B08_Attachment_10_ORPI_Water_System_Replace_Permit_Plan.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
ORPI 240841 Replace Primary Water System for Maint
Solicitation number
140P2024R0150
Issued by

About this file

This document is a Permit Plan form that is part of the permitting process for the Denver Service Center (DSC) to rehabilitate the primary water system for Organ Pipe Cactus National Monument (ORPI).

The Permit Plan identifies the required permits, including: Approval to Construct Drinking Water Facilities (storage tanks and new well) from the Arizona Department of Environmental Quality (ADEQ), and a Construction General Permit for stormwater discharges from ADEQ. The plan provides details on the permit requirements, application fees, issuing agency contacts, and estimated timelines for review and approval. The plan also indicates that an Approval of Construction certificate will be required after construction is completed, prior to system operation. The associated federal contract opportunity is to replace the primary water system at ORPI, which currently uses asbestos-cement pipe.

View the file

Other files

File Type Posted
Sol_140P2024R0150_Amd_0004.pdf PDF
Questions_and_Answers_for_Solicitation_140P2024R0150_0004.xlsx XLSX spreadsheet
Sol_140P2024R0150_Amd_0003.pdf PDF
ORPI_Sign_0003.jpeg JPEG file
Sol_140P2024R0150_Amd_0002.pdf PDF
Answered_Clarification_Questions_0002.pdf PDF
Sol_140P2024R0150_Amd_0001.pdf PDF
B08_Attachment_4B_Project_Experience_Questionnaire__.pdf PDF
B08_Attachment_5E_LmtOnSubconRpt_REQD.xlsx XLSX spreadsheet
B08_Attachment_5A_Solit_VOLUME_II_PSP_Cover.pdf PDF
Sol_140P2024R0150.pdf PDF
B08_Attachment_4C__Key_Personnel_Resume_Form.pdf PDF
B08_Attachment_4D_Solit_PSP_Vol_I_PastPerf_REQD(1).pdf PDF
B08_Attachment_2b_ORPI_CD_SHEETSET-100__Final_CDs_STAMPED-2.pdf PDF
B08_Attachment_4A_Solit_VOLUME_I_PSP_Cover.pdf PDF
B08_Attachment_7_Geotech_Replace_Primary_Park_Water_Systems_FINAL.pdf PDF
B08_Attachment_8_Hydrogeologic_Assessment.pdf PDF
B08_Attachment_6_Construction_Contract_Administration.pdf PDF
B08_Attachment_5C_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Attachment_5D_ORPI_240821_ContractPriceSchedule.xlsx XLSX spreadsheet
B08_P2024R0150__ORPI_240841_SF1442_Clauses_9_30_24.pdf PDF
B08_Attachment_1a_ORPI_Final_CDs_DIV_1_Specifications1.pdf PDF
B08_Attachment_1b_ORPI_Final_CDs_Division_2_Specifications.pdf PDF
B08_Attachment_5B_SF24-23a.pdf PDF
B08_Attachment_3_Wage_Determination.pdf PDF
B08_Attachment_9__Water_System_Basis_Design_Report_SD_Submittal.pdf PDF
B08_Attachment_2a_ORPI_CD_SHEETSET-100__Final_CDs_STAMPED.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Read Me

The Permit Plan is part of a larger Denver Service Center (DSC) permitting process, which consists of Scoping all required permits (Permitting Assessment Form (PAF)); Generating a list of all permits for the project; Assigning permits to be either Government Furnished, Contractor Provided, or Park Acquired; Planning a clear path to acquire each Government Furnished Permits (Permit Plan Form); Develop complete and acceptable applications; and Acquire Government Furnished Permits prior to solicitation.
This workbook contains 2 tabs (worksheets):

1. Read Me - Current worksheet.

2. Form - Blank and used to complete the Permit Plan.

See the DSC Workflows website for:
Permit Plan Sample - A draft Permit Plan that is in progress. The Permit Plan will evolve as the project does in the early stages of design and document efforts pursuing required permits.
Permit Plan Guideline - The Permit Plan with instructions and explanatory text provided to guide in answering questions about permitting and integrate with DSC permitting procedures.
Acronyms & Definitions:
Agency - Agency with Jurisdiction
APA - Administrative Procedures Act
AST - Above Ground Storage Tank
Bid Documents
Contractor Provided Permit
CWA - Clean Water Act
DSC - Denver Service Center
FCC - Federal Communications Commission
Government Furnished Permit
List of All Permits - A list of the name of each permit and the issuing agency. Example: USACE Nation Wide Permit 14.
NPDES - National Pollution Discharge Elimination System (part of CWA)
Permit Plan
Permit Submittal List
Permitting Assessment
RCRA - Resource Conservation and Recovery Act
UST - Underground Storage Tank
WWTP - Waste Water Treatment Plant

&20&K01+048Permit Plan Form https://www.nps.gov/dscw/publicforms.htmhttps://www.nps.gov/dscw/definitionsdc_c.htmhttps://www.nps.gov/dscw/definitionsdc_p.htmhttps://www.nps.gov/dscw/publicforms.htmhttps://www.nps.gov/dscw/definitionsdc_d.htmhttps://www.nps.gov/dscw/definitionsdc_g.htmhttps://www.nps.gov/dscw/definitionsdc_p.htmhttps://www.nps.gov/dscw/definitionsdc_p.htmhttps://www.nps.gov/dscw/definitionsdc_p.htmhttps://www.nps.gov/dscw/definitionsdc_a.htmhttps://www.nps.gov/dscw/definitionsdc_b.htm

FORM

Project Meta Data
PROJECT TITLE:Rehabilitate Primary Park Water SystemsPMIS #:240821PEPC#
PARK:ORPIREGION: IMRPROGRAM:Permit Lead:Darren Stewart
PARK CONTACT:Nick HuckA\E:ajc architectsDSC PM: Steven Splitek
Dates of Assessment:1/11/22A\E CONTACT:Jill A. JonesDSC PS: Kelsey Anderson
Permits to Contracting no later than:Prior to start of construction
Notes:Drinking water system permitted as public water system with Arizona Department of Environmental Quality (ADEQ).
Permits Required
PERMIT: Approval to Construct Drinking Water Facilities (Storage Tanks and New Well)
Permit Standard: Engineering Bulletin 8 and 10Date of information: TBDConsultation Started: TBD
Issuing Agency: AZ Dept. of Environmental QualityApplication Fee:YesAmount of Fee: $800 for each tank, $1,250 well
Agency Contact:wqd_dwser@azdeq.gov602-771-2300Needed Components: Approval to Construct (ATC) application, fee, site plan, construction quality drawings and plans, design report, new source analysis, notice of intent to drill
Est. Permit Timeline
DSC Review date: TBD
Application Submitted: TBD
Duration of AHJ Review (Roll up Total): 53 days
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue: TBDExpected Date of Expiration/ Duration of Permit:ATC is valied for 4 years and 90 days. If Approval of Construction (AOC) is not submitted in this time frame, ATC will be voided.
Construction Monitoring Req.: Yes Notes: Approval of Construction (AOC) application prepared by AZ professional engineer required to confirm construction conforms to approved plans.
Construction Restoration Req.: No Notes:
Post Occupancy Mitigation Req.: No Notes:
Notes: ATC application/permit required for both water storage tanks and new well. A separate ATC is required for each component. AOC application/certificate required after construction and final testing have been completed before system can be operated.
PERMIT: Approval of Construction (AOC) Certificate
Permit Standard: Engineering Bulletin 8 and 10Date of information: TBDConsultation Started: TBD
Issuing Agency: AZ Dept. of Environmental QualityApplication Fee:NoAmount of Fee: NA
Agency Contact:wqd_dwser@azdeq.gov602-771-2300Needed Components: Approval of Construction (AOC) application, Engineering Certification of Completion (ECC), As-Built Plans, Quality Control Testing Results and Calculations, Operation and Maitenance Manucal, New Source Analysis
Est. Permit Timeline
DSC Review date: TBD
Application Submitted: TBD
Duration of Review:
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:NA
Construction Monitoring Req.: Yes Notes: Approval of Construction (AOC) application prepared by AZ professional engineer required to confirm construction conforms to approved plans.
Construction Restoration Req.: No Notes:
Post Occupancy Mitigation Req.: No Notes:
Notes: ATC application/permit required for both water storage tanks and new well. A separate ATC is required for each component. AOC application/certificate required after construction and final testing have been completed before system can be operated.
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
Notes:
PERMIT:
Permit Standard:Date of information:Consultation Started:
Issuing Agency:Application Fee:Amount of Fee:
Agency Contact:Needed Components: cover letter (required), Application (typical), and supporting documents:
Est. Permit Timeline
DSC Review date:
Application Submitted:
Duration of AHJ Review (Total):
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue:Expected Date of Expiration/ Duration of Permit:
Construction Monitoring Req.: Yes / No Notes:
Construction Restoration Req.: Yes / No Notes:
Post Occupancy Mitigation Req.: Yes / No Notes:
PERMIT: Approval to Construct Drinking Water Facilities (Storage Tanks and New Well)
Permit Standard: Engineering Bulletin 8 and 10Date of information: TBDConsultation Started: TBD
Issuing Agency: AZ Dept. of Environmental QualityApplication Fee:YesAmount of Fee: $800 for each tank, $1,250 well
PERMIT: Construction General Permit (CGP) for Stormwater Discharges Associated with Construction Activity
Permit Standard: ARS Title 49, Chapter 2, Article 3.1Date of information: TBDConsultation Started: TBD
Issuing Agency: AZ Dept. of Environmental QualityApplication Fee:YesAmount of Fee: $350
Agency Contact:stormwater@azdeq.gov602-771-2300Needed Components: Notice of Intent (NOI) application, Stormwater Pollution Prevention Plan (SWPPP),
Est. Permit Timeline
DSC Review date: TBD
Application Submitted: TBD
Duration of AHJ Review (Roll up Total): 53 days
1) Completeness (days):
2) Analysis (days):
3) other step (days):
4) Public Review (days):
5) other step (days):
Expected Date of Issue: TBDExpected Date of Expiration/ Duration of Permit:CGP is effective until a Notice of Termination (NOT) is submitted to ADEQ or approved, or until June 30, 2025, whichever occurs first
Construction Monitoring Req.: Yes Notes: Routine inspections and documentation required throughout project per AZDEQ requirements.
Construction Restoration Req.: No Notes:
Post Occupancy Mitigation Req.: No Notes:
n

&"-,Bold"&12Permit Plan for Goverment Furnished Permits for:

ORPI - PMIS# 240821, Rehabilitate Primary Park Water Systems

&9Permit Plan FORM, 12-2-16 National Park Service - Denver Service Center &9&D | page &P of &N mailto:wqd_dwser@azdeq.govmailto:stormwater@azdeq.gov

File details come from the government source that posted it. Updated .