Attachment F - Livermore Drawings - SNR Station Service Upgrades.pdf

PDF 5 MB Posted

Attached to
WAPA- Sierra Nevada Region Substation Service Upgrade Construction Project
Solicitation number
89503120BWA000022
Issued by

About this file

This document contains project drawings and specifications for upgrades to station service equipment at the Lawrence Livermore Substation in California, as well as details of a related competitive small business set-aside solicitation issued by the Western Area Power Administration (WAPA) for construction services.

The solicitation seeks bids for removal and installation of unit substation, pad mount transformers, automatic transfer switches, distribution panels and associated equipment at three WAPA substations. Bids are due by March 30, 2020, with award anticipated between $2.5-5 million. The work includes installation of 230kV bay material and equipment at Livermore, Olinda and Tracy Substations. The solicitation and drawings are available electronically at SAM.gov. Questions must be submitted in writing by the deadline to the specified contracting officer. All responsible sources may submit bids to be considered for award, provided they are registered in SAM.

View the file

Other files

File Type Posted
89503120BWA000022_0003.pdf PDF
Olinda Drawings - Amendment 003.pdf PDF
Tracy Drawings - Amendment 003.pdf PDF
Bid Schedule - Amendment 0003.pdf PDF
Livermore Specification - Amendment 003.pdf PDF
Wage Determination - Alameda County - CA202000018.pdf PDF
Olinda Specification - Amendment 003.pdf PDF
Livermore Drawings - Amendment 003.pdf PDF
Wage Determination - Shasta County - CA20200007.pdf PDF
89503120BWA000022_0003.pdf PDF
Tracy Specification - Amendment 003.pdf PDF
Tracy Revised Specification - Amendment 0002 (2).pdf PDF
Tracy Revised Specification - Amendment 0002.pdf PDF
Revised Bid Schedule - Amendment 0002.pdf PDF
Tracy Revised Specification - Amendment 0002.pdf PDF
Livermore Revised Specification - Amendment 0002.pdf PDF
Olinda Revised Specification - Amendment 0002.pdf PDF
89503120BWA000022_0002.pdf PDF
Olinda Revised Drawing Package - Amendment 0002.pdf PDF
89503120BWA000022_0001.pdf PDF
Site Visit Attendance Roster.pdf PDF
Attachment I - Wage Determination - Alameda County - CA202000018.pdf PDF
Attachment B - Tracy Specification - SNR Station Service Upgrades.pdf PDF
Attachment A - Bid Schedule - SNR Station Service Upgrades.pdf PDF
Attachment G - Olinda Drawings - SNR Station Service Upgrades.pdf PDF
Attachment D - Olinda Specification - SNR Station Service Upgrades.pdf PDF
Attachment C - Livermore Specification - SNR Station Service Upgrades.pdf PDF
Attachment J - Wage Determination - Shasta County - CA20200007.pdf PDF
Attachment E - Tracy Drawings - SNR Station Service Upgrades.pdf PDF
89503120BWA000022.pdf PDF
Attachment H - Submittal Log - SNR Station Service Upgrades.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DRAWINGS

LAWRENCE LIVERMORE SUBSTATION

STATION SERVICE UPGRADES

STATE

SECTION C

DESCRIPTION/SPECIFICATIONS

Spec No. 959

CALIFORNIA

LAWERANCE LIVERMORE SUBSTATION

STATION SERVICE UPGRADES

PROJECT DRAWINGS

A. GENERAL:

CONSTRUCTION DRAWINGS: Construction drawings are the specification drawings and any additional drawings required for use in construction. The construction drawings will be issued after contract award and may include amendment changes and other details, which make the drawings suitable to use for construction purposes.

PROJECT DRAWINGS: Project drawings included herein are reduced reproductions and are not to scale.

Some project drawings show details of fabrication and other information not a part of the work. Disregard information and details, which are not applicable.

STANDARD DRAWINGS: Where details shown on standard drawings included herein differ from construction or project drawings or text, the details of construction or project drawings or text shall govern. A complete set of standard drawings are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

INFORMATIONAL DRAWINGS: Some project drawings have the words “FOR INFORMATION ONLY” appearing above the title block. These drawings show some information, which may be required for bidding purposes. These drawings do not show items to be furnished or work to be performed.

EXISTING INSTALLATION DRAWINGS: Some project drawings have the words “EXISTING INSTALLATION” appearing above the title block. These drawings show the existing installations prior to modifications and may show some new work to be performed.

REFERENCE DRAWINGS: Reference drawings referred to on project drawings and not included herein, are not necessary for bidding purposes.

CONTRACTOR'S RESPONSIBILITY: Check all drawings and advise Western of any errors or omissions.

B. LIST OF DRAWINGS:

LOCATION MAP:

1. LLL 0015 Rev. B – Location, Access Road, & Vicinity

ELECTRICAL:

2. LLL 0001 Rev. B EI – Switching Diagram (Existing Installation)

3. LLL 0001 Rev. C – Switching Diagram

4. LLL 1000 Rev. C EI – Arrangement Plan (Existing Installation)

5. LLL 1000 Rev. D – Arrangement Plan

6. LLL 1100 Rev. B – Equipment and Material Index

7. LLL 1102 – Equipment Identification Signs

8. LLL 1116 Rev. B EI – KY1A Transformer Area Sections P-P and Q-Q (Existing Installation)

9. LLL 1116 Rev. C – KY1A Transformer Area Sections P-P and Q-Q

10. LLL 1511 Rev. C EI – Transformer Area Grounding and Conduit Plan (Existing Installation)

11. LLL 1511 Rev. D - Transformer Area Grounding and Conduit Plan

12. LLL 1610 Rev. B EI – 240/120 Volt Power and Lighting Wiring Diagram (Existing Installation)

13. LLL 1610 Rev. C - 240/120 Volt Power and Lighting Wiring Diagram

14. LLL 1611 Rev. B EI – Transformers KZ1A-KZ2A Wiring Diagram (Existing Installation)

15. LLL 1611 Rev. C - Transformers KZ1A-KZ2A Wiring Diagram

16. LLL 1612 Rev. A – Station Service Panel DZC/DZD Wiring Diagram

CIVIL & SITE DRAWINGS:

17. LLL 2000 Rev. B FIO – Grading and Plot Plan (For Information Only)

FOUNDATION AND STRUCTURAL DRAWING INDEX:

18. LLL 2007 Rev. D – Foundation Designations and Unit Quantities

CONCRETE:

19. LLL 2003 Rev. C EI – Foundation General Plan (Existing Installation)

20. LLL 2003 Rev. D – Foundation General Plan

21. LLL 2004 Rev. B EI – Foundation Plan Transformer Area (Existing Installation)

22. LLL 2004 Rev. C – Foundation Plan Transformer Area

23. LLL 2011 Rev. D – Foundations Outline and Reinforcement

24. LLL 2300 – Foundations Outline and Reinforcement

25. LLL 2301 – Foundation Outline and Reinforcement

CABLE TRENCH:

26. LLL 2015 Rev. B EI – Type “C” Cable Trench (Existing Installation)

27. LLL 2015 Rev. C – Type “C” Cable Trench

28. LLL 2500 – Cable Trench for Station Service Equipment

STEEL STRUCTURES:

29. LLL 2550 – Anchor Bolts

30. LLL 2600 – Station Service Equipment Support Frame

31. LLL 2601 – Station Service Equipment Support Frame Details

SERVICE BUILDING:

32. LLL 3011 Rev. F – Service Building Distribution Boards DHA1 and DHA2 Panel Schedules

33. LLL 3403 – Yard Lighting Circuits and Photocell Yard Lighting Control Wiring Diagram

34. LLL 4000 Rev. I FIO – Service Building Conduit, Arrangement and Grounding (For Information Only) https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx

LAWERANCE LIVERMORE SUBSTATION

STATION SERVICE UPGRADES

PROJECT DRAWINGS

CONTROLS:

35. LLL T601 – RTU AND CONTROL CABLE LIST

#0

Altamont Pass Rd

Old Patterson Pass Rd TRY-LLL 230 kV

LLL 424 115 kV

§̈¦580

I 580

Greenville Rd

S V as co R d

East Ave

Cross Rd

Las Positas Rd

Lupin Way

Flynn Rd N

Av en ue B

Natio nal Dr

Preston Ave

Southfront Rd

1st St

Scenic Ave

S Portal Dr

Av en ue A

W Pe rim ete r D r

Westgate Dr

Je rro ld Rd

La ug hli n R d

Lawrence Dr

Village Dr

Charlotte Way

So ut hg ate

D r

Th un de rb ird Ln

N Inner Loop

He rm an Av e

5th St

Pullman St

Marathon Dr

Unnamed Street

S Inner Loop

Parking Lot

Patterson Pass Rd

Brisa St

Las Positas Rd

Southfront Rd

Livermore

_̂ Lawrence Livermore Substation Alameda County

0 0.25 0.5 0.75 1 Miles

DECEMBER 19, 1988 LLL

WESTERN AREA POWER ADMINISTRATION

AREA OFFICE - SACRAMENTO, CA

LAWRENCE LIVERMORE SUBSTATION

CALIFORNIA

LOCATION, ACCESS ROAD, & VICINITY

GIS

"S

"S

"S"S

"S

"S

#0

LLL 424 115 kV

TRY-LLL 230 kV

Gr ee nv ille

R d

Old Patterson Pass Rd

N Outer Loop

Patterson Pass Rd

Livermore

Site Coordinates Lat: 37° 41' 36.726" N Long: 121° 41' 43.098" W

DESIGNED _______________________ APPROVED __________________________George T. West Don Warner

UNITED STATES DEPARTMENT OF ENERGY

K #0 Substation "S Structure ! Gate

WAPA Transmission Line Access Road Documented Access Road Public Road ROW Maintenance Road Transmission Line ROW Facility Boundary

Adjoining 7.5' Quadrangle Names Center quad is this site

From: Folsom, CA

1. Merge onto US-50 W 17.8 mi

2. Merge onto I-80BUS W 1.2 mi

3. Turn Right onto I-5/CA-99 N 0.2 mi

4. Take the exit on the Left onto I-5 S toward Los Angeles 59.8 mi

5. Slight Right onto I-205 W 13.7 mi

6. Merge onto I-580 W 7.7 mi

7. Take exit 57 toward N Greenville Rd 0.2 mi

8. Merge onto Altamont Pass Rd 0.1 mi

9. Turn Right onto Greenville Rd (signs for Stockton) 1.8 mi

10. Turn Left onto Patterson Pass Road 0.2 mi Destination will be on the Right To: Livermore Substation 8421 Patterson Rd.

Livermore, CA 94550 104 Miles, 1 hour 39 mins

B 5/13/16 N5 - WAH Revised and Redrawn in GIS

1 2 3

5 6 8 9

1:24,000 1 inch = 2,000 feet

1. Tassajara

2. Byron Hot Springs

3. Clifton Court Forebay

4. Livermore

5. Altamont

6. Midway

7. La Costa Valley

8. Mendenhall Springs

9. Cedar Mtn.

This cartographic product and GIS data were prepared in accordance with professional practice standards. The data represented on this map has been developed from the best available sources. Although efforts have been made to ensure that the data is accurate and reliable, errors may be reflected in the data. Users must be aware of these conditions and bear responsibility for the appropriate use of this map. The data on this map is for reference use only.

STATION SERVICE XFMR

KZ1A

13.8KV-240/120V 225KVA

TRANSFORMER KZ1A

AZ1A

SURGE ARRESTER

TRANSFORMER KZ2A

AZ2A

SURGE ARRESTER

STATION SERVICE

SSA

600A 240V

STATION SERVICE

SSB

600A 240V

STATION SERVICE

ATS

600A 240V

STATION SERVICE

DZC

240/120V

STATION SERVICE

DZD

240/120V

STATION SERVICE XFMR

KZ2A

13.8KV-240/120V 225KVA

EMERGENCY GENERATOR

GEN

NORMALLY OPEN

EMERGENCY PANEL TIE

DZC-DZD

NORMALLY OPEN

EMERGENCY PANEL TIE

DZD-DZC

NORMALLY OPEN

EMERGENCY GENERATOR

TRANSFER SEQUENCE INSTRUCTIONS

WARNING

PERSONS NOT FAMILIAR WITH THE OPERATION OF THIS SYSTEM SHALL NOT ATTEMPT TO CHANGE THE POSITION OF ANY OF THESE DEVICES.

FAILURE TO HEED THESE INSTRUCTIONS WILL RESULT IN A LOSS OF POWER AND DAMAGE TO CRITICAL EQUIPMENT.

1. PANEL DZC AND DZD MAIN BREAKERS MUST BE IN THE OPEN POSITION PRIOR TO USING EMERGENCY GENERATOR. DO NOT PARALLEL SOURCES.

6. CLOSE EMERGENCY PANEL TIE BREAKER IN PANEL DZD.

2. OPEN PANEL DZC MAIN BREAKER.

3. CLOSE EMERGENCY PANEL TIE BREAKER IN PANEL DZC.

4. OPEN PANEL DZD MAIN BREAKER.

5. CLOSE EMERGENCY GENERATOR RECEPTACLE BREAKER IN PANEL DZD.

7. CONNECT EMERGENCY GENERATOR TO EMERGENCY GENERATOR RECEPTACLE LOCATED ON PANEL DZD.

LIGHTING

LCU1

CONTACTOR NO. 1

LIGHTING

LCU2

CONTACTOR NO. 2

seela New Stamp

LAWRENCE LIVERMORE SUBSTATION STATION SERVICE UPGRADES
Drawing List
lll_0015b
lll_0001b_ei
lll_0001c
lll_0015b
lll_1000c_ei
lll_1000d
lll_1100b
lll_1102
lll_1116b_ei
lll_1116c
lll_1511c_ei
lll_1511d
lll_1610b_ei
lll_1610c
lll_1611b_ei
lll_1611c
lll_1612a
lll_2000b_fio
lll_2007d
lll_2003c_ei
lll_2003d
lll_2004b_ei
lll_2004c
lll_2011d
lll_2300
lll_2301
lll_2015b_ei
lll_2015c
lll_2500
lll_2550
lll_2600
lll_2601
lll_3011f
lll_3403
lll_4000i_fio
lll_t601

File details come from the government source that posted it. Updated .