Attachment D As Built Drawings and GIS Data Submittal.pdf
PDF 172 KB Posted
- Attached to
- Fiber Construction Services - North Region
- Solicitation number
- 26-448DOIT-TELEC-B-48349
- Issued by
- Jefferson County, Illinois
About this file
This is Attachment D of a specification document from the Illinois Department of Innovation and Technology (DoIT) for contract B-48349 Fiber Construction Services – North Region, outlining the requirements for as-built documentation and Geographic Information System (GIS) data submittal upon project completion.
The vendor is required to submit Record Construction Drawings, an Electronic Data Location File, and GIS Point and Shape Files to DoIT within thirty days of contract or project completion. The Record Construction Drawings must be red-lined to show actual construction performed, including the location of installed conduit and fiber optic cable with fiber count numbers, referenced to permanent landmarks, and measured offsets at intervals of one hundred feet or less. The documentation must indicate installation depth at finished grade or below finished grade, changes from proposed construction, special construction methods, and sequential fiber cable identification at splice points and handhole walls. The Electronic Data Routing and Location File must contain GPS data points in a standardized table format with thirteen specified columns, acquired using calibrated GPS equipment with sub-foot accuracy and utilizing Illinois State Plane coordinates. GPS data must include the fiber or conduit running line every one hundred feet, directional changes, handholes, manholes, warning markers, splice points, and other pertinent construction features. The vendor must also provide three CSV files for each data collection section, specifying geodetic positions in latitude and longitude, grid positions in Illinois State Plane East Zone Coordinates, and raw GPS receiver data files, all named according to detailed nomenclature requirements. Additionally, ESRI format Shape files must be submitted for constructed fiber paths, handholes and manholes, and customer site entry locations, each with specified attribute fields and naming conventions.
No pricing information, funding sources, set-asides, incumbency status, or contract term details are provided in this attachment, as it focuses exclusively on technical data submittal requirements and GIS formatting specifications. GPS equipment must be calibrated every ninety days throughout the contract term, and DoIT will not accept the fiber installation until all required documentation and data are provided in appropriate detail.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Illinois Department of Innovation and Technology
B-48349 Fiber Construction Services - North Region
Attachment D As-Built Drawings and GIS Data Submittal
1.1.1 As -Built Drawings and GIS Data Submittal
1. Documentation Submittal
Vendor shall produce and submit Record Construction Drawings, an Electronic Data Location File, and
Geographical Information System Point and Shape Files to DoIT within thirty (30) days of contract/project completion that describe in detail the as-built condition of the work. DoIT will utilize these submittals to assemble and implement fiber optic statewide system record location parameters.
DoIT will not accept the fiber until this data is provided in appropriate detail as stated above.
a. Record Construction Drawings
The Record Construction Drawings (RCD’s) shall represent the full set of Construction Drawings that have been “red-lined” by the Vendor to show the actual construction performed. The location of the installed conduit and fiber optic cable, including the cable’s fiber count number, shall be indicated on the RCD’s noting the distance of the fiber optic cable and conduit from and referenced to permanent landmarks that include such lines or points as fences, edges of pavement, bridges, underpasses, pedestals, sidewalks, and limits of rights-of-way, among others.
The Vendor shall measure and record the offsets (the distance from the cable or conduit to a physical reference point) on a line perpendicular to the fiber’s or conduit’s longitudinal axis (i.e. the running line) points along the fiber or conduit of one hundred feet (100 ft) or less to the physical reference points and wherever changes in the offset distance and direction of the running line have occurred.
The Vendor shall indicate on the RCD’s the depth of the installation as at finished grade (e.g. 0”) or below finished grade (e.g. - 48”), changes from the proposed construction and notes referencing any special construction such as steel plating, insulation barriers, concrete encasement, and an irregular depth of installation, among others. The Vendor shall record on the RCD’s, the fiber cable’s “sequential” at each splice point and handhole wall.
b. Electronic Data Routing and Location File
The Electronic Data Routing and Location File shall contain a comprehensive set of GPS data location points and recorded in a GPS data table identified by construction package number. The text in the header of the table shall be oriented vertically and shall contain the following 13 columns:
Col. A: Point No. Col. E: Elevation – IL SPC E/W Col. I: Means of Construction
Col. B: Point Code Col. F: Date of Data Col. J: Depth of Install
Col. C: Nothing – IL SPC E/W Col. G: Time of Data Col. K: Latitude
Col. D: Easting – IL SPC E/W Col. H: 000 or Lat # Col. L: Longitude
Col. M: GPS File Name
The content and form of data entered within columns C, D, E, K and L shall be directly entered in the content and form as well as logged into the GPS equipment by which the data was acquired.
Each data point acquired shall be uniquely numbered and shall contain the information necessary to populate each cell of each column in the data point row. The data shall be acquired using calibrated GPS locating equipment recording sub-foot accuracy and utilizing the appropriate state plane coordinate system. Data points acquired shall include, at a minimum, the running line of the fiber or conduit installation every 100 feet, any change of direction of such running line, handholes, manholes, warning markers, warning posts, splice points, locate posts, the start and end of each type of construction, and other pertinent construction features in order to delineate the completed work in the DoIT intended GIS system.
The Vendor shall indicate, in a separate table, the GPS equipment and its manufacturer and model/ serial number that were used to acquire the data. GPS equipment shall be calibrated every 90 days for the term of this agreement.
Point Codes within the GPS Data Table shall be noted as follows:
HHA Handhole type A
HHB Handhole type B
HHC Handhole type C
MHD Manhole type D
FO12 Fiber Optic 12 Count
FO24 Fiber Optic 24 Count
FO48 Fiber Optic 48 Count
FO96 Fiber Optic 96 Count
FO144 Fiber Optic 144 Count
FO288 Fiber Optic 288 Count
FO384 Fiber Optic 384 Count SPL Fiber Optic Splice
ENT Fiber Optic Building Entrance
POP Point of Presence
PAC Fiber Optic Point along Curve
WP Warning Post
LP Locate Post
WS Warning Sign
BP Bore Pit
RR1 RR Crossing 1-1/4 “ HDPE @ 10’ Min.
RR2 RR Crossing 2” Galvanized Steel Conduit
BA Bridge Attachment
Abbreviations for the Means of Construction within the GPS Data Table shall be noted as:
DB Direct Bury
OC Open Cut
DBR Directional Bore
RDB Bore Road
BRX Bore River Crossing
UGT Underground Tunnel Installation
FXC Place fiber in existing conduit
RR1 RR Crossing 1-1/4 “ HDPE @ 10’ Min.
RR2 RR Crossing 2”Galvanized Steel Conduit
BA Bridge Attachment
c. Geographical Information System Point Files
For each section of data collection, submit 3 GPS point files of all points taken. Each of the 3 files will be named according to the following nomenclature:
1. CSV file specifying the geodetic position in latitude and longitude: PP_NNNN_YYYY_MM_DD_LL
2. CSV file specifying the grid position in Illinois State Plane East Zone Coordinates:
PP_NNNN_YYYY_MM_DD_ILSPE
3. GPS Receiver raw data file: PP_NNNN_YYYY_MM_DD_RAW Where:
PP denotes Package Number
NNNN denotes Sequential Number of the data
All sequences shall follow in order of the stationing depicted on the Construction Drawings.
YYYY denotes Year the data was acquired
MM denotes Month the data was acquired
DD denotes Date the data was acquired
LL denotes Longitude and Latitude data
ILSPE denotes Illinois State Plane East Zone Coordinate data
PATH Shape Files Attribute Fields
RAW denotes Raw data
d. Geographical Information System Shape Files
Vendor shall provide ESRI format Shape files of the constructed fiber path that include 1) Fiber path, 2)
Handholes and manholes, and 3) Customer Site entry locations. The following nomenclature and attribute fields shall be used:
Nomenclature for Fiber Path: PP_PATH_ASBLT_YYMMDD
Attribute Field Description Data Type Data Field Properties
PackageNum 2 digit Package # Integer 2 digits: 00
BackBNum Back Bone # Integer Always 000
LateralNum Lateral Number: 010, 017 Integer 3 digits: 000
StrandCnt Strand Count : 012, 144 Integer 3 digits: 000
Length Length of segment in feet from splice to splice Integer 5 digits: 00,000
Constr Means of Construction: DB, OC, DBR, RDB Text 3 characters: AAA
Depth Depth of Installation in inches Integer 3 digits: 000
Nomenclature for Handholes and Manholes: PP_HHMH_ASBLT_YYMMDD
HHMH Shape File Attribute Fields:
Attribute Field Description Data Type Data Field Properties
PackageNum 2 digit Package # Integer 2 digits: 00
ID Handhole / Manhole # shown on Construction Drawings, blank if none shown Integer 3 digits: 000
Splice 1 = splice location 0 = no splice Integer I digit: 0
HMTYPE Handhole Type: A, B, C, or Manhole Type: D Integer 3 digits: 000
Nomenclature for Customer Sites: PP_SITE_ASBLT_YYMMDD
Customer Site Shape File Attribute Fields:
Attribute Field Description Data Type Data Field Properties
PackageNum 2 digit Package # Integer 2 digits: 00
CustID Customer ID # on Construction Drawings Integer 4 digits: 0000
Name Site Name Text 50 characters
Address Address of Customer Site Text 50 characters
Where:
PP denotes package number
YY denotes year the data was acquired
MM denotes month the data was acquired
DD denotes date the data was acquired
PATH is the label indicating the file is a path. Enter as shown.
ASBLT is the label indicating the file is an as-built. Enter as shown.
HHMH is the label indicating the file is for a handhole or manhole. Enter as shown.
SITE is the label indicating the file is for a customer site. Enter as shown.
File details come from the government source that posted it. Updated .