This is a Task Group Instruction (TGI) detailing work requirements for replacing deck covering in compartment 3-158-3-T on the USS SHOUP (DDG-86). The work involves removing existing rubber insulation (6 SF) and chemical-resistant flooring system (120 SF total), and installing new chemical-resistant flooring system (Type IV MIL-PRF-32584) in navy blue with white flake across first and second platforms. The work also includes treating 130 SF of deck plating and installing new compartment insulation (6 SF) made of anti-sweat polyimide on the outboard side bulkhead.

The document specifies procedures including compliance with various naval standards (009-26, 009-32, 009-11), notes potential asbestos hazards, and outlines SRF-JRMC provided services including crane operations, utilities, safety inspections, and QA inspections. The work falls under Project KC1, System 12321, with work dates to be determined per TGI POP List. The document was prepared by H. Ishikawa (Code 231A) and approved by R. Nanba on 19-DEC-2024, with T. Yaginuma serving as Zone Manager.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

08-JAN-2025 1321

20.14.15.2.9020 (September 2024) ICN: 38KC112307 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TRUNK 3-158-3-T DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC1 12321

CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 3-158-3-T

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

CC010732

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

ISHIKAWA, HIROTSUGU 231A 3152436152 19-DEC-2024

APPROVED BY: CODE: PHONE: DATE:

NANBA, RYOUSUKE 231A 3152436141 19-DEC-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

CC01-0732

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE 3-158-3-T 3 U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

123A2107

1. SCOPE/PURPOSE:

1.1 Title: Deck Covering in 3-158-3-T; replace

1.2 Location of Work:

1.2.1 Access Trunk (3-158-3-T)

1.3 Identification:

1.3.1 Quantity (6 SF), Rubber Insulation on Outboard Side Bulkhead in 3-158-3-T at 2nd Platform Level, height of 6 inches from deck, Frames between 158 and 171 [Existing]

Material: Form Rubber, NH Armaflex, 1/4 Inch Thickness

1.3.2 Quantity (120 SF in Total), Chemical-Resistant Floorings System [Existing] Remarks: The quantity is total amount of first platform and second platform

TGI Short Form

08-JAN-2025 1321

20.14.15.2.9020 (September 2024) (Continued) ICN: 38KC112307 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TRUNK 3-158-3-T DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC1 12321

CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 3-158-3-T

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

1.3.3 Quantity (120 SF in Total), Chemical-Resistant Floorings System

Specification: MIL-PRF-32584, Type IV Color: 706 Navy blue color coat with white flake Remarks: The quantity is total amount of first platform and second platform

1.3.4 Quantity (130 SF in Total), Deck Plating including vertical structural surface up to height of One inch from complete chemical-resistant floorings system level

Remarks : The area excepts where rubber insulation is installed.

1.3.5 Quantity (6 SF), Compartment Insulation on Outboard Side Bulkhead in 3-158-3-T at 2nd Platform Level, height of 6 inches from deck, Frames between 158 and 171

Material: Anti-Sweat, Polyimide, One Inch Thickness, MIL-DTL-24688, Type II Remarks : See Ref. No. 3 for material and details

1.4 Security Classification: None.

1.5 Initial Condition:

1.5.1 Potential Asbestos Hazard

1.6 Contractor work start date: See TGI POP List

1.7 Contractor work completion date: See TGI POP List

2. PROCEDURE:

2.1 Remove each existing rubber insulation listed in 1.3.1.

2.2 Accomplish the requirements of 009-26 of Ref. No. One, including Attachment C, for removal of each existing equipment listed in 1.3.2 and installation of each new equipment listed in 1.3.3.

2.2.1 Accomplish the requirements of 009-32 of Ref. No. One, including Table 3, Line(s) 6, Column(s) A, B, and D, for each area listed in 1.3.4. Primer must conform to MIL-PRF-23236, Type V, VI, or VII.

2.3 Accomplish the requirements of 009-11 of Ref. No. One to install each new compartment insulation listed in 1.3.5 in accordance with Ref. No. 3.

2.3.1 Accomplish the requirements of 009-32 of Ref. No. One for receiving surface and top surface where new insulation is installed.

2.4 Notes:

2.4.1 Planner: Code 231A H. Ishikawa, 243-6152

2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.4.3 JCN CC01-0732 is related to this TGI.

2.5 Government Furnished Material (GFM):

08-JAN-2025 1321

20.14.15.2.9020 (September 2024) (Continued) ICN: 38KC112307 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TRUNK 3-158-3-T DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC1 12321

CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 3-158-3-T

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

2.5.1 SRF-JRMC will provide GFM listed in the Material List.

2.6 SRF-JRMC will provide the following service work: (TGI No. 38KC112307S02)

2.6.1 [C740] Crane and crane rigging service.

2.6.2 [X99E] Utility service, electrical.

2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.6.5 [C133] QA inspection for (G) symbols.

08-JAN-2025 1321

20.14.15.2.9020 (September 2024) (Continued) ICN: 38KC112307 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TRUNK 3-158-3-T DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-86 USS SHOUP KC1 12321

CU PHASE TITLE: *F/O - REPLACE DECK COVERING IN 3-158-3-T

FOUO Pg 4 of 4

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N

3 PDD 635-ELM-

230114 SRF-JRMC Std ELM Sub Matl of Elastomeric Plstc Foam for Hull Insul

- Y ALL

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

001 M SOUND CO, ORDERED FOR

KTR

ORIG: C231A H. ISHIKAWA,

243-6152

9Q 5640 014548837 NA 4 N 43445061 2/SH

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38KC112307 KEY OP: A01