with all contract documents prior to submission.
4. CONSTRUCTION SERVICES
a. GENERAL
Aucilla Tram Road Bridge / WCS Access Improvements 10 of 19
i. Following the Issuance of the Construction NTP, the contractor shall provide the following items to the COR at the Preconstruction Meeting for approval and amendment into the contract file.
1. A project schedule reflective of the critical path and other phases of the work.
2. A schedule of the planned Design-Builder site visits. Design Consultants shall periodically, and at appropriate times, visit the site to inspect the construction. They shall prepare a site visit report for each visit and shall submit the reports to the COR within 5 calendar days after the visit. The reports shall include comments about overall quality and accuracy of the construction.
The reports shall also note all deficiencies observed.
ii. Possess and maintain, for the duration of this project, a state license as a general contractor in the State where the project is located, if required by the state.
iii. Provide supervision, labor, materials, equipment, tools, construction equipment and machinery, inspection, testing, start-up, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether incorporated or to be incorporated in the Work.
iv. Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.
v. Perform all construction activities efficiently and with the requisite expertise, skill, and competence to satisfy the requirements of the Contract Documents. At all times exercise complete and exclusive control over the means, methods, sequences, and techniques of construction.
vi. Utilize Subcontractors who are duly licensed and qualified to perform the Work consistent with the Contract Documents. Government may reasonably object to Design-Builder's selection of any Subcontractor.
vii. Design-Builder is responsible for quality control of their own work and work performed by its subcontractors and their sub-subcontractors. Provide and pay for the services of an independent construction materials testing laboratory accredited by an acceptable laboratory accreditation authority.
Laboratory shall sample and test materials and perform required special inspections. Laboratory shall be authorized to perform work in the state where project is located. Government may reasonably object to Design- Builder's selection of laboratory.
viii. Assume responsibility for the proper performance of the Work of Subcontractors and all acts and omissions in connection with such performance. Nothing in the Contract Documents is intended or deemed to create any legal or contractual relationship between Government and any Subcontractor or Sub-Subcontractor.
ix. Coordinate the activities of all Subcontractors. If Government performs other work on the Project or at the Site with separate contractors under Government's control, Design-Builder agrees to reasonably cooperate and
Aucilla Tram Road Bridge / WCS Access Improvements 11 of 19 coordinate its activities with those of such separate contractors so that the Project can be completed in an orderly and coordinated manner without unreasonable disruption.
x. The bridge may be temporarily closed subject to advance approval by the Refuge Manager and Contracting Officer. There is no public vehicle use.
Typical use consists of approximately one Government vehicle per day and 15–20 public pedestrians per day. FWS will coordinate rerouting of Government vehicles and pedestrians when required.
xi. Deviations from the accepted 100% documents: The Contractor does not retain the right to make changes to the accepted documents without following the RFI process indicated herein. Any non-documented or non-approved changes shall be subject to rejection and non-payment.
Specifically reference the Communication Section below.
xii. Record Drawings and Specifications: Maintain one set of working drawings and specifications, for record purposes, on the project site while work is in progress. Clearly and accurately record the as-constructed work in red. Record swing-tie distances from permanent points for all underground items. Include modifications and RFIs.
b. COMMUNICATION
i. The intent of the Design/Build process is for the D/B firm to address all RFI’s and Submittal Reviews for compliance with the construction documents. This allows the Design/Builder to maintain Quality Control.
However, in this process, the FWS Project Manager must be kept aware of all changes for Quality Assurance purposes.
1. RFI Process: Unless a more stringent protocol is accepted in the Design/Build Management Plan, the Design/Builder shall utilize the following protocol:
a. Utilize a RFI Form: All supplemental information and answers to questions shall be documented on Request for Information (RFI) forms. The Design-Builder may choose any format desired for the Request for Information form, but all shall be identified with the words “Request for Information” at the top of the form along with the Government Contract Number, Project Location, Project Title, and the Design-Build Contractor’s Name.
b. Numbering: RFI’s shall be sequentially numbered, logged, and filed and shall be part of the Closeout Documents submitted to the Government.
c. FWS Concurrence: As RFI’s are generated and answered, submit copies to the COR for review within 2 business days for concurrence via email in .pdf format. A non-response from the COR within 4 days of receipt of the RFI will signify concurrence with the RFI answer.
d. RFI Files Onsite: The Site Superintendent shall maintain a file of RFI changes. This RFI file shall be subject to inspection by the FWS without advance notice.
Aucilla Tram Road Bridge / WCS Access Improvements 12 of 19
2. Submittals: Unless a more stringent protocol is accepted in the Design/Build Management Plan, the Design/Builder shall utilize the following protocol.
a. Utilize a Submittal Register: Develop a submittal register keyed to the Drawings and Specifications and update this Register as submittals are logged and processed.
b. Numbering: Submittals shall be sequentially numbered. A completed submittal register shall be submitted with the Project Closeout Documents.
c. FWS Concurrence: Provide the FWS Engineering Project Manager with (1) copy of the approved submittal with updated submittal registers and provide the FWS Construction Inspector (1) copy of the approved submittal with updated submittal register within (2) business days of the approval date.
d. Site Responsibility: The Contractor’s Site Superintendent shall maintain a file of approved submittals and updated accurate submittal register for reference purposes. This Submittal file shall be subject to inspection by the FWS without advance notice.
3. Note: Any delays resulting from FWS questions/stoppages due to a lack of, or inordinately lengthy or unnecessary delays in, the flow of information from the Design/Builder to the FWS for a time period in excess of 21 days, will not give rise to claims for monetary consideration under the contract, including but not limited to requests for equitable adjustments, constructive changes, and other claims for compensation.
c. PAYMENT PROCEDURES
i. Measurement: No measurement of the work will be made unless unit prices are included in the project.
ii. Payment: Payment will be made monthly for approved work performed in accordance with the contract requirements under the items listed in the Schedule of Items and based on the approved Schedule of Values.
1. Note: Undocumented changes which did not follow the RFI process outlined above may be subject to delayed or non-payment.
iii. Schedule of Values: Prepare a Schedule of Values in the format of the American Institute of Architects (AIA) form number G702/703 Application and Certificate for Payment (or approved equivalent format). Submit a detailed Schedule of Values no less than 7 calendar days prior to the start of on-site construction work.
1. Payment Request Data: In addition to data required by the Contracting Officer: (1) Format the Schedule of Values to match the Schedule of Items and show sufficient additional detail to allow accurate calculation of monthly progress payments; and (2)
Aucilla Tram Road Bridge / WCS Access Improvements 13 of 19
Submit updated construction schedule identifying actual work complete.
d. PROJECT SAFETY
i. The Design-Builder is responsible for safety on the project site at all times, from issuance of the Notice to Proceed until final completion and acceptance of the project by the Contracting Officer. Ensure that all onsite activities, equipment, and facilities constructed by the Design-Builder, subcontractor, or supplier conform fully to the standards of the Department of Labor, Occupational Safety and Health Administration (OSHA) 29 CFR 1926 and 1910; and DOI and FWS policies. In addition, the Design- Builder shall adhere to all current Federal, State, and Local safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern. See Section H of the solicitation/contract.
ii. Initiate and maintain, throughout the performance of this contract, an effective safety and health program that provides adequate policies, procedures, and practices to protect employees from, and allow them to recognize, job-related safety and health hazards. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections. Each employee (Design-Builder and subcontractors) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.
iii. Provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel. Where project work affects public roads, provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD) as published by the US Department of Transportation, Federal Highway Administration.
iv. Rollover Protection and Seat Belts: In addition to the Safety and Health requirements of clause Federal Acquisition Regulation (FAR) 52.236-13 of Part 2, Section I of this Contract, rollover protection and seat belts required by 29CFR 1926 (OSHA) shall be extended to include equipment regardless of the year of manufacture.
e. Work Hours: Unless prior approval is obtained from Refuge and COR, all work shall occur from sunrise to sunset.
f. Protections:
i. Comply with all applicable federal, state, and local environmental laws and regulations. This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, erosion control, surface runoff, and cultural resources.
ii. Provide erosion control methods (such as watering dry soils) and appurtenances (such as silt fence) as necessary to prevent wind-borne dust and water-borne silt from leaving the immediate work area.
Aucilla Tram Road Bridge / WCS Access Improvements 14 of 19
iii. Immediately stop working if paleontological, archaeological or historical remains (including burials or skeletal material) are encountered, immediately stop the work and notify the Construction Representative, COR, or Contracting Officer. The Contracting Officer will notify the Regional Archaeologist, so the provisions of 36 CFR 800.7 (Resource Discovered During Construction) and other relevant laws are followed.
Work will cease in the immediate vicinity until permitted to resume by written order from the Contracting Officer. Work in other areas may proceed as approved by the Contracting Officer.
iv. Protect adjacent vegetation, property, structures, and improvements from damage. See Section I of the solicitation /contract.
v. Heavy equipment operated on FWS roads and parking areas shall comply with highway-legal load limits unless explicitly approved otherwise. Prior to operations, the contractor and contracting officer will document condition of roads and parking. The contractor is responsible for repairs of damage to roads and parking caused by their own actions.
vi. Clearing limits and working limits are as shown on the drawings and approved in the field. Do not remove any trees without prior COR field review and approval. If no clearing limits are indicated, contact the COR for clarification. Coordinate with the local FWS staff to select a construction staging area. Construction equipment and operations shall be contained within the work limits and staging areas.
g. Closeout Procedures
i. Training and Operational Demonstration: Train Refuge personnel in routine operation, inspection, and maintenance of the completed access and stop-log system. Demonstrate from above the release, removal, installation, and securing of every stop-log board and retaining device under conditions approved by the COR. The demonstration shall verify that no personnel entry into the water or beneath the bridge is required.
ii. Tools and Spare Parts: Deliver all removable cranks, lifting bars, hooks, keys, specialty tools, spare seals, fasteners, and replacement parts required for operation and maintenance. Portable equipment shall be limited to small hand-operated components integral to the approved system and shall not include a primary davit, crane, temporary work platform, or comparable assembly that must be transported to and erected at the site for routine operation.
iii. Maintenance Materials: Deliver maintenance materials to Refuge Manager, coordinate location of storage. (Provide consumable items in such quantities as needed for the first year of operation.)
iv. Final Inspection: Submit a request in writing to the CO requesting the Final Inspection. Notify the COR at least 10 calendar days prior to the anticipated date of completion of all work. The COR will proceed with Final Inspection as promptly as practicable. The time required for such Final Inspection and for making any corrections as a result thereof shall be included in the contract performance time. The Design-Builder representative responsible for the work shall be present at the Final Inspection and shall submit a preliminary list of unfinished work prior to Final Inspection. See Section E of the solicitation /contract.
Aucilla Tram Road Bridge / WCS Access Improvements 15 of 19
h. Closeout Documents
i. Operation and Maintenance Manuals: Submit three copies of an Operation and Maintenance Manual—two to the Refuge and one to the FWS Project Manager—covering the stop logs, guide and retention system, lifting tools or equipment, access covers or grating, guardrail access features, seals, fasteners, and other maintainable project components. Include operating procedures, inspection and maintenance schedules, troubleshooting guidance, replacement parts, warranties, and manufacturer and supplier contact information.
ii. Operational Permits: Provide copies of all approved operational permits.
Include a list of all monitoring requirements and monitoring frequencies.
iii. Submit a full-size set of red-lined drawings and complete set of specifications that clearly indicates the as-constructed work. As-constructed drawings shall be in .dwg and .pdf format and noted as ‘Final Construction/As-Builts’ in the revision block. Submit one set of final working drawings, one set of reproducible drawings showing as-constructed conditions, and one electronic set complying with FWS CAD Standards. Professional stamps shall be on the Final As-Built drawing sheets
iv. Submit fully executed manufacturer's standard material, product, and equipment warranties.
v. Submit any requested regulatory-agency clearance documents indicating the work complies with their requirements.
vi. After completion of the work and prior to final payment, submit a Release of Claims (Form DI-137 provided by the Contracting Officer), properly executed by the Design-Builder, releasing claims against the United States arising out of this contract, other than claims specifically excepted from the operation of the release. See Section I of the solicitation /contract.
5. SPECIFIC PROJECT REQUIREMENTS
a. Project Work site is accessible from existing public access roads. A staging area approximately 40 feet wide by 500 feet long is available inside the locked gate, extending along the roadway centerline. Use of the area shall be coordinated with the Refuge Manager.
b. If a benchmark is needed, the benchmark that shall be used for vertical control on this project shall be located and identified or created by the Design-Builder during the design phase. FWS has no knowledge of local benchmarks for elevation control.
c. The following are minimum base design and performance requirements. The Design-Builder retains responsibility for means, methods, and final engineering details, but the completed work shall satisfy every design, operational, and performance requirement below:
i. Codes and Standards: Specifications and design shall comply with current Florida Department of Transportation (FDOT).
Aucilla Tram Road Bridge / WCS Access Improvements 16 of 19
ii. Bridge Structural System: Maintain sufficient clear width between bridge rails to accommodate a 96-inch-wide, one-ton dual-wheel Government truck, including required mirror clearance. The existing clear bridge width shall not be reduced by more than 12 inches. Localized deck cutting, notching, coring, drilling, anchorage, or edge reconstruction may be performed only as detailed and sealed by a Florida-licensed structural engineer. Deck modification (if needed) should be limited to the north-side cantilevered overhang outside the exterior tee-beam stem wherever practicable. Do not cut or alter a tee-beam stem, primary girder, pier, abutment, or primary reinforcing steel without specific Government approval.
iii. Water Control Structure: Maintain the structural integrity of the existing WCS concrete. The existing timber stop logs, wood wedges, guide hardware, and related appurtenances may be removed or modified as required for the proposed design. New guide channels, guide extensions, sill components, frames, brackets, anchors, retention components, and related hardware shall be fabricated from corrosion-resistant materials suitable for repeated brackish-water exposure, and shall consist of heavy-duty aluminum, Type 316 or 316L stainless steel, or a compatible combination thereof. Where dissimilar metals are used, provide suitable nonconductive isolation to minimize galvanic corrosion. New guide channels, guide extensions, sill components, frames, brackets, and anchors may be attached to the existing concrete when supported by sealed structural calculations and details.
iv. Permanent Access Concept: Provide one permanent, integrated solution that gives direct operational access to all stop-log boards and retaining devices. Acceptable concepts include the following, individually or in a coordinated hybrid:
1. Localized modification of the north-side cantilevered deck overhang, with a reconstructed edge, permanent opening or removable/hinged cover or grating, and guardrail arrangement that preserves safe vehicle and personnel use.
2. Extension or replacement of the WCS stop-log guides and operating face beyond the bridge overhang using a new corrosion-resistant frame, guides, sill, and retaining system fabricated from heavy-duty aluminum, Type 316 or 316L stainless steel, or a compatible combination thereof, and accessible from above..
3. A hybrid combining limited deck modification with new or extended WCS guides and top-operated retention hardware.
v. Stop-Log Boards and Retention System:
1. Replace all existing timber stop-log boards with fabricated heavy-duty aluminum stop logs suitable for repeated exposure to brackish water. Provide corrosion-resistant lifting hardware, replaceable seals where required, and dimensions compatible with the final guide system and required water-level control increments.
2. Replace the existing wood wedges with a positive, corrosion-resistant retention system operable from above. Acceptable
Aucilla Tram Road Bridge / WCS Access Improvements 17 of 19 mechanisms may include manufacturer-standard keeper bars, compression bars, jack screws, cams, clamps, or equivalent devices. The permanent system shall not require hammering wedges from beneath the bridge.
3. Provide integral lifting or attachment points on each stop log.
Simple hand-operated tools, including lifting hooks, bars, are acceptable, provided they are corrosion-resistant, simple to maintain, and do not require recurring transport and assembly for routine operation.
4. Preserve the existing water-level-management function, board elevation increments, and ability to control flow in either direction.
Do not reduce the clear hydraulic opening or change the control elevation without Government approval.
vi. Operational Performance Requirements:
1. Provide access from the bridge deck or a permanent integral platform to release, inspect, lift, lower, reinstall, and secure every stop-log board and retaining device.
2. Permit routine operation by no more than two trained Refuge employees without entering the water, crawling beneath the bridge, or standing on temporary platforms.
3. Do not use a portable davit, portable crane, or similar system requiring repeated transport, erection, rigging, disassembly, and off-site storage as the primary operating method. FWS uses simple stop-log lifting tools to remove boards.
4. Reduce operator bending and manual force and provide safe hand placement, fall protection, and clear working space. Provide lockable security features to prevent public tampering.
vii. Guardrail and Traffic-Safety Improvements:
1. Replace the bridge-mounted guardrail system on both sides with a low-maintenance, durable, and corrosion-resistant system. All exposed steel components, including rails, posts, base plates, brackets, anchors, fasteners, and miscellaneous hardware, shall be hot-dip galvanized or provided with an approved equivalent corrosion-resistant finish suitable for the coastal environment.
Evaluate and address bridge rail, transitions, approach rail, and end treatments identified in the 2023 Bridge Inspection Report as not meeting current FWS new-rail guidelines, in accordance with applicable FDOT and FWS criteria for this low-volume refuge road. Coordinate the north-side rail, curb, posts, anchorage, covers, grating, and access openings so the completed system provides safe vehicle containment and unrestricted operation of all stop logs. Where dissimilar metals are used, provide suitable isolation to prevent galvanic corrosion
2. Install two OM-3L and two OM-3R object markers, one at each bridge corner, and correct the guardrail deficiencies identified in
Aucilla Tram Road Bridge / WCS Access Improvements 18 of 19 the 2023 Bridge Inspection Report (Attachment C) and any additional deficiencies confirmed during design.
viii. Trim vegetation obstructing the west-approach load-limit sign.
ix. Scour-protection repairs identified in the 2023 Bridge Inspection Report are not included in this project.
x. Investigation and Design Verification:
1. Use existing 1999 bridge plans, the 2023 Bridge Inspection Report, Government-furnished photographs, and field measurements. Verify all critical dimensions, reinforcement locations, anchor locations, stop-log quantities, guide geometry, and operating clearances before final design.
2. A full topographic survey and geotechnical investigation are not anticipated and shall not be included unless technically justified by the selected concept and authorized by the Contracting Officer.
xi. Hydraulic and Environmental Performance:
1. Maintain the existing WCS hydraulic opening, water-level-control function, and flow-reversal capability unless a change is expressly approved. Design new stop logs, guides, frames, seals, and anchors for applicable differential water loads in both flow directions.
2. Refine the design to minimize in-water work, wetland disturbance, turbidity, and permitting burden while meeting all…