B08-Attachment_1_LOWE_Specifications_REV_2026_04_21.pdf

PDF 5 MB Posted

Attached to
Lowell National Historical Park; Rehabilitate Bath
Solicitation number
140P4326R0014
Issued by

About this file

This file contains the project specifications and construction documents for the Lowell National Historical Park bathroom rehabilitation project at the Mogan Cultural Center in Lowell, Massachusetts. The work consists of selective demolition and new construction to modernize and rehabilitate existing restroom facilities to comply with applicable building codes, plumbing standards, mechanical and electrical codes, and ABA Accessibility Standards. The project includes bathroom renovations on the 2nd and 3rd floors of the Mogan Cultural Center, with approximately 560 gross square feet of work, and is estimated at between $500,000 and $1,000,000. Construction activities encompass electrical, plumbing, mechanical, fire protection, and general construction work, including selective demolition of existing conditions. The specifications are comprehensive and cover Division 01 general requirements (project management, construction scheduling, submittals, quality control, safety, temporary facilities), Division 02 selective demolition, and specialized sections addressing metal fabrications, rough carpentry, joint sealants, hollow metal frames and doors, door hardware, non-structural metal framing, gypsum board, ceramic tiling, acoustical ceilings, and resinous flooring systems. Key materials specified include ceramic tile with waterproofing membranes for wet areas, cementitious urethane-based self-leveling flooring systems (Dur-A-Flex product), gypsum board with fire-rating requirements, metal stud framing, and standard hollow metal doors with appropriate hardware and accessibility compliance. The contract requires submission of detailed project management documentation including construction schedules using Critical Path Method, quality control plans, waste management plans with 75 percent diversion rates, indoor air quality management procedures, and operation and maintenance manuals, with substantial completion and final acceptance procedures outlined for NPS review and approval.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lowell National Historical Park

Rehabilitate Parkwide Bathrooms to support Visitor Experience, Accessibility and Safety

Lowell, MA 01852

NPS Contract Number 140P2021D0004

PMIS: 312999 B

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE (NPS)

LOWELL NATIONAL HISTORICAL PARK

REHABILITATE PARKWIDE BATHROOMS

DOCUMENT 000002 - TABLE OF CONTENTS

C o n st r u c ti o n

D c u m e ts

R

C o n st r u c ti c u m e n ts

Division Section Title CURRENT 7/17/2023 5/18/2023

011000 SUMMARY OF WORK 00 00 00

012601 CONTRACT MODIFICATION PROCEDURES 00 00 00

012700 DEFINITION OF CONTRACT LINE ITEMS 00 00

013100 PROJECT MANAGEMENT AND COORDINATION 00 00 00

013216 CONSTRUCTION SCHEDULE 00 00 00

013233 PHOTO DOCUMENTATION 00 00 00

013323 SUBMITTAL PROCEDURES 00 00 00

013523 SAFETY REQUIREMENTS 00 00 00

014000 QUALITY REQUIREMENTS 00 00 00

014200 REFERENCE STANDARDS 00 00 00

015000 TEMPORARY FACILITIES AND CONTROLS 00 00 00

015719.11 INDOOR AIR QUALITY MANAGEMENT 00 00 00

015719.12 NOISE AND ACOUSTICS MANAGEMENT 00 00 00

016700 PRODUCT REQUIREMENTS 00 00 00

017329 CUTTING AND PATCHING 00 00 00

017340 EXECUTION 00 00 00

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 00 00 00

017700 CLOSEOUT PROCEDURES 00 00 00

017823 OPERATION AND MAINTENANCE DATA 00 00 00

017900 DEMONSTRATION AND TRAINING 00 00 00

DIVISION 02 - CONCRETE

024100 SELECTIVE DEMOLITION 00 00 00

DIVISION 05 - METALS

055000 METAL FABRICATIONS 00 00 00

DIVISION 06 - WOODS, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY 00 00 00

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

079200 JOINT SEALANTS 00 00 00

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES 00 00 00

081216 SLIDING WOOD DOORS AND ALUMINUM FRAMES 00 00 00

081416 FLUSH WOOD DOORS 00 00 00

083113 ACCESS DOORS AND FRAMES 00 00 00

087100 DOOR HARDWARE 00 00 00

088115 GLAZING FILM 00 00 00

DIVISION 01 - GENERAL REQUIREMENTS

TABLE OF CONTENTS 000002 - 1

David Lieb Line

David Lieb Line

C o n st r u c ti c u m e

C o n st r u c ti c u m e n ts

Division Section Title CURRENT 7/17/2023 5/18/2023

DIVISION 09 - FINISHES

092216 NON-STRUCTURAL METAL FRAMING 00 00 00

092900 GYPSUM BOARD 00 00 00

093000 TILING 00 00 00

095100 ACOUSTICAL CEILINGS 00 00 00

096723 RESINOUS FLOORING 00 00 00

099123 INTERIOR PAINTING 00 00 00

DIVISION 10 - SPECIALTIES

101400 SIGNAGE 01 01 00

102113 SOLID PLASTIC TOILET COMPARTMENTS 00 00 00

102800 TOILET ACCESSORIES 00 00 00

104416 FIRE EXTINGUISHERS 00 00 00

DIVISION 21 - FIRE PROTECTION

210529

HANGERS AND SUPPORTS FOR FIRE-SUPPRESSION PIPING AND

EQUIPMENT 00 00 00

211313 WET-PIPE SPRINKLER SYSTEM 00 00 00

DIVISION 22 - PLUMBING

220518 ESCUTCHEONS FOR PLUMBING PIPING 00 00 00

220523.12 BALL VALVES FOR PLUMBING PIPING 00 00 00

220523.14 CHECK VALVES FOR PLUMBING PIPING 00 00 00

220529

HANGERS AND SUPPORTS FOR PLUMBING PIPING AND

EQUIPMENT 00 00 00

220533 HEAT TRACING FOR PLUMBING PIPING 00 00 00

220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 00 00 00

220719 PLUMBING PIPING INSULATION 00 00 00

221116 DOMESTIC WATER PIPING 00 00 00

221119 DOMESTIC WATER PIPING SPECIALTIES 00 00 00

221316 SANITARY WASTE AND VENT PIPING 00 00 00

221319 SANITARY WASTE PIPING SPECIALTIES 00 00 00

224213.13 COMMERCIAL WATER CLOSETS 00 00 00

224213.16 COMMERCIAL URINALS 00 00 00

224216.13 COMMERCIAL LAVATORIES 00 00 00

224216.16 COMMERCIAL SINKS 00 00 00

224716 PRESSURE WATER COOLERS 00 00 00

DIVISION 23 - MECHANICAL

230100 COMMON HVAC REQUIREMENTS 00 00 00

230102 COMMON HVAC DEMOLITION REQUIREMENTS 00 00 00

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 00 00 00

230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING 00 00 00

230518 ESCUTCHEONS FOR HVAC PIPING 00 00 00

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 00 00 00

230548 VIBRATION CONTROLS FOR HVAC 00 00 00

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 00 00 00

TABLE OF CONTENTS 000002 - 2

David Lieb Line

C o n st r u c ti c u m e

C o n st r u c ti c u m e n ts

Division Section Title CURRENT 7/17/2023 5/18/2023

230593 TESTING ADJUST AND BALANCING FOR HVAC 00 00 00

230713 DUCT INSULATION 00 00 00

230923 INSTRUMENTATION AND CONTROL FOR HVAC 00 00 00

230993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS 00 00 00

233113 METAL DUCTS 00 00 00

233300 AIR DUCT ACCESSORIES 00 00 00

233416 CENTRIFUGAL HVAC FANS 00 00 00

233713 DIFFUSERS REGISTERS AND GRILLES 00 00 00

DIVISION 26 - ELECTRICAL

260519

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND

CABLES 00 00 00

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 00 00 00

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 00 00 00

260533.13 CONDUITS FOR ELECTRICAL SYSTEMS 00 00 00

260533.16 BOXES AND COVERS FOR ELECTRICAL SYSTEMS 00 00 00

260544

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS

AND CABLING 00 00 00

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS 00 00 00

260923 LIGHTING CONTROL DEVICES 00 00 00

262726 WIRING DEVICES 00 00 00

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS 00 00 00

262913.03 MANUAL AND MAGNETIC MOTOR CONTROLLERS 00 00 00

265119 LED INTERIOR LIGHTING 00 00 00

265213 EMERGENCY AND EXIT LIGHTING 00 00 00

284621.13 CONVENTIONAL FIRE-ALARM SYSTEMS 00 00 00

END OF SECTION

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

TABLE OF CONTENTS 000002 - 3

PMIS 312999 B

NPS 140P2021D0004-05/18/2023

01 10 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Contractor Use of Site

4. Public Use of Site

5. Occupancy Requirements for Buildings

6. Conduct of Operations

7. Work Restrictions

8. Special Construction Requirements

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Lowell National Historical Park

B. The Work consists of:

1. Bathroom renovations in three buildings at the Lowell National Historical Park.

The ONE BUILDING at the Lowell National Historical Park require rehabilitation and modernization to the existing restroom facilities to comply with applicable building, plumbing, mechanical, electrical codes and ABA Accessibility Standards (ABAAS). The three buildings are as follows:

a. Mogan Cultural Center - consists of the modernization of Men’s and Women’s restrooms on the 2nd and 3rd floors. Each of the restrooms is approximately 140 SF. GSF for the project is approximately 560 SF.

2. Demolition:

a. Demolition of the existing construction per the Contract Documents.

3. Construction:

a. New construction includes electrical, plumbing, mechanical, fire protection and general construction per the Contract Documents.

C. Project will be constructed under ONE prime contracts.

1. FY24 Contract1 – Visitor Center and Counting House

01 10 00 - 2

SUMMARY OF WORK

2. FY26 Contract 1 – Mogan Cultural Center

1.3 CONTRACTOR USE OF SITE.

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated in Contract Documents. Do not disturb portions of Project site beyond areas in which the Work is indicated. Coordinate project boundaries and access with the Contracting Officer and Park.

1. Limits: Confine constructions operations to lift shaft, adjacent corridor, and stair hall.

B. Storage of Materials: Off site.

C. Stockpiling: Confine staging area as agreed to by the Contracting Officer.

1.4 PUBLIC USE OF SITE

A. The area will be open to the public during construction.

B. Contractor shall conduct his operations to ensure the least inconvenience to public.

1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy premises during entire construction period, with the exception of areas under demolition and construction.

Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

1.6 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business/calendar days in advance of the work to the Contracting Officer for approval.

No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

01 10 00 - 3

SUMMARY OF WORK

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.

B. Existing Utilities

1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within

25 feet of entrances, operable windows, or outdoor air intakes.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

PMIS-312999 B 01 26 01 - 1

NPS-140P2021D0004-05/18/2023 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating

General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

PMIS-312999 B 01 26 01 - 2

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General

Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

PMIS-312999 B 01 26 01 - 3

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General

Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of

Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|

PMIS-312999 B 01 26 01 - 4

3. Requests for extensions of contract time as a result of change must be justified with a

Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense

Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

PMIS-312999 B 01 26 01 - 5

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army

Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10%

Profit……………… 08%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

Rectangle

PMIS-312999 B 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

PMIS 312999 B 01 27 00 - 1

NPS 140P2021D0004-05/18/2023 DEFINITION OF CONTRACT LINE ITEMS

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) 1-27-21

< NPS 140P2021D0004 PMIS 312999 B >

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS SOLICITATION FY24

A. Contract Line Item Number 0001 Counting House.

1. This item consists of: Modernization of Men’s and Women’s bathrooms in the building and six accessible gender neutral, family restrooms. Each of the restrooms is approximately

70 SF. GSF for the project is approximately 650 SF.

2. Measurement for payment will be based upon completion of the scope of Work indicated on payment application as a percentage of the full scope of Work and the lump sum price as determined by the Contracting Officer. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item Number 0002 Visitor Center – 1st Floor

1. This item consists of: - Modernization of Men’s and Women’s restrooms in the building as well as one accessible gender neutral 1st floor restroom.

2. Measurement for payment will be based upon completion of the scope of Work indicated on payment application as a percentage of the full scope of Work and the lump sum price as determined by the Contracting Officer. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item Number 003 Visitor Center – 2nd Floor

1. This item consists of: Modernization of Men’s and Women’s restrooms in the building as well as two single-use gender neutral 2nd floor restrooms.

David Lieb Line

PMIS 312999 B 01 27 00 - 2

NPS 140P2021D0004-05/18/2023 DEFINITION OF CONTRACT LINE ITEMS

2. Measurement for payment will be based upon completion of the scope of Work indicated on payment application as a percentage of the full scope of Work and the lump sum price as determined by the Contracting Officer. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

3.2 LIST OF CONTRACT LINE ITEMS SOLICITATION FY26

A. Contract Line Item Number 0001 Mogan Cultural Center.

1. This item consists of: Modernization of Men’s and Women’s restrooms on the 2nd and 3rd floors. Each of the restrooms is approximately 140 SF. GSF for the project is approximately

560 SF.

2. Measurement for payment will be based upon completion of the scope of Work indicated on payment application as a percentage of the full scope of Work and the lump sum price as determined by the Contracting Officer. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

David Lieb Line

01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. Project Meetings

7. Environmental Coordination

8. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction

1. NPS Regional Fire Safety (AHJ)

2. Park Accessibility Coordinator

3. City of Lowell Plumbing Authority Having Jurisdiction

B. Construction Permits – Contractor Provided

C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum

01 31 00 - 2 accessibility for required maintenance, service, and repair.

3. Make provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Contractor's Construction Schedule

2. Preparation of the Schedule of Values

3. Delivery and processing of submittals

4. Progress meetings

5. Permit requirements

6. Pre-installation conferences

7. Project closeout activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination

Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed equipment and controls.

e. Indicate required installation sequences.

2. Number of Copies: Submit Portable Document Format (PDF) copies of each submittal.

Contracting Officer will return one copy.

3. Refer to individual Sections for Coordination Drawing requirements for Work in those

01 31 00 - 3

Section

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices.

Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate sub-framing for support of elevator components, mechanical and electrical equipment, and related Work.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Electrical Work:

a. Elevator power and controls, cab and shaft lighting fixtures, emergency battery pack, smoke detector, and other fire-alarm device locations.

b. Panel board modifications

7. Fire-Protection System:

a. Locations of branch lines, pipe drops, and sprinkler heads.

C. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.Coordination

Digital Data Files: Prepare coordination digital data files according to:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document

Format (PDF) file format.

3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of

Drawings for use in preparing coordination digital data files.

a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 1 documents: The following items shall be submitted a minimum of one week prior to

Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre-

Construction Conference.

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

01 31 00 - 4

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. IAQ Management Plan; refer to Sections 015719.11 and 015719.12.

11. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

E. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of

Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on

NPS/DSC workflows website.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by

Contractor.

B. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.Content of RFI:

Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract

Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete RFI Form and send electronically to the Contracting Officer for review via

01 31 00 - 5 email or agreed upon fileshare site (Sharepoint, etc.).

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or

Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Contractor

9. Payroll reports

10. Contract time

11. Liquidated damages

12. Contractor Performance Evaluation

13. Display of Hotline posters

14. Notice to proceed

15. Correspondence procedures

16. NPS/DSC Project website

17. Acceptance/rejection of work

18. Progress meetings

19. Submittal procedures

20. NPS Final Accessibility Inspection

21. Environmental requirements

22. Permit requirements

23. As-constructed drawings/operation and maintenance (O&M) manuals.

01 31 00 - 6

24. Saturday, Sunday, holiday and night work.

25. Reference materials

26. Value engineering

27. Schedule of Values

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the

Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

1) Work in progress and projected.Status of required inspections (Special

Inspections, Accessibility, etc.)

f. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)

g. Construction Schedule update (provide updated Critical Path Method (CPM)).

h. Status of Project Record Drawings and O&M manuals.

i. Other business relating to work.

j. Permit requirements

C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting

Officer of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:

a. Contract Documents

b. Options

c. Related RFIs

d. Related Change Orders

e. Purchases

f. Deliveries

g. Submittals

h. Review of mockups

i. Possible conflicts

j. Compatibility requirements

k. Time schedules

01 31 00 - 7

l. Weather limitations

m. Manufacturer's written instructions

n. Warranty requirements

o. Compatibility of materials

p. Acceptability of substrates

q. Temporary facilities and controls

r. Space and access limitations

s. Regulations of agency(ies) with jurisdiction

t. Testing and inspecting requirements

u. Installation procedures

v. Coordination with other work

w. Required performance results

x. Protection of adjacent work

y. Protection of construction and personnel

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing

Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of Waste Management Plan (WMP).

c. Implementation of Indoor Air Quality (IAQ) Management Plan.

e. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements

2. Regulatory Requirements

3. Construction Waste Management

1.8 PERMITS

A. General:

1. Permits and Responsibilities: Contractor shall, without additional expense to the

01 31 00 - 8

Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract, Contractor will not be considered an agent of the

Government. Contractor shall comply with appropriate Federal, State and local laws.

B. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.

C. Administrative Procedures:

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.

2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.

Upload permits to NPS/DSC management software website when permits are obtained.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

A. Section consists of Construction Schedule requirements including:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and

Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.

A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.

The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.

E. Float: Measure of leeway in starting and completing an activity.

1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.

2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

01 32 16 - 2

3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.

F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: Submit schedules and reports for review by Contracting Officer via email or approved file share site. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.

B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit four digital copies of baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.

D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit three digital copies of the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data.

Provide two paper copies.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision, submit two digital copies of a Time Impact Analysis. Incorporate a Fragmentary

Network (Fragnet) into currently accepted Construction Schedule that demonstrating how

Contractor proposes to incorporate a modification, change, delay, or Contractor request.

1.4 QUALITY ASSURANCE

A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:

1. Review software limitations, content and format for reports.

01 32 16 - 3

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Review time required for review of submittals and re-submittals.

4. Review requirements for tests and inspections by independent testing and inspecting agencies.

5. Review time required for completion and startup procedures.

6. Review time required for obtaining and activating permits.

7. Review and finalize list of construction activities to be included in schedule.

8. Review baseline schedule comments, resolve issues and progress on incorporating them

9. Review procedures for updating schedule.

10. Discuss reporting requirements and establish protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction

Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency of using scheduling software. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of work from parties involved.

3. Coordinate each construction activity in network with other activities and schedule in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting

Officer may request data to verify accuracy of dollar values.