B08_ATT_2_IDIQ_Pricing_Worksheet_2_5_24.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Alaska Legacy and Abandoned Well Remediation IDIQ
Solicitation number
140L0624R0005
Issued by

About this file

This document contains a pricing worksheet template and details for an indefinite delivery, indefinite quantity (IDIQ) contract opportunity with the Bureau of Land Management to provide plugging, abandonment, and remediation services for wells on federal lands in Alaska. Key details include that the IDIQ ceiling for each awarded contract is $200 million, with a minimum guarantee of $25,000. The solicitation requires pricing to be provided for two sample task orders involving well plugging and abandonment projects. Offerors must also disclose their bonding capacity, and subsequent task orders will require performance and payment bonds. The opportunity is fully set aside for Indian Small Business Economic Enterprise entities with a size standard of $47 million.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TAB 1 - Total Evaluated Price

INSTRUCTIONS: Offerors shall fill in pricing in Tabs 2-5. The pricing in Tab 1 will be automatically calculated based on Tabs 3-5 and will be utilized for price evaluation.
Technical Factor 3
Sample Task Order 1: Fish Creek$ - 0
Sample Task Order 2: Cape Halkett$ - 0
Sample Task Order 1 & 2: Fish Creek and Cape Halkett$ - 0

Total Evaluated Price $ - 0

TAB 2 - IDIQ Rates

IDIQ Contract Price Schedule
Labor CategoriesYEAR 1YEAR 2YEAR 3YEAR 4YEAR 5OPTION EXTENSION
Hourly RateHourly RateHourly RateHourly RateHourly RateHourly Rate
Project Manager$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Senior Petroleum Engineer$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Site Superintendent$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Administrative POC$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Qualified Environmental Professional$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

TAB 3 - Sample Task Order 1

Sample Task Order 1 - Contract Price Schedule
Project Title: Plugging and Abandonment of Fish Creek Well Cluster
Notice: Respondents are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQtyUnitUnit PriceTotal Price
1Plugging and Abandonment of Fish Creek1LS$0.00$0.00
2Clean-up of Fish Creek Area1LS$0.00$0.00
3Mobilization and Demobilization1LS$0.00$0.00
4Projecet Management, Planning & Reporting1LS$0.00$0.00
5Inclement Weather - Firm Fixed Unit Price***1LS$0.00$0.00
TOTAL PROPOSED PRICE (Contract Line Item Number 1 through 5) ---------------------------------------------------------------------------------$0.00
***The contractor shall fill out the CLIN 5 subline detail below with daily inclement weather rates in accordance with Section 3.2.3 in the IDIQ Statement of Work. The total amount for CLIN 5 will automatically calculate on the CLIN schedule above.
CLIN 5 - Inclement Weather Pricing Model (Estimated Quantities)
Subline Item NumberSubline Item TitleQtyUnitUnit PriceTotal Price
1Mobilization Phase Inclement Weather Day2DAY$0.00$0.00
2Demobilization Phase Inclement Weather Day2DAY$0.00$0.00
3Remediation Phase Inclement Weather Day2DAY$0.00$0.00
4Plugging & Abandonment Inclement Weather Day2DAY$0.00$0.00
In accordance with Section 3.2.3 of the IDIQ PWS and the included Task Order Statement of Work, inclement weather is defined as low visibility or temperatures causing unsafe conditions (below -50 degrees Fahrenheit or above 30 degrees Fahrenheit) that may cause operations to shut down.

An inclement weather "DAY" is defined as 6 hours or more of work stoppage due to inclement weather. Delays of 4-6 hours shall be billed at 50% of the day rate (unit price). Delays of 6 hours or more shall be billed at the full day rate (unit price).

Quantities of weather delay days are estimated. Actual inclement weather delays will be communicated within 24 hours or less as they occur and will be recorded in daily logs documenting COR approval. Weather day requests shall also include total estimated costs.

TAB 4 - Sample Task Order 2

Sample Task Order 2 - Contract Price Schedule
Project Title: Plugging and Abandonment of Cape Halkett #1
Notice: Respondents are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQtyUnitUnit PriceTotal Price
1Plugging and Abandonment of Cape Halkett #11LS$0.00$0.00
2Clean-up of Cape Halkett Area1LS$0.00$0.00
3Mobilization and Demobilization1LS$0.00$0.00
4Project Management, Planning & Reporting1LS$0.00$0.00
5Inclement Weather - Firm Fixed Unit Price***1LS$0.00$0.00
TOTAL BASE PRICE (Contract Line Item Number 1 through 5) ---------------------------------------------------------------------------------$0.00
***The contractor shall fill out the CLIN 5 subline detail below with daily inclement weather rates in accordance with Section 3.2.3 in the IDIQ Statement of Work. The total amount for CLIN 5 will automatically calculate on the CLIN schedule above.
6Optional Task - Additional Clean-up & Remediation1LS$0.00$0.00
TOTAL PRICE FOR ALL OPTIONS (Contract Line Number 6) -----------------------------------------------------------------------------$0.00
TOTAL PROPOSED BASE & ALL OPTIONS PRICE (Contract Line Item Numbers 1 through 6)$0.00
Contract Line Item Number (CLIN) 5 - Inclement Weather
Subline Item NumberSubline Item TitleQtyUnitUnit PriceTotal Price
1Mobilization Phase Inclement Weather Day1DAY$0.00$0.00
2Demobilization Phase Inclement Weather Day1DAY$0.00$0.00
3Remediation Phase Inclement Weather Day2DAY$0.00$0.00
4Plugging & Abandonment Inclement Weather Day2DAY$0.00$0.00
In accordance with Section 3.2.3 of the IDIQ PWS and the included Task Order Statement of Work, inclement weather is defined as low visibility or temperatures causing unsafe conditions (below -50 degrees Fahrenheit or above 30 degrees Fahrenheit) that may cause operations to shut down.

An inclement weather "DAY" is defined as 6 hours or more of work stoppage due to inclement weather. Delays of 4-6 hours shall be billed at 50% of the day rate (unit price). Delays of 6 hours or more shall be billed at the full day rate (unit price).

Quantities of weather delay days are estimated. Actual inclement weather delays will be communicated within 24 hours or less as they occur and will be recorded in daily logs documenting COR approval. Weather day requests shall also include total estimated costs.

TAB 5 - Sample Task Order 1 & 2

Sample Task Order 1 & 2 - Contract Price Schedule
Project Title: Plugging and Abandonment of Fish Creek Well Cluster and Cape Halkett #1
Notice: Respondents are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQtyUnitUnit PriceTotal Price
1Plugging and Abandonment of Fish Creek1LS$0.00$0.00
2Plugging and Abandonment of Cape Halkett1LS$0.00$0.00
3Clean-up of wellsite Areas1LS$0.00$0.00
4Mobilization and Demobilization1LS$0.00$0.00
5Project Management, Planning & Reporting1LS$0.00$0.00
6Inclement Weather - Firm Fixed Unit Price***1LS$0.00$0.00
TOTAL BASE PRICE (Contract Line Item Number 1 through 6) ---------------------------------------------------------------------------------$0.00
***The contractor shall fill out the CLIN 6 subline detail below with daily inclement weather rates in accordance with Section 3.2.3 in the IDIQ Statement of Work. The total amount for CLIN 6 will automatically calculate on the CLIN schedule above.
7Optional Task - Additional Clean-up & Remediation Cape Halkett1LS$0.00$0.00
TOTAL PRICE FOR ALL OPTIONS (Contract Line Number 7) -----------------------------------------------------------------------------$0.00
TOTAL PROPOSED BASE & ALL OPTIONS PRICE (Contract Line Item Numbers 1 through 7)$0.00
Contract Line Item Number (CLIN) 6 - Inclement Weather
Subline Item NumberSubline Item TitleQtyUnitUnit PriceTotal Price
1Mobilization Phase Inclement Weather Day3DAY$0.00$0.00
2Demobilization Phase Inclement Weather Day3DAY$0.00$0.00
3Remediation Phase Inclement Weather Day3DAY$0.00$0.00
4Plugging & Abandonment Inclement Weather Day3DAY$0.00$0.00
In accordance with Section 3.2.3 of the IDIQ PWS and the included Task Order Statement of Work, inclement weather is defined as low visibility or temperatures causing unsafe coniditions (below -50 degrees Fahrenheit or above 30 degrees Fahrenheit) that may cause operations to shut down.

An inclement weather "DAY" is defined as 6 hours or more of work stoppage due to inclement weather. Delays of 4-6 hours shall be billed at 50% of the day rate (unit price). Delays of 6 hours or more shall be billed at the full day rate (unit price).

Quantities of weather delay days are estimated. Actual inclement weather delays will be communicated within 24 hours or less as they occur and will be recorded in daily logs documenting COR approval. Weather day requests shall also include total estimated costs.

File details come from the government source that posted it. Updated .