This is a Key Personnel and Key Trades form attachment to RFP No. 140P8126R0002 for fire suppression system installation at Grand Canyon-Parashant National Monument. The form serves as a template for contractors to identify and commit to specific personnel and subcontractors essential to project execution.
For key personnel, contractors must assign a Project Manager and an On-site Superintendent to the contract. During the initial 60-day performance period, no substitutions are permitted except in cases of illness, death, or employment termination, with the Contracting Officer to be notified within 15 calendar days. After the 60-day period, any permanent substitutions require 15 days' advance notice and submission of detailed explanations and complete resumes demonstrating comparable qualifications; the Contracting Officer will respond within 15 calendar days. For key trades, contractors must identify firms to perform Sprinkler System Design, Sprinkler System Installation, Fire Alarm Design, and Fire Alarm Installation, either through self-performance or named subcontractors. These trade assignments are permanent throughout the contract duration, and any substitutions require prior Contracting Officer approval with a minimum 15-day advance request period. Substitution requests must include detailed explanations and qualification statements for proposed replacements with comparable qualifications, with approval or denial provided within 15 calendar days of receiving complete information.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Amd_0001_Atch_1_-_Specifications_Revision_0001.pdf | ||
| Sol_140P8126R0002_Amd_0001.pdf | ||
| B08_Atch_4_-_Dellenbaugh_Transportation_Map.pdf | ||
| B08_Atch_9_-_Past_Performance_Questionnaire.docx | DOCX document | |
| B08_Atch_3_-_Product_Data.pdf | ||
| B08_Atch_5_-_Construction_Wage_Determination_5_18_26.pdf | ||
| B08_Atch_6_-_Proposal_Submission_Cover_Page___ToC.docx | DOCX document | |
| B08_Atch_11_-_SF_24_Bid_Bond.pdf | ||
| B08_Atch_12_-_52_209-7_Response_Form.docx | DOCX document | |
| B08_Atch_13_-_52_209-13_Response_Form.docx | DOCX document | |
| B08_Atch_1_-_Specifications.pdf | ||
| Sol_140P8126R0002.pdf | ||
| B08_Atch_8_-_Project_Experience_Questionnaire.docx | DOCX document | |
| B08_Atch_14_-_General_References_Form.docx | DOCX document | |
| B08_Atch_15_-_Subcontracting_Percentage_Worksheet.xlsx | XLSX spreadsheet | |
| B08_Atch_2_-_Drawings.pdf | ||
| B08_Atch_7_-_Price_Schedule.xlsx | XLSX spreadsheet |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. 140P8126R0002, 52.209-7 Certification Company Name: _________________________________
KEY PERSONNEL
(a) The Contractor shall assign to this contract the following key personnel:
Project Manager:
On-site Superintendent:
(b) During the first 60 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 60-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.
(End of clause)
KEY TRADES
(a) The Contractor shall identify firms that will perform the following KEY TRADES under this contract. If Key Trades will be self-performed, note “self-performed” in the appropriate trade; otherwise provide the name(s) of assigned subcontractors.
Sprinkler System Designer:
Sprinkler System Installer:
Fire Alarm Designer:
Fire Alarm Installer:
(b) The assignments above are permanent for the contract duration. The Contractor shall make no substitutions of the above listed Key Trade assignments unless the substitution is approved or directed by the Contracting Officer. The Contractor shall send requests for substitutions to the Contracting Officer a minimum of 15 calendar days prior to any substitution and provide the information required by paragraph (c) below.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete qualification statements for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes shall have comparable qualifications to the firm being replaced. The Contracting Officer will approve or deny substitution requests within 15 calendar days after receipt of all required information. This clause will be modified to reflect any approved changes.
(End of clause)