Attachment D.8 Drawings 8 of 10 (6 Pages).pdf
PDF 16 MB Posted
- Solicitation number
- 36C26323R0042
About this file
This document provides details for a federal contract solicitation. The solicitation number is 36C26323R0042 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23 for preventative Legionella services. The solicitation seeks to address Legionella risks through a multi-phase preventative maintenance program. The description specifies this is for Legionella Phase 3 services under project number 618-18-108. No further information is included on response dates, pricing terms, or incumbent contractors.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TS
TS
KEY NOTES:
GENERAL NOTES:
T S
T S
TS
TS
TS T
S
T S
TS
FFGG
M.C
M.B
REFER TO DETAIL
2/1356-PP106 FOR
VALVE LOCATION.
30 REFER TO DETAIL
1/1356-PP107 FOR
VALVE LOCATION.
5" CW
8" CW
8" CW
8" CW
8" CW
DRAIN
1 1/2" CW
BW.B
BW.C
BW.A
CONNECTION
TO PREVIOUS
PHASE.
8" CW
TO BE
REPLACED
IN NEXT
PHASE
5" CW UP
5" CW UP
4" HW UP
2" RHW UP
3" CW
5" CW
5" CW
2 1/2" HW
2" RHW
M.C
M.A
M.B
8" CW
4" HW
2 1/2" RHW
2 1/2" CW
1 1/2" HW
3/4" RHW
NOTE THAT THESE KEY NOTES ARE SPECIFIC TO THIS DRAWING (DO
NOT REFER TO MASTER KEY NOTES ON SHEET 1356-PP003). NOT ALL
KEY NOTES ARE UTILIZED AND MAY HAVE GAPS OF MISSING NOTE
NUMBERS TO KEEP GROUPS OF TEN NOTES AVAILABLE PER PHASE.
SHUT-OFF VALVE BW.C AND VALVE #M.B TO ISOLATE SECTION OF
PIPING INDICATED FOR REMOVAL. REFER TO GENERAL NOTES FOR
PROVISIONS TO BE TAKEN TO VERIFY ANY EXISTING VALVE LEAKAGE.
ONCE ISOLATED, REMOVE SECTION OF 8" GALVANIZED PIPING LOOP.
CUT INTO SECTIONS SMALL ENOUGH TO TRANSPORT TO LOADING
DOCK AREA FOR REMOVAL. INCLUDE DEMOLITION OF EXISTING
SUPPORTS MOUNTED TO PIPING RACKS, NEW PIPING WILL BE
SUPPORTED ONTO EXISTING RACK STRUCTURE BUT SHOULD BE
PROVIDED WITH NEW PIPE CLAMPS.
NOT USED THROUGH KEY NOTE
INSTALL NEW SECTION OF 8" SCHEDULE 10 STAINLESS STEEL PIPING TO
REPLACE PREVIOUSLY REMOVED. INSTALL IN EXACT SAME LOCATION
AS REMOVED SECTION OF PIPING. PROVIDE NEW SUPPORT CLAMPS
ON EXISTING PIPING RACK AS REQUIRED.
PROVIDE TEMPORARY END CAPS AT EITHER SIDE OF NEW PIPING
SECTION. FIRST PERFORM A PRESSURE TEST ON PIPING SECTION PER
SPECIFICATION REQUIREMENTS, AND THEN STERILIZE PIPING USING
CHLORINE SOLUTION FOR AT LEASE 24 HOURS PRIOR TO FLUSHING.
INCLUDE DRAIN/FILL VALVES ON EITHER END TO ACCOMPLISH.
INSULATE ENTIRE LENGTH OF PIPING PER SPECIFICATION
REQUIREMENTS. INCLUDE CONTINUOUS PVC COVERING THROUGHOUT
AND PREPARE ENDS FOR EXTENSION TO NEXT SUB-PHASE PIPING
WHICH WILL INCLUDE INSULATING ALL VALVE BODIES.
NOT USED THROUGH KEY NOTE
SHUT-OFF VALVE #BW.C AND VALVE #BP.B (BOTH FURTHER OUT TO
NEXT ADJACENT RISER VALVES OUTSIDE THE EXTENTS OF THIS PHASE
DRAWING) TO ISOLATE THIS RISER M FOR VALVE REPLACEMENT.
REFER TO GENERAL NOTES FOR PROVISIONS TO BE TAKEN TO VERIFY
ANY EXISTING VALVE LEAKAGE AND AREAS THAT WILL BE AFFECTED BY
THIS MAJOR WATER OUTAGE.
ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER
SIDE OF COLD WATER RISER TAKE-OFF VALVE WITH NEW STAINLESS 8"
TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD
EXISTING 5" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN
LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING
RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO
UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH
40 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN
OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).
DURING OUTAGE, INSTALL THERMOWELLS ON BOTH HOT AND COLD
WATER MAINS TO ACCEPT AN INSERTION TYPE TEMPERATURE SENSOR
TO BE INTEGRATED INTO BUILDING AUTOMATION SYSTEM FOR
INFORMATION MONITORING AND TRENDING.
INSTALL STRAP ON TEMPERATURE SENSORS INDICATE ON
RECIRCULATION PIPING. REPAIR ANY DAMAGED OR REMOVED
INSULATION ON COMPLETION.
ONCE VALVE INSTALLATION IS COMPLETED, INSULATE ALL AFFECTED
PIPING AND NEW VALVE BODIES COMPLETELY. COVER EVERYTHING
WITH PVC JACKET COVERS AND SEAL AS REQUIRED. INSULATION CAN
OCCUR DURING NORMAL HOURS AFTER OUTAGE COMPLETION, BUT
SHOULD NOT BE DELAYED FOR ANY MORE THAN 3 BUSINESS DAYS.
PHASE 6.1 (DEMO - REFER TO DETAIL 1 AND 10-19 SERIES KEY NOTES):
THE EXISTING GALVANIZED 8" COLD WATER PIPING MAIN TO BE REMOVED
BETWEEN INTERIOR VALVES OF RISERS INDICATED IN KEY NOTES. REFER
TO WORK SEQUENCE DESCRIBED IN 'ISOLATION OF MAIN PIPING LOOP
SECTIONS' BELOW TO EITHER CONFIRM EXISTING VALVES DO NOT LEAK, OR
FOLLOW GUIDELINE PROVISIONS TO BE TAKEN IF THEY ARE FOUND
DEFECTIVE. NO OUTAGES WILL BE REQUIRED DURING THIS SUB-PHASE
WITH MAIN LOOP CONTINUALLY SERVING BOTH SIDES.
PHASE 6.2 (BUILD-BACK - REFER TO DETAIL 2 AND 20-29 SERIES KEY NOTES):
INSTALL NEW PIPING IN SAME LOCATION AS REMOVED SECTION OF 8" COLD
WATER MAIN. MAY REUTILIZE EXISTING PIPING RACK FOR PIPING
SUPPORTS. REFER TO KEY NOTES FOR ADDITIONAL INFORMATION RELATED
TO INSTALLATION.
PHASE 6.3 (RISER VALVE REPLACEMENT - 30+ SERIES KEY NOTES):
AREA SHOWN IN EXPANDED 1/4" = 1'-0" PLAN VIEW SHALL HAVE BOTH 8"
ISOLATION VALVES REPLACED WITH NEW TRIPLE OFFSET BUTTERFLY
VALVES. PLAN FOR OUTAGE OF RISER M AND REPLACE EXISTING 5" TAKE-
OFF VALVE AT SAME TIME. INCLUDE 1.5" DRAIN VALVE AT INTERSECTION
BETWEEN THREE(3) REPLACED VALVES. THIS SUB-PHASE WILL CAUSE A
LARGE DOMESTIC WATER OUTAGE FOR AREAS OF FACILITY THAT MAY BE
CRITICAL, CONTRACTOR SHALL REFER TO 'ALLOWANCE FOR TEMP
FIXTURES OR WATER SERVICES' BELOW FOR ACCOMMODATIONS NEEDED
FOR THOSE AREAS. OUTAGE WILL AFFECT THE FOLLOWING DEPARTMENTS
AND SHOULD BE CAREFULLY COORDINATED WITH VA FACILITIES;
• BASEMENT LEVEL: MECHANICAL ROOM BQ, SAFETY DIRECTOR'S
OFFICE, ENGINEERING, EDUCATION, PHARMACY, INPATIENT, MEDICAL
MEDIA, MAS, SPD, ACS (SPECIALTY) - WARFARIN, NUCLEAR MEDICINE -
PET SUITE
• FIRST FLOOR: ACS - URGENT CARE AND PRIMARY CARE, EDUCATION,
NUTRITION/FOOD SERVICE, VETERANS ASSISTANCE SERVICE
ORGANIZATIONS, RADIOLOGY, PHARMACY OUTPATIENT
• SECOND FLOOR: MECHANICAL ROOM 2B; ACS (SPECIALTY) - EYE,
UROLOGY; VOLUNTARY SERVICE; MEDICAL RESEARCH - BRAIN SCIENCE;
VETERANS ASSISTANCE/SERVICE ORGANIZATIONS; ON-CALL; SURGERY -
OR, AMBULATORY; PATHOLOGY; IRM SERVICE; SURGERY - EXAM.
• THIRD FLOOR: MECHANICAL ROOM 3B, ACS (SPECIALTY) - GI CLINIC,
PRIMARY CARE MED OFFICES, EDUCATION, REHABILITATION MEDICAL
SERVICE, MEDICAL RESEARCH, CHRONIC DISEASE CLINIC
• FOURTH FLOOR: DIRECTOR'S SUITE, EDUCATION, MEDICAL RESEARCH,
ISOLATION OF MAIN PIPING LOOP SECTIONS:
PERFORM THE FOLLOWING PROCEDURE STEPS TO PROPERLY ISOLATE
EACH SECTION OF PIPING LOOP AS DESCRIBED IN PHASING SEQUENCES,
1) SHUT-OFF ISOLATION VALVES ON INTERIOR SIDE OF LOOP BEING
MODIFIED OR REMOVED TO MAINTAIN SERVICES TO ALL RISERS.
2) REMOVE SECTION OF PIPING, OR TAP TEMPORARY DRAIN CONNECTION
TO VERIFY VALVES ARE HOLDING FOR A MINIMUM PERIOD OF 24 HOURS.
3) IF NO VALVE LEAKAGE, OR MINIMAL AMOUNT, IS WITNESSED THAN
PROCEED TO PIPING MODIFICATION AND/OR DEMOLITION SCOPE OF WORK
IDENTIFIED.
4) IF MODERATE OR SIGNIFICANT VALVE LEAKAGE IS WITNESSED THAN
PROVIDE 1.5" VALVE TAP WITH THREADED CONNECTION TO HOSE TO
NEAREST MECHANICAL ROOM DRAIN DISCHARGE LOCATION. THIS
TEMPORARY DRAIN CONNECTION AND HOSE SHALL BE REMOVED ONCE
NEW RISER VALVE REPLACEMENTS ARE COMPLETED.
---CONTRACTOR WILL BE RESPONSIBLE TO KEEP ON SITE AT LEAST FOUR(4)
SETS OF 1.5" VALVES WITH THREADED CONNECTIONS AND TWO(2) 250' LONG
HOSES OF 1.5" DIAMETER IN SIZE.
CONTRACTOR ALLOWANCE FOR TEMP FIXTURES OR WATER SERVICES:
ASSUME THAT DURING THE COURSE OF THE 8 PHASE DOMESTIC WATER
LOOP REPLACEMENT THAT SPECIFIC AREAS WILL REQUIRE TEMPORARY
SINKS AND/OR EXTENSION OF TEMPORARY WATER SERVICES TO THEIR
DEPARTMENT. CONTRACTORS SHALL INCLUDE THE FOLLOWING
ALLOWANCES WITHIN THEIR BASE BID TO ACCOMMODATE THOSE
REQUESTS WHEN THEY ARISE DURING OUTAGE COORDINATION WITH VA
FACILITIES.
• INCLUDE UP TO TWELVE(12) TEMPORARY SINK FIXTURES TIED INTO AN
ADJACENT RISER SERVICE. EACH SINK WILL REQUIRE UP TO 50' OF
COPPER PIPE FOR WATER CONNECTIONS, OTHERWISE HOSE WILL BE
UTILIZED IF DISTANCE EXCEEDS THAT SPECIFIED AMOUNT OF PIPING.
• INCLUDE FOUR(4) TEMPORARY BACK-UP WATER CONNECTIONS FOR
COLD WATER SERVICE TO AN ENTIRE DEPARTMENT. TEMPORARY COLD
WATER MAIN SHALL BE ASSUMED AT 2" SIZE AND EXTEND A MAXIMUM OF
250' TO CONNECT INTO AN ADJACENT RISER SERVICE.
• NOTE THAT THE ABOVE IS FOR ENTIRE PROJECT, NOT PER PHASE.
ZAABBCCDDEEFFGG
STACKED
STACKED
STACKED
STACKED
BW.C
BW.B
BW.A
M.B
M.A'
M.C
ZAABBCCDDEEFFGG
RISER M
STACKED
STACKED
20 202122
2221 22
1356-PP106.1
BW.C
BW.A
BW.B
M.C
M.B
1356-PP106.1
1356-PP106.1
REFER TO PHASE 7.1 FOR
DEMO OF OLD PIPING.
8" CW
C W
C W
4" HW
8" CW
2 1/2" CHW
4" PC
10" HPS
8" CHWS
8" CHWR
FF
2 1/2" RHW
4" HW
8" CW
3/4" CW
2 1/2" PC
3" HWR
2 1/2" HWS
5" MPS2" MPC
4" CHWR
4" CHWS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS SUBMISSION
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
A
C R e v it P ro je c ts
\V A
B u ild in g
P h a s e
M e c h a n ic a l ja s o n g o tt w a lt
.r v t
/3 /2
:4
:0
A M
BASEMENT INTERSTITIAL - PHASE
6 - DOMESTIC WATER PLAN
PREVENT LEGIONELLA,
PHASE III
MINNEAPOLIS
618-14-118
11/30/2022 JG TM / JG618-14-118
1356-PP106.1
1/4" = 1'-0"
ENLARGED - PHASE 6.3
NO SCALE
PHASE 6 - ISOMETRIC VIEW
1/16" = 1'-0"
PHASE 6.1 - DEMO
1/16" = 1'-0"
PHASE 6.2 - NEW
NO SCALE
PHASE 6 ELEVATION - NORTH TUNNEL
NO SCALE
PHASE 6 ELEVATION - WEST INTERSTITIAL
41360DATE REG. NO.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED BY ME
OR UNDER MY DIRECT SUPERVISION AND THAT I
AM A DULY LICENSED PROFESSIONAL ENGINEER
UNDER THE LAWS OF THE STATE OF MINNESOTA.
JASON GOTTWALT, P.E.
11/30/2022
Revisions: Date:
T
STS
TS
TS
T S
T S
T S
KEY NOTES:GENERAL NOTES:
EEFF
RISER M
5" CW
5" CW
2" RHW
2 1/2" HW
8" CW
8" CW
5" CW UP
5" CW UP
2" RHW UP
4" HW UP
3" CW
EEFF
8" CW
8" CW
5" CW
5" CW
2" RHW
2 1/2" HW
5" CW UP
5" CW UP
2" RHW UP
4" HW UP
3" CW
EE
4" HW UP & DN
5" CW UP & DN
5" CW UP & DN
2" RHW DN
1 1/2" RHW UP
3" CW
EE
4" HW UP & DN
5" CW UP & DN
5" CW UP & DN
2" RHW DN
1 1/2" RHW UP
3" CW
EE
1 1/2" RHW DN
1 1/4" RHW UP
4" HW DN
3" HW UP
5" CW DN
4" CW UP
5" CW DN
4" CW UP
4" CW
EE
1 1/4" RHW UP
1 1/2" RHW DN
3" HW UP
4" HW DN
5" CW DN
4" CW UP
5" CW DN
4" CW UP
4" CW
EE
1 1/4" RHW DN
3/4" RHW UP
2 1/2" HW UP
3" HW DN
4" CW UP & DN
4" CW UP & DN
3 1/2" CW
EE
1 1/4" RHW DN
3/4" RHW UP
3" HW DN
2 1/2" HW UP
4" CW UP & DN
4" CW UP & DN
3 1/2" CW
EE
3/4" RHW DN
2 1/2" HW DN
4" CW DN
4" CW DN
2 1/2" CW
2" CW
EE
4" CW DN
4" CW DN 2 1/2" HW DN
3/4" RHW DN
2" CW
2 1/2" CW
1 BEFORE OUTAGE: ROUTE NEW RISER "M" PIPING PARALLEL TO
EXISTING PIPING TO LEVEL ABOVE. NOTE THAT THERE IS AN
EXISTING ABANDONED 5" COPPER PIPE IN PLACE THAT WILL NEED TO
BE DEMOLISHED AND RECYCLED. CONTRACTOR MAY USE THIS
ROUTING FOR NEW STAINLESS STEEL COLD WATER MAIN UP TO BASE
OF RISER.
DURING OUTAGE: REMOVE AND REPLACE MAIN PIPING BETWEEN
VALVES M.B AND M.C. MAKE FINAL CONNECTION TO NEW RISER "M"
PIPING. ABANDON EXISTING COLD WATER RISER PIPING TO BE
DEMOLISHED AFTER ALL RISER "M" FINAL CONNECTIONS ARE MADE
AND OUTAGE IS COMPLETE. CONTRACTOR TO VERIFY PIPE SIZING
AND OUTAGE AREAS PRIOR TO CONSTRUCTION.
AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW
AND KEY NOTE 2.
AFTER OUTAGE: REMOVE ABANDONED COLD WATER RISER PIPING.
DEADLEG OR ABANDONED PIPING SHALL NOT REMAIN.
MAIN PIPING DEMOLITION INDICATED IS TO OCCUR IN THE NEXT
PHASE. REFER TO 1/1356-PP107.1.
BEFORE OUTAGE: ROUTE NEW RISER "M" PIPING PARALLEL TO
EXISTING PIPING TO LEVEL ABOVE. EXTEND NEW TAKEOFFS TO
EXISTING BRANCH TAKEOFFS AND PREPARE FOR NEW CONNECTION.
DURING OUTAGE: DISCONNECT EXISTING BRANCH TAKEOFFS AND
REMOVE TAKEOFF PIPING. MAKE TAKEOFF FINAL CONNECTIONS.
ABANDON EXISTING COLD WATER RISER PIPING TO BE DEMOLISHED
AFTER ALL RISER "M" FINAL CONNECTIONS ARE MADE AND OUTAGE IS
COMPLETE. CONTRACTOR TO VERIFY PIPE SIZING AND OUTAGE
AREAS PRIOR TO CONSTRUCTION.
AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW
AND KEY NOTE 2.
A.
B.
C.
D.
E.
F.
THE OUTLINE OF 'MEANS-AND-METHODS' NOTES BELOW FOR VERTICAL
COLD WATER RISER REPLACEMENTS INDICATED WITHIN THESE
DRAWINGS IS NOT INTENDED TO BE ALL-INCLUSIVE OF EFFORT
REQUIRED BY CONTRACTOR. NOR ARE THESE NOTES AND/OR
SUGGESTIONS MEANT TO LIMIT CONTRACTORS FROM DEVELOPING
THEIR OWN APPROACH THAT MAY BE CONSIDERED MORE COST
EFFECTIVE OR SAFE. THESE NOTES ARE MAINLY MEANT TO QUALIFY
EXISTING CONDITIONS AND DEFINE MINIMUM LEVEL OF PLANNING
REQUIRED BY VA FOR EACH OF THESE TIME SENSITIVE OUTAGES.
NO MAJOR WATER OUTAGE SHALL LAST MORE THAN 12 HOURS IN
DURATION. PLUMBING CONTRACTOR TO DETERMINE ADEQUATE
NUMBER OF PLUMBER CREWS REQUIRED TO PERFORM MULTIPLE
TASKS SIMULTANEOUSLY DURING OUTAGES. ALL OUTAGES SHALL BE
ASSUMED TO BE PERFORMED DURING WEEKEND OR NIGHT OVERTIME
HOURS WHEN BIDDING THIS PROJECT.
VERTICAL RISER REPLACEMENT (TYPE 1 - WITHIN MECHANICAL ROOM)
• FOR RISERS WITHIN MECHANICAL ROOMS, CONTRACTOR SHALL
CORE DRILL HOLES THROUGH FLOOR ADJACENT TO EXISTING
PLUMBING RISER FOR NEW INSTALLATION. EXISTING FLOOR
PENETRATIONS AND/OR SLEEVE SHALL BE PATCHED FLUSH TO
EXISTING FLOOR AS REQUIRE UPON DEMOLITION OF THOSE RISERS.
• EXISTINGT TAKE-OFF VALVES MAY REQUIRE RELOCATION FOR
CONNECTION INTO NEW RISER. VERIFY ADEQUATE ACCESS TO ALL
TAKE-OFF VALVES AND PROVIDE WITH NEW LAMINATE SIGNAGE.
ANY VALVES FOUND AT INACCESSIBLE LOCATIONS SHALL BE
RELOCATED BY CONTRACTOR.
• REFER TO CLIN 3001 FOR REPLACEMENT OF ALL ICRCUIT SETTER
VALVES WITHIN ENTIRE BUILDING. PLUMBING CONTRACTOR MAY
OPT TO HAVE DEDICATED CREWS ASSIGNED TO THIS TASK DURING
RISER OUTAGE TO LIMIT NUMBER OF SECONDARY OUTAGES
REQUIRED. HOWEVER, IF ENOUGH PLUMBERS ARE AVAILABLE TO
ACHIEVE THIS DURING LIMITED OUTAGE TIMEFRAME, THAN REFER
TO GENERAL NOTES ON DRAWING PP002 FOR 'LARGE OUTAGES' TO
PERFORM PRIOR TO THE MAJOR RISER OUTAGE.
VERTICAL RISER REPLACEMENT (TYPE 2 - WITHIN ENCLOSED SHAFT)
• IN GENERAL, MAJOR RATED SHAFTS SHOWN IN THESE DRAWINGS
HAVE EXISTING FULL SIZED ACCESS DOOR FROM BASE OF SHAFT
ON FIRST FLOOR LEVEL. HOWEVER, THAT IS TYPICALLY THE ONLY
ACCESS INTO THESE SHAFTS THAT ARE FULLY OPEN (NO
INTERMEDIATE FLOOR STRUCTURES) UP THROUGH PENTHOUSE
LEVEL WHERE RATED WALLS ARE BUILT-UP WITH LID (TYPICALLY
12'+) WITHIN ENCLOSED PENTHOUSE LEVEL.
• IN ORDER TO GAIN ACCESS TO TOP OF SHAFT, CONTRACTOR WILL
BE REQUIRED TO FURNSIH AND INSTALL FIRE RATED DOOR
ASSEMBLIES FROM PENTHOUSE LEVEL. THESE DOORS MAY BE
USED IN CONJUCTION OF RIGGING FOR BOSUN CHAIRS FROM TOP
OF SHAFT IF CONTRACTOR DEEMS THAT AS SAFE AFTER REVIEW
WITH THEIR INTERNAL SAFETY OFFICIAL.
• IN ADDITION TO ACCESS ON TOP LEVEL OF SHAFT, CONTRACTOR
WILL HAVE OPPORTUNITIES TO INSTALL 24"X24" OR 48"X24" FIRE
RATED ACCESS PANELS ON ANY OTHER LEVEL REQUIRED (BUT
ONLY FROM INTERSTITIAL SPACE, INSTALLATION OF ACCESS
PANELS FROM PATIENT CARE AREAS WILL NOT BE PERMITTED).
• CONTRACTOR WILL BE REQUIRED TO PROVIDE THEIR OWN
SCAFFOLDING REQUIRED AT EACH LEVEL TO INSTALL NEW COLD
WATER RISERS ADJACENT TO EXISTING PRIOR TO SIOWTCHOVER
OUTAGE. SCAFFOLDS SHOULD BE STRATEGICALLY PLACE TO
ALLOW ACCESS FOR RECONNECTION TO FLOOR TAKE-OFF PIPING
INSIDE OF EACH SHAFT.
• EXISTING CONDITION PDF SKETCHES ARE PROVIDED ON DRAWINGS
WHERE WORK INSIDE CONFINED AREAS OF RATED SHAFTS IS
REQUIRED. THESE SKETCHES ARE FOR CONTRACTOR REFERENCE
ONLY AND MAY NOT FULLY INDICATE ALL SERVICES WITHIN SHAFT
ENCLOSURES. CONTRACTOR WILL BE REQUIRED TO FIELD VERIFY
ACTUAL SITE CONDITIONS OF EACH SHAFT WHILE DEVELOPING
ACCESS AND SAFETY PLANNING.
NOTE THAT SOME AREAS HAVE EXISTING COPPER MAINS INTENDED TO
REPLACE GALVANIZED RISERS. HOWEVER THESE MAINS WERE
INSTALLED UP TO 15-25 YEARS AGO AND THEIR INTEGRITY IS
QUESTIONABLE. CONTRACTOR MAY UTILIZE THE EXISTING ROUTE, AND
CORRESPONDING SUPPORT HANGERS, BUT MUST FULLY REMOVE ALL
ABANDONED/UNUSED COPPER PIPING MAINS. ONCE OFF SITE THE
CONTRACTOR MAY TAKE OWNERSHIP OF PIPING FOR RECYLCING OR
REPURPOSING, BUT IT SHALL NOT BE UTILIZED WITHIN THIS PROJECT.
NO EXISTING PIPING WILL BE ALLOWED TO BE LEFT ABANDONED. SOME
AREAS HAVE RESTRICITVE ACCESS DUE TO SURROUNDING PIPES
AND/OR STRUCTURE AND MAY REQUIRE TEMPORARY REMOVAL OF
PIPING OR DUCTWORK TO GAIN ACCESS FOR DEMOLITION.
CONTRACTOR TO ASSUME SOME LEVEL OF DISCONNECT/RECONNECT
OF EXISTING SERVICES TO GAIN ACCCESS FOR COMPLETE DEMOLITION
OF EXISTING PIPING, OR INSTALLATION OF NEW PIPE IN CONGESTED
AREAS. REFER TO DRAWING NOTES FOR ADDITIONAL INFORMATION.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS SUBMISSION
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
A
C R e v it P ro je c ts
\V A
B u ild in g
P h a s e
M e c h a n ic a l ja s o n g o tt w a lt
.r v t
/3 /2
:4
:0
A M
ALL LEVELS - PHASE 6 -
ENLARGED RISER "M" COLD
WATER REPLACEMENT PLANS
PREVENT LEGIONELLA,
PHASE III
MINNEAPOLIS
618-14-118
11/30/2022 JG TM / JG618-14-118
1356-PP106.2
1/8" = 1'-0"
BASEMENT - RISER M REPLACEMENT DEMO
1/8" = 1'-0"
BASEMENT - RISER M REPLACEMENT NEW
1/8" = 1'-0"
FIRST LEVEL - RISER M REPLACEMENT DEMO
1/8" = 1'-0"
FIRST LEVEL - RISER M REPLACEMENT NEW
1/8" = 1'-0"
SECOND LEVEL - RISER M REPLACEMENT DEMO
1/8" = 1'-0"
SECOND LEVEL - RISER M REPLACEMENT NEW
1/8" = 1'-0"
THIRD LEVEL - RISER M REPLACEMENT DEMO
1/8" = 1'-0"
THIRD LEVEL - RISER M REPLACEMENT NEW
1/8" = 1'-0"
FOURTH LEVEL - RISER M REPLACEMENT DEMO
1/8" = 1'-0"
FOURTH LEVEL - RISER M REPLACEMENT NEW
41360DATE REG. NO.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED BY ME
OR UNDER MY DIRECT SUPERVISION AND THAT I
AM A DULY LICENSED PROFESSIONAL ENGINEER
UNDER THE LAWS OF THE STATE OF MINNESOTA.
JASON GOTTWALT, P.E.
TS
TS
TS
TS
KEY NOTES:GENERAL NOTES:
TS
TS
TS
TS
TS
TS
TS
TS
TS
TS
FF
7.B
7.C
REFER TO DETAIL
1/1356-PP108.1 FOR
VALVE LOCATION.
REFER TO DETAIL
2/1356-PP107 FOR
VALVE LOCATION.
4" CW
1356-PP107.1
BP.A
BP.C
BP.B
7.A
4" CW
C W
H W
H W
3/4"
8" CW
2" HW
/2
/2
M.A
M.C
M.B
CONNECTION
TO PREVIOUS
PHASE.
TO BE
DEMOLISHED
IN NEXT
PHASE
8" CW
7.C
7.A
7.B
4" CW
BP.B
BP.C
BP.A
8" CW
3.C
3.B 3.A
NOTE THAT THESE KEY NOTES ARE SPECIFIC TO THIS DRAWING (DO
NOT REFER TO MASTER KEY NOTES ON SHEET 1356-PP003). NOT ALL
KEY NOTES ARE UTILIZED AND MAY HAVE GAPS OF MISSING NOTE
NUMBERS TO KEEP GROUPS OF TEN NOTES AVAILABLE PER PHASE.
SHUT-OFF VALVE M.C AND VALVE 3.B TO ISOLATE SECTION OF PIPING
INDICATED FOR REMOVAL. REFER TO GENERAL NOTES FOR
PROVISIONS TO BE TAKEN TO VERIFY ANY EXISTING VALVE LEAKAGE.
ONCE ISOLATED, REMOVE SECTION OF 8" GALVANZED PIPING LOOP.
CUT INTO SECTIONS SMALL ENOUGH TO TRANSPORT TO LOADING
DOCK AREA FOR REMOVAL. INCLUDE DEMOLITION OF EXISTING
SUPPORTS MOUNTED TO PIPING RACKS, NEW PIPING WILL BE
SUPPORTED ONTO EXISTING RACK STRUCTURE BUT SHOULD BE
PROVIDED WITH NEW PIPE CLAMPS.
NOT USED THROUGH KEY NOTE
INSTALL NEW SECTION OF 8" SCHEDULE 10 STAINLESS STEEL PIPING TO
REPLACE PREVIOUSLY REMOVED. INSTALL IN EXACT SAME LOCATION
AS REMOVED SECTION OF PIPING. NOTE THAT THIS SECTION IS
ROUTED THROUGH INTERSTITIAL AND/OR ABOVE SHOPS AREAS.
PROVIDE TEMPORARY END CAPS AT EITHER SIDE OF NEW PIPING
SECTION. FIRST PERFORM A PRESSURE TEST ON PIPING SECTION PER
SPECIFICATION REQUIREMENTS, AND THEN STERILIZE PIPING USING
CHLORINE SOLUTION FOR AT LEASE 24 HOURS PRIOR TO FLUSHING.
INCLUDE DRAIN/FILL VALVES ON EITHER END TO ACCOMPLISH.
INSULATE ENTIRE LENGTH OF PIPING PER SPECIFICATION
REQUIREMENTS. INCLUDE CONTINUOUS PVC COVERING THROUGHOUT
AND PREPARE ENDS FOR EXTENSION TO NEXT SUB-PHASE PIPING
WHICH WILL INCLUDE INSULATING ALL VALVE BODIES.
NOT USED THROUGH KEY NOTE
SHUT-OFF VALVE 3.C AND VALVE 7.B TO ISOLATE SECTION OF PIPING
INDICATED FOR REMOVAL. REFER TO GENERAL NOTES FOR
PROVISIONS TO BE TAKEN TO VERIFY ANY EXISTING VALVE LEAKAGE.
ONCE ISOLATED, REMOVE SECTION OF 8" GALVANZED PIPING LOOP.
CUT INTO SECTIONS SMALL ENOUGH TO TRANSPORT TO LOADING
DOCK AREA FOR REMOVAL. INCLUDE DEMOLITION OF EXISTING
SUPPORTS MOUNTED TO PIPING RACKS, NEW PIPING WILL BE
SUPPORTED ONTO EXISTING RACK STRUCTURE BUT SHOULD BE
PROVIDED WITH NEW PIPE CLAMPS.
NOT USED THROUGH KEY NOTE
INSTALL NEW SECTION OF 8" SCHEDULE 10 STAINLESS STEEL PIPING TO
REPLACE PREVIOUSLY REMOVED. INSTALL IN EXACT SAME LOCATION
AS REMOVED SECTION OF PIPING. NOTE THAT THIS SECTION IS
ROUTED THROUGH INTERSTITIAL AND/OR ABOVE SHOPS AREAS.
PROVIDE TEMPORARY END CAPS AT EITHER SIDE OF NEW PIPING
SECTION. FIRST PERFORM A PRESSURE TEST ON PIPING SECTION PER
SPECIFICATION REQUIREMENTS, AND THEN STERILIZE PIPING USING
CHLORINE SOLUTION FOR AT LEASE 24 HOURS PRIOR TO FLUSHING.
INCLUDE DRAIN/FILL VALVES ON EITHER END TO ACCOMPLISH.
INSULATE ENTIRE LENGTH OF PIPING PER SPECIFICATION
REQUIREMENTS. INCLUDE CONTINUOUS PVC COVERING THROUGHOUT
AND PREPARE ENDS FOR EXTENSION TO NEXT SUB-PHASE PIPING
WHICH WILL INCLUDE INSULATING ALL VALVE BODIES.
NOT USED THROUGH KEY NOTE
SHUT-OFF VALVE M.C AND VALVE J.B (BOTH FURTHER OUT TO NEXT
ADJACENT RISER VALVES OUTSIDE THE EXTENTS OF THIS PHASE
DRAWING) TO ISOLATE SHAFT 7 FOR VALVE REPLACEMENT. REFER TO
GENERAL NOTES FOR PROVISIONS TO BE TAKEN TO VERIFY ANY
EXISTING VALVE LEAKAGE AND AREAS THAT WILL BE AFFECTED BY
THIS MAJOR WATER OUTAGE.
ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER
SIDE OF COLD WATER RISER TAK-OFF VALVE WITH NEW STAINLESS 8"
TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD
EXISTING 4" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN
LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING
RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO
UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH
40 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN
OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).
ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER
SIDE OF COLD WATER RISER TAK-OFF VALVE WITH NEW STAINLESS 8"
TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD
EXISTING 6" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN
LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING
RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO
UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH
40 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN
OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).
DURING OUTAGE, INSTALL THERMOWELLS ON BOTH HOT AND COLD
WATER MAINS TO ACCEPT AN INSERTION TYPE TEMPERATURE SENSOR
TO BE INTEGRATED INTO BUILDING AUTOMATION SYSTEM FOR
INFORMATION MONITORING AND TRENDING.
INSTALL STRAP ON TEMPERATURE SENSORS INDICATE ON
RECIRCULATION PIPING. REPAIR ANY DAMAGED OR REMOVED
INSULATION ON COMPLETION.
ONCE VALVE INSTALLATION IS COMPLETED, INSULATE ALL AFFECT
PIPING AND NEW VALVE BODIES COMPLETELY. COVER EVERYTHING
WITH PVC JACKET COVERS AND SEAL AS REQUIRED. INSULATION CAN
OCCUR DURING NORMAL HOURS AFTER OUTAGE COMPLETION, BUT
SHOULD NOT BE DELAYED FOR ANY MORE THAN 3 BUSINESS DAYS.
PHASE 7.1 (DEMO - REFER TO DETAIL 1 AND 10-19 SERIES KEY NOTES):
THE EXISTING GALVANIZED 8" COLD WATER PIPING MAIN TO BE REMOVED
BETWEEN INTERIOR VALVES OF RISERS INDICATED IN KEY NOTES. REFER
TO WORK SEQUENCE DESCRIBED IN 'ISOLATION OF MAIN PIPING LOOP
SECTIONS' BELOW TO EITHER CONFIRM EXISTING VALVES DO NOT LEAK, OR
FOLLOW GUIDELINE PROVISIONS TO BE TAKEN IF THEY ARE FOUND
DEFECTIVE. NO OUTAGES WILL BE REQUIRED DURING THIS SUB-PHASE
WITH MAIN LOOP CONTINUALLY SERVING BOTH SIDES.
PHASE 7.2 (BUILD-BACK - REFER TO DETAIL 2 AND 20-29 SERIES KEY NOTES):
INSTALL NEW PIPING IN SAME LOCATION AS REMOVED SECTION OF 8" COLD
WATER MAIN. MAY REUTILIZE EXISTING PIPING RACK FOR PIPING
SUPPORTS. REFER TO KEY NOTES FOR ADDITIONAL INFORMATION RELATED
TO INSTALLATION.
PHASE 7.3 (DEMO - REFER TO DETAIL 3 AND 30-39 SERIES KEY NOTES):
THE EXISTING GALVANIZED 8" COLD WATER PIPING MAIN TO BE REMOVED
BETWEEN INTERIOR VALVES OF RISERS INDICATED IN KEY NOTES. REFER
TO WORK SEQUENCE DESCRIBED IN 'ISOLATION OF MAIN PIPING LOOP
SECTIONS' BELOW TO EITHER CONFIRM EXISTING VALVES DO NOT LEAK, OR
FOLLOW GUIDELINE PROVISIONS TO BE TAKEN IF THEY ARE FOUND
DEFECTIVE. NO OUTAGES WILL BE REQUIRED DURING THIS SUB-PHASE
WITH MAIN LOOP CONTINUALLY SERVING BOTH SIDES.
PHASE 7.4 (BUILD-BACK - REFER TO DETAIL 4 AND 40-49 SERIES KEY NOTES):
INSTALL NEW PIPING IN SAME LOCATION AS REMOVED SECTION OF 8" COLD
WATER MAIN. MAY REUTILIZE EXISTING PIPING RACK FOR PIPING
SUPPORTS. REFER TO KEY NOTES FOR ADDITIONAL INFORMATION RELATED
TO INSTALLATION.
PHASE 7.5 (RISER VALVE REPLACEMENT - 50+ SERIES KEY NOTES):
AREA SHOWN IN EXPANDED 1/4" = 1'-0" PLAN VIEW SHALL HAVE BOTH 8"
ISOLATION VALVES REPLACED WITH NEW TRIPLE OFFSET BUTTERFLY
VALVES. PLAN FOR OUTAGE OF SHAFT 7 AND AREA SERVED BY VALVE BP.A
AND REPLACE EXISTING 4" AND 6" TAKE-OFF VALVES AT SAME TIME.
INCLUDE 1.5" DRAIN VALVE AT INTERSECTION BETWEEN THREE(3)
REPLACED VALVES. THIS SUB-PHASE WILL CAUSE A LARGE DOMESTIC
WATER OUTAGE FOR AREAS OF FACILITY THAT MAY BE CRITICAL,
CONTRACTOR SHALL REFER TO 'ALLOWANCE FOR TEMP FIXTURES OR
WATER SERVICES' BELOW FOR ACCOMODATIONS NEEDED FOR THOSE
AREAS. OUTAGE WILL AFFECT THE FOLLOWING DEPARTMENTS AND
SHOULD BE CAREFULLY COORDINATED WITH VA FACILITIES;
• BASEMENT LEVEL: MECHANICAL ROOM MP, AMMS - WAREHOUSE,
AMMS - WAREHOUSE ADMIN, LAUNDRY, PHARMACY INPATIENT, SPD,
• FIRST FLOOR: RADIOLOGY, MECHANICAL SPACE M1, EDUCATION MENTAL
HEALTH CLINIC, PSYCHIATRIC ADMINISTRATION.
• SECOND FLOOR: SURGERY - WAITING, SURGERY - EXAM, SURGERY -
RECOVERY
• THIRD FLOOR: CARDIOLOGY - EKG, REHABILITATION MEDICAL SERVICE,
CHRONIC DISEASE CLINIC, MEDICAL RESEARCH - OFFICES
• FOURTH FLOOR: HUMAN RESOURCES, MAS, MEDICAL RESEARCH,
CANTEEN, EDUCATION
ISOLATION OF MAIN PIPING LOOP SECTIONS:
PERFORM THE FOLLOWING PROCEDURE STEPS TO PROPERLY ISOLATE
EACH SECTION OF PIPING LOOP AS DESCRIBED IN PHASING SEQUENCES,
1) SHUT-OFF ISOLATION VALVES ON INTERIOR SIDE OF LOOP BEING
MODIFIED OR REMOVED TO MAINTAIN SERVICES TO ALL RISERS.
2) REMOVE SECTION OF PIPING, OR TAP TEMPORARY DRAIN CONNECTION
TO VERIFY VALVES ARE HOLDING FOR A MINIMUM PERIOD OF 24 HOURS.
3) IF NO VALVE LEAKAGE, OR MINIMAL AMOUNT, IS WITNESSED THAN
PROCEED TO PIPING MODIFICATION AND/OR DEMOLITION SCOPE OF WORK
IDENTIFIED.
4) IF MODERATE OR SIGNIFICANT VALVE LEAKAGE IS WITNESSED THAN
PROVIDE 1.5" VALVE TAP WITH THREADED CONNECTION TO HOSE TO
NEAREST MECHANICAL ROOM DRAIN DISCHARGE LOCATION. THIS
TEMPORARY DRAIN CONNECTION AND HOSE SHALL BE REMOVED ONCE
NEW RISER VALVE REPLACEMENTS ARE COMPLETED.
---CONTRACTOR WILL BE RESPONSIBLE TO KEEP ON SITE AT LEAST FOUR(4)
SETS OF 1.5" VALVES WITH THREADED CONNECTIONS AND TWO(2) 250' LONG
HOSES OF 1.5" DIAMETER IN SIZE.
CONTRACTOR ALLOWANCE FOR TEMP FIXTURES OR WATER SERVICES:
ASSUME THAT DURING THE COURSE OF THE 8 PHASE DOMESTIC WATER
LOOP REPLACEMENT THAT SPECIFIC AREAS WILL REQUIRE TEMPORARY
SINKS AND/OR EXTENSION OF TEMPORARY WATER SERVICES TO THEIR
DEPARTMENT. CONTRACTORS SHALL INCLUDE THE FOLLOWING
ALLOWANCES WITHIN THEIR BASE BID TO ACCOMODATE THOSE REQUESTS
WHEN THEY ARISE DURING OUTAGE COORDINATION WITH VA FACILITIES.
• INCLUDE UP TO TWELVE(12) TEMPORARY SINK FIXTURES TIED INTO AN
ADJACENT RISER SERVICE. EACH SINK WILL REQUIRE UP TO 50' OF
COPPER PIPE FOR WATER CONNECTIONS, OTHERWISE HOSE WILL BE
UTILIZED IF DISTANCE EXCEEDS THAT SPECIFIED AMOUNT OF PIPING.
• INCLUDE FOUR(4) TEMPORARY BACK-UP WATER CONNECTIONS FOR
COLD WATER SERVICE TO AN ENTIRE DEPARTMENT. TEMPORARY COLD
WATER MAIN SHALL BE ASSUMED AT 2" SIZE AND EXTEND A MAXIMUM OF
250' TO CONNECT INTO AN ADJACENT RISER SERVICE.
• NOTE THAT THE ABOVE IS FOR ENTIRE PROJECT, NOT PER PHASE.
EEFFGGHH
HH'
M.B
M.C
1356-PP107.1
3.B
3.C
FFGGHH
HH'
1356-PP107.1
3.B
3.C
FF
8" CW
2 1/2" RHW
4" HW
FF
6" CW
8" CW8" CW
4" CW
4" HW
2" HW
2 1/2"
3" CHWS
3" CHWR
4" HWR
1 1/2" HWR
2 1/2" HWS
3/4" MPC
3/4" MPS
3/4" MPC
2" CHWR
FFGGHH
HH'
BP.B
BP.A
BP.C
7.B
7.A
7.C
1356-PP107.1
3.B
3.C
FFGGHH
HH'
41 42
7.B
7.C
1356-PP107.1
3.B
3.C
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS SUBMISSION
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
A
C
C R e v it P ro je c ts
\V A
B u ild in g
P h a s e
M e c h a n ic a l ja s o n g o tt w a lt
.r v t
/3 /2
:4
:0
A M
BASEMENT INTERSTITIAL - PHASE
7 - DOMESTIC WATER PLAN
PREVENT LEGIONELLA,
PHASE III
MINNEAPOLIS
618-14-118
11/30/2022 JG TM / JG618-14-118
1356-PP107.1
1/4" = 1'-0"
ENLARGED - PHASE 7.5
NO SCALE
PHASE 7 - ISOMETRIC VIEW
1/16" = 1'-0"
PHASE 7.1 - DEMO
1/16" = 1'-0"
PHASE 7.2 - NEW
NO SCALE
PHASE 7 ELEVATION - WEST INTERSTITIAL 1
NO SCALE
PHASE 7 ELEVATION - WEST INTERSTITIAL 2
1/16" = 1'-0"
PHASE 7.3 - DEMO
1/16" = 1'-0"
PHASE 7.4 - NEW
SHAFT 3 RISER
VALVE ASSEMBLY
INSTALLED AS
PART OF PHASE 5.
41360DATE REG. NO.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED BY ME
OR UNDER MY DIRECT SUPERVISION AND THAT I
AM A DULY LICENSED PROFESSIONAL ENGINEER
UNDER THE LAWS OF THE STATE OF MINNESOTA.
JASON GOTTWALT, P.E.
TST
S T
S
TS
TS
TS
TS
TS
KEY NOTES:GENERAL NOTES:ZAABBCCDDEEFF
1356-PP107.1
SHAFT 7
8" CW
8" CW
4" CW
/4
C
W
4" CW
3" HW
1 1/4" RHW
C W
1" CW
1" CW
1" CW
1 1/2" CW
2" CW
1 1/4" CW
1/2" CW
4" CW
4" CW
2 1/2" CW
1" CW
4" CW
3" HW
1" RHW
4" CW UP
4" CW UP
3" HW UP
1" RHW UP
ZAABBCCDDEEFF
SHAFT 7
4" CW
/4
C
W
1/2" CW 2" CW
/4
C
W
1" CW
1" CW
1" CW
C W
4" CW
3" HW
1 1/4" RHW
4" CW
/2
C W
1" CW
4" CW
4" CW
3" HW
1" RHW
H W
/4
R
H W
/2
C W
4" CW UP
4" CW UP
3" HW UP
1" RHW UP
/2
C W
1 BEFORE OUTAGE: ROUTE NEW SHAFT 7 PIPING PARALLEL TO
EXISTING PIPING TO LEVEL ABOVE.
DURING OUTAGE: REMOVE AND REPLACE MAIN PIPING BETWEEN
VALVES 7.B AND 7.C. MAKE FINAL CONNECTION TO NEW SHAFT 7
PIPING. ABANDON EXISTING COLD WATER RISER PIPING TO BE
DEMOLISHED AFTER ALL SHAFT 7 FINAL CONNECTIONS ARE MADE
AND OUTAGE IS COMPLETE. CONTRACTOR TO VERIFY PIPE SIZING
AND OUTAGE AREAS PRIOR TO CONSTRUCTION.
AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW
AND KEY NOTE 2.
AFTER OUTAGE: REMOVE THE EXISTING COLD WATER RISER PIPING.
DEADLEG OR ABANDONED PIPING SHALL NOT REMAIN.
BASEMENT AREA SERVED BY THIS COLD WATER MAIN BEING
RELOCATED IS STERILE PROCESSING THAT OPERATES 24/7 AND NOT
TOLERANT OF OUTAGES EXTENDING MORE THAN A FEW HOURS.
CONTRACTOR SHALL HAVE NEW PIPING MAIN IN PLACE AND
SIMULTANEOUSLY CONNECTED TO CENTRAL SYSTEM PRIOR TO
SWITCHING EACH POINT OF CONNECTION. ESSENTIALLY THIS
MEANS THAT WEEKEND OUTAGE OF THIS AREA WOULD NOT BE
ACCEPTABLE, INSTALL ISOLATION VALVES AT EACH TAKE-OFF FOR
INDIVIDUAL OUTAGES AT EACH POINT OF CONNECTION.
PRIOR TO 'MINI-OUTAGES' DESCRIBED IN KEY NOTE #3 ABOVE.
INSTALL NEW 4" STAINLESS STEEL COLD WATER MAIN ALONG
APPROXIMATE ROUTE INDICATED WHICH EXTENDS TO OUTSKIRT
AREA OF HEAVILY CONGESTED INTERSTITIAL SPACE SERVING
STERILE PROCESSING BELOW. NOTE THAT ACCESSIBILITY TO THIS
ROUTE WILL STILL BE 'CHALLENGING'. ALSO NOTE THAT UNLIKE
OTHER AREAS, OUTAGES CAUSED BY DISCONNECTION AND
RECONNECTION OF HEAVILY CONGESTED DUCTWORK AND/OR
MEDICAL GAS PIPING MAY NOT BE ALLOWED DUE TO OUTAGE
RESTRICTIONS FOR CRITICAL SPACES BELOW. FIELD VERIFY SITE
CONDITIONS PRIOR TO BID.
REFER TO DRAWING 1356-PP107.3 FOR CONTINUATION AND
REPLACEMENT OF EXISTING RISER PIPING PARALLEL TO EXISTING.
A.
B.
C.
D.
E.
F.
THE OUTLINE OF 'MEANS-AND-METHODS' NOTES BELOW FOR VERTICAL
COLD WATER RISER REPLACEMENTS INDICATED WITHIN THESE
DRAWINGS IS NOT INTENDED TO BE ALL-INCLUSIVE OF EFFORT
REQUIRED BY CONTRACTOR. NOR ARE THESE NOTES AND/OR
SUGGESTIONS MEANT TO LIMIT CONTRACTORS FROM DEVELOPING
THEIR OWN APPROACH THAT MAY BE CONSIDERED MORE COST
EFFECTIVE OR SAFE. THESE NOTES ARE MAINLY MEANT TO QUALIFY
EXISTING CONDITIONS AND DEFINE MINIMUM LEVEL OF PLANNING
REQUIRED BY VA FOR EACH OF THESE TIME SENSITIVE OUTAGES.
NO MAJOR WATER OUTAGE SHALL LAST MORE THAN 12 HOURS IN
DURATION. PLUMBING CONTRACTOR TO DETERMINE ADEQUATE
NUMBER OF PLUMBER CREWS REQUIRED TO PERFORM MULTIPLE
TASKS SIMULTANEOUSLY DURING OUTAGES. ALL OUTAGES SHALL BE
ASSUMED TO BE PERFORMED DURING WEEKEND OR NIGHT OVERTIME
HOURS WHEN BIDDING THIS PROJECT.
VERTICAL RISER REPLACEMENT (TYPE 1 - WITHIN MECHANICAL ROOM)
• FOR RISERS WITHIN MECHANICAL ROOMS, CONTRACTOR SHALL
CORE DRILL HOLES THROUGH FLOOR ADJACENT TO EXISTING
PLUMBING RISER FOR NEW INSTALLATION. EXISTING FLOOR
PENETRATIONS AND/OR SLEEVE SHALL BE PATCHED FLUSH TO
EXISTING FLOOR AS REQUIRE UPON DEMOLITION OF THOSE RISERS.
• EXISTINGT TAKE-OFF VALVES MAY REQUIRE RELOCATION FOR
CONNECTION INTO NEW RISER. VERIFY ADEQUATE ACCESS TO ALL
TAKE-OFF VALVES AND PROVIDE WITH NEW LAMINATE SIGNAGE.
ANY VALVES FOUND AT INACCESSIBLE LOCATIONS SHALL BE
RELOCATED BY CONTRACTOR.
• REFER TO CLIN 3001 FOR REPLACEMENT OF ALL ICRCUIT SETTER
VALVES WITHIN ENTIRE BUILDING. PLUMBING CONTRACTOR MAY
OPT TO HAVE DEDICATED CREWS ASSIGNED TO THIS TASK DURING
RISER OUTAGE TO LIMIT NUMBER OF SECONDARY OUTAGES
REQUIRED. HOWEVER, IF ENOUGH PLUMBERS ARE AVAILABLE TO
ACHIEVE THIS DURING LIMITED OUTAGE TIMEFRAME, THAN REFER
TO GENERAL NOTES ON DRAWING PP002 FOR 'LARGE OUTAGES' TO
PERFORM PRIOR TO THE MAJOR RISER OUTAGE.
VERTICAL RISER REPLACEMENT (TYPE 2 - WITHIN ENCLOSED SHAFT)
• IN GENERAL, MAJOR RATED SHAFTS SHOWN IN THESE DRAWINGS
HAVE EXISTING FULL SIZED ACCESS DOOR FROM BASE OF SHAFT
ON FIRST FLOOR LEVEL. HOWEVER, THAT IS TYPICALLY THE ONLY
ACCESS INTO THESE SHAFTS THAT ARE FULLY OPEN (NO
INTERMEDIATE FLOOR STRUCTURES) UP THROUGH PENTHOUSE
LEVEL WHERE RATED WALLS ARE BUILT-UP WITH LID (TYPICALLY
12'+) WITHIN ENCLOSED PENTHOUSE LEVEL.
• IN ORDER TO GAIN ACCESS TO TOP OF SHAFT, CONTRACTOR WILL
BE REQUIRED TO FURNSIH AND INSTALL FIRE RATED DOOR
ASSEMBLIES FROM PENTHOUSE LEVEL. THESE DOORS MAY BE
USED IN CONJUCTION OF RIGGING FOR BOSUN CHAIRS FROM TOP
OF SHAFT IF CONTRACTOR DEEMS THAT AS SAFE AFTER REVIEW
WITH THEIR INTERNAL SAFETY OFFICIAL.
• IN ADDITION TO ACCESS ON TOP LEVEL OF SHAFT, CONTRACTOR
WILL HAVE OPPORTUNITIES TO INSTALL 24"X24" OR 48"X24" FIRE
RATED ACCESS PANELS ON ANY OTHER LEVEL REQUIRED (BUT
ONLY FROM INTERSTITIAL SPACE, INSTALLATION OF ACCESS
PANELS FROM PATIENT CARE AREAS WILL NOT BE PERMITTED).
• CONTRACTOR WILL BE REQUIRED TO PROVIDE THEIR OWN
SCAFFOLDING REQUIRED AT EACH LEVEL TO INSTALL NEW COLD
WATER RISERS ADJACENT TO EXISTING PRIOR TO SIOWTCHOVER
OUTAGE. SCAFFOLDS SHOULD BE STRATEGICALLY PLACE TO
ALLOW ACCESS FOR RECONNECTION TO FLOOR TAKE-OFF PIPING
INSIDE OF EACH SHAFT.
• EXISTING CONDITION PDF SKETCHES ARE PROVIDED ON DRAWINGS
WHERE WORK INSIDE CONFINED AREAS OF RATED SHAFTS IS
REQUIRED. THESE SKETCHES ARE FOR CONTRACTOR REFERENCE
ONLY AND MAY NOT FULLY INDICATE ALL SERVICES WITHIN SHAFT
ENCLOSURES. CONTRACTOR WILL BE REQUIRED TO FIELD VERIFY
ACTUAL SITE CONDITIONS OF EACH SHAFT WHILE DEVELOPING
ACCESS AND SAFETY PLANNING.
NOTE THAT SOME AREAS HAVE EXISTING COPPER MAINS INTENDED TO
REPLACE GALVANIZED RISERS. HOWEVER THESE MAINS WERE
INSTALLED UP TO 15-25 YEARS AGO AND THEIR INTEGRITY IS
QUESTIONABLE. CONTRACTOR MAY UTILIZE THE EXISTING ROUTE, AND
CORRESPONDING SUPPORT HANGERS, BUT MUST FULLY REMOVE ALL
ABANDONED/UNUSED COPPER PIPING MAINS. ONCE OFF SITE THE
CONTRACTOR MAY TAKE OWNERSHIP OF PIPING FOR RECYLCING OR
REPURPOSING, BUT IT SHALL NOT BE UTILIZED WITHIN THIS PROJECT.
NO EXISTING PIPING WILL BE ALLOWED TO BE LEFT ABANDONED. SOME
AREAS HAVE RESTRICITVE ACCESS DUE TO SURROUNDING PIPES
AND/OR STRUCTURE AND MAY REQUIRE TEMPORARY REMOVAL OF
PIPING OR DUCTWORK TO GAIN ACCESS FOR DEMOLITION.
CONTRACTOR TO ASSUME SOME LEVEL OF DISCONNECT/RECONNECT
OF EXISTING SERVICES TO GAIN ACCCESS FOR COMPLETE DEMOLITION
OF EXISTING PIPING, OR INSTALLATION OF NEW PIPE IN CONGESTED
AREAS. REFER TO DRAWING NOTES FOR ADDITIONAL INFORMATION.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS SUBMISSION
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
C
C R e v it P ro je c ts
\V A
B u ild in g
P h a s e
M e c h a n ic a l ja s o n g o tt w a lt
.r v t
/3 /2
:4
:1
A M
BASEMENT - PHASE 7 - ENLARGED
SHAFT 7 COLD WATER
REPLACEMENT PLANS
PREVENT LEGIONELLA,
PHASE III
MINNEAPOLIS
618-14-118
11/30/2022 JG TM / JG618-14-118
1356-PP107.2
1/8" = 1'-0"
BASEMENT - SHAFT 7 REPLACEMENT NEW
1/8" = 1'-0"
BASEMENT - SHAFT 7 REPLACEMENT DEMO
NO SCALE
SHAFT 7 - BASEMENT DETAIL
41360DATE REG. NO.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED BY ME
OR UNDER MY DIRECT SUPERVISION AND THAT I
AM A DULY LICENSED PROFESSIONAL ENGINEER
UNDER THE LAWS OF THE STATE OF MINNESOTA.
JASON GOTTWALT, P.E.
KEY NOTES:GENERAL NOTES:
Z
4" CW UP & DN
4" CW UP & DN
3" HW DN
2 1/2" HW UP
1" RHW DN
3/4" RHW UP
Z
4" CW UP & DN
4" CW UP & DN
3" HW DN
2 1/2" HW UP
1" RHW DN
3/4" RHW UP
3" CW
Z
4" CW UP & DN
4" CW UP & DN
2 1/2" HW UP & DN
3/4" RHW UP & DN
Z
4" CW UP & DN
4" CW UP & DN
2 1/2" HW UP & DN
3/4" RHW UP & DN
3" CW
Z
4" CW DN
3" CW UP
4" CW DN
3" CW UP
2 1/2" HW DN
2" HW UP
3/4" RHW UP & DN
Z
4" CW DN
3" CW UP
4" CW DN
3" CW UP
2 1/2" HW DN
2" HW DN
3/4" RHW UP & DN
Z
3" CW DN
3" CW DN
2" HW DN
1/2" RHW DN
Z
3" CW DN
3" CW DN
2" HW DN
1/2" RHW DN
1 BEFORE OUTAGE: ROUTE NEW SHAFT 7 PIPING PARALLEL TO
EXISTING PIPING TO LEVEL ABOVE. EXTEND NEW TAKEOFFS TO
EXISTING BRANCH TAKEOFFS AND PREPARE FOR NEW CONNECTION.
DURING OUTAGE: DISCONNECT EXISTING BRANCH TAKEOFFS AND
REMOVE TAKEOFF PIPING. MAKE TAKEOFF FINAL CONNECTIONS.
ABANDON EXISTING COLD WATER RISER PIPING TO BE DEMOLISHED
AFTER ALL SHAFT 7 FINAL CONNECTIONS ARE MADE AND OUTAGE IS
COMPLETE. CONTRACTOR TO VERIFY PIPE SIZING AND OUTAGE
AREAS PRIOR TO CONSTRUCTION.
AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW
AND KEY NOTE 2.
AFTER OUTAGE: REMOVE ABANDONED COLD WATER RISER PIPING.
DEADLEG OR ABANDONED PIPING SHALL NOT REMAIN.
A.
B.
C.
D.
E.
F.
THE OUTLINE OF 'MEANS-AND-METHODS' NOTES BELOW FOR VERTICAL
COLD WATER RISER REPLACEMENTS INDICATED WITHIN THESE
DRAWINGS IS NOT INTENDED TO BE ALL-INCLUSIVE OF EFFORT
REQUIRED BY CONTRACTOR. NOR ARE THESE NOTES AND/OR
SUGGESTIONS MEANT TO LIMIT CONTRACTORS FROM DEVELOPING
THEIR OWN APPROACH THAT MAY BE CONSIDERED MORE COST
EFFECTIVE OR SAFE. THESE NOTES ARE MAINLY MEANT TO QUALIFY
EXISTING CONDITIONS AND DEFINE MINIMUM LEVEL OF PLANNING
REQUIRED BY VA FOR EACH OF THESE TIME SENSITIVE OUTAGES.
NO MAJOR WATER OUTAGE SHALL LAST MORE THAN 12 HOURS IN
DURATION. PLUMBING CONTRACTOR TO DETERMINE ADEQUATE
NUMBER OF PLUMBER CREWS REQUIRED TO PERFORM MULTIPLE
TASKS SIMULTANEOUSLY DURING OUTAGES. ALL OUTAGES SHALL BE
ASSUMED TO BE PERFORMED DURING WEEKEND OR NIGHT OVERTIME
HOURS WHEN BIDDING THIS PROJECT.
VERTICAL RISER REPLACEMENT (TYPE 1 - WITHIN MECHANICAL ROOM)
• FOR RISERS WITHIN MECHANICAL ROOMS, CONTRACTOR SHALL
CORE DRILL HOLES THROUGH FLOOR ADJACENT TO EXISTING
PLUMBING RISER FOR NEW INSTALLATION. EXISTING FLOOR
PENETRATIONS AND/OR SLEEVE SHALL BE PATCHED FLUSH TO
EXISTING FLOOR AS REQUIRE UPON DEMOLITION OF THOSE RISERS.
• EXISTINGT TAKE-OFF VALVES MAY REQUIRE RELOCATION FOR
CONNECTION INTO NEW RISER. VERIFY ADEQUATE ACCESS TO ALL
TAKE-OFF VALVES AND PROVIDE WITH NEW LAMINATE SIGNAGE.
ANY VALVES FOUND AT INACCESSIBLE LOCATIONS SHALL BE
RELOCATED BY CONTRACTOR.
• REFER TO CLIN 3001 FOR REPLACEMENT OF ALL ICRCUIT SETTER
VALVES WITHIN ENTIRE BUILDING. PLUMBING CONTRACTOR MAY
OPT TO HAVE DEDICATED CREWS ASSIGNED TO THIS TASK DURING
RISER OUTAGE TO LIMIT NUMBER OF SECONDARY OUTAGES
REQUIRED. HOWEVER, IF ENOUGH PLUMBERS ARE AVAILABLE TO
ACHIEVE THIS DURING LIMITED OUTAGE TIMEFRAME, THAN REFER
TO GENERAL NOTES ON DRAWING PP002 FOR 'LARGE OUTAGES' TO
PERFORM PRIOR TO THE MAJOR RISER OUTAGE.
VERTICAL RISER REPLACEMENT (TYPE 2 - WITHIN ENCLOSED SHAFT)
• IN GENERAL, MAJOR RATED SHAFTS SHOWN IN THESE DRAWINGS
HAVE EXISTING FULL SIZED ACCESS DOOR FROM BASE OF SHAFT
ON FIRST FLOOR LEVEL. HOWEVER, THAT IS TYPICALLY THE ONLY
ACCESS INTO THESE SHAFTS THAT ARE FULLY OPEN (NO
INTERMEDIATE FLOOR STRUCTURES) UP THROUGH PENTHOUSE
LEVEL WHERE RATED WALLS ARE BUILT-UP WITH LID (TYPICALLY
12'+) WITHIN ENCLOSED PENTHOUSE LEVEL.
• IN ORDER TO GAIN ACCESS TO TOP OF SHAFT, CONTRACTOR WILL
BE REQUIRED TO FURNSIH AND INSTALL FIRE RATED DOOR
ASSEMBLIES FROM PENTHOUSE LEVEL. THESE DOORS MAY BE
USED IN CONJUCTION OF RIGGING FOR BOSUN CHAIRS FROM TOP
OF SHAFT IF CONTRACTOR DEEMS THAT AS SAFE AFTER REVIEW
WITH THEIR INTERNAL SAFETY OFFICIAL.
• IN ADDITION TO ACCESS ON TOP LEVEL OF SHAFT, CONTRACTOR
WILL HAVE OPPORTUNITIES TO INSTALL 24"X24" OR 48"X24" FIRE
RATED ACCESS PANELS ON ANY OTHER LEVEL REQUIRED (BUT
ONLY FROM INTERSTITIAL SPACE, INSTALLATION OF ACCESS
PANELS FROM PATIENT CARE AREAS WILL NOT BE PERMITTED).
• CONTRACTOR WILL BE REQUIRED TO PROVIDE THEIR OWN
SCAFFOLDING REQUIRED AT EACH LEVEL TO INSTALL NEW COLD
WATER RISERS ADJACENT TO EXISTING PRIOR TO SIOWTCHOVER
OUTAGE. SCAFFOLDS SHOULD BE STRATEGICALLY PLACE TO
ALLOW ACCESS FOR RECONNECTION TO FLOOR TAKE-OFF PIPING
INSIDE OF EACH SHAFT.
• EXISTING CONDITION PDF SKETCHES ARE PROVIDED ON DRAWINGS
WHERE WORK INSIDE CONFINED AREAS OF RATED SHAFTS IS
REQUIRED. THESE SKETCHES ARE FOR CONTRACTOR REFERENCE
ONLY AND MAY NOT FULLY INDICATE ALL SERVICES WITHIN SHAFT
ENCLOSURES. CONTRACTOR WILL BE REQUIRED TO FIELD VERIFY
ACTUAL SITE CONDITIONS OF EACH SHAFT WHILE DEVELOPING
ACCESS AND SAFETY PLANNING.
NOTE THAT SOME AREAS HAVE EXISTING COPPER MAINS INTENDED TO
REPLACE GALVANIZED RISERS. HOWEVER THESE MAINS WERE
INSTALLED UP TO 15-25 YEARS AGO AND THEIR INTEGRITY IS
QUESTIONABLE. CONTRACTOR MAY UTILIZE THE EXISTING ROUTE, AND
CORRESPONDING SUPPORT HANGERS, BUT MUST FULLY REMOVE ALL
ABANDONED/UNUSED COPPER PIPING MAINS. ONCE OFF SITE THE
CONTRACTOR MAY TAKE OWNERSHIP OF PIPING FOR RECYLCING OR
REPURPOSING, BUT IT SHALL NOT BE UTILIZED WITHIN THIS PROJECT.
NO EXISTING PIPING WILL BE ALLOWED TO BE LEFT ABANDONED. SOME
AREAS HAVE RESTRICITVE ACCESS DUE TO SURROUNDING PIPES
AND/OR STRUCTURE AND MAY REQUIRE TEMPORARY REMOVAL OF
PIPING OR DUCTWORK TO GAIN ACCESS FOR DEMOLITION.
CONTRACTOR TO ASSUME SOME LEVEL OF DISCONNECT/RECONNECT
OF EXISTING SERVICES TO GAIN ACCCESS FOR COMPLETE DEMOLITION
OF EXISTING PIPING, OR INSTALLATION OF NEW PIPE IN CONGESTED
AREAS. REFER TO DRAWING NOTES FOR ADDITIONAL INFORMATION.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
CONSTRUCTION
DOCUMENTS SUBMISSION
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRUE NORTH
PLAN NORTH
C
C R e v it P ro je c ts
\V A
B u ild in g
P h a s e
M e c h a n ic a l ja s o n g o tt w a lt
.r v t
/3 /2
:4
:0
A M
LEVELS 1-4 - PHASE 7 - ENLARGED
SHAFT 7 COLD WATER
REPLACEMENT PLANS
PREVENT LEGIONELLA,
PHASE III
MINNEAPOLIS
618-14-118
11/30/2022 JG TM / JG618-14-118
1356-PP107.3
1/8" = 1'-0"
FIRST LEVEL - SHAFT 7 REPLACEMENT DEMO
1/8" = 1'-0"
FIRST LEVEL - SHAFT 7 REPLACEMENT NEW
1/8" = 1'-0"
SECOND LEVEL - SHAFT 7 REPLACEMENT DEMO
1/8" = 1'-0"
SECOND LEVEL - SHAFT 7 REPLACEMENT NEW
1/8" = 1'-0"
THIRD LEVEL - SHAFT 7 REPLACEMENT DEMO
1/8" = 1'-0"
THIRD LEVEL - SHAFT 7 REPLACEMENT NEW
1/8" = 1'-0"
FOURTH LEVEL - SHAFT 7 REPLACEMENT DEMO
1/8" = 1'-0"
FOURTH LEVEL - SHAFT 7 REPLACEMENT NEW
NO SCALE
SHAFT 7 - FIRST LEVEL DETAIL (FOR REFERENCE ONLY)
NO SCALE
SHAFT 7 - SECOND LEVEL DETAIL (FOR REFERENCE ONLY)
NO SCALE
SHAFT 7 - THIRD LEVEL DETAIL (FOR REFERENCE ONLY)
NO SCALE
SHAFT 7 - FOURTH LEVEL DETAIL (FOR REFERENCE ONLY)
41360DATE REG. NO.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED BY ME
OR UNDER MY DIRECT SUPERVISION AND THAT I
AM A DULY LICENSED PROFESSIONAL ENGINEER
UNDER THE LAWS OF THE STATE OF MINNESOTA.
JASON GOTTWALT, P.E.
KEY NOTES: GENERAL NOTES:
X Y Z
3 3
1ISOLATE EXISTING PRESSURE REDUCING STATION SERVING THIS
MECHANICAL ROOM AND OTHER AREAS IN SOUTHWEST QUADRANT
OF BUILDING. FULLY REMOVE EXSITNG TAKE-OFF TEE AND WELD IN
NEW SECTION OF STRAIGHT PIPING TO REPLACE. COORDINATE
OUTAGE DURING PREMIUM HOURS WITHIN MILD WEATHER SEASON
TO MINIMIZE DISRUPTION TO FACILITY. REPAIR ANY REMOVED OR
DAMAGED PIPING INSULATION ON COMPLETION.
REMOVE EIXSTING 30 PSI STEAM PIPING TO WATER HEATERS
SCHEDULED FOR DEMOLITION. INCLUDE REMOVAL OF ALL
ASSOCIATED END OF MAIN STEAM TRAPS AND PIPING COMPONENTS.
REMOVE ALL SUPPORT HANGERS AS REQUIRED AND RESECURE ANY
IMPACTED PIPING ANCHORS THAT MAY HAVE BEEN IMPACTED BY
DEMOLITION.
REMOVE EXISTING INSTANTANEOUS WATER HEATER ALONG WITH ALL
PIPING COMPONENTS, CONTROL SENSORS, AND WIRING. REMOVE
ANY INTEGRATION INTO BUILDING AUTOMATION TO BE REPLACED BY
NEW WATER HEATER INSTALLATION.
REMOVE EXISTING CONDENSATE RETURN PIPINGN UNDERNEATH
SERVICE PLATFORM ALONG WITH ALL SUPPORTS AND INSULATION.
PATCH ALL PIPING PENETRATIONS THROUGH ELEVATED PLATFORM
SERVING AS MEZZANINE FLOOR. WELD STEEL PATCHES AND/OR
GRATING AS REQUIRED AND PAINT ALL AFFECTED AREA TO RESIST
ANY CORROSION ON COMPLETION.
NOTE NOT USED THROUGH
CONTRACTOR TO ISOLATE HIGH PRESSURE STEAM MAIN AT HEADER
TAKE-OFF VALVE. NOTE THAT THIS STEAM RISER WILL AFFECT ENTIRE
QUADRANT OF BUILDING AND SHOULD BE SCHEDULED A MINIMUM OF
2-WEEKS IN ADVANCE WHILE ON PREMIUM OVERTIME DURING MILD
WEATHER TO AVOID RISK TO HOSPITAL OEPRATIONS.
DURING OUTAGE TAP INTO HIGH PRESSURE MAIN AT APPROXIMATE
LOCATION INDICATED AND INSTALL ISOLATION VALVE DETAIL IN KEY
NOTE #12 BELOW. FIELD VERIFY ACTUAL CONDITIONS FOR OFFSET
FROM MAIN REQUIRED TO AVOID EXISTING PIPING SERVICES AND
SUPPORT HANGERS IN THIS CONGESTED AREA.
PROVIDE 4" TRIPLE OFFSET BUTTERFLY VALVE WITH FLANGED
CONNECTIONS AND SPOOL PIECES FOR BYPASS ASSEMBLY. INSTALL
A 1.5" BYPASS AROUND VALVE WITH PISTON VALVE FOR EQUALIZING
LINE PRESSURE PRIOR TO CLOSING HIGH PRESSURE SERVICE.
ROUTE 3/4" HIGH PRESSURE CONDENSATE FROM REDUCING STATION
INLET DRIP LEG TO DISCHARGE INOT EXISTING FLASH TANK.
REFER TO PRESSURE REDUCING STATION DETAIL 7/PP500 FOR ALL
COMPONENTS REQUIRED IN THIS PREMANUFACTURED SKID
ASSEMBLY (CONTRACTOR WILL NOT BE ALLOWED TO FIELD
FABRICATE ON SITE). NOTE THAT HEIGHT OF ASSEMBLY SHALL BE
LIMITED TO FIT UNDERNEATH HPS HEADER. FIELD VERIFY ALL
DIMENSIONS WITH FACOTRY PRIOR TO SHOP DRAWING SUBMITTAL.
ROUTE 3/4" LOW PRESURE CONDENSATE FROM 15 PSI OUTLET DRIOP
LEG TO DISCHARGE DIRECTLY INTO CONDENSATE PUMP.
ROUTE 3" CONDENSATE FROM NEW WATER HEATER ASSEMBLY
ALONG FLOOR (DO NOT LIFT SO THAT GRAVITY DRAINAGE CAN BE
APPLIED WHEN NEEDED). CONNECT DIRECTLY INTO EXISTING
CONDENSATE PUMP WHERE INDICATED.
PROVIDE HEAVY DUTY 18" TALL GUARD RAILS AROUND PERIMETER OF
WATER HEATERS, MANUFACTURERED BY HANDLE-IT, INC.
POSTION WATER HEATERS FAR ENOUGH FROM OBSTRUCTIONS TO
ALLOW FOR FULL REMOVAL OF HEATING TUBE BUNDLES.
A.
B.
C.
D.
E.
MECHANICAL CONTRACTOR SHALL REFER TO THE VA MASTER
SPECIFICATION MANUAL ALONG WITH ANY APPLICABLE STANDARDS
WITHIN THE 2019 HVAC DESIGN GUIDE. ALL REQUIREMENTS OF THOSE
MANUALS SHALL BE MAINTAINED IN ADDITION TO ALL NOTES AND
DESCRIPTIONS INDICATED WITHIN THESE DRAWINGS. ANY CONFLICTS
BETWEEN THOSE DOCUMENTS SHOULD BE BROUGHT TO THE
ATTENTION OF THE ENGINEER FOR INTERPRETATION.
MECHANICAL CONTRACTOR WILL BE RESPONSIBLE TO REVIEW ALL
POTENTIAL OUTAGES RESULTING FROM TIE-INS SHOWN ON THESE
DRAWINGS TO DETERMINE APPROXIMATE AMOUNT OF OVERTIME
REQUIRED TO PERFORM ALL MECHANICAL WORK INDICATED. PROVIDE
THE VA COTR A MINIMUM OF 14 DAYS ADVANCE NOTICE OF ANY
OUTAGE FOR COORDINATION OF SCHEDULES WITH AFFECTED
DEPARTMENTS.
COORDINATE ALL NEW PIPE ROUTING WITH ALL OTHER TRADES TO
INSURE ADEQUATE CLEARANCES FOR PLUMBING, ELECTRICAL
CONDUIT, STRUCTURAL SUPPORTS, PIPING, ETC. ANY UNAVOIDABLE
CONFLICTS SHALL BE BROUGHT TO THE ATTENTION OF THE
ARCHITECT/ENGINEER OF RECORD. PROVIDE ALL OFFSETS AND
TRANSITIONS AS REQUIRED FOR A CLEAN INSTALLATION.
SUPPORT ALL PIPING DIRECTLY TO STRUCTURE. DO NOT SUPPORT ANY
PIPE FROM DUCTWORK, CONDUIT, OR OTHER PIPING ENCOUNTERED.
WHERE MECHANICAL SYSTEMS TO REMAIN ARE DAMAGED, OR
DISTURBED, DURING THE COURSE OF CONSTRUCTION THE
CONTRACTOR WILL BE RESPONSIBLE TO REMOVE DAMAGED PORTIONS
AND INSTALL NEW PRODUCTS OF EQUAL QUALITY AND FUNCTIONALITY.
ALL EXISTING PIPING THROUGH NEW FIRE RATED WALLS SHALL BE
ADEQUATELY FIRE SEALED AS REQUIRED. PIPING PENETRATIONS
THROUGH INTERSTITIAL FLOOR SHALL BE DRILLED, OR CUT, BY THE
CONTRACTOR AND FIRE SEALED AS REQUIRED.
X Y Z AA BB
8" 15# STM
/4
" 1 R
3/4" HPR
/4
" 1 R
4" HPS
3" 15#R
3/4" HPR
1" 15#R
NOTE THAT DOUBLE LINE REPRESENTS STRUCTURAL
MEZZANINE LEVEL WITH SOME PIPING ABOIVE AND BELOW
Project Number
Building Number
Drawing Number
Project Title
Location
Issue DateCheckedDrawn
Drawing Title
Approved:
VA FORM 08 -6231
A
CONSTRUCTION
DOCUMENTS SUBMISSION
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
2 145678910
Phase
ARCHITECT/ENGINEER OF RECORDSTAMP CONSULTANT
3 2 145678910
TRUE NORTH
PLAN NORTH
E
C :\R e v it P ro je c ts
\V A
B u ild in g
- P h a s e
- M e c h a n ic a l 2 ja s o n g o ttw a lt5
.rv t
/3 /2
:2
:1
A M
BASEMENT INTERSTITIAL - PHASE
8 - HYDRONIC DEMOLITION PIPING
PLAN
PREVENT LEGIONELLA,
PHASE III
MINNEAPOLIS
618-14-118
11/30/2022JGJG 618-14-118
1356-MP108.1
1/4" = 1'-0"
ENLARGED DEMOLITION MECHANICAL PLAN - PHASE 8.4
1/4" = 1'-0"
ENLARGED MECHANICAL PLAN - PHASE 8.4
41360 DATEREG. NO.
I HEREBY CERTIFY THAT THIS PLAN,
SPECIFICATION OR REPORT WAS PREPARED BY ME
OR UNDER MY DIRECT SUPERVISION AND THAT I
AM A DULY LICENSED PROFESSIONAL ENGINEER
UNDER THE LAWS OF THE STATE OF MINNESOTA.
JASON GOTTWALT, P.E.
Revisions:Date:
| 1356-PP106-1 - BASEMENT INTERSTITIAL - PHASE 6 - DOMESTIC WATER PLAN |
| 1356-PP106-2 - ALL LEVELS - PHASE 6 - ENLARGED RISER -M- COLD WATER REPLACEMENT PLANS |
| 1356-PP107-1 - BASEMENT INTERSTITIAL - PHASE 7 - DOMESTIC WATER PLAN |
| 1356-PP107-2 - BASEMENT - PHASE 7 - ENLARGED SHAFT 7 COLD WATER REPLACEMENT PLANS |
| 1356-PP107-3 - LEVELS 1-4 - PHASE 7 - ENLARGED SHAFT 7 COLD WATER REPLACEMENT PLANS |
| 1356-MP108-1 - BASEMENT INTERSTITIAL - PHASE 8 - HYDRONIC DEMOLITION PIPING PLAN |
File details come from the government source that posted it. Updated .