Attachment D.6 Drawings 6 of 10 (6 Pages).pdf

PDF 17 MB Posted

Attached to
Y1DA--618-18-108 Prevent Legionella Ph3 36C263-23-AP-0103
Solicitation number
36C26323R0042
Issued by

About this file

This document provides details for a federal contract solicitation. The solicitation number is 36C26323R0042 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23 for preventative Legionella services. The solicitation seeks to address Phase 3 of project 618-18-108 to prevent Legionella bacterial growth through maintenance and inspection of the facility's water systems. The attachment includes drawing number 6 of 10 related to the required plumbing and piping schematics. No pricing, response deadline or award date are specified in this document.

View the file

Other files

File Type Posted
Wage Determination MN20230117 updated 4.14.23.pdf PDF
36C26323R0042 0002.docx DOCX document
Site Visit Sign-in Sheet 4.20.23 (1 Page).pdf PDF
08 31 13 Access Doors and Frames (6 Pages).pdf PDF
36C26323R0042 618-18-108 Prevent Legionella Ph3 QA (2 Pages).pdf PDF
36C26323R0042 0001.docx DOCX document
Revised SOW 5.3.23 (4 Pages).pdf PDF
Attachment J VAAR 852.219-75 Limitations on Subcontracting Cert of Compliance (2 Pages).pdf PDF
Attachment F Wage Determination MN20230117 (9 Pages).pdf PDF
Attachment C Specifications 20230317 (474 Pages).pdf PDF
Attachment D.7 Drawings 7 of 10 (6 Pages).pdf PDF
Attachment E Brand Name Justification and Approval (1 Page)_Redacted.pdf PDF
Attachment D.3 Drawings 3 of 10 (5 Pages).pdf PDF
Attachment B Price Schedule Breakdown (1 Page).pdf PDF
Attachment D.10 Drawings 10 of 10 (6 Pages).pdf PDF
Attachment H Past Performance Questionnaire (3 Pages).docx DOCX document
Attachment I Questions Request Form (1 page).doc DOC document
Attachment D.4 Drawings 4 of 10 (4 Pages).pdf PDF
Attachment G VA6500 Appendix C 1-2-3a-6a-7a-7d-9 and Appendix D (6 pages).pdf PDF
Attachment D.8 Drawings 8 of 10 (6 Pages).pdf PDF
Attachment D.2 Drawings 2 of 10 (5 Pages).pdf PDF
Attachment A Final SOW (4 Pages).pdf PDF
Attachment D.1 Drawings 1 of 10 (7 Pages).pdf PDF
36C26323R0042.docx DOCX document
Attachment D.5 Drawings 5 of 10 (12 Pages).pdf PDF
Attachment D.9 Drawings 9 of 10 (6 Pages).pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABCDEFGNPQRSTUVWXYZAABBCCDDEEFFGGHHJJKKLLMMNNPP

HH'

RISER E

RISER M

SHAFT 2

SHAFT 3

RISER A

SHAFT 7

SHAFT 4

RISER G

RISER K

SHAFT 6

RISER J

1356-PP101.1

1356-PP102.1

1356-PP103.1

1356-PP104.1

1356-PP105.1

1356-PP106.1

1356-PP107.1

1356-PP108.1

HJKLM

- PHASE 1

- PHASE 2

- PHASE 3

- PHASE 4

- PHASE 5

- PHASE 6

- PHASE 7

- PHASE 8

PHASING LEGEND:

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS SUBMISSION

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRUE NORTH

PLAN NORTH

A B

C D

E F

G

H

C R e v it P ro je c ts

\V A

B u ild in g

P h a s e

M e c h a n ic a l ja s o n g o tt w a lt

.r v t

/3 /2

:3

:5

A M

BASEMENT INTERSTITIAL -

OVERALL - DOMESTIC WATER

LOOP REPLACEMENT PLAN

PREVENT LEGIONELLA,

PHASE III

MINNEAPOLIS

618-14-118

11/30/2022 JG TM / JG618-14-118

1356-PP101.0

1/32" = 1'-0"

70 - BASEMENT INTERSTIAL - OVERALL - DOMESTIC WATER LOOP REPLACEMENT PLAN

41360DATE REG. NO.

I HEREBY CERTIFY THAT THIS PLAN,

SPECIFICATION OR REPORT WAS PREPARED BY ME

OR UNDER MY DIRECT SUPERVISION AND THAT I

AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF MINNESOTA.

JASON GOTTWALT, P.E.

11/30/2022

Revisions: Date:

TS

TS

KEY NOTES:

GENERAL NOTES:

TS

TS

T S

T S

TS

G.B

G.C

G.A

5" CW UP

8" CW

8" CW

2 1/2" RHW

4" HW

K.C'

K.A'

K.B'

RISER G

1 1/2" RHW UP

4" HW UP

TO BE

REPLACED

IN NEXT

PHASE

8" CW

G

RISER G

G.A

G.B 31

G.A

G.C

1 1/2" CW

DRAIN

REFER TO DETAIL 2/1356-PP101.1

FOR VALVE LOCATION.

REFER TO DETAIL 1/1356-PP102

FOR VALVE LOCATION.

8" CW

8" CW

8" CW

8" CW

5" CW

H

H W

/2

C H

W

NOTE THAT THESE KEY NOTES ARE SPECIFIC TO THIS DRAWING (DO

NOT REFER TO MASTER KEY NOTES ON SHEET 1356-PP003). NOT ALL

KEY NOTES ARE UTILIZED AND MAY HAVE GAPS OF MISSING NOTE

NUMBERS TO KEEP GROUPS OF TEN NOTES AVAILABLE PER PHASE.

SHUT-OFF VALVE K.C AND VALVE G.B TO ISOLATE SECTION OF PIPING

INDICATED FOR REMOVAL. REFER TO GENERAL NOTES FOR

PROVISIONS TO BE TAKEN TO VERIFY ANY EXISTING VALVE LEAKAGE.

ONCE ISOLATED, REMOVE SECTION OF 8" GALVANZED PIPING LOOP.

CUT INTO SECTIONS SMALL ENOUGH TO TRANSPORT TO LOADING

DOCK AREA FOR REMOVAL. INCLUDE DEMOLITION OF EXISTING

SUPPORTS MOUNTED TO PIPING RACKS, NEW PIPING WILL BE

SUPPORTED ONTO EXISTING RACK STRUCTURE BUT SHOULD BE

PROVIDED WITH NEW PIPE CLAMPS.

NOT USED THROUGH KEY NOTE

INSTALL NEW SECTION OF 8" SCHEDULE 10 STAINLESS STEEL PIPING TO

REPLACE PREVIOUSLY REMOVED. INSTALL IN EXACT SAME LOCATION

AS REMOVED SECTION OF PIPING. PROVIDE NEW SUPPORT CLAMPS

ON EXISTING PIPING RACK AS REQUIRED.

PROVIDE TEMPORARY END CAPS AT EITHER SIDE OF NEW PIPING

SECTION. FIRST PERFORM A PRESSURE TEST ON PIPING SECTION PER

SPECIFICATION REQUIREMENTS, AND THEN STERILIZE PIPING USING

CHLORINE SOLUTION FOR AT LEASE 24 HOURS PRIOR TO FLUSHING.

INCLUDE DRAIN/FILL VALVES ON EITHER END TO ACCOMPLISH.

INSULATE ENTIRE LENGTH OF PIPING PER SPECIFICATION

REQUIREMENTS. INCLUDE CONTINUOUS PVC COVERING THROUGHOUT

AND PREPARE ENDS FOR EXTENSION TO NEXT SUB-PHASE PIPING

WHICH WILL INCLUDE INSULATING ALL VALVE BODIES.

NOT USED THROUGH KEY NOTE

SHUT-OFF VALVE #K.C AND VALVE #4.B (BOTH FURTHER OUT TO NEXT

ADJACENT RISER VALVES OUTSIDE THE EXTENTS OF THIS PHASE

DRAWING) TO ISOLATE THIS RISER G FOR VALVE REPLACEMENT.

REFER TO GENERAL NOTES FOR PROVISIONS TO BE TAKEN TO VERIFY

ANY EXISTING VALVE LEAKAGE AND AREAS THAT WILL BE AFFECTED BY

THIS MAJOR WATER OUTAGE.

ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER

SIDE OF COLD WATER RISER TAKE-OFF VALVE WITH NEW STAINLESS 8"

TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD

EXISTING 5" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN

LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING

RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO

UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH

40 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN

OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).

DURING OUTAGE, INSTALL THERMOWELLS ON BOTH HOT AND COLD

WATER MAINS TO ACCEPT AN INSERTION TYPE TEMPERATURE SENSOR

TO BE INTEGRATED INTO BUILDING AUTOMATION SYSTEM FOR

INFORMATION MONITORING AND TRENDING.

INSTALL STRAP ON TEMPERATURE SENSORS INDICATE ON

RECIRCULATION PIPING. REPAIR ANY DAMAGED OR REMOVED

INSULATION ON COMPLETION.

ONCE VALVE INSTALLATION IS COMPLETED, INSULATE ALL AFFECTED

PIPING AND NEW VALVE BODIES COMPLETELY. COVER EVERYTHING

WITH PVC JACKET COVERS AND SEAL AS REQUIRED. INSULATION CAN

OCCUR DURING NORMAL HOURS AFTER OUTAGE COMPLETION, BUT

SHOULD NOT BE DELAYED FOR ANY MORE THAN 3 BUSINESS DAYS.

PHASE 1.1 (DEMO - REFER TO DETAIL 1 AND 10-19 SERIES KEY NOTES):

THE EXISTING GALVANIZED 8" COLD WATER PIPING MAIN TO BE REMOVED

BETWEEN INTERIOR VALVES OF RISERS INDICATED IN KEY NOTES. REFER

TO WORK SEQUENCE DESCRIBED IN 'ISOLATION OF MAIN PIPING LOOP

SECTIONS' BELOW TO EITHER CONFIRM EXISTING VALVES DO NOT LEAK, OR

FOLLOW GUIDELINE PROVISIONS TO BE TAKEN IF THEY ARE FOUND

DEFECTIVE. NO OUTAGES WILL BE REQUIRED DURING THIS SUB-PHASE

WITH MAIN LOOP CONTINUALLY SERVING BOTH SIDES.

PHASE 1.2 (BUILD-BACK - REFER TO DETAIL 2 AND 20-29 SERIES KEY NOTES):

INSTALL NEW PIPING IN SAME LOCATION AS REMOVED SECTION OF 8" COLD

WATER MAIN. MAY REUTILIZE EXISTING PIPING RACK FOR PIPING

SUPPORTS. REFER TO KEY NOTES FOR ADDITIONAL INFORMATION RELATED

TO INSTALLATION.

PHASE 1.3 (RISER VALVE REPLACEMENT - 30+ SERIES KEY NOTES):

AREA SHOWN IN EXPANDED 1/4" = 1'-0" PLAN VIEW SHALL HAVE BOTH 8"

ISOLATION VALVES REPLACED WITH NEW TRIPLE OFFSET BUTTERFLY

VALVES. PLAN FOR OUTAGE OF RISER G AND REPLACE EXISTING 5" TAKE-

OFF VALVE AT SAME TIME. INCLUDE 1.5" DRAIN VALVE AT INTERSECTION

BETWEEN THREE(3) REPLACED VALVES. THIS SUB-PHASE WILL CAUSE A

LARGE DOMESTIC WATER OUTAGE FOR AREAS OF FACILITY THAT MAY BE

CRITICAL, CONTRACTOR SHALL REFER TO 'ALLOWANCE FOR TEMP

FIXTURES OR WATER SERVICES' BELOW FOR ACCOMODATIONS NEEDED

FOR THOSE AREAS. OUTAGE WILL AFFECT THE FOLLOWING DEPARTMENTS

AND SHOULD BE CAREFULLY COORDINATED WITH VA FACILITIES;

• FIRST FLOOR: HOSPICE/PALLIATIVE, NURSING HOME CARE, MENTAL

HEALTH - PTSR & PPH, CENTRAL STAFF LOCKERS

• SECOND FLOOR: AMBULATORY CARE SERVICE, CENTRAL STAFF

LOCKERS 2C114B, INPATIENT SURGICAL BED, CENTRAL STAFF LOKERS

2H111A

• THIRD FLOOR: INPATIENT MEDICAL BEDS AND HEM/ONC TREATMENT

PRIMARY CARE, CENTRAL STAFF LOCKERS 3C114C, INPATIENT MEDICAL

BEDS, CENTRAL STAFF LOCKERS 3H117D

• FOURTH FLOOR: AMBULATORY CARE SERVICE - PRIMARY CARE

WOMEN'S CLINIC, AMBULATORY CARE SERVICE - SPECIALTY CARE

ONCOLOGY, GERIATRIC CLINIC, EXENDED CARE & REHAB

ISOLATION OF MAIN PIPING LOOP SECTIONS:

PERFORM THE FOLLOWING PROCEDURE STEPS TO PROPERLY ISOLATE

EACH SECTION OF PIPING LOOP AS DESCRIBED IN PHASING SEQUENCES,

1) SHUT-OFF ISOLATION VALVES ON INTERIOR SIDE OF LOOP BEING

MODIFIED OR REMOVED TO MAINTAIN SERVICES TO ALL RISERS.

2) REMOVE SECTION OF PIPING, OR TAP TEMPORARY DRAIN CONNECTION

TO VERIFY VALVES ARE HOLDING FOR A MINIMUM PERIOD OF 24 HOURS.

3) IF NO VALVE LEAKAGE, OR MINIMAL AMOUNT, IS WITNESSED THAN

PROCEED TO PIPING MODIFICATION AND/OR DEMOLITION SCOPE OF WORK

IDENTIFIED.

4) IF MODERATE OR SIGNIFICANT VALVE LEAKAGE IS WITNESSED THAN

PROVIDE 1.5" VALVE TAP WITH THREADED CONNECTION TO HOSE TO

NEAREST MECHANICAL ROOM DRAIN DISCHARGE LOCATION. THIS

TEMPORARY DRAIN CONNECTION AND HOSE SHALL BE REMOVED ONCE

NEW RISER VALVE REPLACEMENTS ARE COMPLETED.

---CONTRACTOR WILL BE RESPONSIBLE TO KEEP ON SITE AT LEAST FOUR(4)

SETS OF 1.5" VALVES WITH THREADED CONNECTIONS AND TWO(2) 250' LONG

HOSES OF 1.5" DIAMETER IN SIZE.

CONTRACTOR ALLOWANCE FOR TEMP FIXTURES OR WATER SERVICES:

ASSUME THAT DURING THE COURSE OF THE 8 PHASE DOMESTIC WATER

LOOP REPLACEMENT THAT SPECIFIC AREAS WILL REQUIRE TEMPORARY

SINKS AND/OR EXTENSION OF TEMPORARY WATER SERVICES TO THEIR

DEPARTMENT. CONTRACTORS SHALL INCLUDE THE FOLLOWING

ALLOWANCES WITHIN THEIR BASE BID TO ACCOMODATE THOSE REQUESTS

WHEN THEY ARISE DURING OUTAGE COORDINATION WITH VA FACILITIES.

• INCLUDE UP TO TWELVE(12) TEMPORARY SINK FIXTURES TIED INTO AN

ADJACENT RISER SERVICE. EACH SINK WILL REQUIRE UP TO 50' OF

COPPER PIPE FOR WATER CONNECTIONS, OTHERWISE HOSE WILL BE

UTILIZED IF DISTANCE EXCEEDS THAT SPECIFIED AMOUNT OF PIPING.

• INCLUDE FOUR(4) TEMPORARY BACK-UP WATER CONNECTIONS FOR

COLD WATER SERVICE TO AN ENTIRE DEPARTMENT. TEMPORARY COLD

WATER MAIN SHALL BE ASSUMED AT 2" SIZE AND EXTEND A MAXIMUM OF

250' TO CONNECT INTO AN ADJACENT RISER SERVICE.

• NOTE THAT THE ABOVE IS FOR ENTIRE PROJECT, NOT PER PHASE.

8" CW

2 1/2" RHW

4" HW

2" SOFT

10" HPS

4" PC

5" CHWR

10" CHWR

10" CHWS

8" CHWR

8" CHWS8" CHWR

8" CHWS

GH

2" SOFT

4" HW

2 1/2" RHW

8" CW10" HPS

4" PC

5" CHWR

10" CHWR

10" CHWS

8" CHWS

8" CHWR

8" CHWS

8" CHWR

GNPQRSTUVW

1356-PP101.1

1356-PP101.1

STACKED

K.B'

TO RISER K

K.A' K.C'

G.B

G.A

G.C

HJKLM

GNPQRSTUVW

1356-PP101.1

1356-PP101.1

STACKED

21 22

1356-PP101.1

K.C'

K.A'

K.B'

G.C

G.B

G.A

HJKLM

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS SUBMISSION

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRUE NORTH

PLAN NORTH

F

C R e v it P ro je c ts

\V A

B u ild in g

P h a s e

M e c h a n ic a l ja s o n g o tt w a lt

.r v t

/3 /2

:3

:3

A M

BASEMENT INTERSTITIAL - PHASE

1 - DOMESTIC WATER PLAN

PREVENT LEGIONELLA,

PHASE III

MINNEAPOLIS

618-14-118

11/30/2022 JG TM / JG618-14-118

1356-PP101.1

NO SCALE

PHASE 1 - ISOMETRIC VIEW

1/4" = 1'-0"

ENLARGED - PHASE 1.3 - DOMESTIC WATER PLAN

NO SCALE

PHASE 1 ELEVATION - SOUTH TUNNEL

NO SCALE

PHASE 1 ELEVATION - EAST TUNNEL

1/16" = 1'-0"

PHASE 1.1 DEMO

1/16" = 1'-0"

PHASE 1.2 NEW

CONNECTION TO EXISTING

VALVE K.C'. VALVE K.C.' TO

BE REPLACED IN PHASE 8.

REFER TO 1356-PP108.1

FOR PHASE 8.

41360DATE REG. NO.

I HEREBY CERTIFY THAT THIS PLAN,

SPECIFICATION OR REPORT WAS PREPARED BY ME

OR UNDER MY DIRECT SUPERVISION AND THAT I

AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF MINNESOTA.

JASON GOTTWALT, P.E.

TS

T S

TS TS

C4-120

KEY NOTES:GENERAL NOTES:G

H

5" CW UP

5" CW UP

4" HW UP

1 1/2" RHW UP

G

G.B

G.C

H

5" CW UP

5" CW UP

4" HW UP

1 1/2" RHW UP

HJKL

1 1/2" RHW UP 4" HW UP

5" CW UP

5" CW UP

5" CW

5" CW

4" HW

1 1/2" RHW

5" CW DN

5" CW DN

1 1/2" RHW DN

4" HW DN

5" CW DN

HJKL

5" CW DN

1 1/2" RHW UP

4" HW UP

5" CW

5" CW

4" HW

1 1/2" RHW

1 1/2" RHW UP

4" HW UP

5" CW UP

5" CW UP

LM

LM

1 1/2" RHW DN

1 1/4" RHW UP 4" HW UP & DN

4" CW UP

5" CW DN

5" CW DN

4" CW UP

LM

LM

LM

LM

1 BEFORE OUTAGE: ROUTE NEW RISER "G" PIPING PARALLEL TO

EXISTING PIPING TO LEVEL ABOVE.

DURING OUTAGE: REMOVE AND REPLACE MAIN PIPING BETWEEN

VALVES G.B AND G.C. MAKE FINAL CONNECTION TO NEW RISER "G"

PIPING. ABANDON EXISTING COLD WATER RISER PIPING TO BE

DEMOLISHED AFTER ALL RISER "G" FINAL CONNECTIONS ARE MADE

AND OUTAGE IS COMPLETE.

AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW AND

KEY NOTE 2.

AFTER OUTAGE: REMOVE ABANDONED COLD WATER RISER PIPING.

DEADLEG OR ABANDONED PIPING SHALL NOT REMAIN.

MAIN PIPING DEMOLITION INDICATED IS TO OCCUR IN THE NEXT PHASE.

REFER TO 1/1356-PP102.1.

BEFORE OUTAGE: ROUTE NEW RISER "G" PIPING PARALLEL TO

EXISTING PIPING TO LEVEL ABOVE. EXTEND NEW TAKEOFFS TO

EXISTING BRANCH TAKEOFFS AND PREPARE FOR NEW CONNECTION.

NOTE THAT THERE IS AN EXISTING 4" COPPER MAIN (NOT CONNECTED

AND EMPTY) THAT WAS PREVIOUSLY ROUTED AND ABANDINED

THROUGH THIS AREA. CONTRACTOR MAY UTILIZE EXISTING ROUTE

AND SUPPORT HANGERS, BUT MUST FULLY REMOVE EXISTING PIPING

THAT WAS NEVER UTILIZED. CONTRACTOR MAY RECYCLE THIS

MATERIAL TO BE REMOVED, BUT MAY NOT REUTILIZE THAT SALVAGED

PIPING FOR ANY PART OF THIS PROJECT.

NOTE THAT THE EXISTING COPPER PIPE TO BE REMOVED IS HIGH

WITHIN MECHANICAL ROOM AND ROUTED ABOVE LARGE EQUIPEMTN

(AHU'S/ETC). CONTRACTOR TO DETERMINE SCISSOR LIFT AND/OR

EQUIPMENT NEEDED FOR INSTALLATION/ACCESS.

DURING OUTAGE: DISCONNECT EXISTING BRANCH TAKEOFFS AND

REMOVE TAKEOFF PIPING. MAKE TAKEOFF FINAL CONNECTIONS.

ABANDON EXISTING COLD WATER RISER PIPING TO BE DEMOLISHED

AFTER ALL RISER "G" FINAL CONNECTIONS ARE MADE AND OUTAGE IS

COMPLETE.

AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW AND

KEY NOTE 2.

A.

B.

C.

D.

E.

F.

THE OUTLINE OF 'MEANS-AND-METHODS' NOTES BELOW FOR VERTICAL

COLD WATER RISER REPLACEMENTS INDICATED WITHIN THESE

DRAWINGS IS NOT INTENDED TO BE ALL-INCLUSIVE OF EFFORT

REQUIRED BY CONTRACTOR. NOR ARE THESE NOTES AND/OR

SUGGESTIONS MEANT TO LIMIT CONTRACTORS FROM DEVELOPING

THEIR OWN APPROACH THAT MAY BE CONSIDERED MORE COST

EFFECTIVE OR SAFE. THESE NOTES ARE MAINLY MEANT TO QUALIFY

EXISTING CONDITIONS AND DEFINE MINIMUM LEVEL OF PLANNING

REQUIRED BY VA FOR EACH OF THESE TIME SENSITIVE OUTAGES.

NO MAJOR WATER OUTAGE SHALL LAST MORE THAN 12 HOURS IN

DURATION. PLUMBING CONTRACTOR TO DETERMINE ADEQUATE

NUMBER OF PLUMBER CREWS REQUIRED TO PERFORM MULTIPLE

TASKS SIMULTANEOUSLY DURING OUTAGES. ALL OUTAGES SHALL BE

ASSUMED TO BE PERFORMED DURING WEEKEND OR NIGHT OVERTIME

HOURS WHEN BIDDING THIS PROJECT.

VERTICAL RISER REPLACEMENT (TYPE 1 - WITHIN MECHANICAL ROOM)

• FOR RISERS WITHIN MECHANICAL ROOMS, CONTRACTOR SHALL

CORE DRILL HOLES THROUGH FLOOR ADJACENT TO EXISTING

PLUMBING RISER FOR NEW INSTALLATION. EXISTING FLOOR

PENETRATIONS AND/OR SLEEVE SHALL BE PATCHED FLUSH TO

EXISTING FLOOR AS REQUIRE UPON DEMOLITION OF THOSE RISERS.

• EXISTINGT TAKE-OFF VALVES MAY REQUIRE RELOCATION FOR

CONNECTION INTO NEW RISER. VERIFY ADEQUATE ACCESS TO ALL

TAKE-OFF VALVES AND PROVIDE WITH NEW LAMINATE SIGNAGE.

ANY VALVES FOUND AT INACCESSIBLE LOCATIONS SHALL BE

RELOCATED BY CONTRACTOR.

• REFER TO CLIN 3001 FOR REPLACEMENT OF ALL ICRCUIT SETTER

VALVES WITHIN ENTIRE BUILDING. PLUMBING CONTRACTOR MAY

OPT TO HAVE DEDICATED CREWS ASSIGNED TO THIS TASK DURING

RISER OUTAGE TO LIMIT NUMBER OF SECONDARY OUTAGES

REQUIRED. HOWEVER, IF ENOUGH PLUMBERS ARE AVAILABLE TO

ACHIEVE THIS DURING LIMITED OUTAGE TIMEFRAME, THAN REFER

TO GENERAL NOTES ON DRAWING PP002 FOR 'LARGE OUTAGES' TO

PERFORM PRIOR TO THE MAJOR RISER OUTAGE.

VERTICAL RISER REPLACEMENT (TYPE 2 - WITHIN ENCLOSED SHAFT)

• IN GENERAL, MAJOR RATED SHAFTS SHOWN IN THESE DRAWINGS

HAVE EXISTING FULL SIZED ACCESS DOOR FROM BASE OF SHAFT

ON FIRST FLOOR LEVEL. HOWEVER, THAT IS TYPICALLY THE ONLY

ACCESS INTO THESE SHAFTS THAT ARE FULLY OPEN (NO

INTERMEDIATE FLOOR STRUCTURES) UP THROUGH PENTHOUSE

LEVEL WHERE RATED WALLS ARE BUILT-UP WITH LID (TYPICALLY

12'+) WITHIN ENCLOSED PENTHOUSE LEVEL.

• IN ORDER TO GAIN ACCESS TO TOP OF SHAFT, CONTRACTOR WILL

BE REQUIRED TO FURNSIH AND INSTALL FIRE RATED DOOR

ASSEMBLIES FROM PENTHOUSE LEVEL. THESE DOORS MAY BE

USED IN CONJUCTION OF RIGGING FOR BOSUN CHAIRS FROM TOP

OF SHAFT IF CONTRACTOR DEEMS THAT AS SAFE AFTER REVIEW

WITH THEIR INTERNAL SAFETY OFFICIAL.

• IN ADDITION TO ACCESS ON TOP LEVEL OF SHAFT, CONTRACTOR

WILL HAVE OPPORTUNITIES TO INSTALL 24"X24" OR 48"X24" FIRE

RATED ACCESS PANELS ON ANY OTHER LEVEL REQUIRED (BUT

ONLY FROM INTERSTITIAL SPACE, INSTALLATION OF ACCESS

PANELS FROM PATIENT CARE AREAS WILL NOT BE PERMITTED).

• CONTRACTOR WILL BE REQUIRED TO PROVIDE THEIR OWN

SCAFFOLDING REQUIRED AT EACH LEVEL TO INSTALL NEW COLD

WATER RISERS ADJACENT TO EXISTING PRIOR TO SIOWTCHOVER

OUTAGE. SCAFFOLDS SHOULD BE STRATEGICALLY PLACE TO

ALLOW ACCESS FOR RECONNECTION TO FLOOR TAKE-OFF PIPING

INSIDE OF EACH SHAFT.

• EXISTING CONDITION PDF SKETCHES ARE PROVIDED ON DRAWINGS

WHERE WORK INSIDE CONFINED AREAS OF RATED SHAFTS IS

REQUIRED. THESE SKETCHES ARE FOR CONTRACTOR REFERENCE

ONLY AND MAY NOT FULLY INDICATE ALL SERVICES WITHIN SHAFT

ENCLOSURES. CONTRACTOR WILL BE REQUIRED TO FIELD VERIFY

ACTUAL SITE CONDITIONS OF EACH SHAFT WHILE DEVELOPING

ACCESS AND SAFETY PLANNING.

NOTE THAT SOME AREAS HAVE EXISTING COPPER MAINS INTENDED TO

REPLACE GALVANIZED RISERS. HOWEVER THESE MAINS WERE

INSTALLED UP TO 15-25 YEARS AGO AND THEIR INTEGRITY IS

QUESTIONABLE. CONTRACTOR MAY UTILIZE THE EXISTING ROUTE, AND

CORRESPONDING SUPPORT HANGERS, BUT MUST FULLY REMOVE ALL

ABANDONED/UNUSED COPPER PIPING MAINS. ONCE OFF SITE THE

CONTRACTOR MAY TAKE OWNERSHIP OF PIPING FOR RECYLCING OR

REPURPOSING, BUT IT SHALL NOT BE UTILIZED WITHIN THIS PROJECT.

NO EXISTING PIPING WILL BE ALLOWED TO BE LEFT ABANDONED. SOME

AREAS HAVE RESTRICITVE ACCESS DUE TO SURROUNDING PIPES

AND/OR STRUCTURE AND MAY REQUIRE TEMPORARY REMOVAL OF

PIPING OR DUCTWORK TO GAIN ACCESS FOR DEMOLITION.

CONTRACTOR TO ASSUME SOME LEVEL OF DISCONNECT/RECONNECT

OF EXISTING SERVICES TO GAIN ACCCESS FOR COMPLETE DEMOLITION

OF EXISTING PIPING, OR INSTALLATION OF NEW PIPE IN CONGESTED

AREAS. REFER TO DRAWING NOTES FOR ADDITIONAL INFORMATION.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS SUBMISSION

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRUE NORTH

PLAN NORTH

F

C R e v it P ro je c ts

\V A

B u ild in g

P h a s e

M e c h a n ic a l ja s o n g o tt w a lt

.r v t

/3 /2

:3

:3

A M

ALL LEVELS - PHASE 1 -

ENLARGED RISER "G" COLD

WATER REPLACEMENT PLANS

PREVENT LEGIONELLA,

PHASE III

MINNEAPOLIS

618-14-118

11/30/2022 JG TM / JG618-14-118

1356-PP101.2

1/8" = 1'-0"

BASEMENT - RISER G REPLACEMENT DEMO

1/8" = 1'-0"

BASEMENT - RISER G REPLACEMENT NEW

1/8" = 1'-0"

FIRST LEVEL - RISER G REPLACEMENT DEMO

1/8" = 1'-0"

FIRST LEVEL - RISER G REPLACEMENT NEW

1/8" = 1'-0"

SECOND LEVEL - RISER G REPLACEMENT DEMO

1/8" = 1'-0"

SECOND LEVEL - RISER G REPLACEMENT NEW

1/8" = 1'-0"

THIRD LEVEL - RISER G REPLACEMENT DEMO

1/8" = 1'-0"

THIRD LEVEL - RISER G REPLACEMENT NEW

1/8" = 1'-0"

FOURTH LEVEL - RISER G REPLACEMENT DEMO

1/8" = 1'-0"

FOURTH LEVEL - RISER G REPLACEMENT NEW

41360DATE REG. NO.

I HEREBY CERTIFY THAT THIS PLAN,

SPECIFICATION OR REPORT WAS PREPARED BY ME

OR UNDER MY DIRECT SUPERVISION AND THAT I

AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF MINNESOTA.

JASON GOTTWALT, P.E.

T S

TS

TS

TS

KEY NOTES: GENERAL NOTES:

T S

TS

TS

TS

TS

TS

TS

G

1 1/2" CW

DRAIN 34

4.C

4.B

REFER TO DETAIL

1/1356-PP103

FOR VALVE

LOCATION.

REFER TO DETAIL

2/1356-PP102

FOR VALVE

LOCATION.

8" CW

8" CW

8" CW

4" CW

H

C W

3" CW

C W

4" CW

3/4" CHW

/2

C H

W

H W

/2

/2

/2

H W

NOTE THAT ALL EXISTING PLUMBING

FIXTURES WITHIN SCI BUILDING

HAVE ALREADY BEEN RETROFIT

WITH MXING VALVES ON HOT WATER

SIDE FOR SCALD PROTECTION. FOR

CONTRACTOR REFERENCE ONLY.

/4

C

H W

H W

G.B

G.A

G.C

8" CW

2 1/2" RHW

4" HW

8" CW

3" CW

2" HW

3/4" RHW

EXISTING DOMESTIC

WATER SERVICE TO

SCI BUILDING

3" CW

4.B

4.A

4.C

8" CW

TO BE

REPLACED

IN NEXT

PHASE

4" CW

TO SHAFT 4. REFER

TO 1356.PP102.2 FOR

CONTINUATION.

NOTE THAT THESE KEY NOTES ARE SPECIFIC TO THIS DRAWING (DO

NOT REFER TO MASTER KEY NOTES ON SHEET 1356-PP003). NOT ALL

KEY NOTES ARE UTILIZED AND MAY HAVE GAPS OF MISSING NOTE

NUMBERS TO KEEP GROUPS OF TEN NOTES AVAILABLE PER PHASE.

SHUT-OFF VALVE G.C AND VALVE 4.B TO ISOLATE SECTION OF PIPING

INDICATED FOR REMOVAL. REFER TO GENERAL NOTES FOR

PROVISIONS TO BE TAKEN TO VERIFY ANY EXISTING VALVE LEAKAGE.

ONCE ISOLATED, REMOVE SECTION OF 8" GALVANZED PIPING LOOP.

CUT INTO SECTIONS SMALL ENOUGH TO TRANSPORT TO LOADING

DOCK AREA FOR REMOVAL. INCLUDE DEMOLITION OF EXISTING

SUPPORTS MOUNTED TO PIPING RACKS, NEW PIPING WILL BE

SUPPORTED ONTO EXISTING RACK STRUCTURE BUT SHOULD BE

PROVIDED WITH NEW PIPE CLAMPS.

PRIOR TO REMOVAL OF SECTION OF 8" PIPING LOOP (PER KEY NOTE #

11) THE SCI CONNECTION WILL NEED TO BE RELOCATED TO BETWEEN

RISER #4 TAKE-OFF VALVES. COORDINATE OUTAGE OF COLD WATER

TO ENTIRE SCI BUILDING PRIOR TO THIS DISCONNECT/RECONNECT.

NOT USED THROUGH KEY NOTE

INSTALL NEW SECTION OF 8" SCHEDULE 10 STAINLESS STEEL PIPING TO

REPLACE PREVIOUSLY REMOVED. INSTALL IN EXACT SAME LOCATION

AS REMOVED SECTION OF PIPING. PROVIDE NEW SUPPORT CLAMPS

ON EXISTING PIPING RACK AS REQUIRED.

PROVIDE TEMPORARY END CAPS AT EITHER SIDE OF NEW PIPING

SECTION. FIRST PERFORM A PRESSURE TEST ON PIPING SECTION PER

SPECIFICATION REQUIREMENTS, AND THEN STERILIZE PIPING USING

CHLORINE SOLUTION FOR AT LEASE 24 HOURS PRIOR TO FLUSHING.

INCLUDE DRAIN/FILL VALVES ON EITHER END TO ACCOMPLISH.

INSULATE ENTIRE LENGTH OF PIPING PER SPECIFICATION

REQUIREMENTS. INCLUDE CONTINUOUS PVC COVERING THROUGHOUT

AND PREPARE ENDS FOR EXTENSION TO NEXT SUB-PHASE PIPING

WHICH WILL INCLUDE INSULATING ALL VALVE BODIES.

PROVIDE NEW 3" TRIPLE OFFSET BUTTERFLY VALVE FOR SCI BUILDING

AT THIS LOCATION. REFER TO PHASE 3.1 FOR DEMOLITION AND

RELOCATION OF EXISTING WATER SERVICE PRIOR TO BEGINNING ANY

DEMOLITION. NOTE THAT SCI BUILDING WILL HAVE A SECOND OUTAGE

DURING PHASE 3.3 WHEN RISER #4 VALVES ARE REPLACED. (NOTE

THAT CONTRACTOR MAY OPT TO MOVE PHASE 3.3 AHEAD OF PHASE 3.1

IF THEY WANT TO AVOID MULTIPLE OUTAGES.)

NOT USED THROUGH KEY NOTE

SHUT-OFF VALVE G.C AND VALVE E.B (BOTH FURTHER OUT TO NEXT

ADJACENT RISER VALVES OUTSIDE THE EXTENTS OF THIS PHASE

DRAWING) TO ISOLATE THIS SHAFT 4 FOR VALVE REPLACEMENT.

REFER TO GENERAL NOTES FOR PROVISIONS TO BE TAKEN TO VERIFY

ANY EXISTING VALVE LEAKAGE AND AREAS THAT WILL BE AFFECTED BY

THIS MAJOR WATER OUTAGE.

ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER

SIDE OF COLD WATER RISER TAK-OFF VALVE WITH NEW STAINLESS 8"

TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD

EXISTING 4" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN

LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING

RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO

UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH

40 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN

OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).

DURING OUTAGE, INSTALL THERMOWELLS ON BOTH HOT AND COLD

WATER MAINS TO ACCEPT AN INSERTION TYPE TEMPERATURE SENSOR

TO BE INTEGRATED INTO BUILDING AUTOMATION SYSTEM FOR

INFORMATION MONITORING AND TRENDING.

INSTALL STRAP ON TEMPERATURE SENSORS INDICATE ON

RECIRCULATION PIPING. REPAIR ANY DAMAGED OR REMOVED

INSULATION ON COMPLETION.

ONCE VALVE INSTALLATION IS COMPLETED, INSULATE ALL AFFECTED

PIPING AND NEW VALVE BODIES COMPLETELY. COVER EVERYTHING

WITH PVC JACKET COVERS AND SEAL AS REQUIRED. INSULATION CAN

OCCUR DURING NORMAL HOURS AFTER OUTAGE COMPLETION, BUT

SHOULD NOT BE DELAYED FOR ANY MORE THAN 3 BUSINESS DAYS.

PHASE 2.1 (DEMO - REFER TO DETAIL 1 AND 10-19 SERIES KEY NOTES):

THE EXISTING GALVANIZED 8" COLD WATER PIPING MAIN TO BE REMOVED

BETWEEN INTERIOR VALVES OF RISERS INDICATED IN KEY NOTES. REFER

TO WORK SEQUENCE DESCRIBED IN 'ISOLATION OF MAIN PIPING LOOP

SECTIONS' BELOW TO EITHER CONFIRM EXISTING VALVES DO NOT LEAK, OR

FOLLOW GUIDELINE PROVISIONS TO BE TAKEN IF THEY ARE FOUND

DEFECTIVE. NO OUTAGES WILL BE REQUIRED DURING THIS SUB-PHASE

WITH MAIN LOOP CONTINUALLY SERVING BOTH SIDES.

PHASE 2.2 (BUILD-BACK - REFER TO DETAIL 2 AND 20-29 SERIES KEY NOTES):

INSTALL NEW PIPING IN SAME LOCATION AS REMOVED SECTION OF 8" COLD

WATER MAIN. MAY REUTILIZE EXISTING PIPING RACK FOR PIPING

SUPPORTS. REFER TO KEY NOTES FOR ADDITIONAL INFORMATION RELATED

TO INSTALLATION.

PHASE 2.3 (RISER VALVE REPLACEMENT - 30+ SERIES KEY NOTES):

AREA SHOWN IN EXPANDED 1/4" = 1'-0" PLAN VIEW SHALL HAVE BOTH 8"

ISOLATION VALVES REPLACED WITH NEW TRIPLE OFFSET BUTTERFLY

VALVES. PLAN FOR OUTAGE OF SHAFT 4 AND REPLACE EXISTING 4" TAKE-

OFF VALVE AT SAME TIME. INCLUDE 1.5" DRAIN VALVE AT INTERSECTION

BETWEEN THREE(3) REPLACED VALVES. THIS SUB-PHASE WILL CAUSE A

LARGE DOMESTIC WATER OUTAGE FOR AREAS OF FACILITY THAT MAY BE

CRITICAL, CONTRACTOR SHALL REFER TO 'ALLOWANCE FOR TEMP

FIXTURES OR WATER SERVICES' BELOW FOR ACCOMODATIONS NEEDED

FOR THOSE AREAS. OUTAGE WILL AFFECT THE FOLLOWING DEPARTMENTS

AND SHOULD BE CAREFULLY COORDINATED WITH VA FACILITIES;

• BASEMENT LEVEL: TELEPHONE OPERATORS (POLICE), CENTRAL STAFF

LOCKER, NUTRITION/FOOD SERVICE, PATHOLOGY.

• FIRST FLOOR: NURSING HOME CARE DINING, VOLUNTARY SERVICE,

CANTEEN SERVICE, TEPT CANTEEN, OUT LEASED SPACE

• SECOND FLOOR: AMBULATORY CARE SERVICE, REHABILITATION

MEDICAL SERVICE, SPECIALTY CARE - TELEMED, EDUCATION, RESEARCH

SERVICE, ON-CALL, IRM SERVICE.

• THIRD FLOOR: AMBULATORY CARE SERVICE: PRIMARY CARE, OFFICES:

INFECTIOUS DISEASE, RHEUMATOLOGY, METABOLIC-ENDOCRINE,

EDUCATION, PULIMINARY CARE, AMBULATORY CARE SERVICE - PRIMARY

CARE, RESPIRATORY THERAPY

• FOURTH FLOOR: SURGERY, EDUCATION, CLINICAL SERVICES

ADMINISTRATION, ENGINEERING SAFETY, DIRECTOR, REHABILITATION

MEDICAL SERVICE - SPEECH PATH, EEG/NEUROLOGY

ISOLATION OF MAIN PIPING LOOP SECTIONS:

PERFORM THE FOLLOWING PROCEDURE STEPS TO PROPERLY ISOLATE

EACH SECTION OF PIPING LOOP AS DESCRIBED IN PHASING SEQUENCES,

1) SHUT-OFF ISOLATION VALVES ON INTERIOR SIDE OF LOOP BEING

MODIFIED OR REMOVED TO MAINTAIN SERVICES TO ALL RISERS.

2) REMOVE SECTION OF PIPING, OR TAP TEMPORARY DRAIN CONNECTION

TO VERIFY VALVES ARE HOLDING FOR A MINIMUM PERIOD OF 24 HOURS.

3) IF NO VALVE LEAKAGE, OR MINIMAL AMOUNT, IS WITNESSED THAN

PROCEED TO PIPING MODIFICATION AND/OR DEMOLITION SCOPE OF WORK

IDENTIFIED.

4) IF MODERATE OR SIGNIFICANT VALVE LEAKAGE IS WITNESSED THAN

PROVIDE 1.5" VALVE TAP WITH THREADED CONNECTION TO HOSE TO

NEAREST MECHANICAL ROOM DRAIN DISCHARGE LOCATION. THIS

TEMPORARY DRAIN CONNECTION AND HOSE SHALL BE REMOVED ONCE

NEW RISER VALVE REPLACEMENTS ARE COMPLETED.

---CONTRACTOR WILL BE RESPONSIBLE TO KEEP ON SITE AT LEAST FOUR(4)

SETS OF 1.5" VALVES WITH THREADED CONNECTIONS AND TWO(2) 250' LONG

HOSES OF 1.5" DIAMETER IN SIZE.

CONTRACTOR ALLOWANCE FOR TEMP FIXTURES OR WATER SERVICES:

ASSUME THAT DURING THE COURSE OF THE 8 PHASE DOMESTIC WATER

LOOP REPLACEMENT THAT SPECIFIC AREAS WILL REQUIRE TEMPORARY

SINKS AND/OR EXTENSION OF TEMPORARY WATER SERVICES TO THEIR

DEPARTMENT. CONTRACTORS SHALL INCLUDE THE FOLLOWING

ALLOWANCES WITHIN THEIR BASE BID TO ACCOMODATE THOSE REQUESTS

WHEN THEY ARISE DURING OUTAGE COORDINATION WITH VA FACILITIES.

• INCLUDE UP TO TWELVE(12) TEMPORARY SINK FIXTURES TIED INTO AN

ADJACENT RISER SERVICE. EACH SINK WILL REQUIRE UP TO 50' OF

COPPER PIPE FOR WATER CONNECTIONS, OTHERWISE HOSE WILL BE

UTILIZED IF DISTANCE EXCEEDS THAT SPECIFIED AMOUNT OF PIPING.

• INCLUDE FOUR(4) TEMPORARY BACK-UP WATER CONNECTIONS FOR

COLD WATER SERVICE TO AN ENTIRE DEPARTMENT. TEMPORARY COLD

WATER MAIN SHALL BE ASSUMED AT 2" SIZE AND EXTEND A MAXIMUM OF

250' TO CONNECT INTO AN ADJACENT RISER SERVICE.

• NOTE THAT THE ABOVE IS FOR ENTIRE PROJECT, NOT PER PHASE.

G

8" CW

2 1/2" CHW

4" HW

2" HW

3" CW

3/4" RHW

H

2" SOFT

10" HPS

5" CHWR

8" CHWR

8" CHWS

2" HW

3/4" CHW

12" CHWS

12" CHWR

8" CHWR

8" CHWS

3" MPC

5" MPS3" HPS

G

TO SCI BLDG.

G.B

G.C

G.A

4.A'

4.C

4.B

H G

1356-PP102.1

1356-PP102.1

4.C

4.B

G.B

G.C

G.A

H

C W

C W

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS SUBMISSION

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRUE NORTH

PLAN NORTH

D

F

C R e v it P ro je c ts

\V A

B u ild in g

P h a s e

M e c h a n ic a l ja s o n g o tt w a lt

.r v t

/3 /2

:3

:0

A M

BASEMENT INTERSTIAL - PHASE 2

- DOMESTIC WATER PLAN

PREVENT LEGIONELLA,

PHASE III

MINNEAPOLIS

618-14-118

11/30/2022 JG TM / JG618-14-118

1356-PP102.1

1/4" = 1'-0"

ENLARGED - PHASE 2.3

NO SCALE

PHASE 2 - ISOMETRIC VIEW

NO SCALE

PHASE 2 ELEVATION - EAST TUNNEL

1/16" = 1'-0"

PHASE 2.1 DEMO

1/16" = 1'-0"

PHASE 2.2 NEW

CONNECTION

TO PREVIOUS

PHASE.

3" CW CONNECTION TO

SCI COLD WATER SERVICE

41360DATE REG. NO.

I HEREBY CERTIFY THAT THIS PLAN,

SPECIFICATION OR REPORT WAS PREPARED BY ME

OR UNDER MY DIRECT SUPERVISION AND THAT I

AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF MINNESOTA.

JASON GOTTWALT, P.E.

T S

T S

TS

TS

TS

TS

TS

TS

TS

KEY NOTES:GENERAL NOTES:

GN

1356-PP103.1

SHAFT 4

2 2 2

HJKLM

1" RHW UP

2 1/2" HW UP

4" CW UP

4" CW UP

C W

4" CW

2 1/2" HW

1" RHW

4" CW

GN

SHAFT 4

5 5

4.C

4.B

HJKLM

4" CW

1" RHW

2 1/2" HW

4" CW

/2

C W

1 1/4" CW3/4" CW

/2

C

W

3/4" CW

4" CW

4" CW UP

4" CW UP

2 1/2" HW UP

1" RHW UP

7 8

N

4" CW UP & DN

4" CW UP & DN

2 1/2" HW UP & DN

3/4" RHW UP & DN

M

N

4" CW UP & DN

4" CW UP & DN

2 1/2" HW UP & DN

3/4" RHW UP & DN

M

N

4" CW UP & DN 2

4" CW UP & DN

2" HW UP

2 1/2" HW DN

3/4" RHW UP & DN

M

N

4" CW UP & DN

4" CW UP & DN

2" HW UP

2 1/2" HW DN

3/4" RHW UP & DN

M

N

3" CW UP

4" CW DN

3" CW UP

4" CW UP

2" HW UP & DN

3/4" RHW UP & DN

M

N

3" CW UP & DN

3" CW UP & DN

2" HW UP & DN

3/4" RHW UP & DN

M

N

3/4" RHW DN

2" HW DN

3" CW DN

3" CW DN

M

N

3" CW DN

3" CW DN

2" HW DN

3/4" RHW DN

M

1 BEFORE OUTAGE: ROUTE NEW SHAFT 4 PIPING PARALLEL TO

EXISTING PIPING TO LEVEL ABOVE.

DURING OUTAGE: REMOVE AND REPLACE MAIN PIPING BETWEEN

VALVES 4.B AND 4.C. MAKE FINAL CONNECTION TO NEW SHAFT 4

PIPING. ABANDON EXISTING COLD WATER RISER PIPING TO BE

DEMOLISHED AFTER ALL SHAFT 4 FINAL CONNECTIONS ARE MADE

AND OUTAGE IS COMPLETE.

AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW

AND KEY NOTE 2.

AFTER OUTAGE: REMOVE ABANDONED COLD WATER RISER PIPING.

DEADLEG OR ABANDONED PIPING SHALL NOT REMAIN.

MAIN PIPING DEMOLITION INDICATED IS TO OCCUR IN THE NEXT

PHASE. REFER TO 1/1356-PP102.1.

BEFORE OUTAGE: ROUTE NEW SHAFT 4 PIPING PARALLEL TO

EXISTING PIPING TO LEVEL ABOVE. EXTEND NEW TAKEOFFS TO

EXISTING BRANCH TAKEOFFS AND PREPARE FOR NEW CONNECTION.

DURING OUTAGE: DISCONNECT EXISTING BRANCH TAKEOFFS AND

REMOVE TAKEOFF PIPING. MAKE TAKEOFF FINAL CONNECTIONS.

ABANDON EXISTING COLD WATER RISER PIPING TO BE DEMOLISHED

AFTER ALL RISER "G" FINAL CONNECTIONS ARE MADE AND OUTAGE IS

COMPLETE.

AFTER OUTAGE: REFER TO ASSOCIATED LEVEL DEMOLITION VIEW

AND KEY NOTE 2.

DURING RISER OUTAGE: DISCONNECT FROM EXISTING COLD WATER

BRANCH AND MAKE FINAL CONNECTION FROM NEW COLD WATER

BRANCH MAIN AT POINT INDICTED ON PLAN. SEE PLAN FOR PIPE

SIZING. CONTRACTOR TO VERIFY PIPE SIZING AND OUTAGE AREAS

PRIOR TO CONSTRUCTION. REMOVE EXISTING PIPING BACK TO

BRANCH MAIN.

NEW 4" STAINLESS STEEL MAIN TO BE INSTALLED PARALLEL WITH

EXISITNG. NO MAJOR DUCTWORK OR PIPING OBSTRUCTIONS.

CONTRACTOR TO PROVIDE NEW SUPPORT HANGERS FOR PARALLEL

PATH. NOTE THAT MAJORITY OF ROUTE SHOWN IS ALONG SERVICE

WALKWAY, CONTRACTOR SHALL NOT IMPEED INTO WALKWAY

WITHOUT PERMISSION OF VA COTR. ALSO NOTE LOW VOLTAGE

TRAYS MAY PARTIALLY BLOCK ACCESS TO WHERE PIPING WILL BE

ROUTED, VERIFY SITE CONDITIONS.

NOTE THAT COLD WATER PIPING WILL NEED TO CROSS LOW

VOLTAGE CABLE TRAY AT THIS LOCATION. COORDINATE

MODIFICATION OF LOW VOLTAGE CABLE TRAYS IF REQUIRED.

CORE DRILL HOLE UP INTO SHAFT #4 AT THIS LOCATION, REFER TO

DETAILS 4 THROUGH 14 ON THIS DRAWING.

A.

B.

C.

D.

E.

F.

THE OUTLINE OF 'MEANS-AND-METHODS' NOTES BELOW FOR VERTICAL

COLD WATER RISER REPLACEMENTS INDICATED WITHIN THESE

DRAWINGS IS NOT INTENDED TO BE ALL-INCLUSIVE OF EFFORT

REQUIRED BY CONTRACTOR. NOR ARE THESE NOTES AND/OR

SUGGESTIONS MEANT TO LIMIT CONTRACTORS FROM DEVELOPING

THEIR OWN APPROACH THAT MAY BE CONSIDERED MORE COST

EFFECTIVE OR SAFE. THESE NOTES ARE MAINLY MEANT TO QUALIFY

EXISTING CONDITIONS AND DEFINE MINIMUM LEVEL OF PLANNING

REQUIRED BY VA FOR EACH OF THESE TIME SENSITIVE OUTAGES.

NO MAJOR WATER OUTAGE SHALL LAST MORE THAN 12 HOURS IN

DURATION. PLUMBING CONTRACTOR TO DETERMINE ADEQUATE

NUMBER OF PLUMBER CREWS REQUIRED TO PERFORM MULTIPLE

TASKS SIMULTANEOUSLY DURING OUTAGES. ALL OUTAGES SHALL BE

ASSUMED TO BE PERFORMED DURING WEEKEND OR NIGHT OVERTIME

HOURS WHEN BIDDING THIS PROJECT.

VERTICAL RISER REPLACEMENT (TYPE 1 - WITHIN MECHANICAL ROOM)

• FOR RISERS WITHIN MECHANICAL ROOMS, CONTRACTOR SHALL

CORE DRILL HOLES THROUGH FLOOR ADJACENT TO EXISTING

PLUMBING RISER FOR NEW INSTALLATION. EXISTING FLOOR

PENETRATIONS AND/OR SLEEVE SHALL BE PATCHED FLUSH TO

EXISTING FLOOR AS REQUIRE UPON DEMOLITION OF THOSE RISERS.

• EXISTINGT TAKE-OFF VALVES MAY REQUIRE RELOCATION FOR

CONNECTION INTO NEW RISER. VERIFY ADEQUATE ACCESS TO ALL

TAKE-OFF VALVES AND PROVIDE WITH NEW LAMINATE SIGNAGE.

ANY VALVES FOUND AT INACCESSIBLE LOCATIONS SHALL BE

RELOCATED BY CONTRACTOR.

• REFER TO CLIN 3001 FOR REPLACEMENT OF ALL ICRCUIT SETTER

VALVES WITHIN ENTIRE BUILDING. PLUMBING CONTRACTOR MAY

OPT TO HAVE DEDICATED CREWS ASSIGNED TO THIS TASK DURING

RISER OUTAGE TO LIMIT NUMBER OF SECONDARY OUTAGES

REQUIRED. HOWEVER, IF ENOUGH PLUMBERS ARE AVAILABLE TO

ACHIEVE THIS DURING LIMITED OUTAGE TIMEFRAME, THAN REFER

TO GENERAL NOTES ON DRAWING PP002 FOR 'LARGE OUTAGES' TO

PERFORM PRIOR TO THE MAJOR RISER OUTAGE.

VERTICAL RISER REPLACEMENT (TYPE 2 - WITHIN ENCLOSED SHAFT)

• IN GENERAL, MAJOR RATED SHAFTS SHOWN IN THESE DRAWINGS

HAVE EXISTING FULL SIZED ACCESS DOOR FROM BASE OF SHAFT

ON FIRST FLOOR LEVEL. HOWEVER, THAT IS TYPICALLY THE ONLY

ACCESS INTO THESE SHAFTS THAT ARE FULLY OPEN (NO

INTERMEDIATE FLOOR STRUCTURES) UP THROUGH PENTHOUSE

LEVEL WHERE RATED WALLS ARE BUILT-UP WITH LID (TYPICALLY

12'+) WITHIN ENCLOSED PENTHOUSE LEVEL.

• IN ORDER TO GAIN ACCESS TO TOP OF SHAFT, CONTRACTOR WILL

BE REQUIRED TO FURNSIH AND INSTALL FIRE RATED DOOR

ASSEMBLIES FROM PENTHOUSE LEVEL. THESE DOORS MAY BE

USED IN CONJUCTION OF RIGGING FOR BOSUN CHAIRS FROM TOP

OF SHAFT IF CONTRACTOR DEEMS THAT AS SAFE AFTER REVIEW

WITH THEIR INTERNAL SAFETY OFFICIAL.

• IN ADDITION TO ACCESS ON TOP LEVEL OF SHAFT, CONTRACTOR

WILL HAVE OPPORTUNITIES TO INSTALL 24"X24" OR 48"X24" FIRE

RATED ACCESS PANELS ON ANY OTHER LEVEL REQUIRED (BUT

ONLY FROM INTERSTITIAL SPACE, INSTALLATION OF ACCESS

PANELS FROM PATIENT CARE AREAS WILL NOT BE PERMITTED).

• CONTRACTOR WILL BE REQUIRED TO PROVIDE THEIR OWN

SCAFFOLDING REQUIRED AT EACH LEVEL TO INSTALL NEW COLD

WATER RISERS ADJACENT TO EXISTING PRIOR TO SIOWTCHOVER

OUTAGE. SCAFFOLDS SHOULD BE STRATEGICALLY PLACE TO

ALLOW ACCESS FOR RECONNECTION TO FLOOR TAKE-OFF PIPING

INSIDE OF EACH SHAFT.

• EXISTING CONDITION PDF SKETCHES ARE PROVIDED ON DRAWINGS

WHERE WORK INSIDE CONFINED AREAS OF RATED SHAFTS IS

REQUIRED. THESE SKETCHES ARE FOR CONTRACTOR REFERENCE

ONLY AND MAY NOT FULLY INDICATE ALL SERVICES WITHIN SHAFT

ENCLOSURES. CONTRACTOR WILL BE REQUIRED TO FIELD VERIFY

ACTUAL SITE CONDITIONS OF EACH SHAFT WHILE DEVELOPING

ACCESS AND SAFETY PLANNING.

NOTE THAT SOME AREAS HAVE EXISTING COPPER MAINS INTENDED TO

REPLACE GALVANIZED RISERS. HOWEVER THESE MAINS WERE

INSTALLED UP TO 15-25 YEARS AGO AND THEIR INTEGRITY IS

QUESTIONABLE. CONTRACTOR MAY UTILIZE THE EXISTING ROUTE, AND

CORRESPONDING SUPPORT HANGERS, BUT MUST FULLY REMOVE ALL

ABANDONED/UNUSED COPPER PIPING MAINS. ONCE OFF SITE THE

CONTRACTOR MAY TAKE OWNERSHIP OF PIPING FOR RECYLCING OR

REPURPOSING, BUT IT SHALL NOT BE UTILIZED WITHIN THIS PROJECT.

NO EXISTING PIPING WILL BE ALLOWED TO BE LEFT ABANDONED. SOME

AREAS HAVE RESTRICITVE ACCESS DUE TO SURROUNDING PIPES

AND/OR STRUCTURE AND MAY REQUIRE TEMPORARY REMOVAL OF

PIPING OR DUCTWORK TO GAIN ACCESS FOR DEMOLITION.

CONTRACTOR TO ASSUME SOME LEVEL OF DISCONNECT/RECONNECT

OF EXISTING SERVICES TO GAIN ACCCESS FOR COMPLETE DEMOLITION

OF EXISTING PIPING, OR INSTALLATION OF NEW PIPE IN CONGESTED

AREAS. REFER TO DRAWING NOTES FOR ADDITIONAL INFORMATION.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS SUBMISSION

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRUE NORTH

PLAN NORTH

D

C R e v it P ro je c ts

\V A

B u ild in g

P h a s e

M e c h a n ic a l ja s o n g o tt w a lt

.r v t

/3 /2

:3

:0

A M

ALL LEVELS - PHASE 2 -

ENLARGED SHAFT 4 COLD WATER

REPLACEMENT PLANS

PREVENT LEGIONELLA,

PHASE III

MINNEAPOLIS

618-14-118

11/30/2022 JG TM / JG618-14-118

1356-PP102.2

1/8" = 1'-0"

BASEMENT - SHAFT 4 REPLACEMENT DEMO

1/8" = 1'-0"

BASEMENT - SHAFT 4 REPLACEMENT NEW

1/8" = 1'-0"

FIRST LEVEL - SHAFT 4 REPLACEMENT DEMO

1/8" = 1'-0"

FIRST LEVEL SHAFT 4 REPLACEMENT NEW

1/8" = 1'-0"

SECOND LEVEL - SHAFT 4 REPLACEMENT DEMO

1/8" = 1'-0"

SECOND LEVEL - SHAFT 4 REPLACEMENT NEW

1/8" = 1'-0"

THIRD LEVEL - SHAFT 4 REPLACEMENT DEMO

1/8" = 1'-0"

THIRD LEVEL - SHAFT 4 REPLACEMENT NEW

1/8" = 1'-0"

FOURTH LEVEL - SHAFT 4 REPLACEMENT DEMO

1/8" = 1'-0"

FOURTH LEVEL - SHAFT 4 REPLACEMENT NEW

NO SCALE

SHAFT 4 - BASEMENT DETAIL

NO SCALE

SHAFT 4 - FIRST LEVEL DETAIL

NO SCALE

SHAFT 4 - SECOND LEVEL DETAIL

NO SCALE

SHAFT 4 - THIRD LEVEL DETAIL

NO SCALE

SHAFT 4 - FOUTH LEVEL DETAIL

41360DATE REG. NO.

I HEREBY CERTIFY THAT THIS PLAN,

SPECIFICATION OR REPORT WAS PREPARED BY ME

OR UNDER MY DIRECT SUPERVISION AND THAT I

AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF MINNESOTA.

JASON GOTTWALT, P.E.

TS

T S

KEY NOTES: GENERAL NOTES:

T S

TS

TS

TS TS

TS

TS

G

E.A

E.B

E.C

331 1/2" CW

DRAIN 34

TO RISER E

REFER TO DETAIL

1/1356-PP105

FOR VALVE

LOCATION.

REFER TO DETAIL

2/1356-PP102

FOR VALVE

LOCATION.

8" CW

8" CW

5" CW

H

H W

/2

C H

W

C W

5" CW

1 1/2" CHW

4" HW

8" CW

4" HW

2 1/2" RHW

4.B

4.A

4.C

8" CW

TO BE

REPLACED

IN NEXT

PHASE

E.C E.A

E.B

A.A

A.C

A.B 8" CW

8" CW

8" CW

8" CW

6" CW

REFER TO DETAIL

1/1356-PP105 FOR

VALVE LOCATION.

REFER TO DETAIL

2/1356-PP103 FOR

VALVE LOCATION.

J

5" CW

6" CW

6"

C W

NOTE THAT THESE KEY NOTES ARE SPECIFIC TO THIS DRAWING (DO

NOT REFER TO MASTER KEY NOTES ON SHEET 1356-PP003). NOT ALL

KEY NOTES ARE UTILIZED AND MAY HAVE GAPS OF MISSING NOTE

NUMBERS TO KEEP GROUPS OF TEN NOTES AVAILABLE PER PHASE.

SHUT-OFF VALVE 4.C AND VALVE E.B TO ISOLATE SECTION OF PIPING

INDICATED FOR REMOVAL. REFER TO GENERAL NOTES FOR

PROVISIONS TO BE TAKEN TO VERIFY ANY EXISTING VALVE LEAKAGE.

ONCE ISOLATED, REMOVE SECTION OF 8" GALVANIZED PIPING LOOP.

CUT INTO SECTIONS SMALL ENOUGH TO TRANSPORT TO LOADING

DOCK AREA FOR REMOVAL. INCLUDE DEMOLITION OF EXISTING

SUPPORTS MOUNTED TO PIPING RACKS, NEW PIPING WILL BE

SUPPORTED ONTO EXISTING RACK STRUCTURE BUT SHOULD BE

PROVIDED WITH NEW PIPE CLAMPS.

NOT USED THROUGH KEY NOTE

INSTALL NEW SECTION OF 8" SCHEDULE 10 STAINLESS STEEL PIPING TO

REPLACE PREVIOUSLY REMOVED. INSTALL IN EXACT SAME LOCATION

AS REMOVED SECTION OF PIPING. PROVIDE NEW SUPPORT CLAMPS

ON EXISTING PIPING RACK AS REQUIRED.

PROVIDE TEMPORARY END CAPS AT EITHER SIDE OF NEW PIPING

SECTION. FIRST PERFORM A PRESSURE TEST ON PIPING SECTION PER

SPECIFICATION REQUIREMENTS, AND THEN STERILIZE PIPING USING

CHLORINE SOLUTION FOR AT LEASE 24 HOURS PRIOR TO FLUSHING.

INCLUDE DRAIN/FILL VALVES ON EITHER END TO ACCOMPLISH.

INSULATE ENTIRE LENGTH OF PIPING PER SPECIFICATION

REQUIREMENTS. INCLUDE CONTINUOUS PVC COVERING THROUGHOUT

AND PREPARE ENDS FOR EXTENSION TO NEXT SUB-PHASE PIPING

WHICH WILL INCLUDE INSULATING ALL VALVE BODIES.

NOT USED THROUGH KEY NOTE

SHUT-OFF VALVE 4.C AND VALVE 2.B' (BOTH FURTHER OUT TO NEXT

ADJACENT RISER VALVES OUTSIDE THE EXTENTS OF THIS PHASE

DRAWING) TO ISOLATE RISER E FOR VALVE REPLACEMENT. REFER TO

GENERAL NOTES FOR PROVISIONS TO BE TAKEN TO VERIFY ANY

EXISTING VALVE LEAKAGE AND AREAS THAT WILL BE AFFECTED BY

THIS MAJOR WATER OUTAGE.

ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER

SIDE OF COLD WATER RISER TAKE-OFF VALVE WITH NEW STAINLESS 8"

TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD

EXISTING 5" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN

LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING

RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO

UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH

40 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN

OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).

DURING OUTAGE, INSTALL THERMOWELLS ON BOTH HOT AND COLD

WATER MAINS TO ACCEPT AN INSERTION TYPE TEMPERATURE SENSOR

TO BE INTEGRATED INTO BUILDING AUTOMATION SYSTEM FOR

INFORMATION MONITORING AND TRENDING.

INSTALL STRAP ON TEMPERATURE SENSORS INDICATE ON

RECIRCULATION PIPING. REPAIR ANY DAMAGED OR REMOVED

INSULATION ON COMPLETION.

ONCE VALVE INSTALLATION IS COMPLETED, INSULATE ALL AFFECT

PIPING AND NEW VALVE BODIES COMPLETELY. COVER EVERYTHING

WITH PVC JACKET COVERS AND SEAL AS REQUIRED. INSULATION CAN

OCCUR DURING NORMAL HOURS AFTER OUTAGE COMPLETION, BUT

SHOULD NOT BE DELAYED FOR ANY MORE THAN 3 BUSINESS DAYS.

NOT USED THROUGH KEY NOTE

SHUT-OFF VALVE E.C AND VALVE 2.B (BOTH FURTHER OUT TO NEXT

ADJACENT RISER VALVES OUTSIDE THE EXTENTS OF THIS PHASE

DRAWING) TO ISOLATE RISER A FOR VALVE REPLACEMENT. REFER TO

GENERAL NOTES FOR PROVISIONS TO BE TAKEN TO VERIFY ANY

EXISTING VALVE LEAKAGE AND AREAS THAT WILL BE AFFECTED BY

THIS MAJOR WATER OUTAGE.

ONCE RISER IS ISOLATED, REPLACE THE TWO(2) 8" VALVES ON EITHER

SIDE OF COLD WATER RISER TAKE-OFF VALVE WITH NEW STAINLESS 8"

TRIPLE OFFSET BUTTERFLY VALVES AND ALSO REPLACE THE THIRD

EXISTING 6" TAKE OFF VALVE WITH THE SAME MODEL VALVE AS MAIN

LOOP. INCLUDE A 1.5" STAINLESS STEEL BALL VALVE FOR DRAINING

RISER IN SECTION OF PIPING BETWEEN THESE THREE VALVES (ALSO

UTILIZE THIS OUTAGE TO CHANGE THAT SECTION OF PIPING WITH SCH

10 STAINLESS STEEL - NO STERILIZING REQUIRED TO SHORTEN

OUTAGE DURATION, BUT STILL THOROUGHLY FLUSH).

INCLUDE A 4" STAINLESS STEEL VALVE FOR TAKE-OFF TO WATER

HEATERS IN SECTION OF EXISTING PIPING TAKE-OFF.

DURING OUTAGE, INSTALL THERMOWELLS ON COLD WATER MAIN TO

ACCEPT AN INSERTION TYPE TEMPERATURE SENSOR TO BE

INTEGRATED INTO BUILDING AUTOMATION SYSTEM FOR INFORMATION

MONITORING AND TRENDING.

ONCE VALVE INSTALLATION IS COMPLETED, INSULATE ALL AFFECT

PIPING AND NEW VALVE BODIES COMPLETELY. COVER EVERYTHING

WITH PVC JACKET COVERS AND SEAL AS REQUIRED. INSULATION CAN

OCCUR DURING NORMAL HOURS AFTER OUTAGE COMPLETION, BUT

SHOULD NOT BE DELAYED FOR ANY MORE THAN 3 BUSINESS DAYS.

PROVIDE A 4" HOT WATER STAINLESS STEEL TRIPLE OFFSET

BUTTERFLY VALVE TO ISOLATE HOT WATER HEATER IN THIS AREA FOR

REPLACEMENT DURING PHASE 4, REFER TO DRAWING PP104.1.

PHASE 3.1 (DEMO - REFER TO DETAIL 1 AND 10-19 SERIES KEY NOTES):

THE EXISTING GALVANIZED 8" COLD WATER PIPING MAIN TO BE REMOVED

BETWEEN INTERIOR VALVES OF RISERS INDICATED IN KEY NOTES. REFER

TO WORK SEQUENCE DESCRIBED IN 'ISOLATION OF MAIN PIPING LOOP

SECTIONS' BELOW TO EITHER CONFIRM EXISTING VALVES DO NOT LEAK, OR

FOLLOW GUIDELINE PROVISIONS TO BE TAKEN IF THEY ARE FOUND

DEFECTIVE. NO OUTAGES WILL BE REQUIRED DURING THIS SUB-PHASE

WITH MAIN LOOP CONTINUALLY SERVING BOTH SIDES.

PHASE 3.2 (BUILD-BACK - REFER TO DETAIL 2 AND 20-29 SERIES KEY NOTES):

INSTALL NEW PIPING IN SAME LOCATION AS REMOVED SECTION OF 8" COLD

WATER MAIN. MAY REUTILIZE EXISTING PIPING RACK FOR PIPING

SUPPORTS. REFER TO KEY NOTES FOR ADDITIONAL INFORMATION RELATED

TO INSTALLATION.

PHASE 3.3 (RISER VALVE REPLACEMENT - 30-39 SERIES KEY NOTES):

AREA SHOWN IN EXPANDED 1/4" = 1'-0" PLAN VIEW SHALL HAVE BOTH 8"

ISOLATION VALVES REPLACED WITH NEW TRIPLE OFFSET BUTTERFLY

VALVES. PLAN FOR OUTAGE OF RISER E AND REPLACE EXISTING 5" TAKE-

OFF VALVE AT SAME TIME. INCLUDE 1.5" DRAIN VALVE AT INTERSECTION

BETWEEN THREE(3) REPLACED VALVES. THIS SUB-PHASE WILL CAUSE A

LARGE DOMESTIC WATER OUTAGE FOR AREAS OF FACILITY THAT MAY BE

CRITICAL, CONTRACTOR SHALL REFER TO 'ALLOWANCE FOR TEMP

FIXTURES OR WATER SERVICES' BELOW FOR ACCOMMODATIONS NEEDED

FOR THOSE AREAS. OUTAGE WILL AFFECT THE FOLLOWING DEPARTMENTS

AND SHOULD BE CAREFULLY COORDINATED WITH VA FACILITIES;

• FIRST FLOOR: HOSPICE/PALLIATIVE, NURSING HOME CARE, EDUCATION

SERVICE, CENTRAL STAFF LOCKERS, MECHANICAL ROOM 1E

• SECOND FLOOR: AMBULATORY CARE SERVICE - PRIMARY CARE -

CCDOR, CENTRAL STAFF LOCKERS, AMBULATORY CARE SERVICE -

COLON-RECTAL, ORTHOPEDIC, MECHANICAL ROOM 2E

• THIRD FLOOR: CLINICAL SERVICES ADMINISTRATION GENERAL INTERNAL

MEDICINE OFFICES, AMBULATORY CARE SERVICE - PRIMARY CARE

STAFF OFFICES, EDUCATION, CENTRAL STAFF LOCKERS,

REHABILITATION MEDICAL SERVICE

• FOURTH FLOOR: AMBULATORY CARE SERVICE - PRIMARY CARE - AEU,

STDU, SPECIALTY CARE NEUROLOGY; DIRECTOR'S SUITE; MEDICAL CARE

COST; PRI CARE - CARDIOLOGY

PHASE 3.4 (RISER VALVE REPLACEMENT - 40+ SERIES KEY NOTES):

AREA SHOWN IN EXPANDED 1/4" = 1'-0" PLAN VIEW SHALL HAVE BOTH 8"

ISOLATION VALVES REPLACED WITH NEW TRIPLE OFFSET BUTTERFLY

VALVES. PLAN FOR OUTAGE OF RISER A AND REPLACE EXISTING 6" TAKE-

OFF VALVE AT SAME TIME. INCLUDE 1.5" DRAIN VALVE AT INTERSECTION

BETWEEN THREE(3) REPLACED VALVES. THIS SUB-PHASE WILL CAUSE A

LARGE DOMESTIC WATER OUTAGE FOR AREAS OF FACILITY THAT MAY BE

CRITICAL, CONTRACTOR SHALL REFER TO 'ALLOWANCE FOR TEMP

FIXTURES OR WATER SERVICES' BELOW FOR ACCOMMODATIONS NEEDED

FOR THOSE AREAS. OUTAGE WILL AFFECT THE FOLLOWING DEPARTMENTS

AND SHOULD BE CAREFULLY COORDINATED WITH VA FACILITIES;

• BASEMENT LEVEL: MECHANICAL ROOM BD, PATHOLOGY, EDUCATION,

MAS, PROSTHETICS,

• FIRST FLOOR: AMBULATORY CARE SERVICE (PRIMARY CARE), CANTEEN

SERVICE, LIBRARY, VOLUNTARY SERVICE, EDUCATION (AUDITORIA), MAS,

NURSING HOME CARE, TRANSITIONAL HOUSING, SECURITY ADMIN,

MECHANICAL ROOM 1D

• SECOND FLOOR: MECHANICAL ROOM 2D; DENTAL SERVICE, ACS

(SPECIALTY) - ENT, DERMATOLOGY, PODIATRY, COLON-RECTAL;

EDUCATION; SPECIALTY CARE - TELEMED; VOLUNTARY SERVICE.

• THIRD FLOOR: MECHANICAL ROOM 3D; DIALYSIS; EDUCATION; PRI

CARE - GI OFFICE; ACS (PRIMARY) - INFECTIONS DISEASE,

RHEUMATOLOGY, METABOLIC, PULMONARY, ALLERGY, CARDIAC,

DIABETES, DIABETES ED., DYSRNYTHMIA, EP CARDIAC DEVICE, GI-

GASTROENTEROLOGY HEPATITIS C SCREENING, IMP. STUDY, SC

CARDIAC, THERAPEUTICS, THYROID; IMAGING.

• FOURTH FLOOR: MECHANICAL ROOM 4D, EDUCATION, MEDICAL

RESEARCH, LIBRARY, HOME BASED PRIMARY CARE, PRI CARE - CALL

CENTER, DIRECTOR'S SUITE.

ISOLATION OF MAIN PIPING LOOP SECTIONS:

PERFORM THE FOLLOWING PROCEDURE STEPS TO PROPERLY ISOLATE

EACH SECTION OF PIPING LOOP AS DESCRIBED IN PHASING SEQUENCES,

1) SHUT-OFF ISOLATION VALVES ON INTERIOR SIDE OF LOOP BEING

MODIFIED OR REMOVED TO MAINTAIN SERVICES TO ALL RISERS.

2) REMOVE SECTION OF PIPING, OR TAP TEMPORARY DRAIN CONNECTION

TO VERIFY VALVES ARE HOLDING FOR A MINIMUM PERIOD OF 24 HOURS.

3) IF NO VALVE LEAKAGE, OR MINIMAL AMOUNT, IS WITNESSED THAN

PROCEED TO PIPING MODIFICATION AND/OR DEMOLITION SCOPE OF WORK

IDENTIFIED.

4) IF MODERATE OR SIGNIFICANT VALVE LEAKAGE IS WITNESSED THAN

PROVIDE 1.5" VALVE TAP WITH THREADED CONNECTION TO HOSE TO

NEAREST MECHANICAL ROOM DRAIN DISCHARGE LOCATION. THIS

TEMPORARY DRAIN CONNECTION AND HOSE SHALL BE REMOVED ONCE

NEW RISER VALVE REPLACEMENTS ARE COMPLETED.

---CONTRACTOR WILL BE RESPONSIBLE TO KEEP ON SITE AT LEAST FOUR(4)

SETS OF 1.5" VALVES WITH THREADED CONNECTIONS AND TWO(2) 250' LONG

HOSES OF 1.5" DIAMETER IN SIZE.

CONTRACTOR ALLOWANCE FOR TEMP FIXTURES OR WATER SERVICES:

ASSUME THAT DURING THE COURSE OF THE 8 PHASE DOMESTIC WATER

LOOP REPLACEMENT THAT SPECIFIC AREAS WILL REQUIRE TEMPORARY

SINKS AND/OR EXTENSION OF TEMPORARY WATER SERVICES TO THEIR

DEPARTMENT. CONTRACTORS SHALL INCLUDE THE FOLLOWING

ALLOWANCES WITHIN THEIR BASE BID TO ACCOMMODATE THOSE

REQUESTS WHEN THEY ARISE DURING OUTAGE COORDINATION WITH VA

FACILITIES.

• INCLUDE UP TO TWELVE(12) TEMPORARY SINK FIXTURES TIED INTO AN

ADJACENT RISER SERVICE. EACH SINK WILL REQUIRE UP TO 50' OF

COPPER PIPE FOR WATER CONNECTIONS, OTHERWISE HOSE WILL BE

UTILIZED IF DISTANCE EXCEEDS THAT SPECIFIED AMOUNT OF PIPING.

• INCLUDE FOUR(4) TEMPORARY BACK-UP WATER CONNECTIONS FOR

COLD WATER SERVICE TO AN ENTIRE DEPARTMENT. TEMPORARY COLD

WATER MAIN SHALL BE ASSUMED AT 2" SIZE AND EXTEND A MAXIMUM OF

250' TO CONNECT INTO AN ADJACENT RISER SERVICE.

• NOTE THAT THE ABOVE IS FOR ENTIRE PROJECT, NOT PER PHASE.

G

8" CW

2 1/2" CHW

4" HW

2" HW

H

10" HPS

2" SOFT

5" CHWR

8" CHWR

8" CHWS

12" CHWS

12" CHWR

8" CHWR

8" CHWS

5" MPS

3" MPC

4" PC

G

1356-PP103.1

4.C

E.C

E.A

E.B

H G

1356-PP103.1

RISER E

4.C

H

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS SUBMISSION

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

TRUE NORTH

PLAN NORTH

D H

C R e v it P ro je c ts

\V A

B u ild in g

P h a s e

M e c h a n ic a l ja s o n g o tt w a lt

.r v t

/3 /2

:3

:4

A M

BASEMENT INTERSTITIAL - PHASE

3 - DOMESTIC WATER PLAN

PREVENT LEGIONELLA,

PHASE III

MINNEAPOLIS

618-14-118

11/30/2022 JG TM / JG618-14-118

1356-PP103.1

1/4" = 1'-0"

ENLARGED - PHASE 3.3 (RISER E)

NO SCALE

PHASE 3 - ISOMETRIC VIEW

1/4" = 1'-0"

ENLARGED - PHASE 3.4 (WATER HEATER TAKE-OFF AND RISER A)

NO SCALE

PHASE 3 ELEVATION - EAST TUNNEL

1/16" = 1'-0"

PHASE 3.1 - DEMO

1/16" = 1'-0"

PHASE 3.2 - NEW

CONNECTION

TO PREVIOUS

PHASE.

41360DATE REG. NO.

I HEREBY CERTIFY THAT THIS PLAN,

SPECIFICATION OR REPORT WAS PREPARED BY ME

OR UNDER MY DIRECT SUPERVISION AND THAT I

AM A DULY LICENSED PROFESSIONAL ENGINEER

UNDER THE LAWS OF THE STATE OF MINNESOTA.

JASON GOTTWALT, P.E.

1356-PP101-0 - BASEMENT INTERSTITIAL - OVERALL - DOMESTIC WATER LOOP REPLACEMENT PLAN
1356-PP101-1 - BASEMENT INTERSTITIAL - PHASE 1 - DOMESTIC WATER PLAN
1356-PP101-2 - ALL LEVELS - PHASE 1 - ENLARGED RISER -G- COLD WATER REPLACEMENT PLANS
1356-PP102-1 - BASEMENT INTERSTIAL - PHASE 2 - DOMESTIC WATER PLAN
1356-PP102-2 - ALL LEVELS - PHASE 2 - ENLARGED SHAFT 4 COLD WATER REPLACEMENT PLANS
1356-PP103-1 - BASEMENT INTERSTITIAL - PHASE 3 - DOMESTIC WATER PLAN

File details come from the government source that posted it. Updated .