Sol_140P2024R0150_Amd_0001.pdf

PDF 84 KB Posted

Attached to
ORPI 240841 Replace Primary Water System for Maint
Solicitation number
140P2024R0150
Issued by

About this file

This document is an amendment to Solicitation No. 140P2024R0150 for the ORPI 240841 project to replace the primary water system for the maintenance and housing area at Organ Pipe Cactus National Monument in Ajo, Arizona.

The key details are:

  • The purpose of this Amendment #1 is to schedule an organized site visit on October 24, 2024 at 8:00 am MST, with participants meeting at the Visitor Center.
  • The existing water distribution system uses asbestos-cement (AC) pipe and requires replacement.
  • The solicitation is being issued by the National Park Service, which is a civilian federal agency under the Department of the Interior.
  • Offers must acknowledge receipt of this amendment prior to the due date and time specified in the solicitation.

View the file

Other files

File Type Posted
Questions_and_Answers_for_Solicitation_140P2024R0150_0004.xlsx XLSX spreadsheet
Sol_140P2024R0150_Amd_0004.pdf PDF
ORPI_Sign_0003.jpeg JPEG file
Sol_140P2024R0150_Amd_0003.pdf PDF
Sol_140P2024R0150_Amd_0002.pdf PDF
Answered_Clarification_Questions_0002.pdf PDF
B08_Attachment_4B_Project_Experience_Questionnaire__.pdf PDF
B08_Attachment_5E_LmtOnSubconRpt_REQD.xlsx XLSX spreadsheet
B08_Attachment_5A_Solit_VOLUME_II_PSP_Cover.pdf PDF
B08_Attachment_10_ORPI_Water_System_Replace_Permit_Plan.xlsx XLSX spreadsheet
B08_Attachment_8_Hydrogeologic_Assessment.pdf PDF
B08_Attachment_6_Construction_Contract_Administration.pdf PDF
B08_Attachment_5C_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Attachment_5D_ORPI_240821_ContractPriceSchedule.xlsx XLSX spreadsheet
B08_P2024R0150__ORPI_240841_SF1442_Clauses_9_30_24.pdf PDF
B08_Attachment_1a_ORPI_Final_CDs_DIV_1_Specifications1.pdf PDF
B08_Attachment_1b_ORPI_Final_CDs_Division_2_Specifications.pdf PDF
B08_Attachment_5B_SF24-23a.pdf PDF
B08_Attachment_3_Wage_Determination.pdf PDF
Sol_140P2024R0150.pdf PDF
B08_Attachment_4C__Key_Personnel_Resume_Form.pdf PDF
B08_Attachment_4D_Solit_PSP_Vol_I_PastPerf_REQD(1).pdf PDF
B08_Attachment_2b_ORPI_CD_SHEETSET-100__Final_CDs_STAMPED-2.pdf PDF
B08_Attachment_4A_Solit_VOLUME_I_PSP_Cover.pdf PDF
B08_Attachment_7_Geotech_Replace_Primary_Park_Water_Systems_FINAL.pdf PDF
B08_Attachment_9__Water_System_Basis_Design_Report_SD_Submittal.pdf PDF
B08_Attachment_2a_ORPI_CD_SHEETSET-100__Final_CDs_STAMPED.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2024R0150 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

ORPI 24084109/30/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/30/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

ORPI 240841 Replace Primary Water System for Maintenance and Housing Area, Organ Pipe

Cactus National Monument, Ajo, AZ

The purpose of this Amendment # 1 is for the following:

1) An organized site visit has been scheduled for October 24,2024 at 8:00 am MST.

Participants shall meet in front of the Visitor Center;

the address is: 10 Organ Pipe Drive, Ajo, AZ 85321.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jason Longshore

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .