B08_Solicitation_Attach_3_Constructability_Checklist.pdf
PDF 72 KB Posted
- Attached to
- REHABILITATE CONATA PICNIC ROAD AND AREA
- Solicitation number
- 140P6324B0007
About this file
This file contains details regarding a federal solicitation for construction services. The solicitation number is 140P6324B0007 and seeks bids to rehabilitate Conata Road and Picnic Area located at Badlands National Park. The Department of the Interior National Park Service Midwest Region is the contracting agency. Contractors should respond with construction services to repair the roadway and picnic facilities. The response due date and anticipated award date are not provided in this attachment, which appears to be a constructability checklist for the work rather than the full solicitation document.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NPS Constructability Checklist National Park Service (NPS) - Denver Service Center (DSC) | 3-20-18
For instructions, see Instructions tab below.
Date: 7/31/2023 Project Title: Repair and Rehabilitation Conata Picnic Road
Park: Badlands National Park Completed By:
PMIS:
(Project Management
Information System)
227786 DBB or DB:
(Design-Bid-Build
OR Design-Build)
DBB
Item Number Project Issues SD Comments Schematic Design
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
PROJECT INTRODUCTION
ANY NON-TYPICAL CONTRACT LINE ITEMS OR
MISCELLANEOUS CONTRACT CONCERNS
No
RECOMMENDED CONTRACT LENGTH; SEASONAL
BREAKS IN CONTRACT; IDENTIFY CONTRACT TIMING
ISSUES THAT NEED TO BE ADDRESSED; IDENTIFY
SPECIFIC PHASING REQUIREMENTS
Able to be completed in one construction season.
May be requirements for avoiding shut down during Sturgis Rally week
No change in duration. Note that the work has been separated into two projects for "NEW" and
"REPAIR" work.
PERMITTING & COMPLIANCE
External Permit or Approval
LIST REQUIRED GOVERNMENT FURNISHED PERMITS
AND APPROVALS: List by Agency-Type: Example: USACE-
CWA404 NWP18. Include contact, and phone number.
IEPA NPDES Notice of Intent
External Permit or Approval
LIST REQUIREMENTS FOR GOVERNMENT FURNISHED
PERMITS: Include inspections, meetings, close out requirements, and drawings.
N/A
External Permit or Approval
LIST REQUIRED CONSTRUCTION CONTRACTOR
FURNISHED PERMITS AND APPROVALS
IEPA NPDES Notice of Intent
External Permit or Approval
DESCRIBE WHERE AND HOW PERMIT REQUIREMENTS
ARE INCLUDED IN DESIGN PACKAGE: For each permit, describe requirement, specification (section and paragraph) and/or drawing number.
IEPA NPDES Notice of Intent- contractor shall obtain prior to construction. ALso will need NOT after project has been completed.
Internal Compliance
IDENTIFY COMPLIANCE REQUIREMENTS:
SHPO, NEPA, EA: List requirement, status, and date or expected date.
IEPA NPDES- site needs to be completed and final stabilization methods installed and established
NPS Constructability Checklist, 3-20-18 | page 1 of 5
Item Number Project Issues SD Comments Schematic Design
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
Internal Compliance
COMPLETE ALL APPROVALS: Director's, DAB, Congressional Funding issues, estimate within available funds? Adequate time to complete work within project and funding constraints?
General
IDENTIFY REQUIRED SPECIAL INSPECTIONS: List inspecting or approving organization and reason required.
N/A Applicable
9a
External Permit or
Approval
Subcontractor(s) for paleontological and archaeological monitoring are required to submit a research permit application with the park.
Added requirement
STAGING AND MOBILIZATION
IDENTIFY AREAS FOR STAGING INCLUDING AREAS FOR
PRIME, SUBS, MATERIAL, AND PARKING; IDENTIFY
AREAS FOR CONSTRUCTION CAMP IF APPLICABLE:
List drawing number(s) showing staging area(s).
Limits of construction provided on plan
IDENTIFY TEMPORARY UTILITIES AVAILABLE FOR
CONSTRUCTION: List drawing number or specification section that indentifies available utilities-electrical, phone, non-potable and potable water, sanitary-provider, meter needed, and responsible cost party. N/A
IDENTIFY CONSTRUCTION LOGISTICS: List drawing numbers that show traffic control, access restrictions, work hour restrictions, bridges, features, other. Demo sheet calls out traffic control, work hour restrictions in specs
IDENTIFY IMPACTS TO PARK AND VISITOR OPERATIONS:
List drawing number(s) or specification section(s) that identifies impacts (e.g. Visitor Impacts, Neighborhood-Urban
Impacts, Detours, Closures).
Park shutdown is impact- spec summary or work
IDENTIFY SITE ACCESS ISSUES: List drawing number(s) or specification section(s) that identify issues (e.g. remote and road type constrained sites, weather closure restrictions, road and bridge load limits, road and tunnel height restrictions, crane and helicopter requirements). No issues anticipated accessing site
SUBMITTALS
LIST MATERIAL SUBMITTALS ON CRITICAL PATH;
FOR DESIGN-BUILD (DB), LIST MATERIAL SUBMITTALS
REQUIRING GOVERNMENT APPROVAL
N/A- Design bid build
LIST LONG LEAD ITEMS; MATERIAL AND EQUIPMENT
AVAILABILITY CONCERNS, SPECIAL DELIVERY
REQUIREMENTS
Steel for group picnic shelter, vault toilet
NPS Constructability Checklist, 3-20-18 | page 2 of 5
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
LIST OF SOLE SOURCE MATERIALS AND GOVERNMENT
FURNISHED MATERIALS OR EQUIPMENT
Toilet vault is manufacturer spec
SITE LAYOUT / RESOURCE PROTECTION
TYPES OF RESOURCE PROTECTION REQUIRED: List where and how requirements are included in design package.
Paleontological monitoring specs have been added to the set - to be provided by the contractor and included in bid price.
19 ACCURATE SURVEY DATA ON PLANS: BMs, TBMs, TOPO
Bench marks and control points on plan established by PLS
PRELIMINARY SITE INVESTIGATION COMPLETE,
EXISTING CONDITIONS VERIFIED AND INCLUDED IN
PACKAGE
Yes
CONSTRUCTION LIMITS CLEARLY SHOWN AND DEFINED
FOR BOTH ACCESS AND CONSTRUCTION: List where and how requirements are included in design package.
Construction limits included on plans
SPECIAL SIGNAGE REQUIREMENTS: Describe and list where requirements are included in design package.
Accessible stall signage- details included in plans
LIST WORK SAFETY CONCERNS, LOCATION, AND
NEEDS: Include Height, Weather, Animal, Aerial, Public
Accessibility, Security, Confined Space, Pathologic, Atmospheric, and others.
Rain, snow, high heat and winds.
DEMOLITION
ALL EXISTING UTILITIES LOCATED AND ACCURATELY
SHOWN: Describe where shown.
No exiting utilities located onsite
TEMPORARY SYSTEMS REQUIRED: Identify for Park or
Public: Access, power, water, sanitary, covered access, exhibit relocation, movement assistance, accessibility.
N/A
SALVAGE, RECYCLING, STORAGE, AND DISPOSAL
REQUIREMENTS: Who is removing salvageable equipment and where requirements are included in design package?
N/A
NPS Constructability Checklist, 3-20-18 | page 3 of 5
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
NOISE / DUST / SAFETY CONCERNS FOR PUBLIC OR
ENVIRONMENT: Describe where included in design package.
Site to be closed during construction
CONSTRAINTS ON MEANS AND METHODS: Blasting, Burning, Tidal, Weather, Public Accessibility, Existing structures/features, Holidays and Seasonal, Permitting, other.
Site to be closed during construction
HAZARDOUS MATERIAL CONSIDERATIONS DEMO
METHODS AND DISPOSAL STATE AND LOCAL
REQUIREMENTS: Describe hazardous materials being addressed, how, and where in design package. Vault for toilet to be pumped prior to demolition of existing vault toilet.
ARCHEOLOGICAL MONITORING REQUIREMENTS:
Describe what is needed and where in design package.
Identify who provides monitor.
See architectural protection spec
CONSTRUCTION
MATERIAL, EQUIPMENT, LABOR AVAILABILITY FOR
REMOTE SITES: Describe issues and where included in design package.
Remote site location
SITE ACCESS RESTRICTIONS TO CONSTRUCTION
OPERATIONS IF DIFFERENT OR MORE SUBSTANTIAL
THAN ITEMS 12 AND 14
Site can be accessed off of main road
ANTICIPATED WEATHER CONSIDERATIONS,
CONSTRUCTION SEASON, OPTIMUM TIME TO
ADVERTISE, RECOMMENDED CONTRACT LENGTH
Rainfall runoff, high heat and winds anticipated during construction. Anticipated contract length is
9 months.
PARK / CONCESSION IMPOSED RESTRICTIONS
INCLUDED IN DESIGN PACKAGE AND IMPACTS ON
SCHEDULE & COST
N/A- no concessions
DESCRIBE FULL SCOPE OF WORK FOR LOCAL UTILITY
COMPANIES AND CONSTRUCTION CONTRACTOR FOR
EACH UTILITY
N/A
DESCRIBE DISRUPTION REQUIREMENTS FOR UTILITY
CONNECTIONS, CLOSURES, AND MAXIMUM ALLOWABLE
INTERRUPTIONS: Describe where addressed in design package. Maximum park shutdown is six weeks called out in specs
NPS Constructability Checklist, 3-20-18 | page 4 of 5
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
SPECIFIC PHASING REQUIREMENTS: Detail what and where where provided in design package.
N/A
DESCRIBE SPECIALIZED MATERIALS/INSTALLATION
METHODS CERTIFICATIONS/TRAINING REQUIREMENTS;
DETAIL GOVERNMENT REQUIRED SPECIALTY SERVICES
OR INSPECTIONS: List requirements.
N/A
COORDINATION WITH PARK OR CONCESSIONAIRE ON
BENEFICIAL OCCUPANCY: Grand opening, fixed completion dates, etc.
N/A
ADJACENT or CONCURRENT CONTRACTS
COORDINATION / OVERLAPS ON CONCURRENT OR
FUTURE CONTRACTS
None anticipated
41 VALUE ENGINEERING POTENTIAL
PROJECT CLOSEOUT
42 TRAINING REQUIREMENTS, CERTIFICATIONS SPECIFIED
N/A
43 OPERATION & MAINTENANCE (O&M) REQUIREMENTS
N/A
LIST PERMITS NEEDING CLOSURE AND POINTS OF
CONTACT: Describe requirement; include specification and/or drawing location for each. NPDES, Notice of Termination (NOT ) required after site has been stabilized.
45 POST CONSTRUCTION REQUIREMENTS
As built survey
LIST LONG TERM MAINTENANCE NEEDS AND LOCATION
IN THE DESIGN PACKAGE.
Maintenance requirements includes sediment removal in the drainage infrastructure including ditches and culverts
NPS Constructability Checklist, 3-20-18 | page 5 of 5