Attachment_B_-_Required_Submittal_Register.docx
DOCX document 36 KB Posted
- Solicitation number
- 41015
- Issued by
- Sacramento County, San Francisco City, California
About this file
This is a Required Submittal Register attachment for the Sacramento County Department of Airports' SMF Pedestrian Walkway Hub - Flight Paths Public Art Installation Project, a CUPCCAA informal bid contract numbered 41015 scheduled for September 2026. The project requires the contractor to furnish all necessary labor, materials, equipment, and work to complete the public art installation in strict conformance with specifications and applicable regulations. The submittal register establishes eleven minimum project-specific and payment-administration submittals required throughout the contract performance period, including baseline scheduling, installation work plans, rigging and equipment qualification packages, safety documentation, artwork receiving and inventory procedures, and final record documentation. Key submittals must be completed at specified intervals, with critical packages such as installation work plans, rigging plans, safety plans, and equipment loading verification due not less than 20 working days before affected field activities. Daily reports are required during field work following Notice to Proceed Phase 2 (NTP-2), and final documentation must be submitted before final inspection and field acceptance.
The submittal register supplements the Standard Construction Specifications and clarifies that county review of submittals does not authorize field mobilization, artwork receipt, or on-site work without express written authorization via NTP-2. The contractor bears full responsibility for accuracy, completeness, coordination, safety, regulatory compliance, and performance of all work. No work dependent upon a submittal may commence until county review is complete and applicable written authorization has been issued. The contractor must establish and maintain record documentation throughout the work period, including photographs, inspection information, permit documentation, and warranty information. Additionally, the contractor must comply with construction-waste requirements, maintaining detailed waste logs and supporting documentation including weight tickets and disposal records, with final waste documentation due before final payment and field acceptance.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SMF Pedestrian Walkway Hub - Flight Paths Public Art Installation Attachment B Attachment B
Sacramento County Department of Airports SMF Pedestrian Walkway Hub - Flight Paths Public Art Installation Project
ATTACHMENT B
REQUIRED SUBMITTAL REGISTER
CUPCCAA Informal Bid | Contract No. 41015 | September 2026 This Attachment identifies the minimum Project-specific and payment-administration submittals required for the SMF Pedestrian Walkway Hub – Flight Paths Public Art Installation Project and supplements Sections 5-8, 7-5, 8-1.02, 8-2.03, 8-5, and 12-1 of the Standard Construction Specifications.
This Attachment identifies only Project-specific and payment-administration content and timing. It does not restate or limit other submittals required by the Standard Construction Specifications, applicable laws, permits, manufacturer or equipment-provider requirements, County Risk Management requirements, or the Contractor’s proposed means and methods.
Submittals authorized under NTP-1 may be prepared, submitted, reviewed, and resubmitted before NTP-2.
County review of a submittal does not authorize field mobilization, artwork receipt, equipment movement, rigging, lifting, installation, or other on-Site Work. Such Work requires NTP-2 or other express written County authorization.
No Work dependent upon a submittal shall begin until the required review is complete and any applicable written County authorization has been issued.
County review does not constitute approval of the Contractor’s means and methods and does not relieve the Contractor of responsibility for the accuracy, completeness, coordination, safety, regulatory compliance, qualifications, or performance of the Work.
The following minimum Project-specific submittals are required:
| No. |
| Submittal |
| Minimum Content |
| Due |
| 1 |
| Baseline CPM Schedule and Updates |
| Schedule identifying the activities and milestones required by Section 7-5. |
| As required by Section 7-5. |
| 2 |
| Schedule of Values |
| Schedule of Values complying with Sections 1, 8-1.02, 8-2.03, and 8-5 of the Standard Construction Specifications. The breakdown shall correspond to the baseline schedule and total the Contract Price. |
| Submit sufficiently in advance to obtain County approval before acceptance of the first Progress Payment request. |
| 3 |
| Installation Work Plan |
| Work sequence; staffing and supervision; artwork receiving and handling; assembly sequence; access and staging; protective measures; equipment interfaces; coordination and review points; inspections; cleanup; punch-list correction; and closeout. |
| Initial plan within 30 Calendar Days after NTP-1. Final plan not less than 20 Working Days before the first affected field activity. |
| 4 |
| Rigging, Lift, Equipment, and Qualification Package |
| Equipment and rigging proposed; lift and connection points; load paths; lift sequence; suspended-load controls; operator, rigger, signal-person, and spotter qualifications; communication procedures; controlled zones; fall-protection and rescue provisions; and engineered calculations when required. |
| Not less than 20 Working Days before the first affected field activity. |
| 5 |
| IIPP; Code of Safe Work Practices; Contract Specific Safety Plan; and Task Specific Safety Plans |
| Safety documents required by Section 12-1 and the Project-specific controls required by the Contract Documents, including elevated Work, equipment movement, rigging, lifting, suspended loads, fall protection, dropped objects, rescue, emergency response, public separation, and airport operational coordination. |
| IIPP, CSWP, and CSSP not less than 20 Working Days before field mobilization. Each applicable TSSP not less than 20 Working Days before the affected high-hazard activity. |
| 6 |
| Equipment Loading and Protection Verification |
| Equipment type, model, operating weight, wheel, track, outrigger or point loads, load distribution, floor-loading verification, route compatibility, operating clearances, and protection of floors, thresholds, joints, walls, glazing, doors, ceilings, and adjacent finishes. |
| Not less than 20 Working Days before equipment delivery or movement at the Site. |
| 7 |
| Artwork Receiving and Inventory Log |
| Delivery and custody information; crate and component inventory; condition photographs; shortages; damaged packaging; damaged or missing components; missing hardware; and written corrective direction. |
| At artwork receipt and updated as required. Artwork receipt shall not occur before NTP-2 unless separately authorized in writing. |
| 8 |
| Artwork and Interface Readiness Verification |
| Visual verification of suspension cables, connection points, elevations, accessibility, clearances, sleeve hardware, orange-scope interfaces, curtain-wall bird locations, rigid attachments, structural-steel restraints, and artwork interfaces; photographs and identification of discrepancies requiring County direction. |
| Initial package not less than 20 Working Days before the first affected activity; update after authorized Site access and before connecting artwork or drilling/fastening at a building interface. |
| 9 |
| Daily Reports |
| Labor, supervision, activities, equipment, deliveries, inspections, safety meetings, controlled work areas, coordination matters, RFIs, changed conditions, incidents, delays, progress, and photographs. |
| Daily during field Work following NTP-2. |
| 10 |
| Record Documentation, Installation Certification, Closeout, and Warranty Package |
| Final installed locations and connections; approved adjustments or deviations; final photographs; alignment confirmation; inspection and permit information; installation certification; punch-list completion; cleanup and demobilization confirmation; warranty; and required closeout documentation. |
| Maintain record information during the Work. Submit the complete final package before final inspection and Field Acceptance. |
| 11 |
| Waste Log and Supporting Documentation |
| Required Waste Log, weight tickets, disposal and recycling records, and other documentation required by applicable construction-waste requirements. |
| Maintain during the Work and submit final documentation before final inspection, Field Acceptance, or final payment, as applicable. |
| Contract No. 41015 |
| CUPCCAA Informal Bid |
| Page 1 of 1 |