Attachment - J-5 LCS RAV Milestones.pdf

PDF 559 KB Posted

Attached to
Request for Proposal - Littoral Combat Ships Continuous Maintenance and Emergent Maintenance IDIQ
Solicitation number
N4034521R0013
Issued by

About this file

This document contains details for a Request for Proposal for Littoral Combat Ships Continuous Maintenance and Emergent Maintenance services. Commander Logistics Group Western Pacific Ship Repair Unit is seeking proposals from qualified U.S. contractors to provide maintenance support for Littoral Combat Ships forward deployed in the Western Pacific region. The solicitation was issued by NAVSUP Fleet Logistics Center Yokosuka Site Singapore and includes 14 attachments and 10 contract data requirements lists. Responses are due by April 21, 2021 and the contract is expected to be awarded by May 30, 2021. The scope of work involves providing maintenance availability periods, arrival briefs, integrated maintenance schedules, 50% conferences, risk assessments, and closeout services to support LCS ships operating in the region.

View the file

Other files

File Type Posted
N4034521R0013 Amendment 0004.pdf PDF
N4034521R0013 Amendment 0003.pdf PDF
N4034521R0013 Amendment 0002.pdf PDF
Q and A 002 - RFP N4034521R0013.pdf PDF
SL720-AA-MAN-030 - Navy Mondernization Process Management and Operationa....pdf PDF
S0400-AD-URM-010 REV 7 TAGOUT USERS MANUAL.PDF PDF
Q and A 001 - RFP N4034521R0013.pdf PDF
N4034521R0013 Amendment 0001.pdf PDF
Q and A 001 - RFP N4034521R0013.pdf PDF
N4034521R0013 Amendment 0001.pdf PDF
S0400-AD-URM-010 REV 7 TAGOUT USERS MANUAL.PDF PDF
SL720-AA-MAN-030 - Navy Mondernization Process Management and Operationa....pdf PDF
N4034521R0013.pdf PDF
C002 - COTS Manual Supp Data draft 11-17-20.pdf PDF
A005 - Demand Only Transaction Reports draft 11-17-20.pdf PDF
J-13 - Past Performance Questionnaire.docx DOCX document
Attachment - J-2 (OEBGD).pdf PDF
J-14 - CM_EM IDIQ Sample Problem Scenario.pdf PDF
A003 - CFR 11-17-20.pdf PDF
A004 - Muster Reporting draft 11-17-20.pdf PDF
A008 - Welding Procedures draft 11-17-20.pdf PDF
Attachment - J-3(TUM).pdf PDF
Attachment - J-9 PMS 505 Instructions for Seaframe Mission Critical Systems.pdf PDF
A001 - Management Plan draft 11-17-20.pdf PDF
Attachment - J-6 Ships 3-M Desk Guide ver6.pdf PDF
J-11 Labor and Material Pricing Worksheet.xlsx XLSX spreadsheet
J-12 - Offerors Question Submittal Form.pdf PDF
Attachment - J-7MILSTRAP DHA BHJ Desk Gude for Demand Only Transaction Reporting 28 SEPT 2016.pdf PDF
J-10 DD 254 _LCS CM_EM IDIQ.pdf PDF
A002 - QAP draft 11-17-20.pdf PDF
C001 - COTS Manuals draft 11-17-20.pdf PDF
A010 - IMS draft 11-17-20.pdf PDF
A007 - Welding Quals and Training draft 11-17-20.pdf PDF
Attachment - J-4 Work Authorization Form (WAF).pdf PDF
A006 - GFM Receipt and bi-weekly Reports draft 11-17-20.pdf PDF
B001 - Logistics Data draft 11-17-20.pdf PDF
A009 - Weight and Stability SRD Reports draft 11-17-20.pdf PDF
N40343521R0013.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-5 – LCS RAV Milestones

Date Milestone Action Responsible

~A-150 Availability Created for Brokering

Establish availability in MFOM - VSB Port Engineer

A-120 Initiate Review of AWRs for Planning

Commence determining AWRs for either 3rd Party

Planning or In-House Planning

CLWP Project Team confirmed.

CLWP SRU PM

& Supv MS

A-120 Availability Created for Planning

CLWP Project Team creates the availability in NMD. CLWP SRU PM

A-120 Initiate Screening of AWRs to the Availability

Continuous determination of AWRs for either AOR

ABR/MSRA or for Navy contracted LCS provider.

Establish weekly TELCON/Meeting review with the

3rd Party Planners. Begin communication and coordination with 3rd Party Planners to develop specifications.

CLWP SRU PM

& MS

A-110 Initiate AWR Review

Conduct continuous reviews of the specs developed by the 3rd

Party Planner. Ship check as necessary to finalize the draft work specs.

CLWP SRU

PM & MS

A-110 LLTM Screening LLTM requirements in excess of 75 days communicated.

3rd Party Planner

/ CLWP SRU MS

A-90 100% RAV Work Package Brokered

All AWRs submitted (any late AWR will be handled in a case-by-case basis as required for execution).

Port Engineer

A-80

LLTM

Procurement Plan

LLTM Identified.

LLTM Procurement Plan submitted to NSA

(CLWP).

3rd Party Planner

A-80 Specifications Planned

100% Work Specifications Planned.

3rd Party Planner

/ CLWP SRU MS

A-78 Specifications Review

Initial Specifications review with 3rd Party Planner;

providing clarification on specification corrections.

3rd Party Planner updates specifications and returns for final review and approval.

CLWP SRU

PM & MS /

3rd Party Planner

A-75 LLTM Review NSA (CLWP) reviews LLTM Procurement Plan.

LLTM Procurement Plan submitted to Contracting

Activity for procurement.

CLWP SRU

PM & MS

A-75 Initial Risk Assessment

Potential risk items identified and communicated in writing to CLWP ACoS for Maintenance/SRU OIC.

CLWP SRU

PM & MS

A-75 100% D-Level Specifications Approved

Detailed review of work specifications complete

Technical review of specifications complete.

CLWP SRU PE

& Supv MS

A-72 IGE Submitted IGE Submitted to Contracting Activity in support of RFP CLWP SRU PM

A-72 Work Package review complete.

Work Specifications bundled for procurement and submitted to Contracting.

Supporting Statement of Work language (if needed) provided for Procurement.

CLWP SRU PM

A-72 Funding Provided Approved Funding Document submitted to Contracting

Activity.

CLWP SRU PM

A-70 Request for Proposal

Issue RFP to executing activities.

Contracting Activity

A-49 Proposals Submitted

Complete Proposal submitted to Contracting Activity.

Executing Activities

A-42 Initial Proposal Review

Initial Technical Evaluation of proposals complete

CLWP SRU

PM & MS

A-40 Discussions Discussions Complete

Contracting Activity / Executing Activities

A-38 Final Proposals Final Proposals Submitted Executing Activities

A-35 Proposals Reviewed

Final Technical Evaluation of proposals complete

CLWP SRU

PM & MS

A-30 Contract Award Contracts awarded to Executing Activity.

Contracting

Activity

A-29 Post Award Meeting

Completion of Post Award Meetings for all awarded contracts.

CLWP SRU

PM & MS

A-20 Work Package Execution Review

(WPER)

The complete Availability Work Package is defined and agreed upon; the AWP is executable within the RAV timeframe, budget, and LMA’s capacity.

CLWP SRU PM

A-10 Arrival Brief Submitted

Arrival Brief submitted to NSA (CLWP SRU). LMA

A-5 IMS

Integrated Maintenance Schedule (IMS) submitted to NSA

(CLWP SRU PM).

LMA

A+0 Ship Arrival Arrival Conference CLWP SRU PM

A+0 Start Start of Availability

A+7 50% Conference Conduct 50% Conference LMA

A+7 Execution Risk Assessment

Potential risks for on-time availability completion communicated in writing to CLWP ACoS for

Maintenance/SRU OIC.

CLWP SRU PM

C-1 Technical Adjudication

All DFS requests are adjudicated with Technical Warrant

Holders (TWH)

CLWP SRU PM

C+0 Completed Completion of Availability

C+3 Closeout Meeting

Completion of Closeout Meeting for all completed contracts.

CLWP SRU

PM/MS

C+7 Lessons Learned All lessons learned submitted and documented. CLWP SRU PM

C+60 Invoices Received

All invoices settled and fund recoupment completed.

CLWP SRU

PM/TDO

C+60 Contract Closeout

All completed contracts are closed-out.

Contracting Activity