Attachment F ColorGard 2.0 Project Calculation.pdf

PDF 15 KB Posted

Attached to
Meacham Maintenance Station Roof Snow Retention System
Solicitation number
S-73000-00014753
Issued by
Union County, Medford City, Oregon

About this file

This document is a ColorGard® 2.0 Project Calculation for the Meacham Maintenance Station (Project ID: 34660), prepared by S-5! for a roofing snow retention system installation. The project involves two separate roof sections - one with an eave to ridge length of 47.5 feet and assembly length of 594.2 feet, and another with an eave to ridge length of 22.5 feet and assembly length of 122 feet. Both roof sections have a 2:12 slope and a vertical roof snow load of 70 psf. The calculation details the required product quantities, including S-5-V clips, ColorGard® UnPunched systems, VersaClips, and SnoClip™ II, with total quantities ranging from 16 to 987 units depending on the specific product and roof section.

The calculation provides technical specifications for the snow retention system, including an allowable system load of 570.3 lbs. per seam (based on a safety factor of 4), a service load of 364.4 lbs. per clamp, and a recommended torque of 130-150 in-lbs. The project requires either one or two rows of assembly with a clamp on every seam, depending on the roof section. The document includes detailed vector force calculations, design vector force per panel, and emphasizes that the calculation does not cover analysis of the building structure or roof attachment, and the accuracy of input fields is the sole responsibility of the submitter.

View the file

Other files

File Type Posted
00014753 RFB Attachments.docx DOCX document
Attachment A Specifications.doc DOC document
00014753 Request For Bids.docx DOCX document
Attachment E Overall Roof Plan.pdf PDF
Notice of Intent to Award OregonBuys~25.pdf PDF
00014753 Intent To Award.xlsx XLSX spreadsheet
00014753 Preliminary Results.xlsx XLSX spreadsheet
00014753 Prebid Meeting Agenda.doc DOC document
00014753 PreBidSignIn.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ColorGard® 2.0 Project Calculation

Project ID: 34660

Project Name: Meacham Maintenance Station

Measurement Units: Imperial

Project Information

Product Quantity

ColorGard® UnPunched 172

S-5-V 987

SnoClip™ II 984

VersaClip 987

1. The undersigned has reviewed the calculation and certifies to the submitter that the calculator provides accurate results assuming the accuracy of the data entered.

2. The undersigned is not the engineer of record for the project.

3. The following certification is limited to the results of the calculation and does not cover any analysis of the building structure or the roof's attachment to the structure, or adequacy of either.

4. Accurate completion of the input fields are the sole responsibility of the submitter. Validity of input fields is not reviewed or evaluated.

Required Product Quantities (Project)

© 2025 S-5! All Rights Reserved.

Roof Name: Eave to Ridge 47.5'

Vertical Roof Snow: 70 psf

Slope: 2 : 12

Eave to Ridge: 47.5 ft

Assembly Length: 594.2 ft

Roof Style: Single-Slope

Panel Width: 16 in

Submitted Roof Information:Vertical Roof Snow: 70 psf

Vector Force

Slope: 2 : 12

Eave to Ridge: 47.5 ft

Panel Width: 16 in

Assembly Length: 594.2 ft

Roof Calculation: Eave to Ridge 47.5'

Allowable System Load: 570.3 lbs. per seam (based on a safety factor of 4)

Service Load: 364.4 lbs. per clamp

Job Requires: 2 rows of assembly with a clamp on every seam

Vector: 70 psf (Vertical Roof Snow Load) x 0.164 (Sine of Angle) = 11.48 psf

Vector/Panel: 11.48 psf (Vector) x 47.5 ft (Eave to Ridge) x 16 in (Panel Width)

Design Vector Force/Panel: 728.8 lbs.

Recommended Torque: 130-150 in-lbs.

Calculated Roof Data

Product Quantity

S-5-V 894

ColorGard® UnPunched 156

VersaClip 894

SnoClip™ II 892

Required Product Quantities (Roof)

Roof Name: Eave to Ridge 22.5'

Vertical Roof Snow: 70 psf

Slope: 2 : 12

Eave to Ridge: 22.5 ft

Assembly Length: 122 ft

Roof Style: Single-Slope

Panel Width: 16 in

Submitted Roof Information:Vertical Roof Snow: 70 psf

Vector Force

Slope: 2 : 12

Eave to Ridge: 22.5 ft

Panel Width: 16 in

Assembly Length: 122 ft

Roof Calculation: Eave to Ridge 22.5'

Allowable System Load: 570.3 lbs. per seam (based on a safety factor of 4)

Service Load: 345.2 lbs. per clamp

Job Requires: 1 row of assembly with a clamp on every seam

Vector: 70 psf (Vertical Roof Snow Load) x 0.164 (Sine of Angle) = 11.48 psf

Vector/Panel: 11.48 psf (Vector) x 22.5 ft (Eave to Ridge) x 16 in (Panel Width)

Design Vector Force/Panel: 345.2 lbs.

Recommended Torque: 130-150 in-lbs.

Calculated Roof Data

Product Quantity

S-5-V 93

ColorGard® UnPunched 16

VersaClip 93

SnoClip™ II 92

Required Product Quantities (Roof)

File details come from the government source that posted it. Updated .