This is a set of 100% design construction drawings for a pavement preservation project across four South Carolina National Park Service facilities: Congaree National Park (CONG), Cowpens National Battlefield (COWP), Kings Mountain National Military Park (KIMO), and Ninety Six National Historic Site (NISI). The project encompasses pavement preservation work totaling 11.48 roadway miles and 0.71 parking miles across Richland, Cherokee, York, and Greenwood counties in South Carolina.
The scope of work includes asphalt patching, crack sealing, seal coating, asphalt overlay, pavement milling, concrete slab replacement, full-depth asphalt reclamation, and aggregate edge support on both roads and parking areas. The contract consists of four base bid packages (CLINs) corresponding to each park location, with four additional option packages available. Work must comply with NPS requirements, South Carolina SCDOT standards, county specifications, and the latest SC Manual for Erosion Control. Key contractor responsibilities include preparing record drawings, performing quality control testing, maintaining erosion control measures throughout construction, protecting existing utilities and trees, coordinating pre-construction conferences with NPS, providing staging areas, maintaining traffic flow and public access, and obtaining all required governmental inspections. Pavement treatments include seal coat applications, 1-inch through 4-inch asphalt mill and overlay options, and full asphalt reconstruction where necessary. Pavement markings must comply with MUTCD standards and include thermoplastic for stop bars and pedestrian crosswalks (Type H) and waterborne traffic paint for all other striping (Type B). The drawings specify detailed temporary traffic control measures, construction phasing requirements to maintain visitor access and emergency vehicle routes, and comprehensive erosion control protocols including silt fence installation, sediment management, and stabilization requirements.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAWING NO.
197,917
SHEET
OF
PKG.
NO.
334914
TITLE OF DRAWING
100% DESIGN REV. 1 DEVELOPMENTAL PLANS
LOCATION WITHIN PARK
CONG, COWP, KIMO, NISI
REGION COUNTY STATE
UNITED STATES
DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE
SOUTHEAST REGION
Mark Sheet Date InitialREVISION QUALITY DESIGN CERTIFICATION Prepared in Accordance with Design Development (Title I)
OR
Variance from Design Development (Title I) Approved by Superintendent on
OR
Construction Drawing Not Preceded by Design Development (Title I)
Project Manager Date
Drawing No.
Date
SER MULTIPLE SC 88
334929 334920 334915
100% DESIGN REV. 1
JULY 2026
NOT FOR CONSTRUCTION
PLANS PREPARED BY:
FOR
U.S. DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE
NOT TO SCALE
SUMMARY INDEX
SHEET AREA DESIGNATOR TITLE OF SHEET
01 - 40 00 GENERAL
41 - 50 01 CONG
51 - 72 02 COWP
73 - 86 03 KIMO
87 - 90 04 NISI
DESCRIPTION OF PROJECT
IMPROVEMENTS: WORK CONSISTS OF
ASPHALT PATCHING, CRACK SEALING,
SEAL COATING, ASPHALT OVERLAY,
PAVEMENT MILLING, CONCRETE SLAB
REPLACEMENT, FULL DEPTH ASPHALT
RECLAMATION, AND AGGREGATE EDGE
SUPPORT
PAVEMENT USAGE: ROAD & PARKING
U.S. DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE
CONGAREE NATIONAL PARK (CONG)
COWPENS NATIONAL BATTLEFIELD (COWP)
KINGS MOUNTAIN NATIONAL MILITARY PARK (KIMO)
NINETY SIX NATIONAL HISTORIC SITE (NISI)
PLANS FOR PROPOSED PROJECT
SC N192 PAVEMENT PRESERVATION, MULTIPLE SITES IN SC
PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS
RICHLAND, CHEROKEE, YORK
AND GREENWOOD COUNTIES, SOUTH CAROLINA
LENGTH 11.48 ROADWAY MILES & 0.71 PARKING MILES
PMIS TABLE
PMIS # PARK CODE
334914 CONG
334929 COWP
334920 KIMO
334915 NISI
AutoCAD SHX Text 02-Jul-26
INDEX OF SHEETS
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
00- C001 2
INDEX OF SHEETS
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
00- C002
GENERAL NOTES:
1. THE CONTRACTOR IS ADVISED THAT THIS PROJECT CONSISTS OF 4 CLINS (BASE BID PACKAGE) AND 4 OPTIONS
(ALTERNATIVE PACKAGES).
2. AS REQUIRED BY THE OWNER, THE CONTRACTOR SHALL PREPARE RECORD DRAWINGS NEATLY DRAFTED WHICH ACCURATELY REFLECT THE RECORD CONDITION OF THE WORK. THE RECORD DRAWINGS SHALL BE STAMPED AND SIGNED WITH THE CONTRACTOR'S LICENSE NUMBER AND SIGNATURE AND SHALL ALSO BE DULY NOTED AS "RECORD"
DRAWINGS. THE DRAWINGS SHALL BE REMITTED TO NPS FOR FINAL RECORDS.
3. THE CONTRACTOR IS SOLELY RESPONSIBLE FOR THE SUPERVISION AND COORDINATION OF ALL CONSTRUCTION
PROCEDURES.
4. ALL NEW WORK SHALL BE PERFORMED IN STRICT ACCORDANCE WITH THE APPLICABLE CODES AND ORDINANCES IN THE EFFECT AT THE TIME OF CONSTRUCTION. IN THE EVENT OF A CONFLICT, THE MORE STRINGENT REQUIREMENT
SHALL GOVERN AND BE MET.
5. SPECIFICATIONS REFERENCED IN THE PLANS SHALL BE THE LATEST EDITION.
6. ALL WORK AND MATERIAL SHALL MEET NPS REQUIREMENTS, THE LATEST COUNTY STANDARD SPECIFICATIONS, THE STATE OF SOUTH CAROLINA MANUALS FOR EROSION CONTROL, AND THE LATEST VERSION OF SCDOT STANDARDS
FOR ROAD AND BRIDGE CONSTRUCTION.
7. ONLY NEW ITEMS MEETING THE REQUIREMENTS OF THIS CONTRACT AND OF RECENT MANUFACTURE, OF QUALITY
SPECIFIED, FREE FROM DEFECTS, WILL BE PERMITTED ON THE PROJECT.
8. THE CONTRACTOR SHALL PERFORM QUALITY CONTROL (QC) AS INDICATED IN THE PROJECT SPECIFICATIONS INCLUDING PROVIDING A QUALITY CONTROL PLAN (QCP) PRIOR TO EXECUTION OF WORK. THE OWNER WILL PERFORM
ADDITIONAL QUALITY ACCEPTANCE (QA) TESTING FOR ACCEPTANCE DETERMINATION.
9. ALL TEMPORARY TRAFFIC CONTROL WORK SHALL CONFORM TO THE LATEST EDITION OF THE "MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES" (MUTCD) AND ALL REVISIONS, UNLESS SUPERCEDED BY THESE PLANS.
10. THE CONTRACTOR SHALL PROVIDE A STAGING AREA ADJACENT TO OR WITHIN THE AREA OF CONSTRUCTION. THE SELECTED LOCATION SHALL BE COORDINATED FOR APPROVAL WITH THE CONTRACTING OFFICER'S
REPRESENTATIVE.
11. THE CONTRACTOR SHALL PROVIDE TEMPORARY BARRICADES TO SEPARATE CONSTRUCTION AREAS FOR PUBLIC SAFETY AROUND ENTIRE PERIMETER OF CONSTRUCTION AREA. AREAS OUTSIDE THE LIMITS OF PROPOSED WORK THAT ARE DISTURBED BY THE CONTRACTOR'S OPERATIONS SHALL BE RESTORED BY THE CONTRACTOR TO THEIR
ORIGINAL CONDITION AT THE CONTRACTOR'S EXPENSE.
12. ALL DIMENSIONS AND MEASUREMENTS ON DRAWINGS ARE IN FEET, EXCEPT WHERE NOTED. LABELED DIMENSIONS
WHERE SHOWN TAKE PRECEDENCE OVER SCALED MEASUREMENTS.
13. ANY WORK UNACCEPTABLE TO THE CONTRACTING OFFICER'S REPRESENTATIVE SHALL BE REPAIRED OR REPLACED
BY THE CONTRACTOR AT NO ADDITIONAL EXPENSE TO THE OWNER.
14. DURING CONSTRUCTION, NO DIRECT DISCHARGE OF WATER TO DOWNSTREAM RECEIVING WATERS WILL BE ALLOWED. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING WATER QUALITY AND SHALL ROUTE DISCHARGE WATER THROUGH APPROPRIATE SEDIMENT CONTROL MEASURES TO REMOVE SILT AND PREVENT SEDIMENT-LADEN
RUNOFF FROM LEAVING THE SITE.
15. THE TERM "PROPOSED" (PROP) MEANS WORK TO BE CONSTRUCTED USING NEW MATERIALS OR, WHERE APPLICABLE, RE-USING EXISTING MATERIALS IDENTIFIED AS "REMOVE AND RESET" (R&R). EXISTING MATERIALS WHICH ARE BEING REMOVED BUT NOT RE-USED ARE IDENTIFIED AS "REMOVE AND STOCKPILE" (R&S) OR "REMOVE & DISCARD" (R&D).
16. THE CONTRACTOR SHALL CHECK ALL EXISTING CONDITIONS SHOWN ON THESE PLANS IN THE FIELD PRIOR TO THE START OF CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE CONTRACTING OFFICER'S REPRESENTATIVE.
17. CONTRACTOR SHALL PROTECT ALL MATERIALS ON THE JOBSITE FROM THE ELEMENTS THROUGHOUT THE PROJECT.
18. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL DAMAGE OR INJURY TO PROPERTY OF ANY CHARACTER, DURING THE EXECUTION OF THE WORK, RESULTING FROM ANY OMISSION, NEGLECT OR MISCONDUCT IN HIS MANNER OR
METHOD OF EXECUTING THE WORK OR AT ANYTIME DUE TO DEFECTIVE WORK OR MATERIALS.
19. THE CONTRACTOR SHALL NOT DEVIATE FROM THESE PLANS AND SPECIFICATIONS WITHOUT PRIOR WRITTEN
CONSENT OF THE CONTRACTING OFFICER'S REPRESENTATIVE.
20. THE QUANTITIES SHOWN IN THE PLAN ARE SOLELY FOR THE INFORMATION OF THE CONTRACTOR. THE CONTRACTOR IS TO VERIFY THE QUANTITIES AS SHOWN WITH THOSE QUANTITIES AS SHOWN ON THE PLAN. ANY DIFFERENCE IN THE QUANTITIES SHOULD BE BROUGHT TO THE ATTENTION OF THE CONTRACTING OFFICER'S REPRESENTATIVE FOR
CLARIFICATION.
21. THE CONTRACTOR SHALL CONTACT THE APPROPRIATE UTILITY COMPANIES TO HAVE THE LOCATIONS OF THEIR UNDERGROUND UTILITIES MARKED PRIOR TO BEGINNING WORK. CAUTION SHALL BE EXERCISED TO AVOID INTERRUPTION OF SERVICES. CONTRACTOR IS RESPONSIBLE FOR REPAIR TO ANY EXISTING BURIED UTILITIES
DAMAGED DURING CONSTRUCTION.
22. WHERE LACK OF INFORMATION, OR DISCREPANCY SHOULD APPEAR IN THE DRAWINGS OR SPECIFICATIONS, THE CONTRACTOR SHALL REQUEST WRITTEN INTERPRETATION FROM THE CONTRACTING OFFICER BEFORE PROCEEDING
WITH THAT PORTION OF WORK.
23. GENERAL CONTRACTOR WILL BE HELD SOLELY RESPONSIBLE FOR COMPLETION OF ALL WORK SHOWN OR
REASONABLY IMPLIED BY THESE DRAWINGS AND/OR SPECIFICATIONS.
24. UPON COMPLETION OF WORK, ALL CONSTRUCTION AREAS SHALL BE LEFT BROOM CLEAN AND FREE FROM DEBRIS.
NO EXCESS MATERIALS SHALL BE LEFT ON SITE.
25. FINAL LOCATION OF ALL CONSTRUCTION ITEMS SHALL BE SUBJECT TO THE APPROVAL OF THE CONTRACTING OFFICER'S REPRESENTATIVE. BEFORE INSTALLATION, THE CONTRACTOR IS TO NOTIFY THE CONTRACTING OFFICER'S REPRESENTATIVE FOR INSPECTION AFTER THE LAYOUT IS COMPLETE. FIELD VERIFY CONSTRUCTION ITEM
LOCATIONS WITH CONTRACTING OFFICER'S REPRESENTATIVE PRIOR TO INSTALLATION.
26. THE CONTRACTOR IS RESPONSIBLE FOR FULLY MAINTAINING ALL PLANTING (INCLUDING, BUT NOT LIMITED TO:
WATERING, SPRAYING, MULCHING, PRUNING, MOWING, FERTILIZING, ETC. OR AS DIRECTED BY THE OWNER'S REPRESENTATIVE) OF AGGREGATE / SEEDING AREAS UNTIL THE WORK IS ACCEPTED IN TOTAL BY THE OWNER'S
REPRESENTATIVE.
27. THE CONTRACTOR SHALL COMPLETELY GUARANTEE AND MAINTAIN ALL AGGREGATE / SEED AREAS. FINAL ACCEPTANCE WILL BE GRANTED UPON COMPLETION OF ENTIRE PROJECT BY THE OWNER'S REPRESENTATIVE.
28. IF GRASS SEEDING IS DONE AT A TIME THAT IS NOT THE APPROPRIATE PLANTING SEASON, TEMPORARY GRASSING SHALL BE USED. TEMPORARY GRASSING SHALL BE WINTER RYE. THE LANDSCAPE CONTRACTOR SHALL THEN BE RESPONSIBLE FOR SEEING ALL TURF AREAS CALLED OUT ON THE PLAN DURING THE NEXT APPROPRIATE PLANTING
SEASON.
29. PREFERABLE SEEDING SCHEDULE IS BETWEEN OCTOBER 15 - MARCH 15.
30. IF THE CONTRACTOR ASCERTAINS AT ANY TIME THAT REQUIREMENTS OF THIS CONTRACT CONFLICT WITH, OR ARE IN VIOLATION OF, APPLICABLE LAWS, CODES, REGULATIONS AND ORDINANCES, HE SHALL NOT PROCEED WITH WORK IN QUESTION, EXCEPT AT HIS OWN RISK, UNTIL THE CONTRACTING OFFICER'S REPRESENTATIVE HAS BEEN NOTIFIED IN WRITING AND WRITTEN DETERMINATION IS MADE BY THE CONTRACTING OFFICER'S REPRESENTATIVE. WHERE COMPLETED OR PARTIALLY COMPLETED WORK IS DISCOVERED TO BE IN VIOLATION WITH APPLICABLE LAWS, CODES, REGULATIONS AND ORDINANCES, CONTRACTOR SHALL BE REQUIRED TO REMOVE THAT WORK FROM THE PROJECT AND REPLACE SUCH WORK WITH ALL NEW COMPLYING WORK AT NO ADDITIONAL COST TO THE OWNER.
SITE NOTES:
1. ALL TREE SAVE AND UNDISTURBED AREAS SHALL BE CLEARLY IDENTIFIED BY FLAGGING OR FENCING PRIOR TO THE
START OF CONSTRUCTION ACTIVITY.
2. ALL UNPAVED AREAS WITHIN THE LIMITS OF DISTURBANCE SHALL BE SEEDED PER THE SPECIFICATIONS.
3. A SMOOTH TRANSITION BETWEEN EXISTING AND NEW PAVEMENT SHALL BE PROVIDED. FIELD ADJUSTMENTS MAY BE
NECESSARY.
4. WHERE A DETAIL IS SHOWN FOR ONE CONDITION, IT SHALL APPLY TO ALL LIKE OR SIMILAR CONDITIONS, EVEN
THOUGH NOT SPECIFICALLY MARKED ON THE DRAWINGS.
5. MONUMENTS (WATER, BOUNDARY) SHALL BE SURVEYED PRIOR TO THE START OF CONSTRUCTION TO VERIFY THEIR ACCURACY AND TO ENSURE THE MONUMENTS ARE PROTECTED FROM DAMAGE DURING CONSTRUCTION ACTIVITIES
AND RESET IN THE SAME LOCATION.
6. NO WORK WILL OCCUR OUTSIDE OF THE LIMITS OF DISTURBANCE WITHOUT CONTRACTING OFFICER'S
REPRESENTATIVE APPROVAL.
7. COLOR OF ALL SURFACE COURSE PAVEMENT AT CHCH SHALL BE OF BROWNISH COLORING (BROWN RIVER ROCK
AGGREGATE).
8. THE CONTRACTOR IS RESPONSIBLE FOR CONTACTING THE N.P.S. TO ARRANGE A PRE-CONSTRUCTION CONFERENCE PRIOR TO ANY LAND DISTURBANCE. THE CONTRACTOR SHALL ALSO NOTIFY THE N.P.S. INSPECTOR 48 HOURS PRIOR
TO BEGINNING EACH PHASE OF CONSTRUCTION.
9. A COPY OF THE APPROVED CONSTRUCTION DOCUMENTS AND ALL PERMITS SHALL BE PRESENT ON SITE WHENEVER
LAND DISTURBING ACTIVITIES ARE IN PROGRESS.
10. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING ACCESS FOR EMERGENCY VEHICLES AROUND AND TO ALL
BUILDINGS DURING CONSTRUCTION.
11. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING ACCESS AND PARKING FOR THE PUBLIC DURING
CONSTRUCTION IN AREAS OUTSIDE THE PROJECT LIMITS.
12. THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ALL REQUIRED GOVERNMENTAL INSPECTIONS.
13. UTILITY DISCLAIMER: THE EXISTING UTILITY LINES SHOWN ARE APPROXIMATE LOCATIONS. THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING UTILITY LOCATIONS. PRIOR TO ANY CONSTRUCTION. ANY DEVIATION FROM THE DESIGN LOCATIONS SHALL BE REPORTED TO THE CONTRACTING OFFICER'S REPRESENTATIVE PRIOR TO CONSTRUCTION.
DAMAGE TO EXISTING UTILITY LINES RESULTING FROM THE CONTRACTOR'S NEGLIGENCE SHALL BE REPAIRED AT THE
CONTRACTORS EXPENSE.
GRADING AND DRAINAGE NOTES:
1. THE CONTRACTOR IS RESPONSIBLE FOR THE MAINTENANCE OF ALL SOIL EROSION AND SEDIMENTATION CONTROL
MEASURES AND BEST MANAGEMENT PRACTICES.
2. CUT AND FILL SLOPES SHALL BE NO STEEPER THAN 3H:1V UNLESS OTHERWISE NOTED ON THE PLANS.
3. CONTRACTOR TO FIELD VERIFY ALL EXISTING GRADES AND DIMENSIONS IN THE FIELD PRIOR TO BEGINNING ANY
WORK. NOTIFY CONTRACTING OFFICER'S REPRESENTATIVE OF ANY DISCREPANCIES.
4. POSITIVE DRAINAGE SHALL BE MAINTAINED AT ALL TIMES DURING AND AFTER CONSTRUCTION. SOIL SOFTENED BY PERCHED WATER IN FOUNDATION AND PAVEMENT AREAS MUST BE UNDERCUT AND REPLACED WITH SUITABLE FILL MATERIALS APPROVED BY THE CONTRACTING OFFICER'S REPRESENTATIVE.GROUNDWATER INFILTRATION INTO EXCAVATIONS SHOULD BE EXPECTED, AND THE WATER SHALL BE REMOVED USING GRAVITY DRAINAGE OR PUMPING.
5. PROPOSED SPOT ELEVATIONS REPRESENT FINISHED PAVEMENT, CURB OR GROUND SURFACE GRADE UNLESS
OTHERWISE NOTED ON DRAWINGS.
6. GRADE TO DRAIN POSITIVELY INTO STORM DRAINS.
7. INSTALL EROSION CONTROL MEASURES PRIOR TO START OF CONSTRUCTION
8. EXISTING TREES SHALL BE PROTECTED FROM CONSTRUCTION ACTIVITIES. CARE SHALL BE TAKEN IN ALL GRADING
ACTIVITIES TO REMAIN OUTSIDE THE DRIP LINES OF EXISTING TREES.
9. GRADES NOT OTHERWISE INDICATED ON THE PLANS SHALL BE UNIFORM LEVELS OR SLOPES BETWEEN POINTS WHERE ELEVATIONS ARE GIVEN. ABRUPT CHANGES IN SLOPE SHALL BE WELL ROUNDED. SITE SHALL BE GRADED TO
ASSURE DRAINAGE OF SURFACE WATER AWAY FROM ANY BUILDING PADS.
10. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING ALL SURFACE AND GROUNDWATER CONTROL MEASURES.
CIVIL NOTES:
1. THE CONTRACTOR SHALL FURNISH ALL MATERIALS, LABOR, EQUIPMENT, TRANSPORTATION AND SERVICES NECESSARY FOR THE SATISFACTORY COMPLETION OF WORK. ALL EQUIPMENT, WORK AND MATERIALS SHALL COMPLY WITH CURRENT, LOCAL AND FEDERAL APPLICABLE CODES AND GOVERNING REGULATIONS.
2. ALL WORK AND ALL MATERIAL FURNISHED SHALL BE IN REASONABLE CONFORMITY WITH TYPICAL SECTIONS, DIMENSIONS, MATERIAL REQUIREMENTS AND TESTING REQUIREMENTS THAT ARE SPECIFIED IN THE CONTRACT, PLANS OR SPECIFICATIONS.
3. ALL EXISTING MATERIALS TO BE REMOVED WITHIN THE LIMITS OF CONSTRUCTION SHALL BE TRANSPORTED TO A LEGAL DISPOSAL LOCATION. STOCK PILING WILL NOT BE ALLOWED WITHIN THE PROJECT LIMITS WITHOUT PRIOR
APPROVAL FROM NPS.
4. THE CONTRACTOR SHALL CONFORM TO APPLICABLE REGULATORY PROCEDURES AND NOTIFY THE OWNER WHEN
DISCOVERING HAZARDOUS OR CONTAMINATED MATERIALS.
5. THE CONTRACTOR SHALL SUBMIT AND RECEIVE APPROVAL OF THEIR EROSION CONTROL PLAN PRIOR TO THE
PRE-CONSTRUCTION MEETING.
6. CONTRACTOR SHALL TRANSITION MILL AT PAVEMENT LIMITS AND AS REQUIRED BY THE CO TO PROVIDE SMOOTH TRANSITION TO ADJACENT PAVEMENTS. ALL TRANSITION MILLING IS INCIDENTAL TO PAVING ITEMS.
7. EXISTING RPMs AT KIMO-0010 SHALL BE REMOVED AND DISCARDED PRIOR RO MILLING, UNLESS OTHERWISE INSTRUCTED BY THE COR. FINAL LIMITS OF PROPOSED RPMs TO BE INSTALLED ARE AS NOTED ON PLANS.
SAFETY AND SECURITY NOTES:
1. PRIOR TO COMMENCING WORK THE CONTRACTOR SHALL FURNISH, ERECT AND MAINTAIN ALL BARRICADES, WARNING SIGNS AND MARKING FOR HAZARDS AND THE CONTROL OF TRAFFIC IN REASONABLE CONFORMITY WITH THE MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES FOR STREET AND HIGHWAYS OR AS REQUIRED BY NPS, SUCH AS TO EFFECTIVELY PREVENT ACCIDENTS IN ALL PLACES WHERE THE WORK CAUSES OBSTRUCTIONS TO THE NORMAL
TRAFFIC OR CONSTITUTES IN ANY WAY A HAZARD TO THE PUBLIC.
2. THE CONTRACTOR SHALL CONTROL HIS OPERATIONS AND THOSE OF HIS SUBCONTRACTORS AND ALL SUPPLIERS TO ASSURE THE LEAST INCONVENIENCE TO THE SITE USERS. THE CONTRACTOR SHALL MAINTAIN FREE AND UNOBSTRUCTED MOVEMENT OF VEHICULAR TRAFFIC AND SHALL LIMIT HIS OPERATIONS FOR THE SAFETY AND
CONVENIENCE OF THE PUBLIC.
3. THE CONTRACTOR SHALL COORDINATE AND BE RESPONSIBLE FOR ALL SAFETY SIGNING, CONES AND DRUMS NECESSARY TO PROVIDE A SMOOTH AND PROPER TRANSITION FOR PEDETRIAN ACCESS AND TRAFFIC FLOW.
GENERAL NOTES
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
00- C003
EROSION CONTROL NOTES:
1. ALL EROSION CONTROL MEASURES SHALL COMPLY WITH THE SOUTH CAROLINA SOIL AND WATER CONSERVATION
COMMISSION'S MANUAL FOR EROSION AND SEDIMENT CONTROL IN SOUTH CAROLINA.
2. CONTRACTOR TO COORDINATE WITH CONTRACTING OFFICER TO ENSURE ALL APPLICABLE CONSTRUCTION AND LAND
DISTURBANCE PERMITS HAVE BEEN OBTAINED PRIOR TO COMMENCING ANY WORK.
3. EROSION CONTROL MEASURES MUST IN PLACE AND OPERATIONAL PRIOR TO ANY LAND DISTURBING ACTIVITIES, AND MUST REMAIN IN PLACE AND MAINTAINED THROUGHOUT THE DURATION OF CONSTRUCTION UNTIL FINAL
STABILIZATION IS ACHIEVED.
4. TEMPORARY CONSTRUCTION ACCESS POINTS MUST BE PROVIDED WHERE CONSTRUCTION VEHICLES EXIT THE
CONSTRUCTION AREA. PUBLIC ROADWAYS MUST BE FREE OF DIRT AND MUD.
5. ANY DISTURBED AREA LEFT EXPOSED FOR 14 OR MORE DAYS SHALL BE STABILIZED WITH MULCH OR TEMPORARY
SEEDING.
6. THE CONTRACTOR SHALL CONTACT THE CONTRACTING OFFICER'S REPRESENTATIVE IF QUESTIONS ARISE CONCERNING TIMING, DESIGN AND/OR EFFECTIVENESS OF THE EROSION CONTROL MEASURES SHOWN ON THE
PLANS.
7. THE CONTRACTOR SHALL TAKE IMMEDIATE ACTION UPON THE DISCOVERY OF ANY DEFICIENCY IN THE EROSIONAL
CONTROL MEASURES.
8. SILT FENCE MUST BE CLEANED OR RECONSTRUCTED ONCE SEDIMENT VOLUMES EXCEED 1/2 OF THE SILT FENCE
HEIGHT OR AS DIRECTED BY THE CONTRACTING OFFICER'S REPRESENTATIVE.
9. SILT FENCE MUST MEET THE REQUIREMENTS OF SECTION 171 - TEMPORARY SILT FENCE OF THE DEPARTMENT OF TRANSPORTATION, STATE OF SOUTH CAROLINA, STANDARD SPECIFICATIONS, LATEST EDITION.
10. SEDIMENT REMOVED FROM SEDIMENT CONTROL STRUCTURES TO BE PLACED AT A LOCATION APPROVED BY THE CONTRACTING OFFICER'S REPRESENTATIVE. THE AREA AROUND THE SEDIMENT DISPOSAL SITE SHALL BE TREATED
AS TO NOT BE CONTAMINATED OR DAMAGED BY THE SEDIMENT RUNOFF.
11. REAPPLICATION OF THE VEGETATIVE MEASURES MAY BE REQUIRED TO MAINTAIN STABILIZATION.
12. THE CONTRACTOR SHALL MAINTAIN A DAILY RAIN GAUGE AND DAILY RAINFALL RECORDS AT THE SITE OR USE A
REFERENCE SITE FOR A RECORD OF THE DAILY PRECIPITATION DURING CONSTRUCTION.
13. CONSTRUCTION SHALL BE SEQUENCED TO MINIMIZE EXPOSURE TIME OF DISTURBED AREAS.
14. THE CONSTRUCTION EXITS SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOW OF MUD ONTO PUBLIC RIGHT-OF-WAY. THIS MAY REQUIRE PERIODIC TOP DRESSING WITH STONE, AS CONDITIONS DEMANDS, AND REPAIR AND/OR CLEAN-OUT OF ANY STRUCTURES USED TO TRAP SEDIMENT. ALL MATERIALS SPILLED, DROPPED, WASHED, OR TRACKED FROM VEHICLES OFF SITE ONTO PUBLIC ROADWAY OR INTO STORM DRAIN MUST BE REMOVED
IMMEDIATELY.
15. PRIOR TO COMMENCING LAND DISTURBANCE ACTIVITY THE UMITS OF LAND DISTURBANCE SHALL BE CLEARED AND ACCURATELY DEMARCATED WITH STAKES, RIBBONS, OR OTHER APPROPRIATE MEANS. THE LOCATION AND EXTENT OF ALL AUTHORIZED LAND DISTURBANCE SHALL OCCUR INSIDE THE LIMITS INDICATED ON THE APPROVED PLANS.
16. IMMEDIATELY AFTER THE ESTABLISHMENT OF CONSTRUCTION ENTRANCES/EXITS, ALL PERIMETER EROSION CONTROL DEVICES AND STORM WATER MANAGEMENT DEVICES SHALL BE INSTALLED PRIOR TO ANY CONSTRUCTION.
17. THE CONTRACTOR SHALL FURNISH AND MAINTAIN ALL NECESSARY BARRICADES WHILE ROADWAY FRONTAGE
IMPROVEMENTS ARE BEING MADE.
18. THE CONSTRUCTION OF THE SITE WILL INITIATE WITH THE INSTALLATION OF EROSION CONTROL MEASURES SUFFICIENT TO CONTROL SEDIMENT DEPOSITS AND EROSION. ALL SEDIMENT CONTROL WILL BE MAINTAINED UNTIL ALL UPSTREAM GROUND WITHIN THE CONSTRUCTION AREA HAS BEEN COMPLETELY STABILIZED WITH PERMANENT
VEGETATION AND ALL ROADS/DRIVEWAYS HAVE BEEN PAVED
19. CONTRACTOR IS RESPONSIBLE FOR MONITORING DOWNSTREAM CONDITIONS THROUGHOUT THE CONSTRUCTION
PERIOD AND CLEARING ANY DEBRIS AND SEDIMENT CAUSED BY CONSTRUCTION.
20. EROSION CONTROL DEVICES SHALL BE INSTALLED IMMEDIATELY AFTER GROUND DISTURBANCE THE LOCATION OF SOME OF THE EROSION CONTROL DEVICES MAY HAVE TO BE ALTERED FROM THAT SHOWN ON THE APPROVED PLANS IF DRAINAGE PATTERNS DURING CONSTRUCTION ARE DIFFERENT FROM THE FINAL PROPOSED DRAINAGE PATTERNS.
IT IS THE CONTRACTOR'S RESPONSIBILITY TO ACCOMPLISH EROSION CONTROL FOR ALL DRAINAGE PATTERNS CREATED AT VARIOUS STAGES DURING CONSTRUCTION. ANY DIFFICULTY IN CONTROLLING EROSION DURING ANY PHASE OF CONSTRUCTION SHALL BE REPORTED TO THE CONTRACTING OFFICER'S REPRESENTATIVE IMMEDIATELY.
21. ALL SILT BARRIERS MUST BE PLACED AS ACCESS IS OBTAINED DURING CLEARING. NO GRADING SHALL BE DONE UNTIL
THE SILT BARRIERS ARE CONSTRUCTED.
22. CONTRACTOR SHALL MAINTAIN ALL EROSION CONTROL MEASURES UNTIL PERMANENT VEGETATION HAS BEEN ESTABLISHED. CONTRACTOR SHALL CLEAN OUT ALL SEDIMENT PONDS WHEN REQUIRED BY CONTRACTING OFFICER'S REPRESENTATIVE OR FULTON COUNTY INSPECTOR. CONTRACTOR SHALL INSPECT EROSION CONTROL MEASURES AT
THE END OF EACH WORKING DAY TO ENDUSE MEASURES ARE FUNCTIONING PROPERLY.
23. SILT BARRIERS TO BE PLACED AT DOWNSTREAM TOE OF ALL CUT AND FILL SLOPES.
24. SEDIMENT / EROSION CONTROL DEVICES MUST BE CHECKED AFTER EACH STORM EVENT. EACH DEVICE IS TO BE MAINTAINED OR REPLACED IF SEDIMENT ACCUMULATION HAD REACHED ONE HALF OF THE CAPACITY OF THE DEVICE.
25. AT THE END OF CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR CLEANING OUT ANY ACCUMULATED
SEDIMENT IN THE STORM SYSTEM ONCE FINAL STABILIZATION AS BEEN ACHIEVED.
26. APPLY PERMANENT SEEDING PER THE EROSION CONTROL PLANS TO ALL DISTURBED AREAS AS SOON AS POSSIBLE
AFTER GRADING IS COMPLETE.
27. SILT FENCE SHALL BE REMOVED ONCE SITE STABILIZATION HAS BEEN ACHIEVED AND ACCEPTED BY THE
CONTRACTING OFFICER'S REPRESENTATIVE.
28. ADDITIONAL EROSION CONTROL MEASURES WILL BE EMPLOYED BEYOND THOSE SHOWN ON THE EROSION CONTROL PLAN. IF NECESSARY ADDITIONAL EROSION CONTROL MEASURES MAY BE REQUIRED WHERE DETERMINED
NECESSARY BY ACTUAL SITE CONDITIONS AND THE NATIONAL PARK SERVICE INSPECTOR.
TREE PROTECTION NOTES:
1. CONTRACTOR TO STAKE THE LIMITS OF CLEARING, GRADING AND WALKWAY LIMITS THAT AFFECT TREE SAVE AREAS
PRIOR TO COMMENCEMENT OF CONSTRUCTION.
2. THE CONTRACTING OFFICER'S REPRESENTATIVE SHALL REVIEW AND APPROVE THE LOCATION OF TREE PROTECTION MEASURES PRIOR TO THE START OF CONSTRUCTION. TREE PROTECTION BARRICADES SHALL BE IN ACCORDANCE WITH THESE PLANS AND SPECIFICATIONS, AND SHALL BE INSTALLED IN LOCATIONS AS DIRECTED BY THE
CONTRACTING OFFICER'S REPRESENTATIVE.
3. ALL GRADING AND EARTHWORK WITHIN PROTECTED ROOT ZONE AREAS SHALL BE DONE BY HAND OR SMALL
EQUIPMENT TO MINIMIZE ROOT DAMAGE.
4. DO NOT OPERATE OR STORE HEAVY EQUIPMENT WITHIN THE DRIP LINES OF TREES TO BE PROTECTED.
UTILITY NOTES:
1. THE LOCATION OF EXISTING UTILITIES AND STORM DRAINAGE SYSTEMS FEATURES SHOWN ON THE PLANS HAVE BEEN DETERMINED FROM NPS SCOPING VISITS AND ARE PROVIDED FOR THE CONVENIENCE OF THE CONTRACTOR. THE ENGINEER ASSUMES NO RESPONSIBILITY FOR THEIR ACCURACY. SHOULD A DISCREPANCY ARISE BETWEEN THESE PLANS AND ACTUAL FIELD CONDITIONS, WHICH WOULD APPRECIABLY AFFECT THE EXECUTION OF THESE PLANS, THE
CONTRACTOR WILL HALT ALL CONSTRUCTION AND NOTIFY NPS IMMEDIATELY.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING AND VERIFYING ALL EXISTING UTILITIES AND FIBER OPTICS PRIOR TO CONSTRUCTION. THE CONTRACTOR SHALL EXERCISE EXTREME CAUTION WHEN CROSSING AN UNDERGROUND UTILITY; WHETHER SHOWN ON THESE PLANS OR FIELD LOCATED. ALL UTILITIES WHICH INTERFERE WITH THE PROPOSED CONSTRUCTION SHALL BE PROTECTED OR RELOCATED BY THE RESPECTIVE UTILITY PROVIDERS AND THE CONTRACTOR SHALL COOPERATE WITH THE UTILITY PROVIDER DURING RELOCATION OPERATIONS. ANY DELAY OR INCONVENIENCE BY THE VARIOUS UTILITIES SHALL BE INCIDENTAL TO THE CONTRACT
AND NO ADDITIONAL COMPENSATION WILL BE ALLOWED.
3. CONTRACTOR SHALL MAINTAIN ALL EXISTING UTILITIES IN GOOD WORKING ORDER AND SHALL PROTECT THEM FROM
DAMAGE UNTIL THE WORK IS COMPLETED AND ACCEPTED.
4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPLACEMENT OF ALL UTILITY STRUCTURES THAT ARE
DAMAGED OR DISTURBED AS A RESULT OF ITS OPERATIONS.
5. ALL EXISTING UTILITY STRUCTURES TO REMAIN SHALL BE ADJUSTED TO FINAL GRADE UNLESS OTHERWISE STATED.
6. CONTRACTOR SHALL FOLLOW LOCAL, STATE AND FEDERAL "CALL BEFORE YOU DIG" LAWS. NOTIFICATION REQUESTS SHALL BE COMPLETED 72 HOURS IN ADVANCE OF ANY EXCAVATION ACTIVITIES. EXCAVATION SHALL NOT PROCEED
UNTIL POSITIVE NOTIFICATIONS HAVE BEEN RECEIVED FROM ALL MEMBER UTILITIES.
7. CONTRACTOR TO PROVIDE POSITIVE DRAINAGE AND MATCH, OR IMPROVE EXISTING DRAINAGE CONDITIONS.
8. WHEN IT IS NECESSARY TO INTERRUPT ANY EXISTING UTILITY SERVICE TO MAKE CORRECTIONS AND/OR CONNECTIONS, A MINIMUM OF 48 HOURS ADVANCE NOTICE SHALL BE GIVEN TO THE OWNER. INTERRUPTIONS IN UTILITY SERVICES SHALL BE OF THE SHORTEST POSSIBLE DURATION FOR THE WORK AT HAND AND SHALL BE
APPROVED IN ADVANCE BY NPS.
9. IN THE EVENT THE UTILITY SERVICE IS INTERRUPTED WITHOUT THE REQUIRED 48 HOURS NOTICE, THEN THE CONTRACTOR SHALL BE FINANCIALLY LIABLE FOR ALL DAMAGES SUFFERED BY THE OWNER DUE TO THE UNAUTHORIZED INTERRUPTION. NPS SHALL BE NOTIFIED IMMEDIATELY. RECONNECTION SHALL BE MADE
IMMEDIATELY.
PAVING NOTES:
1. PAVEMENT SHALL BE OF TYPE, THICKNESS AND CROSS SECTION AS INDICATED ON PLANS.
2. EXISTING PAVEMENTS SHALL BE MILLED WHERE THEY MEET PROPOSED RESURFACING AND SHALL BE SMOOTH AND STRAIGHT. WHERE NEW BITUMINOUS CONCRETE MEETS EXISTING BITUMINOUS CONCRETE SURFACES, MILLED EDGES
ARE TO BE SEALED WITH BITUMEN.
3. ASPHALT EMULSION FOR TACK COAT SHALL BE SPRAY APPLIED FOR DOUBLE OVERLAP COVERAGE AT 0.07 GAL/SY
OVER MICRO MILLED SURFACES, AND 0.05 GAL/SY OVER SMOOTH SURFACES.
4. CONTRACTOR SHALL PERFORM QUALITY CONTROL TESTING FOR CONFORMANCE TO SPECIFICATIONS.
5. CONTRACTOR SHALL MAKE A CONSTRUCTION JOINT AT THE END OF EACH DAY'S CONSTRUCTION BY TRIMMING THE END OF THE COMPACTED MIXTURE TO A STRAIGHT VERTICAL PLANE, NORMAL TO THE CENTERLINE OF THE ROADWAY
AND WITH THE VERTICAL EDGE IN THOROUGHLY COMPACTED MATERIAL.
PAVEMENT MARKING NOTES
1. PAVEMENT SURFACES SHALL BE CLEAN, DRY, AND FREE OF DUST, DEBRIS, OIL, AND CONTAMINANTS PRIOR TO
APPLICATION TO ENSURE PROPER ADHESION.
2. CONTRACTOR SHALL FIELD LAY OUT ALL PAVEMENT MARKINGS IN ACCORDANCE WITH THE PLANS AND MUTCD.
ROADWAY STRIPING SHALL BE STRAIGHT, UNIFORM, AND PROPERLY ALIGNED WITH THE ROADWAY GEOMETRY.
EQUIPMENT SHALL BE PROPERLY CALIBRATED AND OPERATED TO PREVENT WAVINESS, MISALIGNMENT, OR
IRREGULAR WIDTH. FINAL STRIPING LAYOUT SHALL BE REVIEWED AND APPROVED BY THE CO PRIOR TO
INSTALLATION.
3. A MINIMUM 500 LF CONTROL STRIP (OR REPRESENTATIVE PARKING LAYOUT SEGMENT) SHALL BE INSTALLED FOR CO
APPROVAL PRIOR TO FULL PRODUCTION STRIPING.
4. STRIPING EQUIPMENT SHALL BE MAINTAINED IN PROPER WORKING CONDITION. SPRAY NOZZLES SHALL BE CLEAN
AND FUNCTIONING TO ENSURE UNIFORM WIDTH, THICKNESS, AND EDGE DEFINITION.
5. TYPE H - THERMOPLASTIC PAVEMENT MARKINGS SHALL BE USED FOR STOP BARS AND PEDESTRIAN CROSSWALKS.
TYPE B - WATERBORNE TRAFFIC PAINT SHALL BE USED FOR ALL OTHER STRIPING UNLESS OTHERWISE NOTED.
6. 6 THERMOPLASTIC SHALL BE APPLIED IN A SINGLE UNIFORM LAYER AT SPECIFIED THICKNESS. OVERLAPPING PASSES, EXCESSIVE BUILDUP, OR RAISED EDGES THAT CREATE SURFACE IRREGULARITIES WILL NOT BE PERMITTED.
7. ALL PAVEMENT MARKINGS SHALL BE FREE OF MISALIGNMENT, IRREGULAR WIDTH, STREAKING, OVERSPRAY, BUILDUP RIDGES, OR OTHER DEFECTS. NONCONFORMING MARKINGS SHALL BE REMOVED AND REPLACED AT NO ADDITIONAL
COST TO THE OWNER.
DEMOLITION NOTES:
1. THE CONTRACTOR IS RESPONSIBLE FOR CONTACTING THE N.P.S. TO ARRANGE FOR A PRE-CONSTRUCTION
CONFERENCE PRIOR TO ANY LAND DISTURBING ACTIVITIES.
STAGING NOTES:
1. THE PHASING PLANS SHOWN IN THIS PLAN SET ARE PRELIMINARY AND PROVIDED FOR CONCEPTUAL GUIDANCE ONLY.
THE CONTRACTOR SHALL DEVELOP A DETAILED CONSTRUCTION SCHEDULE AND PHASING PLAN BASED ON THEIR MEANS AND METHODS AND SUBMIT IT TO THE CO FOR REVIEW AND APPROVAL PRIOR TO COMMENCING WORK. THE CONTRACTOR'S PROPOSED PHASING MAY DIFFER FROM THE CONCEPTUAL PHASING SHOWN, PROVIDED PROJECT
REQUIREMENTS FOR ACCESS, SAFETY, AND OPERATIONS ARE MAINTAINED.
2. CONTRACTOR SHALL MAINTAIN ADA COMPLIANT PEDESTRIAN ACCESS TO ALL PARK VISITOR CENTERS DURING
CONSTRUCTION
3. ONLY ONE BOAT RAMP PER PARK IS ALLOWED TO BE CLOSED FOR CONSTRUCTION AT ANY GIVEN TIME.
4. CONTRACTOR IS TO MAINTAIN ONE-WAY TRAFFIC AROUND ROAD WORK AREAS. WHEN APPLICABLE, THE CONTRACTOR SHALL PROVIDE FLAGGERS TO ENSURE PROPER FLOW OF TRAFFIC ADJACENT TO WORK AREAS.
5. DURING CONSTRUCTION IN PARKING LOTS, THE CONTRACTOR SHALL MAINTAIN THE MINIMUM NUMBER OF PARKING
SPOTS AS DESIGNATED IN THE SPECIFICATIONS.
6. TEMPORARY PAVEMENT MARKINGS SHALL BE INSTALLED AT THE COMPLETION OF EACH CONSTRUCTION PHASE WHERE FINAL STRIPING IS NOT IMMEDIATELY APPLIED. TEMPORARY MARKINGS SHALL MAINTAIN SAFE AND CLEARLY DEFINED PARKING STALLS, TRAFFIC FLOW, AND PEDESTRIAN CROSSINGS UNTIL FINAL STRIPING IS COMPLETED.
GENERAL NOTES
Abutment Abut. Length of Spiral Ls Aggregate aggr. Longitudinal long.
Ahead AH Low Water LW Alternate alt. Mainline M.L.
Average Daily Traffic ADT Material matl.
Back BK Maximum max.
Backslope Anchor Terminal BAT Mile [Kilometer] post M.P. [K.P.]
Balance Point BP Minimum min.
Bearing brg. Monument mon. or MON
Beginning beg. Mechanically Stabilized Embankment MSE Bench Mark BM Nominal Max. Aggregate Size NMAS
Broken White BW Normal Crown NC or NCR Centerline ℄ North N
Center to Center cc, c-c or c. to c. Original Ground OG Centers ctrs. Out to Out o. to o.
Clear clr. Outside Diameter OD
Column col. On Centers o.c.
Connection conn. Pavement pvmt.
Construction Joint Constr. jt. Plate pl.
Continuous cont. Point of Compound Curve PCC Corrugated Metal Pipe CMP Point of Curve PC
Culvert culv. Point of Curve to Spiral PCS or CS Curve Central Angle (Spiral Curve Transitions) Δc Point of Intersection PI Curve Total Angle (Curve Delta or Deflection) Δ Point of Spiral to Curve PSC or SC
Design Hourly Volume DHV Point of Spiral to Tangent SRS Design Speed V Point of Tangent PT
Diagonal diag. Point of Tangent to Spiral PS or TS Diameter D, dia. Point on Curve POC
Diaphragm diaph. Point on Spiral POS Double Solid Yellow Line DSY Point on Tangent POT
Drawing(s) dwg(s), or drwg(s) Radius R Drop Inlet DI Reinforcement (Reinforced) reinf.
East E Required reqd.
Edge of Pavement EP or EOP Right Rt., rt. or RT
Elevation elev. Right-of-way R/W
Elevation with Number El. 94.161 Roadway Rdwy.
[El. 94.16] Route Rte.
Embankment emb. Section Sec.
End Section ES Solid White SW
Equation EQ or eq. South S Equivalent Single Axle Load ESAL Spacing, spaces, or spaced spa.
Excavation exc. Spiral Center Angle s Expansion Joint exp. jt. Standard std.
Flared Anchor Terminal FAT Station Sta.
Footing ftg. Steel Backed Timber SBT
Galvanized galv. Stiffener stiff.
Gage (Gauge) ga. Stringer stgr.
Gyratory Mix, Asphalt GACP Structure struc.
Concrete Pavement PCC Superelevation rate e
Headwall hdwl. Symmetrical sym.
Hexagon hex. Tangent Distance (tangent length) T
High Water HW Temporary Benchmark TBM Inside Diameter ID Temporary Construction Easement TCE
Joint jt. Thread thd.
Lamination lam. Township T.
Latitude lat. Typical typ.
Left lt., Lt. or LT Vehicle per Hour vph Length of Curve (simple curve) L Vertical point of Intersection VPI
Length of Curve (spiral curve transition) Lc West W
RIGHT-OF-WAY LINE
RIGHT-OF-WAY LINE
with MONUMENT
16 SECTION
SECTION CORNER
4 SECTION CORNER
PROPERTY CORNER
PARCEL NUMBER
EASEMENT (PERMANENT - CONSTRUCTION)
ROUTE NUMBERS
SLOPE STAKE
ROADWAY, EXISTING
RAILROAD
TRAIL
INTERMITTENT DRAINAGE/SMALL CREEK
SPRING
LARGE CREEK/RIVER
LAKE, POND or RESERVOIR; MARSHLAND
EXISTING PROPOSED
SILT FENCE
DIVERSION BERM
DIVERSION CHANNEL
CHECK DAM
RIPRAP/CULVERT RIPRAP
BORING LOCATION
TEST PIT
NORTH ARROW
MATERIAL SOURCE
NO SYMBOL
NO SYMBOL
FOUND PROJECTED
INTERSTATE U.S. STATE
B-1
TP-1
NATIONAL BOUNDARY
STATE BOUNDARY
COUNTY BOUNDARY
CITY BOUNDARY
TOWNSHIP or RANGE LINE
SECTION LINE
4 SECTION LINE
16 SECTION LINE
NATIONAL PARK or FOREST BOUNDARY
PROPERTY LINE
TRAVERSE POINT (HORIZ. & VERT.)
TOP OF TRIANGLE POINTS NORTH
TRAVERSE POINT (HORIZ.)
BRASS CAP
STEEL PIN
HUB & TACK
SPOT ELEVATION
COORDINATE GRID TICK
EXISTING PROPOSED
GATE WITH FENCE
CATTLEGUARD
GUARDRAIL
MEDIAN & SIDE (CONCRETE BARRIER)
SIGNS
RETAINING WALL
OVERHEAD (POWER POLE) UTILITIES
P=ELECTRICAL FOR TRANSMISSION LINE
E= ELECTRICAL FOR DISTRIBUTION LINE
T=TELEPHONE, E&T=JOINT ELECTRICAL & TELEPHONE
FO=FIBER OPTICS
SUPPORT POLE with ANCHOR
TELEPHONE BOOTH or PEDESTAL
STREET LIGHT
UNDERGROUND UTILITIES
G=GAS, O=OIL, P-POWER, SS=SANITARY SEWER,
SD=STORM DRAIN, T=TELEPHONE, W=WATER,
E=ELECTRICAL, FO=FIBEROPTICS
BRIDGE
PIPE CULVERT (ARROW SHOWS FLOW)
PIPE CULVERT with END SECTION PIPE CULVERT with HEADWALL
CULVERT with DROP INLET
BOX CULVERT
UNDERDRAIN
BUILDING
TREELINE; TREE
POST MOUNTED
PORTABLE
PROJECT SPECIFIC SYMBOLS AND ABBREVIATIONS :
LEGEND
SIGN
MONUMENT
FENCE
CURB
STONE CURB
WOODEN CURB
LEGEND
CURB & GUTTER
HISTORICAL
STONE SWALE
CULVERT
UTILITY
PAVED APRON
UNPAVED APRON
LEGEND
TRAFFIC LOOP
GATE
PATCH
AGGREGATE
SEED
PEDESTRIAN
X-ING
PAGE #
DETAIL #
C1
S1
F1
P1
A1
Sw1
T1
Cs1
Cw1
C/G1
Cvt1
U1
Ap1
Au1
G1M1
X1
ITEM ABBREVIATION
NORTH BOUND NB
SOUTH BOUND SB
EAST BOUND EB
WEST BOUND WB
STATION STA
ITEM ABBREVIATION
EXISTING EX
PROPOSED PROP
ROAD RD
PARKWAY PKWY
DRIVE DR
ITEM ABBREVIATION
HIGHWAY HWY
REMOVE & REPLACE R&R
DETACH & RESET D&R
REMOVE & DISCARD R&D
REMOVE & STOCKPILE R&S
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
NOTES:
1. ITEMS IN BLUE ARE
PROPOSED 00-
C004 5
SYMBOLS & ABBREVIATIONS
EXISTING ASPHALT CONCRETE PAVEMENT
VARIESVARIES
DOUBLE APPLICATION HOT APPLIED ASPHALT SEAL COAT
VARIES
MATCH
EXISTING
MATCH
EXISTING
EXISTING ASPHALT CONCRETE PAVEMENT
VARIESVARIES
VARIES
MATCH
EXISTING
MATCH
EXISTING
PAVEMENT PRESERVATION TREATMENT,
SEAL COAT
PAVEMENT PRESERVATION TREATMENT,
CRACK SEAL & SEAL COAT
SEE NOTE 2
DOUBLE APPLICATION HOT APPLIED ASPHALT SEAL COAT
LIMIT OF CONSTRUCTION
LIMIT OF CONSTRUCTION
EX CURB (WHERE PRESENT)
(SEE NOTE 4)
EX CURB (WHERE PRESENT)
(SEE NOTE 4)
1. REFER TO THE PAVEMENT SUMMARY SHEETS FOR AREA
AND EXTENT OF ASPHALT PAVEMENT PRESERVATION
TREATMENT, LIMIT WORK TO THE FOOTPRINT OF THE
EXISTING PAVEMENT.
2. PERFORM CRACK SEALING, FILLING AND SEALING
ACCORDING TO SHEET 12 AT LOCATIONS APPROVED BY
THE COR.
3. PROTECT ROADSIDE ELEMENTS SUCH AS CURB AND
GUTTER, CONCRETE BARRIERS, CONCRETE ISLANDS, AND
MANHOLES FROM ASPHALT OVERSPRAY DURING ALL
ASPHALT PRESERVATION TREATMENT.
4. CURB SHOWN ON ONE SIDE FOR ILLUSTRATION
PURPOSES ONLY. PRESENCE AND LOCATION OF CURBS
WILL VARY BY SITE.
5. REMOVE WHEELSTOPS LOCATED WITHIN THE AREA TO BE
TREATED TO ENSURE THAT ASPHALT PAVEMENT
PRESERVATION TREATMENT IS APPLIED TO THE ENTIRE
PARKING AREA. RESET WHEELSTOPS AFTER PAVING IS
COMPLETED.
6. REMOVE THERMOPLASTIC MARKINGS PRIOR TO PLACING
ASPHALT PAVEMENT PRESERVATION TREATMENT.
7. SUPERPAVE MIXES SHALL UTILIZE PG64-22 LIQUID
ASPHALT GRADING PER SPECIFICATION 32 12 16 UNLESS
OTHERWISE NOTED.
8. SUPERPAVE MIXES SHALL BE TRAFFIC LEVEL B UNLESS
OTHERWISE NOTED.
Notes:
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
00- C301 6
TYPICAL SECTIONS
EXISTING ASPHALT CONCRETE PAVEMENT (AFTER ASPHALT MILLING)
VARIESVARIES
TACK COAT
SUPERPAVE SURFACE COURSE, 2.0" LIFT (SEE NOTE 2)℄
MATCH
EXISTING
MATCH
EXISTING
EXISTING ASPHALT CONCRETE PAVEMENT (AFTER ASPHALT MILLING)
VARIESVARIES
MATCH
EXISTING
MATCH
EXISTING
SUPERPAVE SURFACE COURSE, 2.0" LIFT (SEE NOTE 2)
VARIESVARIES
MATCH
EXISTING
MATCH
EXISTING
PAVEMENT PRESERVATION TREATMENT,
2" ASPHALT MILL & OVERLAY
PAVEMENT PRESERVATION TREATMENT,
4" ASPHALT MILL & OVERLAY (2 LIFTS)
PAVEMENT PRESERVATION TREATMENT,
ASPHALT RECONSTRUCTION
DETAILS NOT TO SCALE
TACK COAT
12.5MM SUPERPAVE BASE COURSE, 2.0" LIFT
SUPERPAVE SURFACE COURSE, 2.0" LIFT (SEE NOTE 2)
TACK COAT
19.0MM SUPERPAVE BASE COURSE, 3.0" LIFT
CRUSHED AGGREGATE BASE COURSE, 6.0" LIFT, COMPACT IN PLACE
EXISTING ASPHALT CONCRETE PAVEMENT
(AFTER ASPHALT MILLING)
VARIESVARIES
VARIES
MATCH
EXISTING
MATCH
EXISTING
PAVEMENT PRESERVATION TREATMENT,
1.0" ASPHALT MILL & OVERLAY
TACK COAT
9.5MM SUPERPAVE SURFACE COURSE, 1.0" LIFT
VARIES
LIMIT OF CONSTRUCTION
LIMIT OF CONSTRUCTION
LIMIT OF CONSTRUCTION
LIMIT OF CONSTRUCTION
VARIES VARIES
VARIES VARIES
EX CURB (WHERE PRESENT)
(SEE NOTE 4)
EX CURB (WHERE PRESENT)
(SEE NOTE 4)
EX CURB (WHERE PRESENT)
(SEE NOTE 4)
EX CURB (WHERE PRESENT)
(SEE NOTE 4)
VARIES VARIES
1. REFER TO THE PAVEMENT SUMMARY SHEETS FOR AREA
AND EXTENT OF ASPHALT PAVEMENT PRESERVATION
TREATMENT, LIMIT WORK TO THE FOOTPRINT OF THE
EXISTING PAVEMENT.
2. AGGREGATE SIZE FOR 2.0" SUPERPAVE SURFACE COURSE
IS DEPENDENT ON THE USAGE. ALL ROADWAYS SHALL
USE A 12.5MM NMAS WHILE ALL PARKING LOTS SHALL USE
A 9.5MM NMAS.
3. PROTECT ROADSIDE ELEMENTS SUCH AS CURB AND
GUTTER, CONCRETE BARRIERS, CONCRETE ISLANDS, AND
MANHOLES FROM ASPHALT OVERSPRAY DURING ALL
ASPHALT PRESERVATION TREATMENT.
4. CURB SHOWN ON ONE SIDE FOR ILLUSTRATION
PURPOSES ONLY. PRESENCE AND LOCATION OF CURBS
WILL VARY BY SITE.
5. REMOVE WHEELSTOPS LOCATED WITHIN THE AREA TO BE
TREATED TO ENSURE THAT ASPHALT PAVEMENT
PRESERVATION TREATMENT IS APPLIED TO THE ENTIRE
PARKING AREA. RESET WHEELSTOPS AFTER PAVING IS
COMPLETED.
6. REMOVE THERMOPLASTIC MARKINGS PRIOR TO PLACING
ASPHALT PAVEMENT PRESERVATION TREATMENT.
7. SUPERPAVE MIXES SHALL UTILIZE PG64-22 LIQUID
ASPHALT GRADING PER SPECIFICATION 32 12 16 UNLESS
OTHERWISE NOTED.
8. SUPERPAVE MIXES SHALL BE TRAFFIC LEVEL B UNLESS
OTHERWISE NOTED.
Notes:
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
00- C302 7
TYPICAL SECTIONS
EXISTING ASPHALT CONCRETE PAVEMENT
PAVEMENT PRESERVATION TREATMENT (SEE SHEETS 00-C301 & 00-C302)℄
ROADWAY OR PARKING AREA WITH CURB
MATCH
EXISTING
MATCH
EXISTING
EXISTING AGGREGATE BASE
ASPHALT PAVEMENT MILLING
(SEE VIEW A-A)
MAINTAIN THE EXISTING
REVEAL (SEE NOTE 4)
EXISTING GROUND
SLOPE VARIES
EXISTING GROUND
SLOPE VARIES
℄ ROAD
PAVEMENT DISTRESS
12.0"12.0"
ASPHALT PATCH PLAN DETAIL
PATCH SAW CUT PARALLEL/PERPENDICULAR
TO DISTRESS
PAVEMENT REPLACEMENT LIMITS
IF THE PATCH LIMIT IS
<24" FROM THE EDGE
OF PAVEMENT, REMOVE
TO EDGE OF PAVEMENT
VA
R
IE
S
3.
0' m in
PAVEMENT PRESERVATION TREATMENT
(SEE SHEETS 00-C303 & 00-C304)
TACK COAT
MILL EXISTING ASPHALT CONCRETE PAVEMENT
(SEE TAPER MILLING TABLE)
EXISTING CONCRETE
GUTTER OR WALKWAY
EXISTING ASPHALT
CONCRETE PAVEMENT
EXISTING BASE
VIEW A-A
TRANSITION PAVEMENT MILLING, WIDTH VARIES
(SEE TAPER MILLING TABLE)
DETAILS NOT TO SCALE
LIMIT OF CONSTRUCTION
NOTES:
1. REFER TO THE PAVEMENT SUMMARY SHEETS FOR AREA AND
EXTENT OF ASPHALT PAVEMENT PRESERVATION TREATMENT, LIMIT
WORK TO THE FOOTPRINT OF THE EXISTING PAVEMENT.
2. PERFORM CRACK SEALING, FILLING AND SEALING ACCORDING TO
SHEET 12 AT LOCATIONS APPROVED BY THE COR.
3. MATCH EXISTING SIDEWALK, ADA RAMPS AND GUTTER ELEVATIONS
BY MILLING ACCORDING TO VIEW A AND TAPER MILLING TABLE OR
AS DIRECTED BY THE COR. TRANSITION TO EXISTING PAVEMENT
ELEVATIONS ACCORDING TO DETAIL E401-01.
4. THE COR WILL DETERMINE THE PATCHING LIMITS BASED ON
CONDITIONS ENCOUNTERED AT TIME OF CONSTRUCTION.
5. REMOVE WHEELSTOPS LOCATED WITHIN THE AREA TO BE TREATED
TO ENSURE THAT ASPHALT PAVEMENT PRESERVATION TREATMENT
IS APPLIED TO THE ENTIRE PARKING AREA. RESET WHEELSTOPS
AFTER PAVING IS COMPLETED.
6. PAVEMENT MARKINGS SHALL MATCH EXISTING LAYOUTS UNLESS
SHOWN DIFFERENTLY ON PLAN. REMOVE THERMOPLASTIC
MARKINGS AND RAISED PAVEMENT MARKERS (RPMs) PRIOR TO
PLACING ASPHALT PAVEMENT PRESERVATION TREATMENT.
7. ALL PATCH SURFACE COURSES WILL BE CONSTRUCTED
MONOLITHICALLY WITH THE MILL AND OVERLAY, WHERE SUCH
TREATMENT COINCIDE WITH THE PATCHING.
8. AGGREGATE SIZE FOR SUPERPAVE SURFACE COURSE IS
DEPENDENT ON THE USAGE. ALL ROADWAYS SHALL USE A 12.5MM
NMAS WHILE ALL PARKING LOTS SHALL USE A 9.5MM NMAS.
9. FOR PATCH TYPE 1, IF UNSUITABLE SUBGRADE MATERIALS ARE
ENCOUNTERED BELOW THE REQUIRED 11" EXCAVATION DEPTH,
REMOVE UNSUITABLE MATERIAL AND BACKFILL IN ACCORDANCE
WITH SECTION 31 23 10 AS DIRECTED BY THE COR.
MILLING DEPTH
0.0" TO 1.0"
1.1" TO 2.0"
2.1" TO 3.0"
3.1" TO 4.0"
MILLING WIDTH
(FT)*
* SEE NOTES
TAPER MILLING TABLE
ASPHALT PAVEMENT PATCH - TYPE 1
SECTION A-A
VARIES
2.0' min.
PAVEMENT PRESERVATION TREATMENT
(SEE SHEET 00-C301, 00-C302 & NOTE 7)
ASPHALT PAVEMENT PATCH TYPE 1:
2" SUPERPAVE SURFACE COURSE (SEE NOTE 8) OVER
3" 19.0MM SUPERPAVE BASE COURSE
SAWCUT/MILL VERTICAL FACE
FULL DEPTH (TYP.)
TACK COAT (TYP.)
EXISTING PAVEMENT (TYP.)
AGGREGATE BASE COURSE, 6" COMPACTED IN-PLACE
REMOVE EXISTING ASPHALT AND
EXCAVATE TO 11" BELOW FINISHED
GRADE. PREPARE AND COMPACT
EXPOSED SUBGRADE (SEE NOTE 9)
SECTION A-A
VARIES
2.0' min.
PAVEMENT PRESERVATION TREATMENT
(SEE SHEET 00-C301 & 00-C302)
ASPHALT PAVEMENT PATCH TYPE 2:
2" SUPERPAVE SURFACE COURSE (SEE NOTE 8) OVER
3" 19.0MM SUPERPAVE BASE COURSE
SAWCUT/MILL
VERTICAL FACE
FULL DEPTH (TYP.)
TACK COAT (TYP.)
EXISTING PAVEMENT (TYP.)
ASPHALT PAVEMENT PATCH - TYPE 2
REMOVE PAVEMENT TO EXISTING
BASE/SUBBASE. FINE GRADE &
COMPACT
00- C303 8
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. JONES
J. GOULD
E. SWEARINGEN
07/26 88PAVEMENT PRESERVATION
SOUTH CAROLINA PARKS (CONG, COWP, KIMO, NISI)
334929 334920 334915
TYPICAL SECTIONS
GRAVEL AND WIRE MESH
DROP INLET PROTECTION (TYPE B)
CURB INLET PROTECTION,
BLOCK AND GRAVEL (TYPE D)
SECTION B-B
CURB INLET PROTECTION,
WOODEN WEIR (TYPE E)
SECTION C-C
BLOCK AND GRAVEL DROP INLET PROTECTION (TYPE C)
SECTION A-A
SILT FENCE DROP INLET PROTECTION (TYPE A)
3' m ax
2" x 4" wood fame
Geotextile
Frame
Drop inlet with grate
Gather excess at corners
Bury geotextile to a depth of 8" (min.)
below ground line
Accumulated sediment
Sediment laden runoff
Gravel filter
Wire mesh
18" min.
m in
Extend mesh 12" (typ.)
Wire mesh Concrete block
Gravel filter
Filtered water
Filtered water
Accumulated sediment
Sediment laden runoff
Filtered water
Drop inlet with grate
2" x 2" wood frame
Wire mesh
Overflow
12" min.
18"
B
BWire mesh
Curb inlet
Gravel filler
Concrete block
Gravel filler
Curb inlet
Sand bag or alternate weightWire mesh
2'-0"
Overflow
Sediment laden runoff
Accumulated sediment
Filtered water
Curb inlet
Wire mesh
2" x 4" wood stud, used to retain concrete blocks
C
C
Wire mesh
Gravel (extends across entire opening length)
Sandbag (typ.)
2" x 4" spacer (typ.)
2" x 4" weir
Emergency overflow
2" x 4" anchor (typ.)6'
12"
12"
1. Provide temporary inlet protection at all inlets located within areas receiving milling, seal-coat, or paving operations.
2. Select the protection method most appropriate for the inlet configuration and drainage condition.
3. Avoid installation methods that cause excessive ponding or restrict parking-lot access, pedestrian movement, or ADA routes.
4. Inspect and maintain inlet protection daily during paving operations and after each rainfall. Remove accumulated debris or millings and restore drainage as needed.
5. Remove inlet protection promptly after final sweeping and before reopening the lot to traffic.
6. For gravel fillers use 2- by 3-inch diameter coarse aggregate.
7. Use wire mesh with 12 - by 12 -inch openings.
8. Use type A inlet protection in sump locations only.
9. Use type B inlet protection only in sump locations where heavy concentrated flows are not expected.
Do not use where ponding around the structure might cause inconvenience or damage.
Notes:
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. BUJWID
J. GOULD
07/26
PAVEMENT PRESERVATION
SOUTH CAROLINA PARK UNITS
334929 334920 334915
00- C501 9
CONSTRUCTION DETAILS
TEMPORARY INLET PROTECTION
DITCH
GRADE*
CHECK DAM
SPACING(S) **
8"
HIGH
12"
HIGH
2% 33 ft 50 ft
3% 22 ft 33 ft
4% 16 ft 25 ft
5% 13 ft 20 ft
* Do not install check dams on grades below 2% ** Adjust spacing as approved based on site conditions
1. Use fiber rolls to intercept and filter runoff from disturbed shoulder or patch areas until permanent stabilization is achieved.
2. Install along the down-slope limit of aggregate/seed repair areas and up-slope of drop inlets in vegetated areas.
3. For use on paved shoulders, support rolls with gravel bags or equivalent ballast.
4. Maintain in place until vegetation is established; remove upon final stabilization.
5. Install, maintain, and remove in accordance with Specification
01.57.23 - Temporary Storm Water Pollution Prevention.
6. Use fiber rolls with a minimum 8-inch diameter. For drain inlet protection, use fiber rolls with a minimum 12-inch diameter.
7. Prior to installation, clear all obstructions including rocks, clods, and debris greater than 1-inch that may interfere with proper function of the fiber roll.
8. For untrenched installation, blow or hand place mulch or compost on uphill side of the slope along the fiber roll.
9. Place fiber rolls on level grade and parallel to contours. Extend both ends of the fiber roll at least 8 feet upslope at 45 degrees to the main alignment.
10. When more than one fiber roll is needed, overlap ends 12 inches minimum and stake.
11. Remove sediment deposits when accumulation is one-half the height of the exposed fiber roll.
12. Replace biodegradable fiber rolls 6 months after installation and photodegradable fiber rolls after 12 months after installation.
13. When fiber rolls are required on paved surfaces, use gravel bags to support them as shown on the inlet protection detail.
Notes:
SLOPE MAX INTERVAL
1V:4H or Flatter 20 Ft
1V:4H - 1V:2H 15 Ft
1V:2H or Steeper 10 Ft
PLAN VIEWINLET PROTECTION
UNTRENCHED INSTALLATION ENTRENCHED INSTALLATION
ROLL OVERLAP
MAXIMUM ALLOWABLE SLOPE
LENGTH ABOVE FIBER ROLLS
FIBER ROLL CHECK DAM
PLAN VIEW
TRAPEZOIDAL DITCHV-DITCH
Upslope stake Downslope stake
Fiber roll, 8" dia. min.
Downslope stakeUpslope stake, place equidistant between downslope stakes
Wood stake, (typ. see Note 6)
Upslope stake Downslope stake
Fiber roll, 8" dia. min.
Fiber roll, 8" dia. min.
Wood stake (typ) See Note 6
Contour line (typ.)
Undisturbed Area
Disturbed Area
Non-woven filter fabric set under drain inlet.
Gravel bag weights at ends and 36" o.c. (typ) See Note 11
Fiber roll, 12" dia. min.
Wood mulch or compost to 12 height of roll
Fiber roll, 8" dia. min.
Wood stake (typ) See Note 6
Trench into ground 13 the diameter of the log, max.
Fiber roll, 8" dia. min.
Wood stake, (typ. see Note 6)
Wood stake, (typ. see Note 6)
2' max.
FlowFlow
Flow Flow
Fl ow
Flow
Flow
Fl ow
Flow
12" min.
4' max.
8' max.
FIBER ROLL ISOMETRIC VIEW
FIBER ROLL CHECK DAM CROSS SECTIONS
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. BUJWID
J. GOULD
07/26
PAVEMENT PRESERVATION
SOUTH CAROLINA PARK UNITS
334929 334920 334915
00- C502 10
CONSTRUCTION DETAILS
FIBER ROLL
Existing asphalt pavement
Existing base course
Saw cut or Mill (Partial or Full Depth of existing asphalt pavement)
New asphalt pavement
New base course
NEW PAVEMENT TRANSITION DETAIL
AGGREGATE SHOULDER SUPPORT DETAIL
EX PAVEMENT
EX EDGE-SHOULDER DROP OFF
(DEPTH VARIES)
EX SHOULDER
VARIES
VARIES
SURFACE PREPARATION
AGGREGATE SHOULDER SUPPORT
Notes:
1. Furnish aggregate shoulder support as shown on the plans or as directed in the field to eliminate edge drop-off.
2. Remove all vegetation, organic material, loose soil, and unsuitable material within the limits of the shoulder repair.
3. Scarify existing shoulder surface to a minimum depth of 2 inches to provide a roughened, firm foundation prior to placement.
4. Compact scarified subgrade to a firm, stable condition. Soft or yielding areas shall be undercut and replaced with suitable material as directed by the CO.
5. Place aggregate/topsoil blend in maximum 6-inch lifts and compact each lift to a firm condition.
6. Shoulder material shall be installed flush with the edge of pavement.
7. Grade shoulder to provide positive drainage away from pavement and match existing ground at outer edge.
8. For COWP, KIMO, and NISI, aggregate shoulder support shall consist of approved aggregate/seed mixes in accordance with Section 32 91 19.14. No seeding is required for aggregate shoulder support at CONG.
Notes:
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. BUJWID
J. GOULD
07/26
PAVEMENT PRESERVATION
SOUTH CAROLINA PARK UNITS
334929 334920 334915
00- C503 11
CONSTRUCTION DETAILS
PAVEMENT TRANSITIONS &
AGGREGATE SHOULDER SUPPORT
Less than 1" See note 3
1" and greater
CRACK SEALING CRACK FILLING
CRACK SEALING AND FILLING
Ensure all remaining overband is flush with the existing surface
Fill crack with hot applied crack filler or hot mix asphalt concrete flush with existing surface
Strike off material 14 inches below existing surface
Seal crack with hot applied crack sealant
1. Apply treatment according to Section 32 01 17.61. Follow manufacturer's recommendations for sealing and filling cracks.
2. Force crack repair material into cracks to ensure adhesion to existing surface.
3. Squeegee excess crack sealing and filling material left above surface. Do no overband cracks.
4. Where routing is not performed or where edge spalling is present, Contractor may place a feathered overband not to exceed 1.5 - 2 in total width and 18 in thickness, tapered to zero at the edges.
Notes:
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. BUJWID
J. GOULD
07/26
PAVEMENT PRESERVATION
SOUTH CAROLINA PARK UNITS
334929 334920 334915
00- C504 12
CONSTRUCTION DETAILS
ASPHALT PAVEMENT CRACK SEALING
AND FILLING
ANGULAR PARKING
HEAD-ON PARKING
WHEELSTOP LAYOUTSECTION C-C
PLAN VIEW
C
CFormed hole for pin (typ.)1' (typ.)
1 2"
6'-7" 90°
Stall lines
Edge of pavement
Edge of pavement
Stall lines
Varies 6" (min.)*
6' - 7'
2'
* Wheelstop
W heelstop6' - 7'
7 12"
1 4"
Pavement surface
1" R
#4 Reinforcing steel (typ.)
See Note 3
1" Grout
2" elastomeric joint sealant
1 18" R 4"
2" 7 8"
1 14"1 2" R
1 4"
1 2"
1 14"
1 4" 1
3 4"
1. Center wheelstops between and perpendicular to stall lines.
2. Variations in wheelstops will be allowed to meet manufacturer's standards as approved.
3. Extend the reinforcing steel to within 1 inch of ends of wheelstop.
Notes:
SUB SHEET NO.
SHEET
OF
PKG.
NO.
334914
TITLE OF SHEETDESIGNED:
CADD:
TECH REVIEW:
DATE:
DRAWING NO.
197,917
N. FARUK
N. BUJWID
J. GOULD
07/26
PAVEMENT PRESERVATION
SOUTH CAROLINA PARK UNITS
334929 334920 334915
00- C505 13
CONSTRUCTION DETAILS
CONCRETE WHEELSTOP
AA
6"
4" Ø X 18" REBAR ANCHOR,
DRIVEN INTO ASPHALT
4" X 6" (NOMINAL) PRESSURE-TREATED
TIMBER (NATURAL/CLEAR FINISH)
67.5°
VARIES
VARIES
VARIES METERED JOINTS,
FLUSH-MOUNTED (TYP.)
PLAN VIEW
WOODEN CURB
SECTION A-A
OPTION 1
ASPHALT PAVEMENT
TREE ISLAND
PAVEMENT-SIDE EDGE OF THE TIMBER
TO BE ROUNDED / CHAMFERED
(MIN. 1" RADIUS)
4" Ø X 18" REBAR ANCHOR,
3' MAX O.C., MIN TWO PER TIMBER
4" X 6" (NOMINAL) PRESSURE-TREATED
TIMBER (NATURAL/CLEAR FINISH)
67.5°
SECTION A-A
OPTION 2
4" COMPACTED GRAVEL BASE
TREE ISLAND
PAVEMENT-SIDE EDGE OF THE TIMBER TO BE
ROUNDED / CHAMFERED (MIN. 1" RADIUS)
4" Ø X 18" REBAR ANCHOR,
3' MAX O.C., MIN TWO PER TIMBER
4" X 6" (NOMINAL) PRESSURE-TREATED
TIMBER (NATURAL/CLEAR FINISH)
6"
4"
ASPHALT PAVEMENT
6"
4"
1. This detail is intended for replacement of existing wooden curbs in kind. Location, orientation, and size shall match existing in field conditions.
2. Wood shall be pressure-treated for ground contact per AWPA
UC4A.
3. Apply clear wood preservative or stain before installation;
retreat field cuts and drilled holes after installation.
4.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .