B08_Attachment_15_Option_Line_Item_Specifications_CS_Reviewed_7_19_22.pdf
PDF 84 KB Posted
- Solicitation number
- 140P3022R0016
About this file
This document outlines an optional line item for contaminated soil remediation as part of a federal solicitation for the East Potomac Maintenance Yard Fuel Station Rehabilitation project. If soil contamination testing reveals contaminated soil, the contracting agency may exercise this option to remove and dispose of up to 500 cubic yards of contaminated soil. The contractor would excavate, remove, and properly dispose of contaminated soil in accordance with the recycling and disposal regulations and environmental regulations sections of the solicitation and resulting contract. The contractor must provide disposal documentation and record hazardous materials on a waste tracking sheet to the contracting officer's representative within 48 hours of disposal. The contractor shall also backfill the excavated area with clean fill material in the same manner as specified for earth moving work.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Option Line Item Contaminated Soil Remediation Specifications
7/19/2022
1.0 Option Line Item – Contaminated Soil Remediation
1.1 If soil contamination testing yields the presence of contaminated soil, this Option Line Item may be exercised, subject to available funds, to remove and replace up to 500 CY of soil.
1.2 The contractor shall excavate, remove, and properly disposed of all contaminated soil up to 500 CY in accordance with Section C.9 RECYCLING AND DISPOSAL OF REFUSE and C.16 ENVIRONMENTAL REGULATIONS of the solicitation and resulting contract. A copy of the disposal ticket shall be provided via email to the COR. The contractor shall record all hazardous materials disposed of on the Waste Tracking Sheet to be submitted to the COR via email within 48 hours of disposal.
1.3 The contractor shall backfill the excavation with uncontaminated/clean fill material up to 500 CY in the same manner outlined in EPMY Specifications, Section 312000 – Earth Moving.