This is a comprehensive construction specification document and contract package for the Whiteriver Hospital Construction project in Whiteriver, Arizona, prepared by SmithGroup for the Indian Health Service (IHS), Division of Engineering Services. The project involves constructing a new 407,000 gross square foot hospital facility to replace the existing Whiteriver Hospital on the Fort Apache Indian Reservation, with construction organized in two phases: Phase 1 covering new hospital construction and enabling infrastructure, and Phase 2 covering demolition of existing structures. The contract is a single prime contract with an estimated project cost of approximately $350-400 million, requiring the contractor to furnish all personnel, materials, services, and facilities necessary for complete hospital construction including architectural, structural, civil, mechanical, plumbing, electrical, and specialty systems work.

The specifications establish detailed requirements across 48 divisions covering general requirements, site work, structural systems, building enclosure, interior finishes, mechanical/plumbing/electrical systems, and specialized hospital equipment. Key contractual requirements include mandatory submission of a Quality Control Plan within 15 days of Notice to Proceed, achievement of LEED v4 BD+C: Healthcare certification, implementation of an Indoor Air Quality Management Plan and Construction Waste Management Plan (targeting 75% waste diversion through at least four diversion streams), and preparation of comprehensive operation and maintenance documentation. The contract incorporates modified technical provisions from the White Mountain Apache Tribe (WMAT) 2023 IDIQ, specifying detailed requirements for water transmission and distribution systems, wastewater infrastructure, and construction procedures. Additional administrative requirements include Preconstruction and Coordination meetings, weekly progress meetings, RFI procedures allowing 7-day responses, submittal review periods of 21 calendar days for initial reviews and 10 business days for resubmittals, and provisions for phased construction with continuous occupancy of existing facilities during Phase 1 and demolition of existing structures only after Phase 1 substantial completion.

View the file

Other files

File Type Posted
A10-1a 0_MEM2026-0618_IHS-Whiteriver-Hospital_BID-Addendum-H.pdf PDF
A10-1b 0_SPEC2026-0618_Specifications_IHS-Whiteriver-Hospital_BID-ADD-H.pdf PDF
A10-3a Attachment J12a AZ FORM 5000HC_TPT HEALTHCARE EXEMPTION CERTIFICATE.pdf PDF
Amend9 - WR Construction - 17 Jun 2026.pdf PDF
A9-1b BP1_DWG2026-0612_15_ELECTRICAL_IHS-Whiteriver-Hospital_BID-ADD-G.pdf PDF
A8-1e BP1_DWG2026-0609_16_ICT_IHS-Whiteriver-Hospital_BID-ADD-F.pdf PDF
A7-1a 0_MEM2026-0528_IHS-Whiteriver-Hospital_BID-Addendum-E.pdf PDF
A7-1d BP1_DWG2026-0528_15_ELECTRICAL_IHS-Whiteriver-Hospital_BID-ADD-E.pdf PDF
A7-1e BP1_DWG2026-0528_16_ICT_IHS-Whiteriver-Hospital_BID-ADD-E.pdf PDF
A7-1h BP4_DWG2026-0528_16_ICT_IHS-Whiteriver-Pump-House_BID-ADD-E.pdf PDF
A7-2b Contact list Service Unit - RFI 109.xlsx XLSX spreadsheet
A6-1d BP1_DWG2026-0521_06_LANDSCAPE_IHS-Whiteriver-Hospital_BID-ADD-D.pdf PDF
A6-3a Attachment J06a - Building AZ20260027 rev-0518.pdf PDF
A6-3c Attachment J06c - Heavy AZ20260054 rev-0518.pdf PDF
A6-1a 0_MEM2026-0520_IHS-Whiteriver-Hospital_BID-Addendum-D.pdf PDF
A6-1b SPEC2026-0520_Specifications_IHS-Whiteriver-Hospital_BID-ADD-D.pdf PDF
A6-1c BP1_DWG2026-0520_05_CIVIL_IHS-Whiteriver-ADOT-PLANS_BID-ADD-D.pdf PDF
A6-1e BP1_DWG2026-0520_08_ARCHITECTURAL_IHS-Whiteriver-Hospital_BID-ADD-D.pdf PDF
A6-2 WR Pre-Proposal_RFIs 001 - 121.xlsx XLSX spreadsheet
A5-3 WR Standard Form 1442.pdf PDF
A5-1b SPEC2026-0514_Specifications_IHS-Whiteriver-Hospital_BID-ADD-C.pdf PDF
A5-1d BP1_DWG2026-0514_06_LANDSCAPE_IHS-Whiteriver-Hospital_BID-ADD-C.pdf PDF
A5-2 WR Pre-Proposal_RFIs 001 - 069.xlsx XLSX spreadsheet
Amend4 - WR Construction - 7 May 2026.pdf PDF
A4-1b SPEC2026-0430_Specifications_IHS-Whiteriver-Hospital_BID-ADD-B.pdf PDF
A4-1a 0_MEM2026-0430_IHS-Whiteriver-Hospital_BID-Addendum-B.pdf PDF
A4-1f BP1_DWG2026-0430_15_ELECTRICAL_IHS-Whiteriver-Hospital_BID-ADD-B.pdf PDF
A3-1 Section B.pdf PDF
A3-2 Attachment J11 EPA Schedule.xlsx XLSX spreadsheet
A3-3 WR Pre-Proposal_RFIs 001 - 050.xlsx XLSX spreadsheet
Amend2 - WR Construction - 24 April 2026.pdf PDF
A2-1a MEM2026-0416_IHS-Whiteriver-Hospital_BID-Addendum-A.pdf PDF
A2-1b SPEC2026-0416_Specifications_IHS-Whiteriver-Hospital_BID-ADD-A.pdf PDF
A2-1e BP1_DWG2026-0416_08_ARCHITECTURAL_IHS-Whiteriver-Hospital_BID-ADD-A.pdf PDF
A2-1f BP1_DWG2026-0416_15_ELECTRICAL_IHS-Whiteriver-Hospital_BID-ADD-A.pdf PDF
A2-1h BP3_DWG2026-0416_05_CIVIL_IHS-Hon-Dah-UC_BID-ADD-A.pdf PDF
Amend1 - WR Construction - 14 April 2026.pdf PDF
A1-2a WR Pre-Proposal Mtg Attendee List - Original Written.pdf PDF
B01 RFP Whiteriver Hospital Construction 75H70126R00016.pdf PDF
B01 Attachment J01 BP3_01_GENERAL_IHS-HonDah-WWTP_FINAL-CD.pdf PDF
B01 Attachment J02b Specs (Vol 2).pdf PDF
B01 Attachment J02c Specs (Vol 3).pdf PDF
B01 Attachment J02f SWTP Specs (Vol 6).pdf PDF
Attachment J06a - Building AZ20260027.pdf PDF
Attachment J10 Subcontracting Plan (Large Business).docx DOCX document
B01 Attachment J01 BP4_01_GENERAL_IHS-Whiteriver-Pump-House_FINAL-CD.pdf PDF
B01 Attachment J02d Specs (Vol 4).pdf PDF
Attachment J06b - Highway AZ20260033.pdf PDF
Attachment J07 Company Technical Experience Construction Sheet.docx DOCX document
Attachment J08 - Key Personnel Resume Form.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prepared for: INDIAN HEALTH SERVICE

100% CONSTRUCTION DOCUMENTS

Project No: 14904.000

5 MARCH 2026

VOLUME 1

Prepared by:

SMITHGROUP 14904.000 INDIAN HEALTH SERVICE

WHITERIVER HOSPITAL

FINAL CONSTRUCTION DOCUMENTS

23 JANUARY 2026

SEALS PAGE 000107 - 1

DOCUMENT 000107 - SEALS PAGE

Include on this Seals Page Document the seals of the design professionals of record required by statute to affix their seal to the documents. Where required, include a description of the Specification Sections prepared under the direction of each design professions *EDIT FOR YOUR PROJECT-USE DIVISION AND/OR SECTION NUMBERS*.

If such listing is required, you may alternatively use the MasterSpec seals page instead of this SmithGroup seals page.

Architect SmithGroup, Inc.

Phoenix, AZ Matthew Hess, AIA, NCARB

Responsible for Divisions 01-49 Sections except where indicated as prepared by other design professionals of record.

Structural Engineer PK Associates and Pimara Paul Koehler Scottsdale, Arizona Christa Chau, PE, SE Responsible for: Division 03, Sections 030000 and 032000; Division 04, Section 042000; Division 05, Sections 051200 and 053100; and Division 31, Section 316329

Civil Engineer Dibble & Associates Consulting Engineers, Inc.

Phoenix, Arizona

Christina Shannon Mauck, PE

Responsible for: Division 01, Section 015713, Division 02, Section 024100, Division 09, Section 099713, Division 31, Sections 312213, 312300, 312316.16, 312323.13, 312333, 312500, Division 32, Sections 321123, 321216, 321313, 321315, Division 33, Sections 331000, 331623, 333000, 333213, 333723, 334213

Fire Protection Engineer

Phoenix, AZ Andrew Ochsankehl, PE Responsible for: Division 13, Section 131200*; Division 21, Sections 211300, 213000, 210533; Division 27, Section 273226; Division 28, Section 283111

*Fire Protection Related Requirements Only

SEALS PAGE 000107 - 2

Electrical Engineer

Phoenix, AZ Daniel L. Peterson, PE Responsible for: Division 26, except for those Sections labeled with “WWTP”

Communications (AV, IT, Security) Designer

Washington, DC David K. Glenn, RCDD Responsible for: Division 27, Sections 270413, 270526, 270528, 270536, 270544, 270553, 271100, 271300, 271500, 272100, 273226, 274116, 275113, 275119, 275123, 275223, 275313, 275316 and 275319; and Division 28, Sections 280413, 280513, 280526, 280528, 281300, 281600, 282300 and 285000

Landscape Architect

Phoenix, AZ Richard P. Jones, PLA Responsible for: Division 32, Sections 321316, 321373, 321716, 321723, 323113, 323119, 323213, 324020, 328000, 329100, 329220, 329300

Civil Engineer Dibble & Associates Consulting Engineers, Inc.

Phoenix, Arizona

Ian B. Mowry, PE

Responsible for: Division 31, Sections 312213, 312300, 312316, 312323, 312500; Division 32, Sections 321123, 321216, 321315; Division 33, Section 4213; Division 34, Sections 340114, 347113, 347116

SEALS PAGE 000107 - 3

Structural Engineer Morrison-Maierle Phoenix, Arizona

Michael Brennan, PE Responsible for structural specifications for the WWTPs:

Division 03: 033000; Division 05: 051400, 055000, 055200, 055300; Division 13: 133419; Division 41:

413313, 413313.01

Electrical Engineer

Phoenix, Arizona Michael Brandt, PE

Responsible for electrical specifications for the WWTPs:

Division 26: 260400, 260519, 260523, 260526, 260529, 260533, 260536, 260543, 260544, 260548.16, 260553, 260573.13, 260573.16, 260573.19, 260913, 260923, 262213, 262413, 262416, 262419, 262713, 262726, 262813, 262816, 262923, 263213, 263353, 263600, 264313, 265100, 265600

Plumbing Engineer

Phoenix, Arizona Jody Waverek, PE

Responsible for plumbing specifications for the WWTPs:

Division 22: 220517, 220518, 220519, 220523.12, 220523.14, 220529, 220548, 220553, 220719, 221116, 221119, 221123, 221123.13, 221316, 221429, 223300, 224213.13, 224213.16, 224216.13, 224216.16, 224223, 224500

Mechanical Engineer

Phoenix, Arizona Jody Waverek, PE Responsible for mechanical specifications for the WWTPs: Division 23: 230513, 230529, 230548, 230553, 230593, 230713, 230716, 230900, 233113, 233300, 233423, 233713, 237416.11, 238126, 238239

SEALS PAGE 000107 - 4

Environmental Engineer

Phoenix, Arizona Ulrike Lashley, PE

Responsible for the following specifications for the WWTPs: Division 09: 099600; Division 10: 101400.01, 104352; Division 40: 400205, 400510, 400510.03, 400510.04, 400510.09, 400510.12, 400510.13, 400510.30, 400553, 400555, 400557, 406110, 406115, 406116, 406120, 406120.01, 406120.02, 406120.03, 406120.04, 406121, 406124, 406127, 406128, 406140, 406160, 406171, 406176, 406177, 406180, 406181, 406182, 406191; Division 41: 413313.17; Division 43:

431030, 431111, 432256, 432321, 432331, 432331.01, 432358, 433230, 433269, 434010; Division 46: 460754, 460754.01, 460754.02, 460754.03, 460754.04, 460754.05, 460754.06, 460754.07, 460754.08, 460754.09, 460754.10, 461155, 461155.01, 461155.02, 461155.03, 461155.04, 462113, 462113.01, 462113.02, 462113.03, 465035, 465035.01, 465035.02, 465131, 465131.01, 465131.02

Hazardous Building Materials

Mabbett & Associates, Inc.

Stoneham, Massachusetts

Michael Delaney, Asbestos Designer

Responsible for: 028200, 028313

END OF DOCUMENT 000107

TABLE OF CONTENTS TOC - 1

TABLE OF CONTENTS

Volume 1

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 001000 - SOLICITATION, CONTRACT LINE-ITEM NUMBER (CLIN) SCHEDULE

SECTION 002000 - INSTRUCTIONS FOR PROCUREMENT

SECTION 002100 - INSTRUCTIONS

SECTION 002113 - INSTRUCTIONS TO BIDDERS

SECTION 002116 - INSTRUCTIONS TO PROPOSERS

SECTION 002200 - SUPPLEMENTARY INSTRUCTIONS

SECTION 002216 - SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS

SECTION 003000 - AVAILABLE INFORMATION

SECTION 004000 - PROCUREMENT FORMS AND SUPPLEMENTS

SECTION 004300 - BID BOND FORM

SECTION 004373 - PROPOSED CONSTRUCTION SCHEDULE FORM

SECTION 004500 - REPRESENTATIONS AND CERTIFICATIONS

SECTION 005000 - CONTRACTING FORMS AND SUPPLEMENTS

SECTION 005100 - NOTICE OF AWARD

SECTION 005200 - AGREEMENT FORMS

SECTION 006000 - PROJECT FORMS

SECTION 006100 - BOND FORMS

SECTION 006200 - CERTIFICATES

SECTION 007000 - CONDITIONS OF THE CONTRACT

SECTION 007100 - CONTRACTING DEFINITIONS

SECTION 007200 - GENERAL CONDITIONS

SECTION 007300 - SUPPLEMENTAL CONDITIONS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 011000 - SUMMARY

SECTION 012300 - OPTIONS

SECTION 012500 - SUBSTITUTION PROCEDURES

SECTION 012510 - SUBSTITUTION REQUEST FORM

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

SECTION 012614 - REQUESTS FOR INFORMATION

SECTION 012900 - PAYMENT PROCEDURES

SECTION 012973 - SCHEDULE OF VALUES

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

TABLE OF CONTENTS TOC - 2

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION

SECTION 013300 - SUBMITTAL PROCEDURES

SECTION 013330 - SUBMITTAL COMPLIANCE FORM

SECTION 013526 - GOVERNMENT SAFETY REQUIREMENTS

SECTION 013573 - DELEGATED DESIGN REQUIREMENTS AND PROCEDURES

SECTION 014200 - REFERENCES

SECTION 014339 - EXTERIOR WALLS MOCKUPS

SECTION 014500.00 10 - QUALITY CONTROL

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

SECTION 015713 - TEMPORARY EROSION AND SEDIMENT CONTROL

SECTION 015731 - INDOOR AIR QUALITY (IAQ) MANAGEMENT

SECTION 016000 - PRODUCT REQUIREMENTS

SECTION 017300 - EXECUTION

SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

SECTION 017700 - CLOSEOUT PROCEDURES

SECTION 017823 - OPERATION AND MAINTENANCE DATA

SECTION 017839 - PROJECT RECORD DOCUMENTS

SECTION 017900 - DEMONSTRATION AND TRAINING

SECTION 018113 - SUSTAINABLE DESIGN REQUIREMENTS

SECTION 018900 - SITE CONSTRUCTION PERFORMANCE REQUIREMENTS

SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS

SECTION 019119 - BUILDING ENCLOSURE COMMISSIONING

SECTION 019200 - FACILITY OPERATION, MAINTENANCE, AND TROUBLESHOOTING

MOBILE GRAPHICAL INFORMATION MANAGEMENT PLATFORM

DIVISION 02 - EXISTING CONDITIONS

SECTION 024100 - SITE DEMOLITION

SECTION 028200 - ASBESTOS ABATEMENT

SECTION 028313 - LEAD HAZARD CONTROL

TABLE OF CONTENTS TOC - 3

DIVISION 03 – CONCRETE

SECTION 032000 - CONCRETE REINFORCEMENT

SECTION 033000 - CAST-IN-PLACE CONCRETE

SECTION 033000 - CAST-IN-PLACE CONCRETE - WWTP

SECTION 033543 - POLISHED CONCRETE FINISHING

SECTION 035400 - CAST UNERLAYMENT

DIVISION 04 – MASONRY

SECTION 042000 - UNIT MASONRY ASSEMBLIES

SECTION 042500 - TERRA COTTA RAINSCREEN SYSTEM

SECTION 042505 - STABILIZED RAMMED EARTH

SECTION 042613 - MASONRY VENEER

DIVISION 05 – METALS

SECTION 051200 - STRUCTURAL STEEL FRAMING

SECTION 051400 - STRUCTURAL ALUMINUM

SECTION 053100 - STEEL DECKING

SECTION 054000 - COLD FORMED METAL FRAMING

SECTION 054300 - SLOTTED CHANNEL FRAMING

SECTION 055000 - METAL FABRICATIONS

SECTION 055000 - METAL FABRICATIONS-WWTP

SECTION 055113 - METAL PAN STAIRS

SECTION 055119 - METAL GRATING STAIRS

SECTION 055200 - HANDRAILS AND RAILIINGS

SECTION 055300 - FABRICATED GRATING

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

SECTION 061053 - MISCELLANEOUS ROUGH CARPENTRY

SECTION 061600 - SHEATHING

SECTION 064116 - PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

SECTION 066119 - QUARTZ SURFACING FABRICATIONS

SECTION 066400 - PLASTIC PANELING

SECTION 068300 - COMPOSITE PANELING

TABLE OF CONTENTS TOC - 4

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

SECTION 071113 - BITUMINOUS DAMPPROOFING

SECTION 071326 - SELF-ADHERING SHEET WATERPROOFING

SECTION 071413 - HOT FLUID-APPLIED RUBBERIZED ASPHALT WATERPROOFING

SECTION 071900 - WATER REPELLENTS

SECTION 072100 - THERMAL INSULATION

SECTION 072600 - VAPOR RETARDERS

SECTION 072726 - FLUID-APPLIED MEMBRANE AIR BARRIERS

SECTION 074213.13 - FORMED METAL WALL PANELS

SECTION 074213.23 - METAL COMPOSITE MATERIAL WALL PANELS

SECTION 074213.33 - FORMED METAL SCREENWALL PANELS

SECTION 074293 - SOFFIT PANELS

SECTION 075419 - POLYVINYL-CHLORIDE (PVC) ROOFING

SECTION 076200 - SHEET METAL FLASHING AND TRIM

SECTION 077129 - MANUFACTURED ROOF EXPANSION JOINTS

SECTION 077200 - ROOF ACCESSORIES

SECTION 077273 - VEGETATED ROOF SYSTEMS

SECTION 078100 - APPLIED FIREPROOFING

SECTION 078123 - INTUMESCENT FIREPROOFING

SECTION 078413 - PENETRATION FIRESTOPPING

SECTION 078443 - JOINT FIRESTOPPING

SECTION 079200 - JOINT SEALANTS

SECTION 079219 - ACOUSTICAL JOINT SEALANTS

SECTION 079513.13 - INTERIOR EXPANSION JOINT COVER ASSEMBLIES

SECTION 079513.16 - EXTERIOR EXPANSION JOINT COVER ASSEMBLIES

Volume 2

DIVISION 08 – OPENINGS

SECTION 081113 - HOLLOW METAL DOORS AND FRAMES

SECTION 081216 - ALUMINUM FRAMES

SECTION 081416 - FLUSH WOOD DOORS

SECTION 081473 - SLIDING WOOD DOORS

SECTION 083113 - ACCESS DOORS AND FRAMES

SECTION 083313 - COILING COUNTER DOORS

SECTION 083323 - OVERHEAD COILING DOORS

SECTION 083343 - OVERHEAD COILING SMOKE CURTAINS

TABLE OF CONTENTS TOC - 5

SECTION 083516 - SIDE-FOLDING SECURITY GRILLES

SECTION 084123 - INTERIOR ALUMINUM-FRAMES ENTRANCES AND STOREFRONTS

SECTION 084126 - ALL-GLASS ENTRANCES

SECTION 084229.23 - SLIDING AUTOMATIC ENTRANCES

SECTION 084243 - INTENSIVE CARE UNIT/CRITICAL CARE UNIT (ICU/CCU)

ENTRANCES

SECTION 084313 - ALUMINUM-FRAMED STOREFRONTS

SECTION 084413 - GLAZED ALUMINUM CURTAIN WALLS

SECTION 085619 - PASS WINDOWS

SECTION 086200 - UNIT SKYLIGHTS

SECTION 087100 - DOOR HARDWARE

SECTION 088000 - GLAZING

SECTION 088113 - DECORATIVE GLASS GLAZING

SECTION 088300 - MIRRORS

SECTION 088813 - FIRE-RATED GLAZING

DIVISION 09 – FINISHES

SECTION 090561.13 - MOISTURE VAPOR EMISSION CONTROL

SECTION 092116.23 - GYPSUM BOARD SHAFT WALL ASSEMBLIES

SECTION 092216 - NON-STRUCTURAL METAL FRAMING

SECTION 092900 - GYPSUM BOARD

SECTION 093013 - CERAMIC TILING

SECTION 095113 - ACOUSTICAL PANEL CEILINGS

SECTION 095423 - LINEAR METAL CEILINGS

SECTION 095446 - ACOUSTICAL BAFFLE SYSTEM

SECTION 096513 - RESILIENT BASE AND ACCESSORIES

SECTION 096516 - RESILIENT SHEET FLOORING

SECTION 096519 - RESILIENT TILE FLOORING

SECTION 096566 - RESILIENT ATHLETIC FLOORING

SECTION 096623 - RESINOUS MATRIX TERRAZZO FLOORING

SECTION 096723 - RESINOUS FLOORING

SECTION 096813 - TILE CARPETING

SECTION 097200 - WALL COVERINGS

SECTION 097723 - FABRIC-WRAPPED PANELS

SECTION 098316 - ACOUSTICAL CEILING INSULATION

SECTION 098433 - SOUND ABSORBING WALL UNITS

SECTION 099113 - EXTERIOR PAINTING

TABLE OF CONTENTS TOC - 6

SECTION 099123 - INTERIOR PAINTING

SECTION 099600 - HIGH-PERFORMANCE COATINGS

SECTION 099600 - HIGH-PERFORMANCE COATINGS - WWTP

SECTION 099713 - COATINGS FOR WELDED STEEL WATER STORAGE TANK

DIVISION 10 – SPECIALTIES

SECTION 101100 - VISUAL DISPLAY UNITS

SECTION 101400 - SIGNAGE

SECTION 101400.01 - IDENTIFYING DEVICES

SECTION 102113.14 - STAINLESS-STEEL TOILET COMPARTMENTS

SECTION 102123 - CUBICLE CURTAINS AND TRACK

SECTION 102239 - FOLDING PANEL PARTITIONS

SECTION 102600 - WALL AND DOOR PROTECTION

SECTION 102800 - TOILET, BATH, AND LAUNDRY ACCESSORIES

SECTION 103100 - MANUFACTURED FIREPLACES

SECTION 104352 - FIRST AID AND SAFETY EQUIPMENT

SECTION 104413 - FIRE PROTECTION CABINETS

SECTION 104416 - FIRE EXTINGUISHERS

SECTION 105113 - METAL LOCKERS

SECTION 107516 - GROUND-SET FLAGPOLES

SECTION 108219 - EXTERIOR SOUND PANELS

DIVISION 11 – EQUIPMENT

SECTION 110800 - EQUIPMENT COMMISSIONING

SECTION 111313 - LOADING DOCK BUMPERS

SECTION 111316 - LOADING DOCK SEALS

SECTION 111319 - STATIONARY LOADING DOCK EQUIPMENT

SECTION 111326 - LOADING DOCK LIGHTS

SECTION 114000 - FOODSERVICE EQUIPMENT

SECTION 117000 - HEALTHCARE EQUIPMENT

SECTION 117100 - MEDICAL STERILIZING EQUIPMENT

SECTION 117311 - PATIENT LIFTS

SECTION 118129 - FACILITY FALL PROTECTION

SECTION 118201 - HYDRAULIC CART TIPPER

SECTION 118226 - FACILITY WASTE COMPACTORS

TABLE OF CONTENTS TOC - 7

DIVISION 12 – FURNISHINGS

SECTION 122413 - ROLLER WINDOW SHADES

SECTION 123553 - GENERAL REQUIREMENTS FOR LABORATORY CASEWORK AND

FUME HOODS

SECTION 123553.03 - ADAPTABLE LABORATORY CASEWORK SYSTEMS

SECTION 123553.19 - WOOD LABORATORY CASEWORK

SECTION 123570 - HEALTHCARE CASEWORK

SECTION 123623.13 - PLASTIC-LAMINATE-CLAD COUNTERTOPS

SECTION 123661.16 - SOLID SURFACING COUNTERTOPS

SECTION 123661.19 - QUARTZ AGGLOMERATE COUNTERTOPS

SECTION 124816 - ENTRANCE FLOOR GRILLES

SECTION 126100 - FIXED UPHOLSTERED SEATING

DIVISION 13 - SPECIAL CONSTRUCTION

SECTION 131200 - ALUMINUM ROOFTOP HELISTOPS

SECTION 131224 - EXTERIOR WATER FEATURE

SECTION 133419 - METAL BUILDING SYSTEMS

SECTION 134900 - RADIATION PROTECTION

SECTION 134920 - RFI/EMI SHIELDING

DIVISION 14 - CONVEYING EQUIPMENT

SECTION 142100 - ELECTRIC TRACTION ELEVATORS

SECTION 149200 - PNEUMATIC TUBE SYSTEM – 6 INCH

Volume 3

DIVISION 21 - FIRE SUPPRESSION

SECTION 210533 - HEAT TRACING FOR FIRE-SUPPRESSION PIPING

SECTION 210800 - FIRE SUPPRESSION SYSTEMS COMMISSIONING

SECTION 211300 - FIRE SPRINKLER AND STANDPIPE SYSTEMS

SECTION 213000 - FIRE PUMPS, PUMP CONTROLLERS, AND

OTHER APPURTENANCES

TABLE OF CONTENTS TOC - 8

DIVISION 22 – PLUMBING

SECTION 220513 - COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT

SECTION 220516 - EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING

SECTION 220517 - SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

SECTION 220517 - SLEEVES AND SLEEVE SEALS PLUMBING PIPING-WWTP

SECTION 220518 - ESCUTCHEONS FOR PLUMBING PIPING

SECTION 220518 - ESCUTCHEONS FOR PLUMBING PIPING - WWTP

SECTION 220519 - METERS AND GAGES FOR PLUMBING PIPING

SECTION 220519 - METERS AND GAGES FOR PLUMBING PIPING - WWTP

SECTION 220523.12 - BALL VALVES FOR PLUMBING PIPING

SECTION 220523.12 - BALL VALVES FOR PLUMBING PIPING - WWTP

SECTION 220523.13 - BUTTERFLY VALVES FOR PLUMBING PIPING

SECTION 220523.14 - CHECK VALVES FOR PLUMBING PIPING

SECTION 220523.14 - CHECK VALVES FOR PLUMBING PIPING - WWTP

SECTION 220523.15 - GATE VALVES FOR PLUMBING PIPING

SECTION 220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND

EQUIPMENT

SECTION 220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND

EQUIPMENT - WWTP

SECTION 220533 - HEAT TRACING FOR PLUMBING PIPING

SECTION 220548 - VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND

EQUIPMENT

SECTION 220548 - VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND

EQUIPMENT - WWTP

SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT–

SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT - WWTP

SECTION 220716 - PLUMBING EQUIPMENT INSULATION

SECTION 220719 - PLUMBING PIPING INSULATION

SECTION 220719 - PLUMBING PIPING INSULATION - WWTP

SECTION 220800 - PLUMBING SYSTEMS COMMISSIONING

SECTION 221113 - FACILITY WATER DISTRIBUTION PIPING

SECTION 221116 - DOMESTIC WATER PIPING

SECTION 221116 - DOMESTIC WATER PIPING - WWTP

SECTION 221117 - RECLAIMED-WATER PIPING

SECTION 221119 - DOMESTIC WATER PIPING SPECIALTIES

SECTION 221119 - DOMESTIC WATER PIPING SPECIALTIES - WWTP

SECTION 221123 - DOMESTIC WATER PUMPS

SECTION 221123 - DOMESTIC WATER PUMPS - WWTP

SECTION 221123.13 - DOMESTIC-WATER PACKAGED BOOSTER PUMPS

TABLE OF CONTENTS TOC - 9

SECTION 221123.13 - DOMESTIC-WATER PACKAGED BOOSTER PUMPS - WWTP

SECTION 221316 - SANITARY WASTE AND VENT PIPING

SECTION 221316 - SANITARY WASTE AND VENT PIPING - WWTP

SECTION 221323 - SANITARY WASTE INTERCEPTORS

SECTION 221413 - FACILITY STORM DRAINAGE PIPING

SECTION 221423 - STORM DRAINAGE PIPING SPECIALTIES

SECTION 221429 - SUMP PUMPS

SECTION 221429 - SUMP PUMPS - WWTP

SECTION 223100 - DOMESTIC WATER SOFTENERS

SECTION 223200 - DOMESTIC WATER FILTRATION EQUIPMENT

SECTION 223300 - ELECTRIC, DOMESTIC-WATER HEATERS

SECTION 223300 - ELECTRIC, DOMESTIC-WATER HEATERS - WWTP

SECTION 224213.13 - COMMERCIAL WATER CLOSETS

SECTION 224213.13 - COMMERCIAL WATER CLOSETS - WWTP

SECTION 224213.16 - COMMERCIAL URINALS

SECTION 224213.16 - COMMERCIAL URINALS - WWTP

SECTION 224216.13 - COMMERCIAL LAVATORIES

SECTION 224216.13 - COMMERCIAL LAVATORIES - WWTP

SECTION 224216.16 - COMMERCIAL SINKS

SECTION 224216.16 - COMMERCIAL SINKS - WWTP

SECTION 224223 - COMMERCIAL SHOWER

SECTION 224223 - COMMERCIAL SHOWER - WWTP

SECTION 224300 - HEALTHCARE PLUMBING FIXTURES

SECTION 224500 - EMERGENCY PLUMBING FIXTURES

SECTION 224500 - EMERGENCY PLUMBING FIXTURES - WWTP

SECTION 224700 - DRINKING FOUNTAINS AND WATER COOLERS

SECTION 226113 - COMPRESSED-AIR PIPING FOR LABORATORY AND HEALTHCARE

FACILITIES

SECTION 226119 - COMPRESSED-AIR EQUIPMENT FOR LABORATORY AND

HEALTHCARE FACILITIES

SECTION 226213 - VACUUM PIPING FOR LABORATORY AND HEALTHCARE

FACILITIES

SECTION 226219 - VACUUM EQUIPMENT FOR LABORATORY AND HEALTHCARE

FACILITIES

SECTION 226313 - GAS PIPING FOR LABORATORY AND HEALTHCARE FACILITIES

TABLE OF CONTENTS TOC - 10

SECTION 226400 - MEDICAL GAS ALARMS

SECTION 226713 - PROCESSED WATER PIPING FOR LABORATORY AND

HEALTHCARE FACILITIES

SECTION 226719 - PROCESSED WATER EQUIPMENT FOR LABORATORY AND

HEALTHCARE FACILITIES

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

SECTION 230130.51 - HVAC AIR-DISTRIBUTION SYSTEM CLEANING

SECTION 230513 - COMMON MOTOR REQUIREMENTS FOR HVAC AND PLUMBING

EQUIPMENT

SECTION 230513 - COMMON MOTOR REQUIREMENTS FOR HVAC AND PLUMBING

EQUIPMENT - WWTP

SECTION 230516 - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

SECTION 230517 - SLEEVES AND SLEEVE SEALS FOR HVAC AND PLUMBING PIPING

SECTION 230518 - ESCUTCHEONS FOR HVAC PIPING

SECTION 230519 - METERS AND GAGES FOR HVAC PIPING

SECTION 230523 - GENERAL-DUTY VALVES FOR HVAC PIPING

SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT -

WWTP

SECTION 230548 - VIBRATION AND SEISMIC CONTROLS FOR HVAC

SECTION 230548 - VIBRATION AND SEISMIC CONTROLS FOR HVAC - WWTP

SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT - WWTP

SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC

SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC - WWTP

SECTION 230713 - DUCT INSULATION

SECTION 230713 - DUCT INSULATION - WWTP

SECTION 230716 - HVAC EQUIPMENT INSULATION

SECTION 230716 - HVAC EQUIPMENT INSULATION - WWTP

SECTION 230719 - HVAC PIPING INSULATION

SECTION 230800 - HVAC SYSTEMS COMMISSIONING

SECTION 230900 - INSTRUMENTATION AND CONTROL FOR HVAC

SECTION 231113 - FACILITY FUEL-OIL PIPING

SECTION 231126 - FACILITY LIQUEFIED-PETROLEUM GAS PIPING

SECTION 232113 - HYDRONIC PIPING

SECTION 232116 - HYDRONIC PIPING SPECIALTIES

SECTION 232123 - HYDRONIC PUMPS

SECTION 2323000 - REFRIGERANT PIPING

TABLE OF CONTENTS TOC - 11

SECTION 232513 - WATER TREATMENT FOR CLOSED-LOOP HYDRONIC SYSTEMS

SECTION 233113 - METAL DUCTS

SECTION 233113 - METAL DUCTS - WWTP

SECTION 233300 - AIR DUCT ACCESSORIES

SECTION 233300 - AIR DUCT ACCESSORIES - WWTP

SECTION 233416 - CENTRIFUGAL HVAC FANS

SECTION 233423 - HVAC POWER VENTILATORS

SECTION 233423 - HVAC POWER VENTILATORS - WWTP

SECTION 233433 - AIR CURTAINS

SECTION 233600 - AIR TERMINAL UNITS

SECTION 233713 - DIFFUSERS, REGISTERS, AND GRILLES

SECTION 233713 - DIFFUSERS, REGISTERS, AND GRILLES - WWTP

SECTION 233723 - HVAC GRAVITY VENTILATORS

SECTION 234100 - PARTICULATE AIR FILTRATION

SECTION 234200 - GAS-PHASE AIR FILTRATION

SECTION 235213 - ELECTRIC BOILERS

SECTION 235700 - HEAT EXCHANGERS FOR HVAC

SECTION 236423.13 - AIR-COOLED, SCROLL WATER CHILLERS

SECTION 236423.14 - AIR SOURCE CHILLER-HEATER

SECTION 236426 - AIR-COOLED CENTRIFUGAL WATER CHILLERS

SECTION 237200 - AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

SECTION 237323 - CUSTOM OUTDOOR CENTRAL-STATION AIR-HANDLING UNITS

SECTION 237416.11 - PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING

UNITS

SECTION 237416.11 - PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING

UNITS - WWTP

SECTION 238123.12 - LARGE CAPACITY (7 TONS (25 KW AND LARGER), COMPUTER-

ROOM AIR-CONDITIONERS

SECTION 238123.13 - COMPUTER-ROOM AIR-CONDITIONERS

SECTION 238126 - SPLIT-SYSTEM AIR-CONDITIONERS

SECTION 238126 - SPLIT-SYSTEM AIR-CONDITIONERS - WWTP

SECTION 238214 - CHILLED BEAMS

SECTION 238216 - AIR COILS

SECTION 238219 - FAN COIL UNITS

SECTION 238239 - UNIT HEATERS

SECTION 238239 - UNIT HEATERS - WWTP

SECTION 238316 - RADIANT-HEATING HYDRONIC PIPING

SECTION 238413 - HUMIDIFIERS

SECTION 238610 - BI-POLAR IONIZATION AIR PURIFICATION SYSTEM

TABLE OF CONTENTS TOC - 12

DIVISION 25 - INTEGRATED AUTOMATION

NOT APPLICABLE

Volume 4

DIVISION 26 – ELECTRICAL

SECTION 260400 - COMMON WORK RESULTS FOR ELECTRICAL

SECTION 260400 - COMMON WORK RESULTS FOR ELECTRICAL - WWTP

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

– WWTP

SECTION 260523 - CONTROL-VOLTAGE ELECTRICAL POWER CABLES

SECTION 260523 - CONTROL-VOLTAGE ELECTRICAL POWER CABLES - WWTP

SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS - WWTP

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS - WWTP

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS - WWTP

SECTION 260536 - CABLE TRAYS FOR ELECTRICAL SYSTEMS - WWTP

SECTION 260539 - UNDERFLOOR RACEWAYS FOR ELECTRICAL SYSTEMS

SECTION 260543 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL

SYSTEMS - WWTP

SECTION 260543 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL

SYSTEMS-WWTP - M-M

SECTION 260544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND

CABLING

SECTION 260544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND

CABLING - WWTP

SECTION 260548.16 - SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION 260548.16 - SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS - WWTP

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS - WWTP

SECTION 260573.13 - OVERCURRENT PROTECTIVE DEVICE SHORT-CIRCUIT STUDY

SECTION 260573.13 - OVERCURRENT PROTECTIVE DEVICE SHORT-CIRCUIT STUDY -

WWTP

SECTION 260573.16 - OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

TABLE OF CONTENTS TOC - 13

SECTION 260573.16 - OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY -

WWTP

SECTION 260573.19 - OVERCURRENT PROTECTIVE DEVICE ARC-FLASH STUDY

SECTION 260573.19 - OVERCURRENT PROTECTIVE DEVICE ARC-FLASH STUDY –

WWTP

SECTION 260800 - ELECTRICAL SYSTEMS COMMISSIONING

SECTION 260913 - ELECTRICAL POWER MONITORING AND CONTROL

SECTION 260913 - ELECTRICAL POWER MONITORING AND CONTROL - WWTP

SECTION 260923 - LIGHTING CONTROL DEVICES

SECTION 260923 - LIGHTING CONTROL DEVICES - WWTP

SECTION 260943 - NETWORK LIGHTING CONTROLS

SECTION 260943.23 - RELAY-BASED LIGHTING CONTROLS

SECTION 262213 - LOW-VOLTAGE DISTRIBUTION TRANSFORMERS

SECTION 262213 - LOW-VOLTAGE DISTRIBUTION TRANSFORMERS - WWTP

SECTION 262300 - LOW-VOLTAGE SWITCHGEAR

SECTION 262313 - PARALLELING LOW-VOLTAGE SWITCHGEAR

SECTION 262413 - SWITCHBOARDS

SECTION 262413 - SWITCHBOARDS - WWTP

SECTION 262416 - PANELBOARDS

SECTION 262416 - PANELBOARDS - WWTP

SECTION 262419 - MOTOR CONTROL CENTERS - WWTP

SECTION 262713 - ELECTRICITY METERING

SECTION 262713 - ELECTRICITY METERING - WWTP

SECTION 262726 - WIRING DEVICES

SECTION 262726 - WIRING DEVICES - WWTP

SECTION 262743 - ELECTRIC-VEHICLE SERVICE EQUIPMENT - AC LEVEL 1 AND

LEVEL 2

SECTION 262813 - FUSES

SECTION 262813 - FUSES - WWTP

SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS

SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS - WWTP

SECTION 262923 - VARIABLE-FREQUENCY MOTOR CONTROLLERS

SECTION 262923 - VARIABLE-FREQUENCY MOTOR CONTROLLERS - WWTP

SECTION 263100 - PHOTOVOLTAIC COLLECTORS

SECTION 263213 - ENGINE GENERATORS

SECTION 263213 - ENGINE GENERATORS - WWTP

SECTION 263233 - ROTARY UNINTERRUPTIBLE POWER UNITS

SECTION 263353 - STATIC UNINTERRUPTIBLE POWER SUPPLY

SECTION 263353 - STATIC UNINTERRUPTIBLE POWER SUPPLY - WWTP

TABLE OF CONTENTS TOC - 14

SECTION 263600 - TRANSFER SWITCHES

SECTION 263600 - TRANSFER SWITCHES - WWTP

SECTION 263650 - GENERATOR DOCKING STATIONS

SECTION 264113 - LIGHTNING PROTECTION FOR STRUCTURES

SECTION 264313 - SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER

CIRCUITS - WWTP

SECTION 264313 - SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER

CIRCUITS-WWTP

SECTION 265100 - INTERIOR LIGHTING

SECTION 265100 - INTERIOR LIGHTING - WWTP

SECTION 265600 - EXTERIOR LIGHTING

SECTION 265600 - EXTERIOR LIGHTING - WWTP

DIVISION 27 – COMMUNICATIONS

SECTION 270413 - COMMON SUBMITTAL REQUIREMENTS FOR COMMUNICATIONS

SECTION 270526 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS

SECTION 270528 - PATHWAYS FOR COMMUNICATIONS SYSTEMS

SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

SECTION 270544 - SLEEVES AND SLEEVE SEALS FOR COMMUNICATIONS

PATHWAYS AND CABLING

SECTION 270553 - IDENTIFICATION FOR COMMUNICATIONS SYSTEMS

SECTION 270800 - COMMUNICATIONS SYTEMS COMMISSIONING

SECTION 271100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS

SECTION 271300 - COMMUNICATIONS BACKBONE CABLING

SECTION 271500 - COMMUNICATIONS HORIZONTAL CABLING

SECTION 272100 - DATA COMMUNICATIONS NETWORK EQUIPMENT

SECTION 273226 - TWO-WAY COMMUNICATIONS SYSTEM

SECTION 274116 - INTEGRATED AUDIOVISUAL SYSTEMS AND EQUIPMENT

SECTION 275113 - PAGING SYSTEMS

SECTION 275119 - SOUND MASKING SYSTEMS

SECTION 275123 - EMERGENCY HELP POINTS AND CALL BOXES

SECTION 275223 - NURSE CALL AND CODE BLUE SYSTEMS

SECTION 275313 - SYNCHRONIZED CLOCK SYSTEM

SECTION 275316 - PATIENT, INFANT, AND EQUIPMENT RFID TRACKING SYSTEMS

SECTION 275319 - DISTRIBUTED ANTENNA STSYTEMS

TABLE OF CONTENTS TOC - 15

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

SECTION 280413 - COMMON SUBMITTAL REQUIREMENTS FOR ELECTRONIC SAFETY

AND SECURITY

SECTION 280513 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND

SECURITY

SECTION 280526 - GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND

SECURITY

SECTION 280528 - PATHWAYS FOR ELECTRONIC SAFETY AND SECURITY

SECTION 280544 - SLEEVES AND SLEEVE SEALS FOR ELECTRONIC SAFETY AND

SECURITY PATHWAYS AND CABLING

SECTION 280800 - ELECTRONIC SAFETY AND SECURITY SYSTEMS COMMISSIONING

SECTION 281300 – ACCESS CONTROL

SECTION 281600 - INTRUSION DETECTION SYSTEM

SECTION 282300 - VIDEO SURVEILLANCE

SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

SECTION 285000 - SECURITY CONTROL SYSTEM

Volume 5

DIVISION 31 – EARTHWORK

SECTION 312213 - ROUGH GRADING

SECTION 312300 - EXCAVATION AND FILL

SECTION 312316.16 - STRUCTURAL EXCAVATION FOR MINOR STRUCTURES

SECTION 312323.13 - BACKFILL

SECTION 312333 - TRENCHING AND BACKFILL

SECTION 312500 - EROSION AND SEDIMENTATION CONTROLS

SECTION 313116 - TERMITE CONTROL

SECTION 316329 - DRILLED CONCRETE PIERS AND SHAFTS

TABLE OF CONTENTS TOC - 16

DIVISION 32 - EXTERIOR IMPROVEMENTS

SECTION 321123 - AGGREGATE BASE COURSES

SECTION 321216 - ASPHALT PAVING

SECTION 321223 - IMPRINTED ASPHALT

SECTION 321313 - CONCRETE PAVING

SECTION 321315 - CONCRETE WALKS, CURBS AND GUTTERS

SECTION 321316 - DECORATIVE CONCRETE PAVING

SECTION 321373 - CONCRETE PAVING JOINT SEALANTS

SECTION 321716 - MANUFACTURED TRAFFIC-CALMING DEVICES

SECTION 321723 - PAVEMENT MARKINGS

SECTION 323113 - CHAIN LINK FENCES AND GATES

SECTION 323119 - DECORATIVE METAL FENCES AND GATES

SECTION 323213 - CAST-IN-PLACE CONCRETE RETAINING WALLS

SECTION 324020 - PIPE AND TUBE RAILINGS

SECTION 328000 - IRRIGATION SYSTEM

SECTION 329100 - SOIL PREPARATION (TOPSOIL)

SECTION 329220 - NATIVE SEEDING

SECTION 329300 - EXTERIOR PLANTINGS

DIVISION 33 - UTILITIES

SECTION 331000 - WATER UTILITIES

SECTION 331623 - WELDED STEEL WATER STORAGE TANK AND FOUNDATION

SECTION 333000 - SANITARY SEWERAGE UTILITIES

SECTION 333213 - PACKAGE LIFT STATION

SECTION 333723 - SLIDE GATE

SECTION 334213 - STORMWATER CULVERTS AND DRAINAGE FACILITIES

DIVISION 34 - TRANSPORTATION

SECTION 340114 - SIGNING AND MARKING

SECTION 344113 - TRAFFIC SIGNALS

SECTION 347100 - ADOT REQUIREMENTS

SECTION 347113 - VEHICLE BARRIERS

SECTION 347116 - IMPACT ATTENUATING DEVICES

TABLE OF CONTENTS TOC - 17

DIVISION 40 - PROCESS INTERCONNECTIONS

SECTION 400205 - PIPING SCHEDULE

SECTION 400510 - PIPING - GENERAL

SECTION 400510.03 - DPS - EPOXY LINED DUCTILE IRON PIPE AND FITTINGS

SECTION 400510.04 - DPS - MILL TYPE STEEL PIPE AND FITTINGS (GENRAL SERVICE)

SECTION 400510.09 - DPS STAINLESS STEEL PIPE AND FITTINGS

SECTION 400510.12 - DPS - POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS

SECTION 400510.13 - DPS - CHLORINATED POLYVINYL CHLORIDE (CPVC) PIPE

AND FITTINGS

SECTION 400510.30 - DPS HIGH DENSITY POLYETHYLENE (HDPE) PIPE

AND TUBING

SECTION 400533 - MANUAL VALVES

SECTION 400555 - SELF CONTAINED AUTOMATIC VALVES

SECTION 400557 - POWER OPERATED GATE AND VALVE ASSEMBLIES

SECTION 406110 - PROCESS INSTRUMENTATION AND CONTROLS SYSTEM (PICS)

GENERAL

SECTION 406115 - PICS SCOPE OF WORK

SECTION 406116 - PICS ENCLOSURES

SECTION 406120 - PROCESS CONTROL NARRATIVES (PCNs)

SECTION 406120.01- PCN-INFLUENT PUMP STATION

SECTION 406120.02 - PCN-EQ BASIN TRANSFER PUMP STATION

SECTION 406120.03 - PCN-AEORBIC SLUDGE DIGESTER

SECTION 406120.04 - PCN-EFFLUENT PUMPING SYSTEM

SECTION 406121 - PICS PROCESS TAPS AND PRIMARY ELEMENTS

SECTION 406124 - PICS INSTRUMENTATION CABLE

SECTION 406127 - PICS INDUSTRIAL ETHERNET NETWORK

SECTION 406128 - PICS MISCELLANEOUS EQUIPMENT

SECTION 406140 - PICS INSTRUMENTATION REQUIREMENTS

SECTION 406160 - PICS PLC I-O INDEX

SECTION 406171 - INSTRUMENT SPECIFICATIONS

SECTION 406176 - PLANT CONTROL SYSTEM (PCS) SOFTWARE REQUIREMENTS

SECTION 406177 - PLANT CONTROL SYSTEM (PCS) HARDWARE AND SOFTWARE

SECTION 406180 - PICS TESTING, CALIBRATION, AND INSTALLATION VERIFICATION

SECTION 406181 - PICS COMMISSIONING AND START-UP

SECTION 406182 - PICS PERSONNEL TRAINING

SECTION 406191- PICS SPARE PARTS

TABLE OF CONTENTS TOC - 18

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

SECTION 412213.17 - DAVIT AND GANTRY CRANES

SECTION 413313 - OVERHEAD TRAVELING CRANES

SECTION 413313.01 - DETAIL SPECIFICATION - TREATMENT PLANT BRIDGE CRANE

DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE

EQUIPMENT

SECTION 431030 - SUBMERSIBLE NON-CLOG CENTIFUGAL PUMPS

SECTION 431111 - BLOWERS

SECTION 432256 - SUBMERSIBLE MIXERS

SECTION 432321 - RECLAIMED EFFLUENT PUMPING SYSTEMS

SECTION 432331 - NPW PUMPING SYSTEMS

SECTION 432331.01 - PCN NON-POTABLE WATER SYSTEM

SECTION 432332 - RECLAIMED WATER PUMPING SYSTEM

SECTION 432358 - POSITIVE DISPLACEMENT ROTARY LOBE PUMPS

SECTION 433230 - ODOR CONTROL BIOTRICKLING SYSTEM

SECTION 433269 - CHEMICAL FEED SKID – PERISTALTIC PUMPS

SECTION 434010 - CHEMICAL STORAGE AND CONTAINMENT

DIVISION 46 – WATER AND WASTEWATER EQUIPMENT

SECTION 460754 - MEMBRANE BIOREACTOR PACKAGE PLANT SYSTEM

SECTION 460754.01 - DES-SKID COMPONENTS

SECTION 460754.02 - DES-SUBMERSIBLE MIXERS

SECTION 460754.03 - DES-FLEXIBLE MEMBRANE DIFFUSERS

SECTION 460754.04 - DES-SUBMERSIBLE PUMPS

SECTION 460754.05 - DES SELF-PRIMING CENTRIFUGAL PUMPS

SECTION 460754.06 - DES-REGENERATIVE BLOWERS

SECTION 460754.07 - DES-PROCESS INSTRUMENTATION

SECTION 460754.08 - PACKAGE MBR SYSTEM - LAYOUT DRAWINGS

SECTION 460754.09 - PACKAGE MBR SYSTEM - P&ID DDRAWINGS

SECTION 460754.10 - DES-CHEMICAL FEED SKIDS

SECTION 461155 - SLUDGE DEWATERING SYSTEM - GENERAL

SECTION 461155.01 - DES VOLUTE PRESS

SECTION 461155.02 - DES POLYMER BLENDING SYSTEM

SECTION 461155.03 - DES SCREW CONVEYOR

SECTION 461155.04 - PCN-SLUDGE DEWATERING SYSTEM

SECTION 462113 - SCREENING AND GRIT REMOVAL SYSTEM - GENERAL

TABLE OF CONTENTS TOC - 19

SECTION 462113.1 - DES - COARSE SCREENING AND GRIT REMOVAL PACKAGE

SYSTEM

SECTION 462113.2 - DES - FINE SCREENING

SECTION 462113.3 - DES - MANUAL BAR SCREEN

SECTION 465035 - WASTEWATER ULTRAVIOLET DISINFECTION SYSTEM

SECTION 465035.01 - DES-HOSPITAL WASTEWATER ULTRAVIOLET DISINFECTION

SYSTEM

SECTION 465035.02 - DES HON-DAH WASTEWATER ULTRAVIOLET DISINFECTION

SYSTEM

SECTION 465131 - AERATION EQUIPMENT – GENERAL

SECTION 465131.01 - DES-FINE BUBBLE AERATION

SECTION 465131.02 - DES-COARSE BUBBLE AERATION

END OF TABLE OF CONTENTS

SOLICITATION, CONTRACT LINE ITEM NUMBER

SCHEDULE

001000 - 1

SECTION 001000 – SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

INSTRUCTIONS FOR PROCUREMENT 002000 - 1

SECTION 002000 – INSTRUCTIONS FOR PROCUREMENT

INSTRUCTIONS 002100 - 1

SECTION 002100 – INSTRUCTIONS

INSTRUCTIONS TO BIDDERS 002113 - 1

SECTION 002113 – INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO PROPOSERS 002116 - 1

SECTION 002116 – INSTRUCTIONS TO PROPOSERS

SUPPLEMENTARY INSTRUCTIONS 002200 - 1

SECTION 002200 – SUPPLEMENTARY INSTRUCTIONS

SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS 002216 - 1

SECTION 002216 – SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS

AVAILABLE INFORMATION 003000 - 1

SECTION 003000 – AVAILABLE INFORMATION

PROCUREMENT FORMS AND SUPPLEMENTS 004000 - 1

SECTION 004000 – PROCUREMENT FORMS AND SUPPLEMENTS

BID BOND FORM 004300 - 1

SECTION 004300 – BID BOND FORM

PROPOSED CONSTRUCTION SCHEDULE FORM 004373 - 1

SECTION 004373 – PROPOSED CONSTRUCTION SCHEDULE FORM

REPRESENTATION AND CERTIFICATIONS 004500 - 1

SECTION 004500 – REPRESENTATIONS AND CERTIFICATIONS

CONTRACTING FORMS AND SUPPLEMENTS 005000 - 1

SECTION 005000 – CONTRACTING FORMS AND SUPPLEMENTS

NOTICE OF AWARD 005100 - 1

SECTION 005100 – NOTICE OF AWARD

AGREEMENT FORMS 005200 - 1

SECTION 005200 – AGREEMENT FORMS

PROJECT FORMS 006000 - 1

SECTION 006000 – PROJECT FORMS

BOND FORMS 006100 - 1

SECTION 006100 – BOND FORMS

CERTIFICATES 006200 - 1

SECTION 006200 – CERTIFICATES

CONDITIONS OF THE CONTRACT 007000 - 1

SECTION 007000 – CONDITIONS OF THE CONTRACT

CONTRACTING DEFINITIONS 007100 - 1

SECTION 007100 – CONTRACTING DEFINITIONS

GENERAL CONDITIONS 007200 - 1

SECTION 007200 – GENERAL CONDITIONS

SUPPLEMENTARY CONDITIONS 007300 - 1

SECTION 007300 – SUPPLEMENTARY CONDITIONS

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work performed by Owner.

5. Work under Owner's Separate Contracts.

6. Owner-furnished/Contractor-installed (OFCI) products.

7. Owner-furnished/Owner-installed (OFOI) products.

8. Contractor's use of site and premises.

9. Work restrictions.

10. Specification and Drawing conventions.

B. Related Requirements:

1. Section 013573 "Delegated Design Requirements and Procedures" for definitions, submittal procedures, responsibilities, and scheduling requirements associated with delegated design.

1.2 DEFINITIONS

A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.

1.3 PROJECT INFORMATION

A. Project Identification: IHS Whiteriver Hospital.

1. Project Location: 200 W. Hospital Drive, Whiteriver, Arizona 85941.

B. Owner: Indian Health Service, Two Renaissance Square, 40 North Central Avenue, Suite 601, Phoenix, Arizona 85004.

C. Architect: SmithGroup, 455 North Third Street, Phoenix, Arizona 85004.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:

1. The proposed new Whiteriver Hospital will consist of an approximately 407,000 gross square foot building. It will be a modern, technologically advanced facility with enough space and staff to provide an expanded level of health care services specifically designed to meet the health care needs of the American Indian and Alaskan Natives in the Whiteriver service unit. Scope shall include Civil, Landscape, Architectural, Structural, Mechanical, Plumbing, and Electrical; in compliance with the latest applicable building Codes and regulations. The new facility will be constructed to provide the best possible environment for care with emphasis placed on care and safety.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

SUMMARY 011000 - 2

C. The Engaging of Testing Agencies: All testing required here within is the responsibility of the Contractor, including but not limited to all references to "Owner testing agency", "Owner will engage a qualified testing agency....", et al.

1.5 PHASED CONSTRUCTION

A. Construct the Work in phases, with each phase substantially complete as indicated on the Drawings and as indicated below:

1. Phase 1 - New Hospital Construction, includes the following:

a. Civil: Enabling Infrastructure: Refer to all "Phase 1" labeled documents.

Temporary Parking

1) Reroute existing site water and sewer utilities

2) New ADOT driveways, loop road; and drive access reconfiguration of existing hospital to loop road.

3) Utility improvements beneath the roads noted above.

4) Selective demolition as required to enable the above.

5) New Visitor Parking (South).

b. Civil: New Hospital and Infrastructure Construction: Refer to all "Phase 1" labeled documents.

1) Utility campuses and accompanying infrastructure.

2) Remaining roadways and parking lot.

3) Pumphouse

c. Architectural: Refer to Sheets A1.00, A1.1.0d, and A1.1.1.

1) New Hospital

2) New Hospital Utility Campus

3) New Hon-Dah Utility Campus

d. Electrical:

1) Power: Refer to Sheet E1.1.P1

2) Lighting: Refer to Sheet E1.4

e. Fire Alarm: No work.

f. Landscape:

1) Overall Tree Plan: Refer to Sheet LP100.

2) Overall Hardscape Plan: Refer to Sheet LS100.

g. Note: Existing Helipad shall remain operational at all times.

h. Note: Existing Hospital shall remain operational at all times.

2. Phase 2 - Demolish Existing, includes the following (except where otherwise indicated):

a. Phase 2 shall not commence until Phase 1 is complete, to include the new hospital fully occupied and operational.

b. Civil: Existing Utility Infrastructure Demolition: Refer to all "Phase 2" labeled documents.

1) At existing Hospital

2) At Garret Building

3) Elsewhere where shown

c. Civil: New Construction: Refer to Refer to all "Phase 2" labeled documents.

1) Remaining parking lot construction.

d. Architectural: Refer to Sheets A1.1.1d and A1.1.2.

1) New North Parking

2) Wayfinding Signage

SUMMARY 011000 - 3

e. Electrical:

1) Power: Refer to Sheet E1.1.P2

2) Lighting: Refer to Sheet E1.5

f. Fire Alarm: Refer to sheet FA6.3

1) Connect the Utility Campuses, SSB, Admin, and Facility Maintenance building fire alarm systems to annunciate at Main Hospital Security Control Room.

g. Landscape:

1) Overall Tree Plan: Refer to Sheet LP100B.

2) Overall Hardscape Plan: Refer to Sheet LP100B.

h. Note: Existing Helipad shall remain operational throughout Phase 2 until decommissioned.

B. Before commencing the Work of each Phase, submit an updated copy of Contractor's construction schedule, showing the sequence, commencement and completion dates, and move-out and -in dates of Owner's personnel for all phases of the Work.

1.6 WORK PERFORMED BY OWNER

A. Cooperate fully with Owner, so work may be carried out smoothly, without interfering with or delaying Work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.

1.7 WORK UNDER OWNER'S SEPARATE CONTRACTS

A. Work with Separate Contractors: Cooperate fully with Owner's separate contractors, so work on those contracts may be carried out smoothly, without interfering with or delaying Work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under Owner's separate contracts.

B. Owner's Responsibilities: Owner will furnish products indicated and perform the following, as applicable:

1. Provide to Contractor Owner-reviewed Product Data, Shop Drawings, and

Samples.

2. Provide for delivery of Owner-furnished products to Project site.

3. Upon delivery, inspect, with Contractor present, delivered items.

a. If Owner-furnished products are damaged, defective, or missing, arrange for replacement.

4. Obtain manufacturer's inspections, service, and warranties.

5. Inform Contractor of earliest available delivery date for Owner-furnished products.

C. Contractor's Responsibilities: The Work includes the following, as applicable:

1. Designate delivery dates of Owner-furnished products in Contractor's construction schedule, utilizing Owner-furnished earliest available delivery dates.

2. Review Owner-reviewed Product Data, Shop Drawings, and Samples, noting discrepancies and other issues in providing for Owner-furnished products in the Work.

3. Receive, unload, handle, store, protect, and install Owner-furnished products.

4. Make building services connections for Owner-furnished products.

5. Protect Owner-furnished products from damage during storage, handling, and installation and prior to Substantial Completion.

6. Repair or replace Owner-furnished products damaged following receipt.

SUMMARY 011000 - 4

1.8 OWNER-FURNISHED/CONTRACTOR-INSTALLED (OFCI) PRODUCTS

A. Owner's Responsibilities: Owner will furnish products indicated and perform the following, as applicable:

1. Provide to Contractor Owner-reviewed Product Data, Shop Drawings, and

Samples.

2. Provide for delivery of Owner-furnished products to Project site.

3. Upon delivery, inspect, with Contractor present, delivered items.

4. If Owner-furnished products are damaged, defective, or missing, arrange for replacement.

5. Obtain manufacturer's inspections, service, and warranties.

6. Inform Contractor of earliest available delivery date for Owner-furnished products.

B. Contractor's Responsibilities: The Work includes the following, as applicable:

1. Designate delivery dates of Owner-furnished products in Contractor's construction schedule, utilizing Owner-furnished earliest available delivery dates.

2. Review Owner-reviewed Product Data, Shop Drawings, and Samples, noting discrepancies and other issues in providing for Owner-furnished products in the Work.

3. Receive, unload, handle, store, protect, and install Owner-furnished products.

4. Make building services connections for Owner-furnished products.

5. Protect Owner-furnished products from damage during storage, handling, and installation and prior to Substantial Completion.

6. Repair or replace Owner-furnished products damaged following receipt.

1.9 OWNER-FURNISHED/OWNER-INSTALLED (OFOI) PRODUCTS

A. The Owner will furnish and install products indicated.

1.10 CONTRACTOR'S USE OF SITE AND PREMISES

A. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits and Phases indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits on Use of Site: Confine construction operations to areas and area of work

Phases indicated.

2. Roadways, Driveways, Walkways, and Entrances: Keep roadways, driveways, loading areas, and entrances serving premises open, clear, and available at all times to Owner, Owner's employees, and emergency vehicles, unless indicated otherwise on the Drawings and as indicated otherwise below:

3. Do not use these areas for parking or for storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

c. The indicated Contractor Laydown Area for the duration of Phases 1 and 2 is part of the Base Bid. Voluntary Options will be considered. No spaces shall be used outside Phase 1 boundary.

SUMMARY 011000 - 5

4. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

5. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.

Repair damage caused by construction operations.

D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.11 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work to between 6 a.m. to 6 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services in accordance with requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted.

F. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

G. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Owner's representative.

1.12 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the

Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

SUMMARY 011000 - 6

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.

C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings and published as part of the U.S. National CAD Standard.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

OPTIONS 012300 - 1

SECTION 012300 - OPTIONS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for options.

1.2 DEFINITIONS

A. Option: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if the Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Options described in this Section are part of the Work only if enumerated in the

Agreement.

2. The cost or credit for each option is the net addition to or deduction from the

Contract Sum to incorporate options into the Work. No other adjustments are made to the Contract Sum.

1.3 PROCEDURES

A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the option into Project.

1. Include, as part of each option, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of alternate.

B. Execute accepted options under the same conditions as other Work of the Contract.

C. Schedule: A Part 3 "Schedule of Options" Article is included at the end of this Section.

Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.

PART 2 - PRODUCTS…