This is a Consent to Subcontract template that outlines the requirements prime contractors must submit to CMS for subcontractor approval under FAR 52.244-2. The document is related to the RMADA 3 IDIQ contract opportunity from CMS.
The template requires prime contractors to provide detailed information including: description of supplies/services to be subcontracted, subcontract type, proposed subcontractor identification, proposed price, cost/pricing data documentation, Cost Accounting Standards certifications, and a comprehensive negotiation memorandum. The negotiation memorandum must cover elements such as price negotiations, pricing considerations, cost data requirements, reliance on subcontractor data, data accuracy issues, price objective differences, and incentive fee plans. The template also requires disclosure of any approved purchasing systems and existing relationships between the prime and subcontractor.
View the file
Other files
Show 40 more
Latest 50 of 60 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSENT TO SUBCONTRACT
PRIME CONTRACT NUMBER:
PRIME CONTRACTOR:
In accordance with FAR 52.244-2, the Prime Contractor must submit the following to CMS for consideration of Subcontractor consent:
Description of supplies or services to be subcontracted:
Identification of the type of subcontract:
Identification of the proposed subcontractor:
The proposed subcontract price:
The subcontractor’s current, complete, and accurate cost or pricing data and Certificate of Current Cost or Pricing Data, if required by other contract provisions:
The subcontractor’s Disclosure Statement or Certificate relating to Cost Accounting Standards when such data are required by other provisions of this contract:
A Negotiation Memorandum reflecting--
A. The principal elements of the subcontract price negotiations;
B. The most significant considerations controlling establishment of initial or revised prices;
C. Reason cost or pricing data were or were not required;
D. Extent, if any, to which the prime contractor did not rely on the subcontractor’s cost or pricing data in determining the price objective and in negotiating the final price;
E. Extent to which it was recognized in the negotiation that the subcontractor’s cost or pricing data were not accurate, complete, or current; the action taken by the prime contractor and the subcontractor; and the effect of any such defective data on the total price negotiated;
Attachment J.2 Consent to Subcontract
Pg. 1 of 2
F. Reasons for any significant difference between the prime contractor price objective and the price negotiated; and
G. A complete explanation of the incentive fee or profit plan when incentives are used. The explanation shall identify each critical performance element, management decisions used to quantify each incentive element, reasons for the incentives, and a summary of all trade-off possibilities considered.
Does the subcontractor have an approved purchasing system?
Does a close working relationship or ownership affiliation between the prime and subcontractor exist? If so, explain the relationship and/or affiliation.