This document is an API 653 in-service inspection report for an aboveground storage tank located at U.S. Army Garrison Kwajalein Atoll in the Republic of the Marshall Islands. The inspection was conducted on September 29, 2017 to evaluate the tank's integrity and establish a database for future inspections. Key findings and recommendations are provided for the 45-foot diameter tank, including the need for repairs to cracks in the secondary containment, deteriorated couplings on the fire suppression system piping, coating repairs, and installation of safety equipment like confined space markings and a grounding bar. Calculations determine the tank shell has over 30 years of remaining life. Appendices provide engineering data, drawings, photographs, and checklists documenting the inspection results.

View the file

Other files

File Type Posted
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Combined Synopsis-Solicitation - W9128F24Q0001 Amendment 0002.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Questions and Answers - W9128F24Q0001.pdf PDF
Combined Synopsis-Solicitation - W9128F24Q0001 Amendment 0001.pdf PDF
Attachment 1 - CLIN Schedule - KWA Tank Inspection.pdf PDF
Attachment I - API External Inspection Template.docx DOCX document
Attachment J.2 Kwajalein-Fac 935 (Tank 14)-Ext Final-2017.pdf PDF
Attachment J.4 Kwajalein-Fac 951 (Tank 8)-FINAL-2017.pdf PDF
Attachment 2 - PWS - SP-POL-CMP-INSPECT-FY24-KWA.pdf PDF
Attachment J.8 Kwajalein Fac 957 (tank 11) Old Report 2006.pdf PDF
Attachment B - KWA Fuels Tank Storage List.xlsx XLSX spreadsheet
Attachment F - API Internal Inspection Template.docx DOCX document
Attachment J.1 Kwajalein -Fac 954 (Tank 16 - Ext Final-2018.pdf PDF
Combined Synopsis-Solicitation - W9128F24Q0001.pdf PDF
Attachment A - General Installation Security Requirements.docx DOCX document
Attachment J.6 Kwajalein Fac 953 (Tank 17) pre-rpr 2017.pdf PDF
Attachment C - Tank Data Sheet.xlsx XLSX spreadsheet
Attachment E - API Internal Inspection Telecon Briefing Template.docx DOCX document
Attachment J.7 Kwajalein-Fac 956 (Tank 12)-Ext Final-2017.pdf PDF
Attachment J.9 Kwajalein-Fac 958 (Tank 10)-FINAL-1994.pdf PDF
Attachment J.3 Kwajalein-Fac 936 (Tank 13) Ext Final - 2018.pdf PDF
Attachment G - Return To Service Letter.docx DOCX document
Attachment 3 - 52.212-1 Addendum - KWA Tank Inspection.pdf PDF
Attachment D - Monthly Contractors Progress Management and Status Report.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USArmyCorpsofEngineers
OmahaDistrict
API653In‐Service
InspectionReport
U.S.ArmyGarrisonKwajaleinAtoll
FacilityNumber955
TankNumber15
USArmyCorpsofEngineersCenterofExpertiseforPetroleum,Oils,andLubricants
(USACEPOL‐MCX)
September29,2017

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

TableofContents
ACRONYMSANDABBREVIATIONS .............................................................................................................................................. 3

GENERAL SUMMARY

INSPECTION DATE

STATE REGULATIONS

PREVIOUS INSPECTION DATES

RECOMMENDED FUTURE INSPECTION DATES (CALCULATIONS SHALL BE PROVIDED)

GENERAL TANK INFORMATION

A. GENERAL PROJECT INFORMATION

1. API 653 Inspection

2. Site Information

B. TANK INSPECTION COMMENTS

1. Tank Construction

2. Tank Foundation

3. Tank Shell

4. Tank Appurtenances

5. Tank Coating

6. Tank Piping System

7. Fire Protection System

8. Secondary Containment

9. Cathodic Protection

C. FINDINGS AND RECOMMENDATIONS

1. MANDATORY REPAIRS per API 653, UFC 3‐460‐01, or AW 78‐24‐27 Standards

2. REQUIRED REPAIRS to Fully Comply with API 653 or Federal, State, and Local Codes………………………...…………11

3. RECOMMENDED REPAIRS as Part of Regular Maintenance…………………………………………………………………………..22

APPENDIX A: ENGINEERING CALCULATIONS AND DRAWINGS

A.1 SHELL SERVICE LIFE EVALUATION

A.2 SHELL SETTLEMENT EVALUATION

A.3 ULTRASONIC UT DATA

A.4 CONTAINMENT LAYOUT DRAWING

A.5 SHELL LAYOUT DRAWING

A.6 ROOF LAYOUT DRAWING

A.7 OSHA ACCESS STRUCTURE REPORT

APPENDIX B: 3‐D DOCUMENTATION AND ANALYSIS

APPENDIX C: API 653 CHECKLISTS FOR TANK INSPECTIONS

APPENDIX D: PHOTOGRAPHS

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

ACRONYMS AND ABBREVIATIONS

API American Petroleum Institute

ASME American Society of Mechanical Engineers

ASNT American Society of Non‐Destructive Testing

ARD Anti‐rotation device

ATG Automatic Tank Gauge

BBL Barrel

CFR Code of Federal Regulations

CP Cathodic Protection

DFT Dry Film Thickness

HLA High Level Alarm

HLCS High Level Control Shutoff

HHLA High‐High Level Alarm

LLA Low Level Alarm

LLLA Low‐Low Level Alarm

MFL Magnetic Flux Leakage

MT Magnetic Particle Testing

NACE National Association of Corrosion Engineers

NDT Non‐Destructive Testing

NFPA National Fire Protection Association

PSI Pounds per Square Inch

PT Penetrant Testing

P/V Pressure/Vacuum

RP Recommended Practice

PST Product Saver Tank

RT Radiography Testing

TML Thickness Measurement Location

TRV Thermal Relief Valve

UFC Unified Facilities Criteria

UFGS Unified Facilities Guide Specifications

ULS Ultra Low Sulfur

UT Ultrasonic Testing

VT Visual Testing

VPI Valve Position Indicator

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

GENERALSUMMARY
SummaryofInspection
AnAPIStandard653In‐ServiceinspectionofTank15(Facility955)atUSAGKwajalein‐Atoll,Republicofthe
MarshallIslandswascompletedonSeptember29,2017toevaluatethetank’sintegrity,collectdata,andestablisha
databaseforfutureinspectionsandevaluations.Theshellservicelifeevaluationperformedashavinggreaterthan
30yearsofremainingshelllifeundercurrentconditions.InspectionResultsarelistedinSectionC.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

INSPECTION DATE

API In‐Service (External) Inspection Date: 29 September 2017

Equipment (s) Used:

UltrasonicThickness(A‐scan/B‐scan)Testing
Manufacturer:GeneralElectric
Model:DMSGo+
CalibrationMethodsUsed:ZeroingProcedure,CopperCoatingCalibrationProcedure,andTwoPoint

Calibration Procedure

TankSettlementSurveying
Manufacturer:NorthwestInstrument
Model:NRL802KRotatingwithNLD5GLaserReceiver
CalibrationMethodsUsed:Mainandtransversehorizontalaxeschecksat100ft.≤1/16inch
TankShellSurveying
Manufacturer:LeicaGeosystem
Model:3DDisto
CalibrationMethodsUsed:Tiltsensorcalibrationautomaticallyperformedwithunitsetat<3°and

crosshairs calibration using target at a distance > 25 m

Inspector(s): Benyam Berhane

STATEREGULATIONS
StateRegulationforAPIIn‐ServiceTankInspectionsN/A
StateRegulationforAPIOut‐of‐ServiceTankInspectionsN/A
NOTE:Iftherearenostateregulationsfortankinspections,thenN/Ashallresidein‐placeofthenumberofyears
betweeninspections.Ifstateregulationsreside,therecommendedfutureinspectiondatesshallbebasedon
whicheverismorestringentbetweentheAPIinspector’scalculationsandthestateregulations.
PREVIOUSINSPECTIONDATES
APIOut‐of‐Service(Internal)InspectionDate:16June2011
APIIn‐Service(External)InspectionDate:19March2010
RECOMMENDEDFUTUREINSPECTIONDATES(CALCULATIONSSHALLBEPROVIDED)
APIOut‐of‐Service(Internal)InspectionDate:16June2031PerAPI653Section6.4.2‐
SubsequentInternalInspectionInterval
(16June2021IAWUFC)

API In‐Service (External) Inspection Date: 29 September 2022

BenyamBerhane
MechanicalEngineer/Sr.Inspector
InterSpec,LLC
API653CertifiedInspectorNo.28492

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

GENERAL TANK INFORMATION

ITEMDESCRIPTION
OwnerU.SArmy
LocationU.S.ArmyGarrisonKwajaleinAtoll;RMI
FacilityNumber955
TankNumber15
State/CountryKwajaleinAtoll/ RepublicofMarshallIslands
City‐
InspectionDate29September2017
TankManufacturerUnknown
DesignStandardUnknown(AssumedAPISTD12CEleventhEdition)
DateofConstruction1954
TankContentsDiesel(F‐76)
TankSerialNumberNone
TankDiameter45Feet
ShellHeight47.83Feet
ProductHeight46Feet
TankCapacity13,500BBL(567,000gallons)
FoundationConcreteRingWall

Construction

Bottom Lap‐Welded (Cone‐Down)

Shell Butt‐Welded (Cylindrical)

Floating Roof None

Fixed Roof Lap‐Welded (Cone‐Down)

Material

Bottom Carbon Steel (Unknown Specification)

Shell Carbon Steel (Unknown Specification)

Floating Roof NA

FixedRoofCarbonSteel(UnknownSpecification)
CathodicProtectionImpressedCurrent
InteriorCoatingSystemUnknown
ExteriorCoatingSystemThinFilmEpoxy/Polyurethane (DateCompletedUnknown)
LevelGaugingENRAFAutomaticTankGaugewithVarec2500MechanicalTapeGauge
OverfillProtection
HydraulicallyOperatedHighLevelShut‐offValvewithDedicatedFloat(Setat
46.00Feet)
PipingReceipt8"CarbonSteel
Issue8"CarbonSteel
LowSuction4"CarbonSteel
WaterDraw‐Off‐‐

Level Alarms

Low‐LevelAlarm:7.172Feet
Low‐LowLevelAlarm:2.39Feet
High‐LevelAlarm:46.00Feet
High‐HighLevelAlarm:48.00Feet
High‐LevelControlShutoff:46.00Feet

Type of Internal Floating Roof

NA

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

A. GENERAL PROJECT INFORMATION

1. API653Inspection
ThisprojectwillperformAPI653inspectionsofvarioustanksatfacilitiesthroughouttheUnited
States/OCONUS.Additionalconsiderationisgiventofederal,state,andlocalregulations,aswellas
applicablemilitarycriteriaandgeneralindustrystandards.

An API Standard 653 In‐Service (External) inspection was performed on Tank 15 (FAC 955).

2. SiteInformation
OnSeptember29,2017Burns&McDonnellandoursub‐consultant(InterSpec)performedanAPI653
In‐Service(External)inspectionofTank15(Facility955)locatedatU.S.ArmyGarrisonKwajaleinAtoll,
RMI.USAGKwajaleinAtoll(USAG‐KA)ishometotheRonaldReaganBallisticMissileDefenseTestSite.
TheReaganTestSiteisaMajorRangeandTestFacilityBaseundertheDoDwiththeprimarymissionof
researching,developingtests,anddevelopingmissiledefenseandspaceprograms.

Tank 15 is used as an aboveground diesel fuel storage tank supporting the installation fueling needs.

B. TANK INSPECTION COMMENTS

1. TankConstruction
Tank15(FAC955)isanominal13,500BBL,45‐footdiameterby47.83‐foottall,F‐76(diesel),
abovegroundverticalstoragetank.Thetankwasconstructedin1954presumablytoAPISTD12C
EleventhEdition.Therearenodataornameplatesaffixedonthetank.Therewerenoindicationsof
significantmodificationssincetheoriginalconstruction.Therewerenodocumentationsindicating
repairsormodifications.Thetankisretrofittedwithlevelalarmsandahighliquidlevelshut‐off
system,aswellasrepairsmadetothecircumferentialstairwaytread.
2. TankFoundation
Thetanksitsonaconcreteringwallfoundationthatisapproximately10to14"abovethesecondary
containmentfloor.Thefoundationisnotdesignedwithaleakdetection(tell‐tale)systemthatextends
tothecenterofthetank.Theflexiblemembraneliner(FML)forthesecondarycontainmentisattached
tothefoundation,butthebattenstripswerenotvisibleattheareaexcavated.Accessiblesectionsofthe
foundationwerevisuallyevaluatedduringtheinspectionforbrokenconcrete,spalling,cracks,and
vegetationagainstthebottomofthetank.Nospallingandvegetationwerepresent.Thefoundation‐to‐
chimeinterfaceissealed.Minorsealantdeteriorationispresentthroughout,withanapproximatetotal
of63linearfeetofdeterioratedcaulkingidentified.Shellsettlementsurveyswereperformedduring
theinspectioninaccordancewithAnnexBofAPIStandard653.Settlementresultsarelistedin
AppendixA.Thereisnoindicationofsignificantsettlement.Overall,thefoundationappearstobeisin
satisfactorycondition.
3. TankShell
Thetankshellisconstructedfromcarbonsteelmaterialofanunknownspecification.Theshellisof
cylindricaldesign,butt‐weldedtogether,andconsistingofseven(7)coursesfillet‐weldedtothefixed
roof.Evaluatedtheshellforplumbness,roundness,peaking,andbanding;allofwhichwerefoundtobe
withintheallowabletolerancesoftheAPIStandard653.Visuallyinspectedtheexterioroftheshell.
Inspectedthecoatingfordis‐bonding,adhesion,deterioration,anddiscoloration.Thetankshellis

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

equippedwith20"manholes(180°apart).Thetankisequippedwithashellmountedlowlevelalarm
andhigh‐highlevelalarms,aswellasahigh‐levelshut‐off.Theshellwasevaluatedforremainingmetal
thicknessutilizingultrasonictechnology.Theultrasonicthicknessmeasurementsandthickness
measurementlocations(TML)arelistedintheShellPlateThicknessMeasurementstableinAppendix
A.Aservicelifeevaluationperformedshowstheshellwithgreaterthan30yearsofremaininglife
undercurrentconditions.Theengineeringcalculations,asperAPIStandard653,fortheservicelife
evaluationareshowninAppendixAunder“ServiceLifeEvaluation.”Thetankshellisinsatisfactory
mechanicalcondition.
4. TankAppurtenances
a. GeodesicDomeRoof

None (equipped with carbon steel fixed roof).

b. Gauging

Thetank’sEnraf(Model#854)ATGisinstalledthrougha6‐inchnozzlemountedonthe
roofmanholecover.Itisnotknownifthestillingwellisslottedorifitisequippedwithan
8‐inchwellinsidethetank.TheEnrafsystemwasreportedasnotinworkingorderatthe
timeoftheinspection.Thereisasixinchmanualgaugingandsamplinghatch,butitdoes
nothaveastillingwellinsidethetank.TheATGwaterprobeisinstalledinthesameroof
manholecoverwithafourinchnozzleflange.Thetankisequippedwithafloatandtape
typemechanicaltapegaugemanufacturedbyShand&Jurs(Model92021).Thesystemisin
workingconditionandhasareportedproductlevelof44.094’.
c. LevelAlarms
Thehighlevelalarm,theHLVfloatchamber,andthehigh‐highlevelalarmaremountedon
theshellandareaccessibleviathecircumferentialstairway.Thetankisequippedwitha
low‐levelalarm,butnoindependentlow‐lowlevelalarmsystemwasinstalled,asrequired
bymilitarycriteria.
d. StairsandPlatforms
Thetank’sfixedroofisaccessiblebyacircumferentialstairwaymountedontheshellofthe
tankwithatopplatform.Thestairsandplatformwereinspectedforcorrosionand
structuralsoundness.Thecircumferentialstairwayhandrailisconstructedwith1½"angle
ironhandrailsandcoatedsteelplatetreadswithnon‐slipprofile.Thetopplatformisa
carbonsteelgratingtype,andseveralcircumferentialstairwaytreadswerereplacedinthe
pastwithcarbonsteelgrating.Theoverallgeneralconditionofthestairsandplatformare
mostlysatisfactory(withsomeexception–SeeSectionC).
e. GroundingandBonding
Thereisonegroundingcablemechanicallyconnectedtoalugonthetank’sshellandoneCP
structureleadcablethatisexothermicallyattachedtothebottomextension.Thegrounding
rodpenetratesthroughthesecondarycontainmentfloorlinerandisattachedtoa
groundingcable.Thetankisnotequippedwithacoppergroundingbarforpersonnelstatic
electricdischarge(typicallyrequiredbymilitarycriteria).

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

5. TankCoating
Thetankshell,roof,circumferentialstairway,handrails,piping,andappurtenancesarecoated.The
exteriorcoatingisanepoxywithpolyurethanetop.Thecoatingontheexteriorofthetankwas
completedinSeptember2012.TheinteriorcoatingisalsolistedasbeingcompletedinSeptemberof
2012(presumablythebottomandpartialonthefirstshellcourse).Isolatedcoatingfailurewasnoted
ontheappurtenances,circumferentialstairway,platform,productpiping,andvalveswithinthe
secondarycontainment.
6. TankPipingSystem
Thefuelisreceivedthrough8‐inchcarbonsteelpiping,andproductisissuedfromthetankthroughan
8‐inchcarbonsteelpipe.Thetankisalsoequippedwithotherauxiliarypipingforthewaterdraw(NPS
2),butitdidnothaveaproductsavertank(PST).Thereisa6‐inchblindflange,anditispresumedto
beeitherlowsuctionpipingorwaterdraw.Inspectedandevaluatedeachtanknozzleinaccordance
withAPIStandards650and653.Identifiedthetypeanduseofeachshellnozzleandmeasuredthe
nozzleneckthicknessonallaccessibleshellnozzles.Evaluatedallnozzlesandreinforcementplatesfor
leaksandcorrosion.
7. FireProtectionSystem
Thestoragetankisequippedwithasurfaceapplicationfixedfoamfiresuppressionsystemthatusesa
mobilefoamsupply.OneNPS8foamchamberismountedapproximately12inchesdownfromthetop
ofthetankonshellcourseseven.AllVictauliccouplingsforthefiresuppressionsystempipinghave
deterioratedfasteners.Nofirehydrantswerenotednearthetankduringtheinspection.
8. SecondaryContainment
Thetanksitsinsideanearthensecondarycontainmentbasinwithageotextilelinerpositioned
approximatelyeighttoteninchesbelowthesoilandconcretedikewalls.Theoveralldimensionofthe
secondarycontainmentis131.42feetx131.25feet,withaverticalheightof68.5"‐78"(totopsoil).The
secondarycontainmentisequippedwitha6"draininletandadrainvalvethattietotheunderground
PVCpipingsystemtotheOWS.Thesecondarycontainmentreleasevalveishousedinsideavalvepit
adjacenttothedraininletwithinthedike.ThePVCpipingsystemismanifoldedtogetherandcannotbe
individuallyisolatedoutsideofthevalvepit.Thedrainline,thedraininlet,andvalvepitwerevisually
evaluatedtodetermineifthedrainagesystemisliquid‐tight.Thevalvepithasraincovers,butstanding
waterwasnotedinthevalvepit.Additionaltestingandevaluationmayberequiredtodetermineifthe
valvepitisliquid‐tight.Theliquidinthevalvepitwaslowerthantheliquidintheadjacentdraininlet
andthussuggeststhatthedraininletissatisfactory.However,thesourceofthestandingwaterinthe
valvepitshouldbedetermined.
Thesecondarycontainmentwasvisuallyevaluatedduringtheinspectionforbrokenconcrete,spalling,
cracks,andvegetationgrowth.Minorhairlinecracks(temperaturecracks)andsomemoderatecracks
werenotedinthesecondarycontainmentwall.Anapproximatetotalof118linearfeetofcracksinthe
secondarycontainmentwallwereidentified.Hairlinecracksdonotseriouslyaffectthestrengthofthe
concretestructures;however,thesecrackscanbepotentialaccesspointsformoistureorwater
seepagethatcouldcorrodethereinforcingsteel(rebar).ThereareseveralCPtestport/anodeaccess
PVCopeningsaroundtheperimeterofthetankthatpenetratetheFML.SomeofthesePVCopenings
havedeterioratedcaulking.Thesecondarycontainmentisinmostlysatisfactorymechanicalcondition,
withtheexceptionofthediscrepanciesidentifiedinSectionCbelow.Fieldassessmentindicatesthat

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

thesecondarycontainmentisofsufficientsizetocontainatotaltankloss.Thesecondarycontainment
ispartiallyslopedtoallowfordrainageawayfromthetank.
Aformalsecondarycontainmentevaluation,inaccordancewith40CFR112,mayberequiredinorder
tosatisfyfederal,state,andlocalrequirements.
9. CathodicProtection
AnimpressedcurrentCathodicProtection(CP)systemisinstalledonthistankandservesmultiple
ASTsatthetankfarm(Tank10,11,12,15,16,and17).TheCPsystemismanufacturedbyCorrpower
(ModelCOYSE50‐34RSerial#CO11957).Thisunitisa50volt34ampereair‐cooledrectifierunit
(numberedCP3)andismountedontheoutsideofthepumphouseonthenortheastendofthe
secondarycontainment.TheJanuary2017reportprovidedindicatedthatTank#15isreceiving
cathodicprotectionbasedontheNACEcriterion.Therectifier,anodejunctionbox,andtankjunction
boxallareinsatisfactorycondition.
Atthetimeoftheinspection,therectifierwaspoweredonandinserviceableoperationcondition.Base
personnelperformedtherequiredtestinganddatalogging.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

C. FINDINGS AND RECOMMENDATIONS

Thetankisgenerallynotinaccordancewithcurrentmilitarycriteriaforsomeofthetankdesign,
appurtenances,andpipingconfiguration.Therefore,therecommendationsarenotmeanttobringthetankinto
fullcompliancewithUFC3‐460‐01orAW78‐24‐27standardsbutrathertoidentifytheseitemsforthe
owner/user’splanedupgrades,rehabilitation,andpriorityrepairs.Mandatoryrepairsshouldbecompletedto
assurecompliancewithindustrystandards,aswellasfederalorstatejurisdictionalrequirements.
Duringthisevaluation,thetankwasfoundtobeinagenerallyserviceablecondition,withnoimminentriskto
operationandoverallintegrity.However,therewereseveraldeficienciesthatwerenoted.Thesenoted
deficienciesarelistedbelowinnoparticularorder,withrepairrecommendations.
AllrepairsandmodificationsshouldbeperformedinaccordancewithAPIstandard653,UFC3‐460‐01,DoD
StandardDesign78‐24‐27,andapplicableUFGSspecifications.
1. MANDATORYREPAIRSperAPI653,UFC3‐460‐01,orAW78‐24‐27Standards
Mandatoryrepairsrepresentitemsthatrequireimmediateattention,inordertopreventimminentrisk
tosystemoperators,equipmentintegrity,ortheadjacentenvironment.Thetankshouldremainoutof
serviceuntiltheserepairsarecompleted.

No mandatory repairs were identified for this tank.

2. REQUIREDREPAIRStoFullyComplywithAPI653orFederal,State,andLocalCodes
Requiredrepairsrepresentitemsthatshouldbeaddressedinatimelymanner,inordertoprevent
futurepotentialriskstosystemoperators,equipmentintegrity,ortheadjacentenvironment.These
itemsareberequiredbyAPI‐653orfederal,state,andlocalcodes.
a. SecondaryContainmentCracks
OBSERVATION:Unsealedcrackswereidentifiedinthesecondarycontainmentwall(thisincludes
areasthatwerepreviouslysealed).
CodeREFERENCE:40CFRSection112.7(c)statesthattheentiresecondarycontainmentsystem,
“includingwallsandfloor,mustbecapableofcontainingoilandmustbeconstructedsothatany
dischargefromaprimarycontainmentsystem...willnotescapecontainmentbeforecleanupoccurs.”
§§112.8(c)(2)and112.12(c)(2)statethatdikedareasmustbe“sufficientlyimpervioustocontainoil.”
RECOMMENDATION:Repairallexposedcracksinthesecondarycontainmentwallsbygrindingina
V‐shapepattern,withatleast¼‐inchwidthatthesurfaceandadepthofatleast¼‐inchandsealing
withflexibleurethane(e.g.Sikaflex1c)orasimilarapprovedsealant(Quantity:118linearfeet).

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

b. SecondaryContainmentDrain
OBSERVATION:Thevalvepithasraincovers,butstandingwaterwasnotedinthevalvepit.Theliquid
inthevalvepitwasthesamelevelastheadjacentdraininletandthussuggeststhatthedraininlet
couldpossiblybeleaking.Thesourceofthestandingwaterinthevalvepitshouldbedetermined.
Theliquidinthevalvepitwasnotclear,andthedrainvalvewasnotvisible.Theliquidlookslike
sludge,butthereisnohydrocarbonodor.
CodeREFERENCE:40CFRSection112.7(c)(Seereferencefromabove)
RECOMMENDATION:UpgradetheconcretedraininletasdetailedinAW78‐24‐27DrawingCD.09
Detail3orsimilar.UseductileironpipinginlieuofthePVCdikedrainlines.Ataminimum,
investigateandrepairthesourceofwater/sludgeinsidethevalvepit.Slopedikebasinsurfacesa
minimumof1%fordrainage.Drainageswalesshouldbeslopednoflatterthan0.5%todrainageinlet
(seeAW78‐24‐27).
c. SecondaryContainmentPenetration
OBSERVATION:Thesecondarycontainmenthasalinerwithanearthencover.Theconditionofthe
linerisunknown,butsomepenetrationincludingthePVCcathodicprotectionanodeaccesscapsand
thetankgroundingrodsleeveshavedeterioratedcaulkingandloosehoseclamps.Ahigherrateof
raindisplacementwasnotedforthissecondarycontainmentcomparedtotheotherASTdikesystems
(ParticularlyTank8and9withoutearthencover).Someofthewaterdisplacementislikelydueto
thewaterabsorptionrateofthesoil/vegetation.However,theevaporationoftheexcesswaterabove
gradeisexpectedtobeconstantforalldikesunlessthereisadeterioratedliner.
CodeREFERENCE:40CFRSection112.7(c)(Seereferencefromabove)
RECOMMENDATION:ResealallPVCFMLpenetrationsandsecurethehoseclamps.Seesimilar
applicationoverconcreteinAW78‐24‐27DrawingCD.02Detail2.

Drain Valve Valve Pit Rain Cover

Drain Inlet (holes)

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

d. SecondaryContainmentLinerMountingStrip
OBSERVATION:Thesecondarycontainmenthasalinerwithanearthencover.Thelinerisadheredto
thetankfoundationbutdoesnotappeartohavebattenstrips.Asectionofthefoundationwas
excavatedbyhand,andtheperimetermountingstripcouldnotbelocated(seesecondphotobelow).
Theperimeterofthedikewallsandpipesupportpiersarenotaccessibleforinspection.
CodeREFERENCE:40CFRSection112.7(c)(Seereferencefromabove)
RECOMMENDATION:Removemultiplesectionsandinvestigatetheconditionsonthelinerattachments
totheperimeterofthefoundation,dikewalls,andpipesupportpiers.ConsiderupgradingtoAW
78‐24‐27DrawingD.03Detail4withanchoragebolts,battenstrips,andsealant(similartotherestof
theASTs).
e. SecondaryContainmentWallPenetration
OBSERVATION:Thecontainmentpipingpenetratesthroughthesecondarycontainmentwallswithout
theuseofanadequatepipesleeve/seal.Somehavebeenretrofittedwithcompressionsealsbutdo
nothavepipesleeves(Quantity:6).
CodeREFERENCE:40CFRSection112.7(c)(Seereferencefromabove)
RECOMMENDATION:Resealallsecondarycontainmentwallpenetrations.Considerupgradingall
secondarycontainmentwallpenetrationsperAW78‐24‐27DrawingCD.08DetailNA(CONCRETE
WALLPENETRATIONDETAIL)

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

f. DeterioratedVictauliccoupling(AssociatedwiththeFireSuppressionSystem)
OBSERVATION:AllVictauliccouplingsforthefiresuppressionpipinghavedeterioratedbolts.Several
locationshavecompletelyfailedVictauliccouplings.Thiscouldresultinabreachinthesecondary
containmentbecausethispipeextendsoutsideofthesecondarycontainment,andasimilartypeof
corrosionwasnotedoncouplingfastenersoutsideofthedike.Asectionofthefiresuppressionpiping
isalsoroutedundergroundoutsideofthedike,andthetightnessofthepipingisunknown.Thefire
suppressionsystemwillnotfunctionwiththesedeterioratedcouplingfasteners.
CodeREFERENCE:40CFRSection112.7(c)(Seereferencefromabove).AlsoNFPA11Section4.7.1.4,
“Whereexposedtocorrosiveinfluences,thepipingshallbecorrosionresistantorprotectedagainst
corrosion”InterSpecconcludestheintegrityofthepipingisdependentonthefastenersthus
incorporatingthecodereferenceforthecouplingfasteners.
RECOMMENDATION:Replacealldeterioratedbolts,couplings,andpipe.Repairthepipetomeetthe
requirementsofNFPA11Section4.7.1.4byinstallingstainlesssteelfasteners.
g. CorrosionandPittingonContainmentPiping
OBSERVATION:Coatingfailureandcorrosionwasnotedontheproductpipinginsidethesecondary
containment.Thereareisolatedcoatingfailureandpittingthroughoutthedikearea.
CodeREFERENCE:APIRP574Section7.4.14(CreviceCorrosion).APIRP574Section10.1.6.3(Loss
inthickness)
RECOMMENDATION:Replacethespoolsofpipingthathavesignificantpittingandcorrosion.Itmaybe
practicaltoconductadetailedAPISTD570inspectionofthecontainmentpipingtogetanoverall
conditionassessment.NDTtoolssuchasaguidedwaveexaminationcanalsobeemployedtogetthe
conditionoftheinaccessibleareasbetweenpipesupports,sleevedpiping,wrappedpiping,or
throughthedikewallpenetration.Guidedwaveexaminationisascreeningtoolusedtoinspectlarge
sectionsofpipingfromasingletestlocation.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

h. TankGroundingLug
OBSERVATION:Thetankgroundingstrapisboltedtothetankshell(mechanicaljointonacoated
interface)andhasnoreinforcementplatesperAPISTD6560andAW78‐24‐27DrawingED.02Detail
2. Itiscoveredwithfoammaterial.
CodeREFERENCE:AW78‐24‐27DrawingED.02Detail2.(SeealsoAPI650Section5.8.11.3)
RECOMMENDATION:Exothermicallyweldthegroundingcabletothelugandinstallreinforcementat
theshell,inaccordancewithAW78‐24‐27DrawingED.02Detail2.Note:ifrepairsareelectednotto
bedone,thepaintshouldberemovedwherethecableboltstothelug,toprovideabetterconnection
totheground(Quantity:1groundconnections).NotethecurrenteditionofAPISTD650suggestsa
maximumlugspacingof100ft.withaminimumoffourlugs.
i. ShellManholeCoverwithnoHingeorDavitArm
OBSERVATION:Theshellmanholecoversarenotequippedwithahingeordavitarmtofacilitatethe
handlingofthemanholecoverplates.
CodeREFERENCE:APISTD650Section5.8.3.5states,“Shellmanholecoversshallhavetwohandles.
Thosecoversweighingmorethan34kg(75lb)shallbeequippedwitheitherahingeordavitto
facilitatethehandlingofthemanholecoverplate.Thedavitsupportarmshallnotbeweldeddirectly
totheshellwithoutareinforcingplate.”AlsoAW78‐24‐27drawingD.10detail3.
RECOMMENDATION:InstallashellmanholedavitarmIAWwithAPISTD650andAW78‐24‐27
drawingD.10detail3.(Quantity:2)

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

j. TopPlatformGratingNotSecuredDown
OBSERVATION:Thecircumferentialstairwaytopplatformdoesnothaveanchor/saddleclips.
CodeREFERENCE:OSHAandAW78‐24‐27DrawingD.11Detail1,“Gratingshallbeanchoredwith
saddleclips.”
RECOMMENDATION:Securethegratingwithanchors.
k. CrackedGasket
OBSERVATION:TheTRVtestcheckvalveflangefortheproductissuenozzlehasacrackedgasket.
CodeREFERENCE:APIRP574Section10.3.5.1,“Sitesshouldhaveaprogramtoassurethatflangesare
madeupproperly.Propermake‐upofeveryflangeinapipingsystemisimportantforreliability.
Propermake‐upincludestheuseofthepropergasketandfastenermaterial,typeandsize,proper
positioningofthegasketandpropertorquingofthefasteners.Theassuranceprogramshouldinclude
proceduresforgasketandfastenerselectionandforfastenertorquing.”
RECOMMENDATION:Replacethegasket(1”flange).

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

l. NonstandardGasket
OBSERVATION:TheTRVvalveflangeforthereceiptandissuenozzlesdonothaveastandardgasket.
CodeREFERENCE:APIRP574Section10.3.5.1(Seeabove)
RECOMMENDATION:IsolatethevalveandreplaceallgasketsassociatedwithTRV(12flanges,NPS1).
m. CircumferentialStairwayTreadCorrosion
OBSERVATION:Thereisminortomoderatecoatingfailurewithassociatedcorrosion.
CodeREFERENCE:OSHA29CFR1910,SubpartD,“Walking‐workingsurfacesaremaintainedfreeof
hazardssuchassharporprotrudingobjects,looseboards,corrosion,leaks,spills,snow,andice.”
RECOMMENDATION:Repairthecoatingandreplacethetreadswithexcessivecorrosion(4treads
noted).Allfuturetreadreplacementshouldproviderisesthatareuniformthroughouttheheightof
thecircumferentialstairway.Replace/repairthecorrodedtreads(4).

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

n. CorrosiononPipingandPipeSupports
OBSERVATION:Thepipingandpipesupportswithinthetank’ssecondarycontainmenthavemoderate
corrosion.Themajorityofthepipesupportshavecompletelydeteriorated.
CodeREFERENCE:APIRP574Section7.4.14(ContactPointCorrosion)APIRP574Section8.2
(Properpositionandfunctionofsupports,hangers,andanchors).InaccordancewithAPI570Section
7.5,“Pipingshallbesupportedandguidedsothat(a)itsweightiscarriedsafely,(b)ithassufficient
flexibilityforthermalexpansionorcontraction,and(c)itdoesnotvibrateexcessively.”
RECOMMENDATION:Repairthecoatingfailureonthepiping.Replacethedeterioratedpipingsupports
perAW78‐24‐27DrawingCD.13Detail1and2.
o. NoorFadedConfinedSpaceMarkingsatManholes
OBSERVATION:Thetankisnotequippedwithaconfinedspacemarking.
CodeREFERENCE:InaccordancewithOSHARegulation29CFR1910.146(c)(2),“Iftheworkplace
containspermitspaces,theemployershallinformexposedemployees,bypostingdangersignsorby
anyotherequallyeffectivemeans,oftheexistenceandlocationofandthedangerposedbythepermit
spaces.NOTE:AsignreadingDANGER‐‐PERMIT‐REQUIREDCONFINEDSPACE,DONOTENTERor
usingothersimilarlanguagewouldsatisfytherequirementforasign.”
RECOMMENDATION:Installconfinedspacemarkingsonalltankentrypoints.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

p. Conduit,JunctionBoxes,Fittings,andMountingHardware
OBSERVATION:Theconduits,junctionboxes,fittings,andmountinghardwarewithinthesecondary
containmenthavedeteriorated.ThiswillnotmeettheClass1,Division1ratingrequirementsfor
hazardouslocations.Therearecorrodedconduitsupportclampsalongthecircumferentialstairway.
CodeREFERENCE:AllwiringandfittingsinaClassIlocationthatisabulkplantorterminalmust
complywiththeapplicableprovisionsofNECArticle501orArticle505[515.7].
RECOMMENDATION:Replaceallcorroded/deterioratedconduits,junctionboxes,fittings,and
mountinghardware.
q. TankFoundationSpalling/Break
OBSERVATION:Thereisanareaofspalling/breakmeasuringapproximately9‐inchx10‐inchanda
crackapproximately6‐inchlongneartheabandonedwaterdrawnozzlethroughthefoundation.
CodeREFERENCE:APISTD653Section4.5.1,“Temperaturecracks(hairlinecracksofuniformwidth)
donotseriouslyaffectthestrengthoftheconcretefoundationstructure;however,thesecrackscan
bepotentialaccesspointsformoistureorwaterseepagethatcouldeventuallyresultincorrosionof
thereinforcingsteel.”
RECOMMENDATION:Repairtheareaofspalling/breakandrecoattodeterwaterintrusiontotherebar.
r. CorrodedFastenersonHLV
OBSERVATION:ThereissignificantcorrosiononthebodycoverfastenerontheHighLiquidLevel
shut‐offvalve(HLV).Thefastenersdonotappeartohavesufficientthreadengagementduetothe

corrosion.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

CodeREFERENCE:API570Section5.15,“Flangefastenersshouldbeexaminedvisuallyforcorrosion
andthreadengagement.Fastenersshouldbefullyengaged.Anyfastenerfailingtodosoisconsidered
acceptablyengagedifthelackofcompleteengagementisnotmorethanonethread.”
RECOMMENDATION:Replacethecorrodedstudsandbolts.
s. CorrodedValveHandWheelonDBBValves
OBSERVATION:Boththereceiptandissuevalvehandleshavemoderatecorrosionwiththroughholes.
Notethevalvehandwheelmaybreakoffmakingvalveclosuredifficultorimpossible.
CodeREFERENCE:NFPA30Section22.13.2“Eachconnectiontoanabovegroundtankthroughwhich
liquidcannormallyflowshallbeprovidedwithaninternaloranexternalvalvelocatedascloseas
practicaltotheshellofthetank.”
RECOMMENDATION:Replacethevalvehandles(Quantity:2,NPS8DAN‐EXvalves).
t. DripsonSSTubingFittings
OBSERVATION:Smalldripswerenotedonthestainlesssteeltubingcompressionfittingpilotvalvefor
thehighliquidlevelshut‐offvalve.
CodeREFERENCE:InaccordancewithNFPA30,paragraph21.8.6,“Storagetanksandtheir
appurtenances,includingnormalvents,emergencyvents,overfillpreventiondevices,andrelated
devices,shallbeinspectedandmaintainedtoensurethattheyfunctionasintendedinaccordance
withwrittenprocedures.”
RECOMMENDATION:Repairthefittings.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

u. PittingonNPS6BlankNozzle
OBSERVATION:AnareaofinactivepipingwasnotedontheNPS6blanknozzleneck.Apittingdepth
ofapproximately0.1875"wasrecoded.Thenozzleneckultrasonicthicknessreadingis0.412".There
issufficientthicknesstomeettherequirementsofAPIstandards,andnorepairisrequired.
CodeREFERENCE:APIRP574Section7.4.14(CreviceCorrosion).APIRP574Section10.1.6.3(Loss
inthickness).
RECOMMENDATION:EvaluateatthenextAPISTD653inspection.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

3. RECOMMENDEDREPAIRSasPartofRegularMaintenance
Recommendedrepairsrepresentitemsthatshouldbeaddressedinatimelymanner,inorderto
preventfuturepotentialriskstosystemoperators,equipmentintegrity,ortheadjacentenvironment.
a. TankBottomExtension(Chime)
OBSERVATION:Thefoundation‐to‐chimeinterfaceissealed.Minorsealantdeteriorationispresent.
CodeREFERENCE:Maintainawaterproofsealatthetankchimeringwallfoundationinterface(UFC3‐
460‐03Section10.3.3).
RECOMMENDATION:Repairtheareasoffailedsealantbyapplyingapolysulfidemasticsealant
caulking.NOTE:Donotcaulktheend(side)ofthechime.SeeAW78‐24‐27DrawingD.04Detail3.
Repairthecoatingonthechimearea.(Quantity:63linearfeet).
b. ExteriorCoatingFailuresonTankandAppurtenances
OBSERVATION:Thereisisolatedcoatingfailureontheexteriorshellmostlyaroundthetopplatform,
circumferentialstairway,shellmanholes,andfixedroof.Similarisolatedcoatingfailurewasnotedon
theHLVtubingsupportmountingbrace.Thereismoderatecoatingfailureandcorrosionnotedon
theLLA,HLA,HHLA,andHLVpipenipplesandflanges.Allthelevelsensorchambersalsohave
moderatecorrosion.
CodeREFERENCE:UFC3‐460‐01,Section8‐3.10andSection9‐10
RECOMMENDATION:Mechanicallycleanandrecoattheareasofcoatingfailureonthetankshell,
circumferentialstairway,landing,piping,andappurtenances.Repairsshouldbeaccomplishedusing
anepoxybasedcoatingsystemorequivalent.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

c. ProductSaverTank(PST)
OBSERVATION:ThetankisnotequippedwithProductSaverTank(PST).
CodeREFERENCE:InstallawaterdrawoffsystemperAW78‐24‐27DrawingD.13Detail5.IAWUFC
3‐460‐01Section3‐6.6.7.“Mountpermanentlyinstalledpumpsonsubstantialfoundationsof
reinforcedconcretedesignedinaccordancewithHydraulicInstituteStandards.”
RECOMMENDATION:AddnewPSTinaccordancewithAW78‐24‐27.
d. TankElectronicATGandWaterProbe
OBSERVATION:Thetank’sEnraf(Model#854)isinstalledthrougha6‐inchnozzlemountedonthe
roofmanholecover.Itisnotknownifthestillingwellisslottedorifitisequippedwithan8‐inchwell
insidethetank.TheEnrafsystemwasreportedtobeinnon‐workingorderatthetimeofthe
inspection.TherearemoderatecoatingfailureandcorrosionontheadapterflangeforboththeATG
andwaterprobe.
CodeREFERENCE:UFC3‐460‐01Table8‐1(itempands)andAW78‐24‐27DrawingD.07Detail3,4
and5)
RECOMMENDATION:ReplaceorrepairtheATG.InstallstillingwellsIAWwithAW78‐24‐27.
e. IndependentLow‐LowLevelAlarm
OBSERVATION:Thetankisnotequippedwithanindependentlow‐lowlevelalarm.Thereisalow
levelalarmsensorinstalledonthesideofthetankshell(seephotobelow).
CodeREFERENCE:UFC4603‐460‐01Table8‐1(k)andAW78‐24‐27DrawingD.12Detail1
RECOMMENDATION:Installanindependentlow‐lowlevelalarm.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

f. SampleGaugeWell
OBSERVATION:Therearetwomanualsampling/gaugingwells.Thetankisequippedwithasixinch
andfourinchgaugehatchonthefixedroof.
CodeREFERENCE:UFC4603‐460‐01Table8‐1(s)andAW78‐24‐27DrawingD.07Detail2
RECOMMENDATION:Installa10‐inchroofnozzleandanaluminum,slottedstillingwellthatextendsto
within3inchesofthebottomofthetankforgaugingandsamplingwithadatumplatetoestablisha
gaugingzeropoint.
g. FixedRoofPerimeterGuardrail
OBSERVATION:Thefixedroofhas2partialperimeterguardrails.
REFERENCE:AW78‐24‐27DrawingD.11Detail5
RECOMMENDATION:InstallaperimeterguardrailaroundthecircumferenceofthefixedroofIAWAW
78‐24‐27DrawingD.11.
h. TankMarking(NFPADiamond)
OBSERVATION:ThetankisnotequippedwithanNFPAmarking.
CodeREFERENCE:MarkthetankinaccordancewithNFPA704.AW78‐24‐27DrawingD.13Detail3
Note4) “ProvidehazardidentificationsystemlabelinginaccordancewithNFPA704.”
RECOMMENDATION:InstallanNFPA704marking.
i. BlockandBleedValveMissingTube
OBSERVATION:TheproductreceiptandissueDBBvalvesaremissingthemanualbleedvalvegoose
necktube.Coating,water,andsomecorrosionwerenotedinsidethedifferentialthermalrelief(DTR)

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

valves,andlongtermexposuretotheinternalsectionoftheDTRvalvecouldcausethesystemtonot
performasdesigned.TheDTRvalvehandleswerenotedtohavecoatingfailureandcorrosion
CodeREFERENCE:Generalmaintenance/manufacturerdrawing.
RECOMMENDATION:Reinstallthegoosenecktubetopreventdrainageofbodyliquidandtoprevent
wateranddebrisfromenteringtheDTRvalve.Thetubeshouldbeabovethehighestpointofthe
bodycavity.Asteelplugcanalsobeusedtopreventwaterintrusion.
j. BlockandBleedValveVPICorrosion
OBSERVATION:ThewaterdrawnozzleDBBvalvehasmoderatecorrosion.Thevalveposition
indicator(VPI)iscorroded.ThevalvepositionwillbedifficulttodetectfromadistancewhentheVPI
iscompletelydeteriorated.Thedustcapismissing.
CodeREFERENCE:Generalmaintenance/manufacturerdrawing.
RECOMMENDATION:Replacethevalveoperator.InstallaCamlockcap.
k. PersonnelStaticElectricDischarge
OBSERVATION:Thetankisnotequippedwithacoppergroundingbarforpersonnelstaticelectric
discharge(typicallyrequiredbymilitarycriteria).
CodeREFERENCE:UFC3‐460‐03Section2‐3.21andAW78‐24‐27DrawingD.11Detail4
RECOMMENDATION:Installacoppergroundingbarforpersonnelstaticelectricdischargeatthebase
ofthecircumferentialstairway.

API 653 In‐Service Inspection Report USAG Kwajalein‐Atoll

l. AST ExteriorFireProtectionWaterSystems
OBSERVATION:ThetankdoesnotappeartomeettheequipmentrequirementforASTexteriorfire
protectionsystem.Thestandpostmountedwaterjetmonitorwasnotedalongthefacilityfenceline
northeastcornerofthedike.
CodeREFERENCE:UFC3‐460‐03Section2‐15.2.1
RECOMMENDATION:InstalladditionalservicesforthetankexteriorfireprotectionwatersystemsIAW
UFC3‐460‐01Section2‐15.2.1(fireprotectionwatermains,hydrants,valves,pumps,andapplication
devicesoutsideofdike)tocontrolbrushandgrassfiresandcoolingofstoragetanksintheeventofa
fireexposure.

API 653 In-Service Inspection Report USAG Kwajalein-Atoll

APPENDIX A: ENGINEERING CALCULATIONS AND DRAWINGS

A.1 SHELL SERVICE LIFE EVALUATION

A.2 SHELL SETTLEMENT EVALUATION

A.3 ULTRASONIC UT DATA

A.4 CONTAINMENT LAYOUT DRAWING

A.5 SHELL LAYOUT DRAWING

A.6 ROOF LAYOUT DRAWING

A.7 OSHA ACCESS STRUCTURE REPORT

Where:

t min = minimum acceptable shell thickness for each course, in inches; however, t min shall not be less than 0.1 inch for any tank course.

t nom = nominal shell thickness, in inches.

t act = current measured shell thickness, excluding pits and corrosion, in inches.

t prev = previous measured shell thickness, excluding pits and corrosion or t nom , in inches.

D = nominal diameter of the tank, in feet.

H = height from the bottom of the shell course under considerations to the established maximum liquid level, in feet.

H c = calculated safe fill height, in feet, for the current product.

G = specific gravity of the contents.

Y = specified minimum yield strength of the plate; use 30,000 pounds per square inch if not known (N/A for riveted tanks).

T = smaller of the specified minimum tensile strength of the plate or 80,000 pounds per square inch; use 55,000 psi if not known (N/A for riveted tanks).

S = The maximum allowable stress, in pounds per square inch. For welded tanks, use the smaller of 0.80Y or 0.429T for the bottom and the second course or the smaller of 0.88Y or 0.472T for all other courses. For riveted tanks, use S =21,000 psi. For elevated temperatures above

O F, the maximum allowable stress shall be the smaller of 2/3 the minimum yield strength multiplied by the M-factor (M) of API Standard 650 Appendix M or the product design stress value listed in Table M-1a or M-1b of API Standard 650.

E = original joint efficiency for the tank. Use Table 4-2 from API Standard 653 if original E is unknown; E =1.0 when evaluating the retirement thickness in a corroded plate, when away from welds or joints by at least the greater of one inch or twice the plate thickness. For riveted tanks, use E =1.0 for shell plates when greater than 6 inches from rivets; use the value of E from API Standard 653 Table 4-3 when within 6 inches of rivets.

L r = remaining life of the shell, in years.

C r = shell corrosion rate, in inches per year.

I ut = inspection interval for the next ultrasonic inspection, in years (not to exceed 15 years).

I v = inspection interval for the next visual external inspection, in years (not to exceed 5 years).

Y = years between the previous measured shell thickness (t prev ) and the current measured shell thickness (t act ), in years.

The maximum inspection intervals are determined by the most restrictive shell course in regard to the remaining life and the corrosion rate calculations for each shell course using the following formulas:

A.1 Shell Service Life Evaluation tmin =

2.6(H−1)DG

SE

Lr = tact − tmin

Cr Cr = tprev − tact

𝞓Y

Iut = tact − tmin

2Cr Iv = tact − tmin

4Cr

1) Minimum Required Thickness

D = 45 feet

G = 0.86

𝞓Y = 63 years

Course

No.

Plate

Specification

Course

Height

(feet)

Product

Height

(feet)

(H )

Maximum

Allowable

Stress

(psi)

(S )

Joint

Efficiency

(E )

Minimum

Acceptable

Thickness

(inches)

(t min )

Previous

Measured

Thickness

(inches)

(t prev )*

Current

Measured

Thickness

(inches)

(t act )

1 Unknown 6.92 46.00 23,600 0.85 0.226 0.328 0.313

2 Unknown 6.08 39.08 23,600 0.85 0.191 0.297 0.276

3 Unknown 6.96 33.00 26,000 0.85 0.146 0.281 0.249

4 Unknown 6.96 26.04 26,000 0.85 0.114 0.281 0.256

5 Unknown 6.96 19.08 26,000 0.85 0.100 0.281 0.252

6 Unknown 6.96 12.13 26,000 0.85 0.100 0.281 0.264

7 Unknown 6.96 5.17 26,000 0.85 0.100 0.281 0.27

*The t prev values were based on t nom .

A.1 Shell Service Life Evaluation

0.000

0.050

0.100

0.150

0.200

0.250

0.300

0.350

1 2 3 4 5 6 7

In c h e s

Course

Thickness Graph tprev tact tmin

A.1 Shell Service Life Evaluation

2) Corrosion Rate, Remaining Life and Inspection Intervals

Course

No.

Corrosion

Rate

(in./yr)

(C r )

Remaining

Life

(years)

(L r )

Next

Visual

Inspection

(years)

(I v )

Next

Ultrasonic

Thickness

Inspection

(years)

(I ut )

1 0.00024 364 5 15

2 0.00033 256 5 15

3 0.00051 202 5 15

4 0.00040 354 5 15

5 0.00046 327 5 15

6 0.00027 600 5 15

7 0.00018 956 5 15

Note: The engineering data used to calculate in-service period of operation (Remaining Life) assumes the tank remains in the same service and all corrosion rates remain constant. The maximum safe fill height for the tank is not limited other than by the established maximum operating liquid level and any other appurtenance such as overflow, vents, or firefighting system.

0.00000

0.00010

0.00020

0.00030

0.00040

0.00050

0.00060

1 2 3 4 5 6 7

In c h e s P e r

Y e a r

Course

Course Corrosion Rate Graph

Corrosion Rate

3) Projected Thickness Chart and Graph

Course #1:

Year Thickness tmin

2017 0.313 0.22571785

2022 0.312 0.22571785

2027 0.311 0.22571785

2037 0.308 0.22571785

2047 0.306 0.22571785

*based on same service and corrosion rates.

Course #2:

Year Thickness tmin

2017 0.276 0.191

2022 0.274 0.191

2027 0.273 0.191

2037 0.269 0.191

2047 0.266 0.191

*based on same service and corrosion rates.

Anticpated Thickness (5 yrs)*

Anticpated Thickness (10 yrs)*

Anticpated Thickness (20 yrs)*

Anticpated Thickness (30 yrs)*

Current Thickness:

Current Thickness:

Anticpated Thickness (5 yrs)*

Anticpated Thickness (10 yrs)*

Anticpated Thickness (20 yrs)*

Anticpated Thickness (30 yrs)*

0.000

0.050

0.100

0.150

0.200

0.250

0.300

0.350

2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047

In c h

Year

Course #1 Projected Thickness Graph

Thickness tmin

0.000

0.050

0.100

0.150

0.200

0.250

0.300

2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047

In c h

Course #2 Projected Thickness Graph

Thickness tmin

Course #3:

Year Thickness tmin

2017 0.249 0.146

2022 0.246 0.146

2027 0.244 0.146

2037 0.239 0.146

2047 0.234 0.146

*based on same service and corrosion rates.

Course #4:

Year Thickness tmin

2017 0.256 0.114

2022 0.254 0.114

2027 0.252 0.114

2037 0.248 0.114

2047 0.244 0.114

*based on same service and corrosion rates.

Anticpated Thickness (20 yrs)*

Anticpated Thickness (30 yrs)*

Anticpated Thickness (20 yrs)*

Anticpated Thickness (30 yrs)*

Current Thickness:

Anticpated Thickness (5 yrs)*

Anticpated Thickness (10 yrs)*

Current Thickness:

Anticpated Thickness (5 yrs)*

Anticpated Thickness (10 yrs)*

0.000

0.050

0.100

0.150

0.200

0.250

0.300

2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047

In c h

Course #3 Projected Thickness Graph

Thickness tmin

0.000

0.050

0.100

0.150

0.200

0.250

0.300

2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047

In c h

Course #4 Projected Thickness Graph

Course #5:

Year Thickness tmin

2017 0.252 0.100

2022 0.250 0.100

2027 0.247 0.100

2037 0.243 0.100

2047 0.238 0.100

*based on same service and corrosion rates.

Course #6:

Year Thickness tmin

2017 0.264 0.100

2022 0.263 0.100

2027 0.261 0.100

2037 0.259 0.100

2047 0.256 0.100

*based on same service and corrosion rates.

Anticpated Thickness (20 yrs)*

Anticpated Thickness (30 yrs)*

Anticpated Thickness (30 yrs)*

Current Thickness:

Anticpated Thickness (5 yrs)*

Anticpated Thickness (10 yrs)*

Current Thickness:

Anticpated Thickness (5 yrs)*

Anticpated Thickness (10 yrs)*

Anticpated Thickness (20 yrs)*

0.