Attachment V - AIR Process_REV A.pdf
PDF 992 KB Posted
- Attached to
- NOAA SHIP FAIRWEATHER DRY DOCKING Federal contract opportunity
- Solicitation number
- 1305M223QNMAN0143
About this file
This document outlines the Additional Item Requirements (AIR) process for the NOAA SHIP FAIRWEATHER dry docking solicitation. The National Oceanic and Atmospheric Administration (NOAA) will use this process to execute additional requirements throughout contract performance. When a condition is found, the contractor submits a report to the Contracting Officer's Representative and team. The COR issues a response and may require an AIR. For AIRs, the COR requests addition from Contracting only. Contracting then issues a Request for Pricing to the contractor. The contractor must respond within three days with a quote, production impact analysis, and alternative proposals. Contracting reviews the quote with the COR if needed. Negotiations may occur, and if agreed, the Contracting Officer issues a Notice to Proceed authorizing the AIR work. Once several AIRs are approved, a consolidated modification will be issued.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF 30 AMENDMENT 0006.doc | DOC document | |
| 2019 Valve list NOAA Fairweather Dry docking.docx | DOCX document | |
| Attachment III - Past Performance Questionnaire_REV B.pdf | ||
| SF 30 AMENDMENT 0005.doc | DOC document | |
| SF 30 AMENDMENT 0004.doc | DOC document | |
| SF 30 AMENDMENT 0003.doc | DOC document | |
| SF 30 AMENDMENT 0003.doc | DOC document | |
| SF 30 AMENDMENT 0002.doc | DOC document | |
| FA-S4801-11_SEWAGE AND PLUMBING DRAIN PIPING SYSTEM Rev - (Revised with comments).pdf | ||
| SF 30 AMENDMENT 0001.doc | DOC document | |
| Attachment III - Past Performance Questionnaire_REV A.pdf | ||
| Attachment I - Specification_REV A.pdf | ||
| Attachment VI - Subcontracting Plan Outline.pdf | ||
| Attachment IV - Price Schedule.xlsx | XLSX spreadsheet | |
| RFQ 1305M223QNMAN0143.pdf | ||
| Attachment V - AIR Process.pdf | ||
| Attachment III - Past Performance Questionnaire.pdf | ||
| Attachment I- Specification.pdf | ||
| Attachment II - Past Performance Information Form.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA EASTERN ACQUISITION DIVISION (EAD)
Additional Item Requirements (AIR) Process for the Drydock Repairs of the
NOAA SHIP FAIRWEATHER:
Pursuant to CAR 1352.271-72 ADDITIONAL ITEM REQUIREMENTS (AIR) - GROWTH WORK (APR 2010), the following process shall be used throughout the performance of the contract to execute AIRs.
Exceptions to this process are expected throughout the period of performance (PoP) and will be addressed on a case by case basis.
1. Contractor submits Condition Found Report (CFR) to the Contracting Officer’s Representative (COR) and copies the Contracting Team (Contracting). For this contract, Contracting includes Contract Specialist (CS) Jim Van Natta and Contracting Officer (CO) Ashley Perry.
2. COR issues Condition Report Response (CRR) and sends it back to the Contractor and copies Contracting. The response will include:
a) acknowledgment of receipt of the Condition Report.
b) additional information and/or comments from the Government, if needed.
c) notice that an AIR will be issued, if needed.
3. If an AIR is required the COR will send the AIR form to Contracting ONLY. The AIR is an internal document from the COR to the Contracting Officer requesting to add an item to the requirement (contract). Not every AIR will have a related CFR as some represent additional requirements identified by the COR.
4. Unless Contracting has additional questions for the COR, the Contracting Team will issue a Request for Pricing (RFP) to the Contractor.
5. The Contractor shall respond to the AIR with a quotation for the additional work requested within three
(3) days of receipt of the AIR. Contractors shall provide quote to Contracting ONLY. Contractor response to AIR shall include an analysis of the requirements against the production chart and shall include the following additional information:
a. A firm statement concerning impacts to the production chart: This statement shall either confirm that the additional work can be accomplished within the current PoP, or it shall state that the additional work will affect the PoP completion date. In case of the latter, the quote shall note the primary and any secondary work items that would be affected, including an excerpt of the contractor’s planning production chart showing the impact to the project.
b. The contractor shall also provide an analysis and alternative proposal to maintain existing PoP, including such things as alternative procedures, accelerated and/or premium labor efforts, or any other solutions contractor may present to avoid contract PoP extensions.
6. Upon receipt of the quote from the Contractor, the quote will be reviewed by Contracting who will consult with the COR if necessary.
7. Negotiations may take place prior to accepting the pricing to address any issues/concerns that the Government has with the quote (omissions, justification of materials/hours, etc).
Attachment V
1305M223QNMAN0143
10. Once all aspects of the AIR have been negotiated, if necessary, and agreed by both the Contractor and Contracting, the Contracting Officer signs a Notice to Proceed (NTP).
11. Contracting distributes NTP, this AIR is now considered a part of the contract and work can start.
12. To reduce the amount of modifications to the contract, once a number of AIRs have been authorized through an NTP a consolidated modification will be issued memorializing the agreed to AIRs.