This document contains a price proposal form for a waste water treatment plant repair by replacement project. The form includes contract line items for the base price of the entire work in accordance with the drawings and specifications, excluding demolition. A separate line item is included for demolition with a proposed price of $1.2 million. Award will be made based on the total price for the base work. The price proposal form also notes that options, if exercised, will be added to the base price for evaluation purposes and will not obligate the government to exercise the options. Pricing must be firm fixed for the base work and any options. The document provides pricing instructions and notes bonding requirements if an option for demolition is exercised.

Text of this file

PRICE PROPOSAL FORM

PART 1 GENERAL

CONTRACT LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide the Contract Line Item (CLIN) lump sum price for the following items:

CLIN 0001 - BASE PRICE. Price includes the following:

CLIN 0001. Price for the entire work Waste Water Treatment Plant Repair by Replacement, in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN0002)

CLIN

DESCRIPTION

TOTAL PRICE FOR CLIN 0001AA

WASTE WATER TREATMENT PLANT REPAIR BY REPLACEMENT.

CLIN 0002 Option Item No. 1 - Price includes the following:

CLIN

DESCRIPTION

TOTAL PRICE FOR CLIN 0002

Demolition

1.2 GENERAL BID NOTES

Award will be made on the total sum of Contract Line Item 0001.For CLINs enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

The Government reserves the unilateral right to award CLIN 0002 to the Contractor at the proposed price upon award or within 120 calendar days after the contract award. A firm fixed proposed price is required for CLIN 0001 and CLIN 0002.No provision is made for economic price adjustment. If Options are exercised, the contract completion date remains 465 calendar days after award of the contract.

Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).

The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

If CLIN 0002 is exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all Items.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Document --

Other files

File Type Posted
Amendment 3 -- N4008519R9103.pdf PDF
AMENDMENT (3) ATTACHMENT 1 PPI LIST.doc DOC document
Amendment 3 - Attachment 3 N40085-19-R-9103_S91_Narrative.pdf PDF
Amendment 3 -- Attachment 2 Sewer Plant Disinfectant System_2009.pdf PDF
AMMENDMENT (2) ATTACHMENT 1 PPI LIST.doc DOC document
Amendment 2 - 19R91030002.pdf PDF
ATTACH 1 - Security Access Request SECNAV Form 5512-1 (new) EXP 2021.pdf PDF
Amendment 1 -- 19R91030001.pdf PDF
ATTACH 3 - Security Access Request ODP.xls XLS spreadsheet
ATTACH 2 - 1.A.1. CUSFF_NAVNORTH COVID-19 Screening Questionnairev2020.04.18.pdf PDF
1605706_Dwgs_13of13.pdf PDF
RFP N4008519R9103.pdf PDF
1605706_Dwgs_10of13.pdf PDF
1605706_dwgs_9of13.pdf PDF
1605706_Dwgs_6of13.pdf PDF
1605706_Dwgs_8of13.pdf PDF
Specification Amendment Work Restrictions.docx DOCX document
1605706_Dwgs_3of13.pdf PDF
1605706_Dwgs_1of13.pdf PDF
Attachment C - Pre-Proposal Inquiry Log.doc DOC document
1605706_dwgs_11of13.pdf PDF
1605706_Dwgs_4of13.pdf PDF
1605706_Dwgs_5of13.pdf PDF
1605706_Dwgs_2of13.pdf PDF
1605706_dwgs_12of13.pdf PDF
Attachment A - Construction Design Exp.docx DOCX document
1605706_Dwgs_7of13.pdf PDF
Attachment B - Past Performance Questionnaire.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .