This document is an Attachment B detailing NASA's Financial Management Reporting Requirements for a future contract (RFP 80GSFC25R7005, Contract TBD). The requirements specify that the contractor must submit NASA 533 series reports following NASA Procedural Requirements NPR 9501.2E, with detailed financial reporting protocols.
Key reporting requirements include: submitting separate 533 reports for each Work Breakdown Structure (WBS) Level 2 element, providing a comprehensive breakdown of labor hours and costs across prime and subcontractor categories, and including narrative explanations for any cost or labor hour variances exceeding ±10%. Reports must be distributed within specific timeframes - the initial report within 30 working days after contract award, monthly reports by the 10th working day of the following month, and quarterly reports by the 15th day preceding the quarter being reported. The reports must cover detailed cost categories including direct labor hours, overhead expenses, other direct costs, and various fee components.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT B
FINANCIAL MANAGEMENT REPORTING
REQUIREMENTS
June 2014
RFP 80GSFC25R7005
CONTRACT TBD
Contract TBD Attachment ?
(06/2014) 2
FINANCIAL MANAGEMENT REPORTING REQUIREMENTS
Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.
a. Level of Detail
The Contractor’s 533 Reports shall contain a summary of total contract costs, as well as a separate 533 Report for each Work Breakdown Structure (WBS) Level 2 element of the Statement of Work. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.
b. Variance Narrative Reporting
In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month at the total contract level. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)
Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.
c. Distribution
The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.
After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period. The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.
d. Reporting Requirements
Each individual report shall address each line item within contract clause 1852.216-85 ESTIMATED COST AND AWARD FEE separately and include a cumulative summary
(06/2014) 3 for the contract in its entirety. Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:
1. Prime Direct Labor Hours:
(List applicable labor categories)
Total Prime Direct Labor Hours
2. Subcontractor Direct Labor Hours:
Subcontractor A Direct Labor Hours
Subcontractor B Direct Labor Hours (List applicable labor categories)
Subcontractor C Direct Labor Hours
Total Subcontractors Direct Labor Hours
3. Total Prime and Subcontractors Direct Labor Hours
4. Prime Direct Labor Costs:
Total Prime Direct Labor Costs
5. Prime Overhead Expense
6. Other Direct Costs (ODCs):
a. Subcontracts (list separately, Subcontractor A, B, C, etc.)
b. Material
c. Travel
d. Other (specify)
Total ODCs
7. Subtotal (Direct Labor, Overhead & ODCs)
8. G&A Expense
(06/2014) 4
9. Total Estimated Cost
10. Provisionally Billed Award Fee
11. Award Fee Earned
12. Fixed Fee
13. Total Cost-Plus-Award-Fee (CPAF)