B08_Attach_1_DEWA_310424_Slope_Failure_Specs_100P_2026-05-07.pdf

PDF 4 MB Posted

Attached to
DEWA 310424 - Safety and Pavement Improvements to
Solicitation number
140P2026R0043
Issued by

About this file

Summary of Project Specifications Document

This document comprises the detailed project specifications for DEWA 310424, a federal construction contract for Safety and Pavement Improvements to Route 209 and McDade Trail Relocation at Delaware Water Gap National Recreation Area in New Jersey and Pennsylvania. The work encompasses roadway reconstruction, pavement milling and overlay, full-depth patching, slope stabilization, drainage improvements, boardwalk and retaining wall construction, unpaved trail construction, guardrail replacement, signage installation, and pavement markings extending along Route 209 from Mile Marker 13.7 to 18.3 and the McDade Trail relocation. The project is divided into four primary contract line items (base bid work) valued on a lump-sum, percent-of-completion payment basis, with five additional bid options for pavement preservation, wayfinding signage, and guardrail work. The project falls under three PMIS numbers (310424, 325752, and 324741) administered by the National Park Service Denver Service Center.

The specifications establish comprehensive administrative and construction requirements including site use limitations, material storage in designated parking areas only, public access maintenance during construction, work hour restrictions (7:00 a.m. to 6:00 p.m. Monday-Friday with prior approval for weekends/holidays), and a maximum 5-month continuous road closure authorization for specific sections. The contractor must adhere to Davis-Bacon wage rates, submit a detailed construction schedule using Critical Path Method software within 30 days of notice to proceed, and maintain monthly schedule updates tied to payment requests. Key submittal requirements include a Schedule of Values, baseline CPM schedule, accident prevention plan, quality control plan, storm water pollution prevention plan, waste management plan, coordination drawings, and photo documentation. The contract utilizes NPS project management software for communication and document sharing and requires compliance with a Geotechnical Engineering Report and Wetlands/Waters Delineation Report provided with the project documents. Contract modifications are subject to strict cost and overhead limitations, with home office overhead capped at 10%, profit at 5.7% for contractor self-performed work, and aggregate markup not exceeding 25% across all tiers.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Delaware Water Gap National Recreation Area New Jersey & Pennsylvania

SAFETY AND PAVEMENT IMPROVEMENTS TO ROUTE 209

DEWA

PMIS Number 310424, 325752, 324741

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

DEWA - 310424 TOC-1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photo Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 90 00 Acceptance of Work

DIVISION 02 – EXISTING CONDITIONS

02 41 13 Selective Site Demolition 02 41 19 Removal of Structures and Obstructions 02 41 20 Structure Excavation and Backfill

DIVISION 03 – CONCRETE

03 30 53 Miscellaneous Cast-In-Place Concrete 03 41 40 Elevated Precast Concrete Boardwalk

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 90 01 Boardwalk and Trail Rail

DIVISION 10 – SPECIALTIES

10 14 53 Traffic Signage

DIVISION 31 – EARTHWORK

31 00 00 Earthwork 31 11 00 Clearing and Grubbing

DEWA - 310424 TOC-2

31 22 19 Finish Grading 31 23 17 Roadway Reconditioning 31 23 19 Dewatering 31 23 23.33 Flowable Fill 31 25 00 Erosion and Sedimentation Control 31 32 19.23 Geotextile Layer Separation 31 37 00 Rip Rap 31 51 15 Permanent Slope Stabilization – Percussion Driven Earth Anchors 31 62 16.16 Steel H-Piles 31 63 29 Drilled Shafts 31 66 15 Helical Piles

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 16.71 Cold Milling Asphalt Paving 32 01 17.61 Sealing Cracks in Asphalt Paving 32 01 17.62 Stress Absorbing Membrane Interlayer 32 01 17.71 Partial Depth Patching of Flexible Paving 32 01 17.72 Full Depth Patching of Flexible Paving 32 11 23 Aggregate Base Course 32 12 13.13 Asphalt Tack Coat 32 12 16 Standard Asphalt Pavement 32 16 23 Gravel Trails 32 17 22 Temporary Pavement Markings and Markers 32 17 23 Pavement Markings 32 17 23.43 Snowplowable Raised Pavement Markers 32 32 15 Precast Modular Block Gravity Retaining Wall 32 91 19.12 Salvaged Topsoil 32 91 19.13 Topsoil Placement and Grading 32 91 19.14 Aggregate Topsoil Course 32 92 20 Seeding and sodding

DIVISION 33 – UTILITIES

33 41 00 Storm Drainage Piping - HDPE 33 41 16.19 Pipe Underdrains 33 42 11 Stormwater Pipe – Welded Steel 33 42 23 Headwalls and Endwalls for Stormwater Piping 33 42 31 Stormwater Area Drains and Inlets 33 42 41 Gratings and Frames for Stormwater Drainage Inlets 33 47 26.09 Regenerative Stormwater Conveyance

DIVISION 34 – TRANSPORTATION

34 01 00 Maintenance of Traffic 34 71 13.26 Guardrail

DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT

44 11 13 Fugitive Dust Control

DEWA 310424

112723

01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Construction Contractor Use of Site

3. Public Use of Site

4. Conduct of Operations

5. Work Restrictions

6. Special Construction Requirements

7. Soils Investigation Report

8. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Delaware Water Gap National Recreation Area: Slope Failure Repair and Multi- Use Trail Relocation at Highway 209 (Route 014) and the McDade Trail in Pennsylvania.

Extending along or adjacent to Route 209 at MP 14.0, 15.0 and MP 16.1 to 17.8 with the relocation of the McDade Trail. The Work consists of:

1. The Work consists of roadway reconstruction, pavement milling, full depth patching, asphalt overlay, paved trail construction, slope stabilization, drainage improvements, boardwalk construction, retaining wall construction, unpaved trail construction, guide rail removal and installation, signage, and pavement markings.

B. Project will be constructed under a single prime contract.

1.3 CONSTRUCTION CONTRACTOR USE OF SITE

A. General: Construction Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the locations shown in the plans.

2. Limit site disturbance, including earthwork and clearing of vegetation as depicted in the construction drawings. Any deviation from defined LOD shall be approved by the CO.

B. Storage of Materials: Confine storage of materials to existing parking lots at project locations approved by the CO. Staging areas shall be on hard surfaces only. Locations will be discussed

01 11 00 - 2 during the project kickoff meeting. Staging areas shall be returned to their original conditions immediately upon vacating the staging area and prior to final completion. Storage of all materials shall be done in a manner than does not restrict use or access to buildings, sheds, machinery, and other features]>.

C. Parking: Confine parking to the parking lot closest to the area of construction. In addition, parking is allowed in the work zone or lane closure provided adequate traffic control measures are in place as approved by the CO.

D. Stockpiling: Stockpiling of materials are based on project location within the park. Locations will be discussed during the project kickoff meeting.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Construction Camp: Establishment of a camp within park will not be permitted.

H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.

I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

1.4 PUBLIC USE OF SITE

A. Construction Contractor shall conduct his operations to ensure the least inconvenience to public.

Road closures and detours have been authorized as shown on Sheets C3,C3.01, and C3.02 of the plans. Detour operations shall be limited to a maximum of 5 consecutive months and shall be limited to construction of culverts, slope stabilization, and McDade Trail. Durations of closures shall be approved by the CO. Additional time or short durations may be granted with prior

01 11 00 - 3 approval by the CO. The detour will be permitted for work at approximately Station 55+00 and between the stations 172+00 to 249+00. All other work shall be accomplished utilizing single lane closures.

1.5 CONDUCT OF OPERATIONS

A. Construction Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend and Federal Holiday Hours: No work shall be performed on the weekends and federal holidays without prior approval by the CO.

B. Extended work hours and workdays may be requested with a written request to the CO at least two (2) working days prior to the extended work periods.

1.7 EXISTING UTILITIES

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Construction Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management and Communication Software: Software administered by NPS shall be used to manage communication and document sharing during construction.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using NPS project management and communication software.

1.9 SOILS INVESTIGATION REPORT

A. The report Geotechnical Engineering Report DEWA 310424 Route 109 Potential Slope Failure Delaware and Dingman Twps, Pennsylvania, prepared by Terracon is provided with this package.

01 11 00 - 4

B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.

1.10 ADDITIONAL REPORTS

A. The report Delaware Water Gap National Recreation Area Wetlands/Waters Delineation Report dated September 2024 prepared by Environmental Systems Analysis, Inc. is provided with this package.

B. In case of conflict between report and drawings or specifications, drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

012721

01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

01 26 01 - 2

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

01 26 01 - 3

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

01 26 01 - 4 utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID%3D396735%7C

01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead ....................... 10% Profit ....................... 5.7%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

01 27 00 - 7

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number [0001] Route 209 (Route 0014) Pavement Improvements Mile Marker 13.7 to 18.3 PMIS 310424.

This item consists of milling, full depth patching, crack seal and fill, Stress Absorbing Membrane Interlayer (SAMI), overlay, pavement markings, shoulder restoration shoulder removal and restoration, asphalt and gravel aprons, guardrail replacement inlet repair and replacement and MUTCD signing from approximate Mileposts 13.7 to 18.3.

1. Measurement for payment will be determined based on percent of construction complete.

2. Payment will be made at the contract lump sum price.

B. Contract Line Item Number [0002] Slope Failures and culverts PMIS 310424

1. This item consists of culver repair/replacement, headwall/endwall, and stone protection outlet as indicated in the following locations:

• STA 100+85 Head Cut Outfall Repair,

• STA 109+67 Culvert Endwall & Outfall,

• STA. 183+10 Culvert, Endwall & Outfall

• STA. 187+90 Endwall & Outfall

• STA. 200+00 Culvert, Endwall, & Outfall

• STA. 206+76 Inlets, Culvert, Headwall & Outfall with Slope Repair,

• STA. 212+76 Inlets, Culvert, Headwall & Outfall,

• STA 228+80 Endwall & Outfall

• STA 232+05 Culverts, Headwall and Outfall

• STA. 240+35 Culvert, Inlets, Endwall & Outfall,

• STA 234+35 Abandon Culvert, Jack & Bore, Access & Repair,

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item Number [0003] Slope Failures, Culverts McDade Trail – ERFO PMIS 325752

01 27 00 - 8

1. This item consists of culvert repair/replacment, headwall/endwall, and stone protection outlet, McDade Trail Construction, and Guardrail as noted in the following locations:

• STA. 55+00 Remove Culvert, Inlets, Culvert, End Wall, Slope Repair, Bridge, McDade Trail

• STA. 214+50 to 224+50 McDade Trail & Guard Rail

• STA. 217+35 to 222+72 Culvert & Underdrain

• STA. 219+50 Abandon Culvert, & Slope Repair

• STA. 222+83 Inlets, Culvert, Headwall, Outfall Slope Repair

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item Number [0004] Slope Failures, Culverts McDade Trail – Disaster PMIS 324741

1. This item consists trail clearing, excavation, gravel trail construction, paved trail construction, pile driving, wall excavation, wall construction, precast concrete trail construction, and metal guard rail in the following locations:

• STA. 183+10 Culvert, Endwall & Outfall

• STA. 200+00 Culvert, Endwall & Outfall

• STA. 172+80 to 214+50 & 224+50 to 248+80 McDade Trail and Guard Rail

• McDade Trail Offroad STA. 700+00 to 710+00 Including Bridge

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item Number [0005] Bid Option 1 – Route 209 MM 0-7 Crack Seal Cyclic funding

1. This item is for crack seal and fill for Rt 209 from Mile Marker 0 to 7 of the existing pavement.

including providing moving maintenance of traffic per MUTCD

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

F. Contract Line Item Number [0006] Bid Option 2 – Route 209 Pavement Preservation PMIS 310424

1. This item consists of milling, full depth patching, crack seal and fill, SAMI, overlay, pavement markings, shoulder restoration shoulder removal and restoration, asphalt and gravel aprons, guardrail replacement inlet repair and replacement and MUTCD signing from approximate Mileposts 18.3 to 19.3.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

G. Contract Line Item Number [0007] Bid Option 3 – Route 209 Pavement Preservation PMIS 310424

1. This item consist of milling, full depth patching, crack seal and fill, SAMI, overlay, pavement markings, shoulder restoration shoulder removal and restoration, asphalt and gravel aprons, guardrail replacement inlet repair and replacement and MUTCD signing from approximate Mileposts 19.3 to 20.3.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

H. Contract Line Item Number [0008] Bid Option 4 – McDade Trail – Disaster PMIS 324741

1. This item consists of removing the McDade Trail Wall and trail at grade from Base Bid and Replace with McDade Trail Boardwalk per the Boardwalk Trail Details on C8.01 to C8.92 and per the specifications at the following locations:

• STA. 192+38 to STA. 196+63

• STA. 202+15 to STA. 203+63

• STA. 210+88 to STA. 212+99

01 27 00 - 9

• STA. 217+20 to STA. 232+63

• STA. 234+13 to STA. 236+16

• STA. 236+56 to STA. 237+38

• STA. 244+36 to STA. 245+67

• STA. 246+23 to STA. 248+25

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

I. Contract Line Item Number [0009] Bid Option 3 – Route 209 Wayfinding Signage PMIS 310424

1. This item consists of providing Wayfinding signage from approximate Mileposts 13.7 to 20.3.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

J. Contract Line Item Number [0010] Bid Option 4 – Route 209 Wayfinding Signage PMIS 310424

1. This item consists of providing Wayfinding signage from approximate Mileposts 0.0 to 7.0.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

K. Contract Line Item Number [0011] Bid Option 5 – McDade Trail Guide Rail PMIS 324741

1. This item consists of providing Natina Coated guard rail from approximate Sta 172+80 to Sta

248+80.

2. Measurement for payment will be determined based on percent of construction complete.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. NPS Project Management and Communication Software

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Construction Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Construction Contractors to ensure maximum accessibility for required maintenance, service, and repair.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

01 31 00 - 2

3. Make provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other Construction Contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Construction Contractor Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

9. Commissioning activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and controls.

e. Indicate required installation sequences.

2. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.

01 31 00 - 3

3. Follow NPS DSC Electronic Drawing Standards. See CAD/BIM (Computer Aided Design/Building Information Modeling) & Drafting Standards page > DSC Requirements section.

B. Coordination Digital Data Files: Prepare coordination digital data files according to:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.

3. Contracting Officer will furnish Construction Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

C. Division 1 documents:

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Construction Contractor Commissioning Plan

11. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

D. Provide items listed to Contracting Officer at least one week prior to Pre-Construction Conference, or as directed by Contracting Officer.

1. Failure to submit items may result in:

a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.

b. Work shall not commence until written Notice to Proceed has been issued and Certificates of Insurance and SF1413 documents are received for Construction Contractor and all Subcontractors.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Construction Contractor shall prepare and submit an RFI utilizing form created on NPS project management and communication software.

https://www.nps.gov/dscw/ds-cad-bim-drafting.htm https://www.nps.gov/dscw/ds-cad-bim-drafting.htm

01 31 00 - 4

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Construction Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Construction Contractor's suggested resolution: If suggested resolution impacts Contract

Time or Contract Sum, Construction Contractor shall state impact in RFI.

8. Construction Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete and submit on NPS project management and communication software.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Construction Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.6 PROJECT MANAGEMENT AND COMMUNICATION SOFTWARE

A. Use to manage project communication and document sharing during contract period on:

01 31 00 - 5

1. Project directory

2. Project correspondence

3. Meeting agendas and minutes

4. Contract modifications forms and logs

5. RFI form and processing

6. Task and issue management

7. Photo documentation

8. Baseline schedule, schedule updates and calendar management

9. Submittal form and processing

10. Payment coordination documentation

11. Reminder and tracking functions

12. Archiving functions

13. Notification of submittal and RFI statuses and current responsible party

14. Permits and addendums

B. Some documents are not suitable to be shared using NPS project management and communication software. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared and shall be coordinated with project team as appropriate.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Construction Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Construction Contractor

9. Payroll reports

10. Contract time

11. Liquidated damages

12. Construction Contractor Performance Evaluation

13. Display of Hotline posters

14. Notice to proceed

15. Correspondence procedures

16. NPS project management and communication software

17. Acceptance/rejection of work

18. Progress meetings

19. Submittal procedures

20. NPS Final Accessibility Inspection

21. Environmental requirements

22. Permit requirements

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials

01 31 00 - 6

26. Value engineering

27. Schedule of Values

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Construction Contractor.

1. Attendees: In addition to Government Representatives, each Construction Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented.

Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)

h. Construction Schedule update (provide updated Critical Path Method (CPM)).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements

C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:

a. Contract Documents

b. Options

c. Related RFIs

d. Related Change Orders

e. Purchases

f. Deliveries

g. Submittals

h. Review of mockups

i. Possible conflicts

j. Compatibility requirements

k. Time schedules

l. Weather limitations

01 31 00 - 7

m. Manufacturer's written instructions

n. Warranty requirements

o. Compatibility of materials

p. Acceptability of substrates

q. Temporary facilities and controls

r. Space and access limitations

s. Regulations of agency(ies) with jurisdiction

t. Testing and inspecting requirements

u. Installation procedures

v. Coordination with other work

w. Required performance results

x. Protection of adjacent work

y. Protection of construction and personnel

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.

1.8 ENVIRONMENTAL COORDINATION

A. Construction Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Construction Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project;; familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of Waste Management Plan (WMP).

c. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.

d. Training for Construction Contractor personnel in accordance with position requirements.

e. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements

2. Regulatory Requirements

01 31 00 - 8

3. Noise and Acoustics Management

4. Temporary Storm Water Pollution Prevention Environmental Management

5. Construction Waste Management

C. Construction Contractor’s Environmental Training Program: Construction Contractor shall provide environmental training for workers performing work on project site. Training shall include:

1. Overview of environmental issues related to Project.

2. Review of site-specific procedures and management plans:

a. Construction Waste Management

b. Noise and Acoustics Management

c. Temporary Storm Water Pollution Prevention

3. Pollution Prevention (P2) practices: Submit evidence of participation in P2 programs.

4. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Construction Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.

1.9 PERMITS

A. General:

1. Permits and Responsibilities: Construction Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Construction Contractor shall also be responsible for damages to persons or property that occur as a result of Construction Contractor’s fault or negligence;

and for materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract, Construction Contractor will not be considered an agent of the Government. Construction Contractor shall comply with appropriate Federal, State and local laws.

B. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.

C. Administrative Procedures:

01 31 00 - 9

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.

2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.

3. Upload permits to NPS project management and communication software when permits are obtained.

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

010824

01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of Construction Schedule requirements including:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Construction Contractor. It shall assist the Construction Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Construction Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.

A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.

The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.

E. Float: Measure of leeway in starting and completing an activity.

01 32 16 - 2

1. Float: Not for the exclusive use or benefit of the Government or Construction Contractor but is…