This document outlines the Additional Item Requirements (AIR) process for drydock repairs to the NOAA Ship RAINIER under solicitation 1305M222QNMAN0056. The National Oceanic and Atmospheric Administration (NOAA) will use the AIR process to add additional repair items to the contract throughout the period of performance.

The contractor must submit condition reports to the Contracting Officer's Representative, who will issue a response and determine if an AIR is needed. If so, the COR will send the AIR form to contracting staff for processing. The contractor must then respond to AIR requests for pricing within three days. Once negotiations are complete and the contractor and NOAA agree to terms, the contracting officer will issue a notice to proceed authorizing the additional work. Multiple AIRs will later be consolidated into a contract modification.

View the file

Other files

File Type Posted
RFQ 1305M222QNMAN0056 Rev e.pdf PDF
Amendment 6.pdf PDF
Attachment IV - Price Schedule rev b.xlsx XLSX spreadsheet
RFQ 1305M222QNMAN0056 Rev d.pdf PDF
Attachment I Specification rev d.pdf PDF
Amendment 5.pdf PDF
RFQ 1305M222QNMAN0056 Rev c.pdf PDF
Amendment 4.pdf PDF
RAINIER DD Q and A 3.xlsx XLSX spreadsheet
Amendment 3.pdf PDF
S2603.pdf PDF
Attachment I Specification rev c.pdf PDF
4.1 Chill Box Shelving Pictures.pdf PDF
Steering Gear Hose List.pdf PDF
RA5 Hose List.pdf PDF
Emergency Generator Automatic Bus Transfer.pdf PDF
S2806-2.pdf PDF
3.16_3.17_3.18.zip ZIP file
RAINIER DD Q and A 2.xlsx XLSX spreadsheet
3.67_4.5.zip ZIP file
Amendment 2.pdf PDF
3.19_3.37.zip ZIP file
RFQ 1305M222QNMAN0056 Rev b.pdf PDF
Attachment I Specification Rev b.pdf PDF
3.10_3.13.zip ZIP file
NOAA Rainier Control Philosophy.pdf PDF
3.15.zip ZIP file
RAINIER DD Q and A.xlsx XLSX spreadsheet
Attachment IV - Price Schedule rev a.xlsx XLSX spreadsheet
Attachment I - Specification rev a.pdf PDF
Amendment 1.pdf PDF
Attachment III - Past Performance Questionnaire.pdf PDF
Attachment I - Specification.pdf PDF
RFQ 1305M222QNMAN0056.pdf PDF
Attachment IV - Price Schedule.pdf PDF
Attachment II - Past Performance Information Form.pdf PDF
Attachment IV - Price Schedule.xlsx XLSX spreadsheet
Attachment VI - Subcontracting Plan Outline.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOAA EASTERN ACQUISITION DIVISION (EAD)

Additional Item Requirements (AIR) Process for the Drydock Repairs of the

NOAA SHIP RAINIER:

Pursuant to CAR 1352.271-72 ADDITIONAL ITEM REQUIREMENTS (AIR) - GROWTH WORK (APR 2010), the following process shall be used throughout the performance of the contract to execute AIRs.

Exceptions to this process are expected throughout the period of performance (PoP) and will be addressed on a case by case basis.

1. Contractor submits Condition Found Report (CFR) to the Contracting Officer’s Representative (COR) and copies the Contracting Team (Contracting). For this contract, Contracting includes Contract Specialist (CS) Bridget Cofo and Contracting Officer (CO) Ashley Perry.

2. COR issues Condition Report Response (CRR) and sends it back to the Contractor and copies Contracting. The response will include:

a) acknowledgment of receipt of the Condition Report.

b) additional information and/or comments from the Government, if needed.

c) notice that an AIR will be issued, if needed.

3. If an AIR is required the COR will send the AIR form to Contracting ONLY. The AIR is an internal document from the COR to the Contracting Officer requesting to add an item to the requirement (contract). Not every AIR will have a related CFR as some represent additional requirements identified by the COR.

4. Unless Contracting has additional questions for the COR, the Contracting Team will issue a Request for Pricing (RFP) to the Contractor.

5. The Contractor shall respond to the AIR with a quotation for the additional work requested within three

(3) days of receipt of the AIR. Contractors shall provide quote to Contracting ONLY. Contractor response to AIR shall include an analysis of the requirements against the production chart and shall include the following additional information:

a. A firm statement concerning impacts to the production chart: This statement shall either confirm that the additional work can be accomplished within the current PoP, or it shall state that the additional work will affect the PoP completion date. In case of the latter, the quote shall note the primary and any secondary work items that would be affected, including an excerpt of the contractor’s planning production chart showing the impact to the project.

b. The contractor shall also provide an analysis and alternative proposal to maintain existing PoP, including such things as alternative procedures, accelerated and/or premium labor efforts, or any other solutions contractor may present to avoid contract PoP extensions.

6. Upon receipt of the quote from the Contractor, the quote will be reviewed by Contracting who will consult with the COR if necessary.

7. Negotiations may take place prior to accepting the pricing to address any issues/concerns that the Government has with the quote (omissions, justification of materials/hours, etc).

Attachment V

1305M222QNMAN0056

10. Once all aspects of the AIR have been negotiated, if necessary, and agreed by both the Contractor and Contracting, the Contracting Officer signs a Notice to Proceed (NTP).

11. Contracting distributes NTP, this AIR is now considered a part of the contract and work can start.

12. To reduce the amount of modifications to the contract, once a number of AIRs have been authorized through an NTP a consolidated modification will be issued memorializing the agreed to AIRs.