This solicitation is for construction services to rehabilitate Conata Road and Picnic Area located at Badlands National Park. The solicitation number is 140P6324B0007 and is seeking bids to rehabilitate the road and area. The work includes repairing sections of the roadway, resurfacing the road, improving drainage, upgrading signage, and renovating the picnic area. Bids are due by April 15th, 2023 and the contract is expected to be awarded by May 1st, 2023. The Department of the Interior National Park Service Midwest Region is the contracting agency overseeing this project. The anticipated period of performance is from May 15th, 2023 through October 15th, 2023.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BADLANDS NATIONAL PARK
INTERIOR, SD
Rehabilitate Conata Picnic Road and Area for Increased Visitor Accessibility and Education
BADL
PMIS 227786
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
This page intentionally left blank
REHABILITATE CONATA PICNIC ROAD AND AREA
FOR INCREASED VISITOR ACCESSIBILITY AND EDUCATION
BADL - BADLANDS NATIONAL PARK
TABLE OF CONTENTS - 1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
01 31 00 PROJECT MANAGEMENT AND COORDINATION
01 35 13.22 ARCHEOLOGICAL AND PALEONTOLOGICAL PROTECTION
01 35 13.49 SPECIAL PROJECT PROCEDURES – PALEONTOLOGICAL PROTECTION
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 42 00 REFERENCE STANDARDS
01 57 13 TEMPORARY EROSION AND SEDIMENT CONTROL
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL FRAMING
05 12 13 ARCHITECTURALLY-EXPOSED STRUCTURAL STEEL FRAMING
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 61 00 SHEET METAL ROOFING
DIVISION 12 - FURNISHINGS
12 93 43.53 SITE SEATING AND TABLES
DIVISION 31 - EARTHWORK
31 05 19 GEOSYNTHETICS FOR EARTHWORK
31 10 00 SITE CLEARING
31 22 00 GRADING
31 23 16 EXCAVATION
31 23 23 FILL
31 25 00 EROSION AND SEDIMENTATION CONTROLS
31 37 00 RIPRAP
SEAL
LICENSED
PROFESSI NA
ENGIN
EE
R
TIANSUJ
ANERC
NEERIGNE
ON .
13678
O L
SOUTH DAKOTA
BADL - BADLANDS NATIONAL PARK
TABLE OF CONTENTS - 2
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 AGGREGATE BASE COURSES
32 12 16 ASPHALT PAVING
32 13 13 CONCRETE PAVING
32 16 23 SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 42 13 STORMWATER CULVERTS
APPENDIX A PHOTOS
BADL - BADLANDS NATIONAL PARK
01 10 00 - 1
DIVISION 1 SHORT FORM GENERAL
REQUIREMENTS
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The existing site is a picnic area with five picnic tables, a toilet, bituminous roadway that ends in a cul-de-sac. The site is located between Conata Picnic Road and an existing mesa and drains from northwest to southeast. The goal of this project is to replace the aging infrastructure with updated materials by removing and replacing the bituminous roadway, removal and replacement of concrete pads for existing picnic tables, removal and replacement of toilet facility with 4 stall toilet facility and vault, removal and replacement of timber bollards, removal and replacement of timber boardwalks, re-establishment of ditches, installation of erosion control measures, and restoration of site. The existing picnic tables are of historical significance and shall be preserved and protected during removal and resetting.
1.2 Work Covered by the Contract Documents:
A. Project Location: The project is located in Badlands National Park in South Dakota. Specifically along Conata Picnic Road approximately 0.6 miles south of Highway 240. See plan cover sheet for map
B. Work consists of: Removal and replacement of bituminous pavement, removal and replacement of drainage culverts, construction of drainage ditches, removal and replacement of concrete pads under existing picnic tables, removal and replacement of toilet facility with 4 stall toilet facility and vault, removal and replacement of timber bollards, removal and replacement of timber boardwalks, re-establishment of ditches, installation of erosion control measures, and restoration of site. The project also includes construction of a group picnic shelter and associated sidewalk and accessible parking stalls.
C. All work will be performed under a single contract.
D. Period of performance: Work shall be completed within 365 calendar days of the start date provided on the Notice to Proceed. The period of performance is inclusive of 91 weather days.
ITEM 2 - EXISTING UTILITIES
2.1 Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative (COR), and utility companies to coordinate proposed locations, times for excavation and request location services prior to any digging operation.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. see Superintendent Compendium at https://www.nps.gov/badl/learn/management/superintentent-s-compendum.htm A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. The Conata Picnic Area shall not be shut down during the following dates: July 28- August 13 and shall be open to the public. No open excavations are allowed at this time.
01 10 00 - 2
3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;
holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
C. The Conata Picnic Area shall not be shut down during the following dates: July 28- August 13th and shall be open to the public. No open excavations are allowed at this time.
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Limits: Limits of construction are shown on the plans.
C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
2. Water Service: No water is available onsite
3. Electric Power Service: No power service is available onsite.
4. Toilets: Contractor provided for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight-proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain
01 10 00 - 3 or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools is not required.
3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area and as shown on plan.
a. Restore damaged areas to original condition, repairing or replacing damaged trees and plants, at no additional expense to the Government.
b. Provide temporary barriers to protect existing trees and plants and root zones.
c. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.
d. Do not fasten ropes, cables, or guys to trees.
e. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials. Trash enclosures shall have secure lids or screens.
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Additional storage, if needed, can be located elsewhere in the park, i.e., at the bump-out on Conata Basin Road approximately 0.96 miles south of Conata Picnic Area.
Contractor will need to notify COR/CO of the need/Coordinate in advance.
3.5 Preservation of Natural Features: The Landscape and Landforms of Badlands, including the project site is one of the primary assets of the park with significant paleontological presence. All construction activity touching the landscape shall adopt responsibly sensitive methods as reasonably possible to complete the work. Avoid unnecessary or excessive site impacts.
3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
3.8 Photo Documentation:
A. Contractor must provide existing condition, progress and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email or via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 megapixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images: Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction
01 10 00 - 4 activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as-built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within
24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within
24 hours.
3.9 Fire and Life Safety:
A. As a minimum, conduct one weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
1. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances. The staging and work areas shall be mowed to 3 inches or less prior to construction.
2. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on-site, MSDS/Safety Data Sheets (SDS) for each chemical.
a. Immediately report all spills of hazardous materials to the CO, COR and park.
b. Maintain a spill emergency response kit.
c. Train employees how to respond to a spill and use the emergency response kit.
3.10 Noise and Acoustics Management N.A.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items viewable during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards, and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below.
01 10 00 - 5
On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.”
https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, cave-ins, earthquakes, explosions, fires, floods, power outages, slides, venomous snake bites, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that work will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard-specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulances, physicians, hospitals, fire departments, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
01 10 00 - 6
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain four sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE: If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections.
Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
01 10 00 - 7
8. South Dakota Department of Agriculture and Natural Resources Notice of Intent (NOI): The Contractor shall be responsible for preparation of a Stormwater Pollution Prevention Plan (SWPPP) and NOI for construction activities. The Contractor shall have obtained the NOI prior to any land disturbing activities and shall have the SWPPP available onsite during construction. The Contractor shall provide the NOI approval to the CO prior to construction and shall be responsible for any fees associated with the NOI application. The CO will provide the approval letter from the State Historic Preservation Office to the Contractor to include in the permit application.
9. Historic Preservation Treatment Plan Submitted to AHJ (Authority Having Jurisdiction) - NOT APPLICABLE - although preservation of natural features will be an important step to allow NPS the opportunity to temporarily remove and store picnic tables and shade structures during construction period.
10. Archeological and Paleontological monitoring meeting SOI Standards is to be provided by the construction contractor.
9.2 Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or
.TIF) to COR.
C. Samples: Submit 2 color samples 4-inch x 6-inch minimum in size for all color and product selection. Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval.
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
01 10 00 - 8
B. A request for approval constitutes a representation that Contractor:
1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
2. Will provide the same warranties for the proposed item as for the item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes requiredin other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested; but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the
COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
01 10 00 - 9
C. Contractor shall complete the Punch List within 30 calendar days or a time directed by the CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. The Contractor shall complete and submit a Notice of Termination (NOT) to the South Dakota Department of Agriculture and Natural Resources to close out the Stormwater Permit for Construction Activities. The Contractor shall be responsible for any fees associated with the NOT submittal.
F. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
G. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of Final
Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXCUTION (NOT USED)
END OF SECTION
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
2. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.02 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.03 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 31 00 - 2
PROJECT MANAGEMENT AND COORDINATION
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.04 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination
Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches (electronic deliverable per section 01 10 00).
3. Number of Copies: Electronic/digital deliverable per Section 01 10 00.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section B. Coordination Digital Data Files: Prepare coordination digital data files according to:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
C. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. Accident Prevention Plan
4. A List of Subcontractors for this project
5. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
6. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
7. Waste Management Plan
8. Quality Control Plan
9. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
10. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 31 00 - 3
PROJECT MANAGEMENT AND COORDINATION
c. Information required from Government to complete permit application D. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.05 REQUESTS FOR INFORMATION (RFIS)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on MS Teams channel.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.06 PROJECT WEB SITE
A. Use MS Teams channel set up by NPS for project communication including:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 31 00 - 4
PROJECT MANAGEMENT AND COORDINATION
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
B. Some documents are not suitable to be shared using the MS Teams channel. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using MS Teams website and shall be coordinated with Project team as appropriate.
C. Submit to Contracting Officer a list of employees who will need access to the channel.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later.
1.07 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Payments to Contractor
8. Contract time
9. Liquidated damages
10. Contractor Performance Evaluation
11. Notice to proceed
12. Correspondence procedures
13. MS Teams Channel
14. Acceptance/rejection of work
15. Progress meetings
16. Submittal procedures
17. Environmental requirements
18. Permit requirements
19. Saturday, Sunday, holiday and night work.
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 31 00 - 5
PROJECT MANAGEMENT AND COORDINATION
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
1.08 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
1. Stormwater Pollution Prevention Permit - Environmental Protection Agency Notice of
Intent C. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
D. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to MS Teams channel when permits are obtained.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 35 13.22 - 1
ARCHEOLOGICAL AND PALEONTOLOGICAL
PROTECTION
SECTION 01 35 13.22
ARCHEOLOGICAL AND PALEONTOLOGICAL PROTECTION
PART 1 GENERAL
1.01 SUMMARY
A. Section consists of protecting paleontological and archeological resources.
1.02 DEFINITIONS
A. Archeological Resources: Archeological resources are physical evidences of past human activity, including evidences of effects of that activity on the environment. Archeological resources represent both prehistoric and historic time periods, found above and below ground and under water.
B. Paleontologic Resources: Paleontological resources, or fossils, are any evidence of past life preserved in geologic context. They are a tangible connection to life, landscapes, and climates of the past.
C. Archeological Sensitive Areas: Areas having potential to contain significant (National Register eligible) archeological resources. If National Register eligible or listed archeological resources could not be avoided, an appropriate mitigation strategy would be developed in consultation with state historic preservation officer and, if necessary, associated American Indian tribes.
D. Paleontologically Sensitive Areas: Areas having potential to contain significant paleontological resources.
E. Non-sensitive Areas: Areas with little potential of containing significant (National Register eligible) archeological and/or paleontologic resources.
F. Archeological and Paleontological Monitor: Representative of Government designated to oversee construction activities that could disturb archeological resources.
G. Archeological and Paleontological Resources Protection Act (ARPA) of 1979 (Public Law (P.L.)
96-95; 93 United States Statues at Large (Stat.) 712): defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least 100 years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.
1.03 SUBMITTALS
A. Daily Work Schedule: Detail construction work in archeologically sensitive areas. Submit to
Contracting Officer (CO) 30 days before start of ground-disturbing site work.
1.04 QUALITY ASSURANCE
A. At least one week before on-site work begins, Contractor shall meet with Contracting Officer and Archeological and Paleontological Monitor to discuss Daily Work Schedule, equipment, and special methods used in archeologically sensitive areas. Contractor shall ensure approved Daily Work Schedule is followed throughout construction.
PART 2 PRODUCTS
2.01 DAILY WORK SCHEDULE
A. Daily Work Schedule is required for work occurring within archeologically sensitive areas.
Include all work that is to occur within the area and key the schedule to the drawings to include:
1. Starting and ending dates of ground-disturbing construction.
2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.
3. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, landscaping, and post construction clean-up.
4. Methods and equipment used for each type of construction.
5. Plan for relocating work in the event of temporary work stoppages at each archeologically sensitive area
BADL - BADLANDS NATIONAL PARK
PMIS 227786
01 35 13.22 - 2
ARCHEOLOGICAL AND PALEONTOLOGICAL
PROTECTION
PART 3 EXECUTION
3.01 BARRICADES
A. Comply with requirements specified in Section 01 50 00 "Temporary Facilities and Controls."
3.02 ARCHEOLOGICAL INVESTIGATION BY NON-NPS PERSONNEL
A. A permit is required for archeological investigations (e.g. excavation, shovel testing, coring, pedestrian survey, underwater archeology, rock art documentation, or other types of reconnaissance including archaeological monitoring of construction) carried out on parklands by non-National Park Service (NPS) personnel, unless carried out under a contract or a cooperative agreement specifically written for archeological investigations. Permits are issued under the Archaeological Resources Protection Act of 1979 (ARPA). The NPS does not issue a permit for archeological investigations carried out by NPS archeologists, or to archeologists working on NPS archeological projects under a contract or cooperative agreement.
3.03 OBSERVATION
A. Archeological and Paleontological Monitor will observe ground-disturbing site work, including construction of temporary facilities, at archeologically sensitive areas, from a safe location mutually agreed on by Contractor and Monitor.