This document outlines the Additional Item Requirements (AIR) process for the NOAA SHIP FAIRWEATHER dry docking solicitation. The National Oceanic and Atmospheric Administration (NOAA) will use this process throughout contract performance to execute any AIRs. The contractor submits condition reports to the Contracting Officer's Representative and team. The COR issues a response and may require an AIR. For AIRs, the COR requests additional items from contracting and the contractor provides pricing within three days. Contracting negotiates with the contractor as needed and the Contracting Officer issues a notice to proceed once agreed. Consolidated modifications will memorialize authorized AIRs to reduce contract modifications.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA EASTERN ACQUISITION DIVISION (EAD)
Additional Item Requirements (AIR) Process for the Drydock Repairs of the
NOAA SHIP FAIRWEATHER:
Pursuant to CAR 1352.271-72 ADDITIONAL ITEM REQUIREMENTS (AIR) - GROWTH WORK (APR 2010), the following process shall be used throughout the performance of the contract to execute AIRs.
Exceptions to this process are expected throughout the period of performance (PoP) and will be addressed on a case by case basis.
1. Contractor submits Condition Found Report (CFR) to the Contracting Officer’s Representative (COR) and copies the Contracting Team (Contracting). For this contract, Contracting includes Contract Specialist (CS) Bridget Cofo and Contracting Officer (CO) Ashley Perry.
2. COR issues Condition Report Response (CRR) and sends it back to the Contractor and copies Contracting. The response will include:
a) acknowledgment of receipt of the Condition Report.
b) additional information and/or comments from the Government, if needed.
c) notice that an AIR will be issued, if needed.
3. If an AIR is required the COR will send the AIR form to Contracting ONLY. The AIR is an internal document from the COR to the Contracting Officer requesting to add an item to the requirement (contract). Not every AIR will have a related CFR as some represent additional requirements identified by the COR.
4. Unless Contracting has additional questions for the COR, the Contracting Team will issue a Request for Pricing (RFP) to the Contractor.
5. The Contractor shall respond to the AIR with a quotation for the additional work requested within three
(3) days of receipt of the AIR. Contractors shall provide quote to Contracting ONLY. Contractor response to AIR shall include an analysis of the requirements against the production chart and shall include the following additional information:
a. A firm statement concerning impacts to the production chart: This statement shall either confirm that the additional work can be accomplished within the current PoP, or it shall state that the additional work will affect the PoP completion date. In case of the latter, the quote shall note the primary and any secondary work items that would be affected, including an excerpt of the contractor’s planning production chart showing the impact to the project.
b. The contractor shall also provide an analysis and alternative proposal to maintain existing PoP, including such things as alternative procedures, accelerated and/or premium labor efforts, or any other solutions contractor may present to avoid contract PoP extensions.
6. Upon receipt of the quote from the Contractor, the quote will be reviewed by Contracting who will consult with the COR if necessary.
7. Negotiations may take place prior to accepting the pricing to address any issues/concerns that the Government has with the quote (omissions, justification of materials/hours, etc).
Attachment V
1305M223QNMAN0143
10. Once all aspects of the AIR have been negotiated, if necessary, and agreed by both the Contractor and Contracting, the Contracting Officer signs a Notice to Proceed (NTP).
11. Contracting distributes NTP, this AIR is now considered a part of the contract and work can start.
12. To reduce the amount of modifications to the contract, once a number of AIRs have been authorized through an NTP a consolidated modification will be issued memorializing the agreed to AIRs.