B08_Solicitation_Attach_6_Period_of_Performance_Schedule.xlsx
XLSX spreadsheet 10 KB Posted
- Attached to
- REHABILITATE CONATA PICNIC ROAD AND AREA
- Solicitation number
- 140P6324B0007
About this file
This solicitation is for construction services to rehabilitate Conata Road and Picnic Area located at Badlands National Park. The solicitation number is 140P6324B0007 and was issued by the Department of the Interior National Park Service Midwest Region. The solicitation seeks bids to rehabilitate Conata Road and the surrounding picnic area, which will include repairing the road surface and upgrading amenities in the picnic area. Bids are due by the date specified in the Period of Performance and Schedule attachment. The awarded contractor will be expected to complete all rehabilitation work within the timeframe outlined in the same attachment.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Estimated Period of Performance Schedule | |||||
| Year 2024 | Start date | End Date | POP Days | ||
| Pre Winter | 2024 | 16-Jun-24 | 30-Oct-24 | 136 | |
| Post Winter | 2025 | 15-Mar-25 | 30-Oct-25 | 229 | |
| 365 | Total POP Used | ||||
| Pre Winter Work 2024 | |||||
| Pre Winter Start date will be determined by issuance of Notice to Proceed. | |||||
| Work May start earlier or later than June 16, 2024 as agreed upon by | |||||
| the Government and Contractor. Calendar days will be adjusted accordingly. | |||||
| Pre Winter End date may end earlier or later than October 30, 2024 as agreed upon by | |||||
| the Government and Contractor. Calendar days will be adjusted accordingly. | |||||
| Post Winter Work 2025 | |||||
| Post Winter start date will be determined by an updated Notice to Proceed. | |||||
| Work may start earlier or later than March 15, 2025 as agreed upon by the | |||||
| Government and Contractor. Calendar days will be adjusted accordingly. | |||||
| Post Winter End date may end earlier or later than October 30, 2025 as agreed upon by | |||||
| the Government and Contractor. Calendar days will be adjusted accordingly. | |||||
| The Government anticipates the project will be completed by October 30, 2025. | |||||
| Additional Notes | |||||
| The "Road" can not be completely shutdown, limited access is needed | |||||
| between Memorial day weekend to labor day weekend. | |||||
| All limited/shutdown access falls directly on the contractor. |