Attachment A Special Provisions OR 11 MP 4 To Weston Intchge Chip Seal Project .pdf
PDF 453 KB Posted
- Attached to
- OR11: MP 4 to Weston Intchge. Chip Seal Project
- Solicitation number
- S-73000-00014662
- Issued by
- Union County, Oregon
About this file
These Special Provisions detail a highway construction project by the Oregon Department of Transportation (ODOT) for a chip seal application on Oregon-Washington Highway OR11 between MP 4 and Weston Interchange in Umatilla County, scheduled for September 2025. The project scope includes installing temporary traffic control, constructing an emulsified asphalt chip seal and fog coat, installing permanent pavement markings, and performing additional incidental work as specified in the contract documents. The work will be conducted using 2024 Oregon Standard Specifications for Construction, with a specific focus on a single application emulsified asphalt chip seal treatment.
The project involves applying polymer-modified emulsified asphalt (PMCRS-2h) and graded aggregate at specific rates, with strict requirements for material quality, application techniques, and performance standards. A comprehensive warranty period of one year is included, during which the contractor is responsible for addressing any failures such as loss of aggregate cover, flushing, or visual defects. The contract includes a price adjustment mechanism based on the expected life of the chip seal, with potential 5% increases or decreases depending on performance evaluations. The project will use specific traffic control measures, including limitations on work hours and lane closures, with work restricted between June 1 and August 15 to ensure optimal construction conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00014662 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00014662 Intent To Award.xlsx | XLSX spreadsheet | |
| Attachment C Bid Pricing Form~18.xlsx | XLSX spreadsheet | |
| Attachment E Minimal Assessment Memorandum.pdf | ||
| Attachment D Material Source Narrative.pdf | ||
| 00014662 Addendum 1.docx | DOCX document | |
| Carbon Dioxide ITB 20250815~1.pdf | ||
| 00014662 Addendum 2.docx | DOCX document | |
| Attachment B Plans~9.pdf | ||
| 00014662 Invitation.To.Bid.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
FOR HIGHWAY CONSTRUCTION
OREGON DEPARTMENT OF TRANSPORTATION
SALEM, OREGON
CHIP SEAL
OR11: MP 4 TO WESTON INTCHGE. CHIP SEAL PROJECT
OREGON-WASHINGTON HIGHWAY
UMATILLA COUNTY
SEPTEMBER 2025
OREGON DEPARTMENT OF TRANSPORTATION
FOR
Chip Seal OR11: MP 4 to Weston Intchge. Chip Seal Project
Oregon-Washington Highway Umatilla County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project forTemporary traffic control, permanent pavement markings and roadway items. Modified Special Provisions were prepared by me or under my supervision.
Sections 00220, 00221, 00222, 00223, 00224, 00225, 00280, 00305, 00705, 00860 & 00867
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
2025.07.28 14:51:00 -07'00'
FOR
Chip Seal OR11: MP 4 to Weston Intchge. Chip Seal Project
Oregon-Washington Highway Umatilla County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for contaminated media. Modified Special Provisions were prepared by me or under my supervision.
Section 00294
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
14:51:24 -07'00'
FOR
Chip Seal OR11: MP 4 to Weston Intchge. Chip Seal Project
Oregon-Washington Highway Umatilla County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for agency provided material source and staging areas. Modified Special Provisions were prepared by me or under my supervision.
Sections 00235, 00237 & 00335
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
15:30:01 -07'00'
FOR
Chip Seal
Oregon-Washington Highway Umatilla County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for _emulsified asphalt chip seal. Modified Special Provisions were prepared by me or under my supervision.
Section 00710
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
2025.07.30 09:09:07 -07'00'
TABLE OF CONTENTS FOR SPECIAL PROVISIONS
WORK TO BE DONE
SECTION 00150 - CONTROL OF WORK
SECTION 00165 - QUALITY OF MATERIALS
SECTION 00210 - MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC
CONTROL
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
SECTION 00235 - AGENCY PROVIDED MATERIAL SOURCES
SECTION 00237 - AGENCY-PROVIDED STAGING AREAS
SECTION 00280 - EROSION AND SEDIMENT CONTROL
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00294 - CONTAMINATED MEDIA
SECTION 00305 - CONSTRUCTION SURVEY WORK
SECTION 00335 - BLASTING METHODS AND PROTECTION OF EXCAVATION
BACKSLOPES
SECTION 00705 - EMULSIFIED ASPHALT PRIME COAT AND EMULSIFIED
ASPHALT FOG COAT
SECTION 00710 - SINGLE APPLICATION EMULSIFIED ASPHALT CHIP SEAL
SECTION 00860 - LONGITUDINAL PAVEMENT MARKINGS - PAINT
SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND
BARS
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 1
SPECIAL PROVISIONS
WORK TO BE DONE
The Work to be done under this Contract consists of the following:
1. Install temporary traffic control.
2. Construct emulsified asphalt chip seal and fog coat.
3. Install permanent pavement markings.
4. Perform additional and Incidental Work as called for by the Specifications and Plans.
APPLICABLE SPECIFICATIONS
2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION. The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Specifications. Sections of the technical specifications not identified in the Plans and Specifications remain applicable to the Contract according to their original terms.
Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in an exhibit or attachment to the Contract or in the Plans and Specifications as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it.
Bidders can access the Standard Specifications online at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
CLASS OF PROJECT
This is a State Project.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 2
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 3
SECTION 00150 - CONTROL OF WORK
Comply with Section 00150 of the Standard Specifications modified as follows:
00150.15(b) Agency’s Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Engineer will perform the Agency responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.5 (see Section 00305).
00150.15(c) Contractor’s Responsibilities - Replace this subsection, except for the subsection number and title, with the following:
The Contractor shall perform the Contractor responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305).
The Contractor shall perform slope staking including intersections and set stakes defining limits for clearing which approximate Right-of-Way and easements.
00150.50(c) Contractor’s Responsibilities – Replace the bullet that begins “In addition to the notification required…” with the following bullet:
• In addition to the notification required in OAR 952-001-0090(7), notify the Engineer and the Utility as soon as the Contractor discovers any previously unknown Utility conflicts or issues. Contrary to the OAR, stop excavating until directed by the Engineer and allow the Utility a minimum of two weeks to relocate or resolve the previously unknown Utility issues; and
Add the following subsection:
00150.50(f) Utility Information (No Anticipated Relocations) - Within the Project limits, there are no anticipated relocations with the Utilities listed in Table 00150-1. The Contractor shall contact those Utilities having buried facilities and request that they locate and mark them for their protection prior to construction.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 4
Table 00150-1
Utility
Contact Person's Name, Address, Email, and Phone Number
Pacific Power Doug Triebelhorn Power Estimator P.O. Box 220 Pendleton, OR 97801 Douglas.Triebelhorn@PacifiCorp.com Work: (541) 278-2957 Cell: (541) 240-1480
City of Milton-Freewater Richard Jolly Electric Superintendent P.O. Box 6, 722 S. Main Milton-Freewater, OR 97862 richard.jolly@milton-freewater-or.gov Work: 541-938-8231
Windwave Communications Jack Halbert OSP O&M and Design P.O. Box 1390, 73500 Rupe Kennedy Rd.
Boardman, OR 97818 jhalbert@windwave.tc Work: (541) 676-9663 ext 113 Cell: (541) 561-3862
Pacific Power, City of Milton-Freewater - Power Suppliers -
Energized power lines overhang portions of the Work with a minimum vertical clearance of 18 feet. The Contractor shall maintain at least 10 feet of safety clearance. Exceptions require written approval from the Power Supplier(s) and may require an on-site safety watcher, at no cost to the Contractor. The Contractor shall provide the Engineer a copy of the written approval of exception before beginning Work.
Windwave Communications - Telecommunication Utilities -
The Contractor shall obtain written approval from Telecommunication Utilities that have fiber optic communication cable facilities, for excavating within 10 feet of a buried fiber optic communications cable. Telecommunication Utilities may require an on-site safety representative at no cost to the Contractor for monitoring purposes. The Contractor shall provide the Engineer a copy of the written approval before beginning Work.
00150.91 Post-Construction Review - Replace this subsection, except for the subsection number and title, with the following:
The Contractor shall attend a Post-Construction Review meeting to be held by the Agency prior to issuance of Third Notification but not earlier than 45 Days following the date of Second Notification. The time and place of this meeting will be announced by the Engineer at least 15 Days prior to the meeting date. The purpose of this meeting is to examine the Project for possible process improvements that may benefit future projects. The Contractor’s attendance at the Post-Construction Review meeting is mandatory.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 5
SECTION 00165 - QUALITY OF MATERIALS
Comply with Section 00165 of the Standard Specifications modified as follows:
00165.35(e) Certificate of Origin of Construction Materials – Remove this section.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 6
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.02(a) General Requirements - Add the following bullet(s) to the end of the bullet list:
• During stage construction, provide continuous 24-hour flagger operation, with a minimum of 2 flaggers. Occupy the advance flagger stations, as directed.
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
Traffic Lanes may be closed on the Oregon - Washington Highway OR11 when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
Single Lane Closures – One Traffic Lane on the Oregon – Washington Highway OR11 may be closed during the following times:
• April 1 to October 31, weekly, Sunday at 9 p.m. through Friday at 3 p.m.
Two-lane Closures – Two Traffic Lanes on the Oregon – Washington Highway OR11 between mile point 19.10 and mile point 20.40 may be closed during the following times:
• April 1 to October 31, weekly, Sunday at 9 p.m. through Friday at 3 p.m.
One Traffic Lane may be closed on all other adjacent Roadways within the Project Site not listed above, when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
• Daily, Monday through Thursday, between 7:00 a.m. and 7:00 p.m.
• Friday, between 7:00 a.m. and 3:00 p.m.
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
Comply with Section 00221 of the Standard Specifications modified as follows:
00221.06 Traffic Control Plan - Replace this subsection with the following subsection:
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 7
00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs –
(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:
(1) Agency Traffic Control Plan - If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.
(2) Contractor-Modified Traffic Control Plan - The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer. Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.
The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor. The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.
To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.
If requesting a Contractor-modified Agency TCP, or a TCP developed by the Contractor, at a minimum the request shall meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP).
Provide the following information:
• Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.
• A TPAR plan that includes:
• Details and features used to provide pedestrian accessibility.
• Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.
• Temporary alternate facilities or detour routes for pedestrian traffic.
• Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.
• Proposed order and duration of the TCM.
• A detailed temporary striping plan.
If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 8
The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.
Once a TCP has been accepted by the Engineer, any additional modifications must be submitted by the Contractor for Agency review following the procedure described above. The Engineer is not obligated to consider additional modifications to a previously approved TCP.
(b) Tourist-Oriented Directional and Business Logo Signs - Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:
(1) No Signs - If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or
(2) Signs - Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.
00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:
• Providing, surfacing, maintaining, removing, and restoring the TPAR.
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
Comply with Section 00222 of the Standard Specifications modified as follows:
00222.40(e) Temporary Sign Placement - Add the following to the end of the bullet list:
• Place a “WAIT FOR FLAGGER” (CR4-23) sign approximately 50 feet in advance of each flagger station, facing incoming pedestrian traffic. Install the sign on a conical marker or other temporary sign support, as shown or as directed. Do not allow the sign installation height or location to block the visibility of the flagger for incoming Public Traffic.
• Install a 54-inch "TRUCKS LEAVING HIGHWAY XXXX FT" sign in advance of each entrance point to the Work Area at sign spacing “A” from the “TCD Spacing Table” shown on the Standard Drawings. Install a 54-inch "TRUCKS ENTERING HIGHWAY XXXX FT" sign in advance of each exit point from the Work Area at sign spacing “A” from the “TCD Spacing Table” shown on the Standard Drawings.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 9
• Install "ROAD WORK AHEAD" (W20-1-48) signs with a 36 by 24-inch "FINES DOUBLE" (R2-6aP) rider on the Oregon - Washington Highway, according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans except do not install the "FINES DOUBLE" rider on concrete barrier mounted signs.
• Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK"
(CG20-2A-24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans.
• During Emulsified Asphalt surface treatment operations, protect traffic by installing signing according to the "LOOSE GRAVEL IN ROADWAY SIGNING" detail shown on the Standard Drawings. The maximum length of loose Sand or Gravel shall not exceed 5 miles.
• When the existing centerline striping on the Oregon - Washington Highway is obliterated, do the following:
• Place a "NO CENTER LINE" (W8-12) sign with a 24 by 18-inch "NEXT 16 MILES"
(W7-3aP) plaque, approximately 2,500 feet in advance of each end of the Project.
• Place "NO CENTER LINE" (W8-12) signs on approximately 2 mile intervals for each direction of traffic.
• Place a "DO NOT PASS" (R4-1) sign on each side of the Roadway at the beginning of each existing no passing zone(, as necessary, except, if the length between two consecutive existing no passing zones is 1,300 feet or less, combine the no passing zones and place one "DO NOT PASS" sign on the right side of the Roadway at the beginning of each subsequent no passing zone within the combined zones).
• Place a "PASS WITH CARE" (R4-2) sign on the right side of the Roadway at the end of each existing no passing zone. If the length between no passing zones is 1,300 feet or less, do not install the "PASS WITH CARE" signs within the combined zones.
Instead, place one “PASS WITH CARE” sign on the right side of the Roadway at the end of the last no passing zone in a combined zone. Cover the "PASS WITH CARE" signs with a non-transparent weather and wind proof cover each time they are within an active Work Area controlled by flaggers with or without pilot cars, or when directed.
• Install two sign flag boards above "ROAD WORK NEXT 5 MILES", "ROAD WORK
AHEAD", and "NO CENTER LINE" (with "NEXT 16 MILES" rider) post mounted signs.
• Install a "24 HR FLAGGING AHEAD" (CW20-9) sign in each direction approximately 250 feet prior to the "BE PREPARED TO STOP" sign. Remove the temporary signs when 24-hour flagging is no longer required, or as directed.
• For paving operations on non-freeways, place “ABRUPT EDGE” (CW21-9) and “ROAD
WORK XX MPH” (CW20-1a) signs as shown. Use an “XX” value equal to 10 mph below the current posted regulatory speed. If a speed is posted for a temporary regulatory speed reduction, that speed is the current posted regulatory speed.
• For all other moving operations that do not create an abrupt edge adjacent to traffic, omit the “ABRUPT EDGE” signs.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 10
• Install a 60 by 24-inch "ROAD WORK NEXT 5 MILES" (CG20-1) sign on the Oregon - Washington Highway, in advance of the "ROAD WORK AHEAD" (W20-1) sign according to sign spacing "A" from the "TCD Spacing Table" shown on the Standard Drawings.
• Install a 60 by 36-inch "INTERMITTENT ROAD WORK NEXT 16 MILES" (CG20-13) sign on the Oregon - Washington Highway, in advance of the "ROAD WORK AHEAD" (W20-1) sign on each end of the Project according to sign spacing "A" from the "TCD Spacing Table" shown on the Standard Drawings.
• Install a 72 by 24-inch "CONSTRUCTION VEHICLE DO NOT FOLLOW" (CW23-14) sign on rigid substrate on the back of all Material or Equipment delivery vehicles.
• During pilot car operations, install a 15 by 24-inch "WAIT FOR PILOT CAR" (CR4-20) sign at stop-controlled side roads and accesses intersecting the Highway within the limits of the pilot car operation at the following locations:
• Jim Road, OR11 MP 5.61
• Havana-Helix Hwy, OR11 MP 6.19
• Tubbs Ranch Road, OR11 MP 6.31
• Rothrock Road, OR11 MP 9.06
• Mann Road, OR11 MP 11.64
• Spring Hollow Road, OR11 MP 12.23
• Rainville Road, OR11 MP 12.75
• Woodward Road, OR11 MP 14.82
• Pamburn Road, OR11 MP 16.07
• First Street, OR11 MP 16.25
• Third Street and Brooks Road, OR11 MP 16.43
• Wildhorse Road, OR11 MP 16.84
• Athena-Holdman Hwy, OR11 MP 17.32
• Banister Road, OR11 MP 17.52
• Schrimpf Road, OR11 MP 18.99
• Key Road, OR11 MP 19.29
• During pilot car operations, install a 12 by 12-inch "WAIT FOR PILOT CAR" (CR4-20a) sign in private residential driveways accessing the Highway within the limits of the pilot car operation. Place the sign in the driveway facing the private residence and so the sign face is not visible to Public Traffic on the Highway. Do not use the sign for apartments, condominiums or business accesses.
• At accesses, side roads, or residential driveways where "WAIT FOR PILOT CAR" (CR4-20) signs are installed, do not allow traffic to be stopped or held for longer than 20 minutes.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 11
• In addition to the signs, public notification (e.g. flyers, door hangers) may be used to inform the residents that may be affected by the pilot car operations and the "WAIT FOR PILOT CAR" signs.
• During pilot car operations, install a 15 by 24-inch "WAIT FOR PILOT CAR" (CR4-20) sign at stop-controlled side roads and accesses intersecting the Highway within the limits of the pilot car operation.
• During pilot car operations, install a 12 by 12-inch "WAIT FOR PILOT CAR" (CR4-20a) sign in private residential driveways accessing the Highway within the limits of the pilot car operation. Place the sign in the driveway facing the private residence and so the sign face is not visible to Public Traffic on the Highway. Do not use the sign for apartments, condominiums or business accesses.
• At accesses, side roads, or residential driveways where "WAIT FOR PILOT CAR" (CR4-20) signs are installed, do not allow traffic to be stopped or held for longer than 20 minutes.
• In addition to the signs, public notification (e.g. flyers, door hangers) may be used to inform the residents that may be affected by the pilot car operations and the "WAIT FOR PILOT CAR" signs.
• For each location of the "WAIT FOR PILOT CAR" sign, closely monitor for traffic compliance, operation, and safety at least once per hour during pilot car operations. If operational issues are observed, or if notified of operational issues, at stop-controlled accesses or side roads utilizing the "WAIT FOR PILOT CAR" (CR4-20) sign, remove the sign and replace it with a flagger.
00222.80(a) Area Basis -
Add the following sentence to the end of the paragraph that begins "Temporary signs will…":
No measurement of quantities will be made for “CONSTRUCTION VEHICLE DO NOT FOLLOW” (CW23-14) signs.
00222.90 Payment -
Add the following to the end of this subsection:
Payment will be made for not more than 2 sets of Work Area signs. All additional sets of Work Area signs will be at no additional cost to the Agency.
Add the following to the end of this subsection:
No separate or additional payment will be made for furnishing, installing, and maintaining 72 by 24-inch "CONSTRUCTION VEHICLE DO NOT FOLLOW" (CW23-14) signs. Payment will be included in 00221.90(b).
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 12
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
Comply with Section 00223 of the Standard Specifications.
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
Comply with Section 00224 of the Standard Specifications.
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
Comply with Section 00225 of the Standard Specifications modified as follows:
Install temporary flexible oiling pavement markers for temporary centerline marking as follows:
Place and maintain one temporary flexible oiling pavement marker on 40-foot spacing in tangent and curve sections except as below.
Place and maintain one temporary flexible oiling pavement marker on 20-foot spacing in curved alignment sections identified by a speed rider displaying less than the posted speed and channelization areas.
Establish alignment for placing the temporary flexible oiling pavement markers as follows:
Control markers at:
200-foot intervals on tangents 50-foot intervals on curves 40-foot intervals on curves with speed rider Use string line or other appropriate means to maintain proper alignment of the markers.
Adjust placement to avoid straddling a longitudinal joint, while maintaining a suitable alignment of markers.
Remove and replace misaligned markers at no additional cost to the Agency.
00225.90 Payment – Replace the paragraph that begins “Item (a)…” with the following paragraph:
Item (a) includes installation and removal of temporary pavement markers having either one or two reflective faces.
Replace the paragraph that begins “Item (b)…” with the following paragraph:
Item (b) includes installation of flexible temporary pavement markers and removal of flexible temporary pavement markers and temporary flexible pavement marker covers.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 13
Add the following paragraph after the paragraph that begins “Item (b)…”:
Items (c) and (e) include removal of the temporary tape.
SECTION 00235 - AGENCY PROVIDED MATERIAL SOURCES
Section 00235, which is not a Standard Specification, is included in this Project by Special Provision.
Description
00235.00 Scope - This Work consists of utilizing Agency provided prospective or mandatory material sources as the Contractor elects or as required for the construction of the Contract.
00235.01 Material Source Specific Requirements - The following prospective material source, for the production of all the aggregate products for this Project, that may warrant investigation and consideration for use by the Contractor on this Project is as follows:
(a) Prospective Material Source, Dry Creek Quarry:
• Source Number - OR-30-019-5
• DOGAMI Number - 30-0047
• Location - Approximately 5 miles northeast of Athena on OR11 in the E1/2 of
Section 35, T. 05 N., R. 35 E., W.M.
• Access - Adjacent east of MP 22.9 of OR11.
• Available Area for Equipment Setup, Stockpiling, and Processing Aggregate:
• Existing - 10 acres
• Development - 2 acres
If the Contractor elects not to utilize the above listed source(s) 00160.60 applies.
00235.03 Laws - Conduct operations within the material source according to all applicable State, county, and federal laws including mining and fire laws. Provide, operate, and maintain wildland firefighting equipment appropriate for the current fire levels on-site at all times during all material source operations.
00235.04 Permits - Copies of the Plans, permit, and the material source narrative for the material source are available for inspection at the Project Manager's office. Operations within the material source shall conform to the stipulations and conditions of these documents and to all of the requirements of the Contract.
Subsection Source Name Documents 00235.01(a) Dry Creek
Quarry Department of Geology and Mineral Industries (DOGAMI) Permit, County Land Use Permit
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 14
00235.05 Pre-Work Meeting - Before occupying the material source, attend a pre-work meeting at the material source with the Engineer and the following owners or representatives:
Subsection Source Name
Contact Names and phone numbers
00235.01(a
Dry Creek Quarry
ODOT Geologist: Scott Billings 541) 410-6693
00235.06 Source Occupancy - Coordinate material source occupancy with the Engineer.
The material source information listed in Table 00235-1 below shall be as shown. Do not operate beyond the material source Work area boundary as shown unless otherwise directed in writing.
Table 00235-1
Subsection Source Name Source items shown 00235.01(a) Dry Creek
Quarry Work area boundary, excavation area, reject fines stockpile, scalpings stockpile, oversize storage area, safety berm, bench access road, stockpile and processing area, access roads
00235.07 Source Development - If proposing changes to the material source development plan, submit a source development plan as an unstamped Working Drawing according to
00150.35. Do not begin Work in a material source until the source development plan has been approved in writing by the Engineer.
Develop a site-specific Erosion and Sediment Control Plan for the material source according to 00280.04 and submit it to the Engineer at or before the pre-work meeting. Construct stormwater control berm(s) as needed to control runoff. Do not allow any materials, including sediments, Aggregate or crushing by-products to enter into waterways or Wetlands.
Develop a site-specific Pollution Control Plan for each material source according to 00290.30(b), and submit it to the Engineer at or before the pre-work meeting. Include the following requirements in the Pollution Control Plan:
• Do not discharge waste or by-product if it contains any substance in concentrations that could contaminate Soils or result in harm to fish, wildlife, or water sources.
• Store bag-house sludge, lime, and all potentially hazardous materials and solid waste in a manner that prevents seepage into the ground or groundwater sources. Lined sumps or pits are allowable options for storage. If pits or sumps are used, construct adequate berms or provide other measures to prevent breaching of the pits or sumps.
• For materials capable of causing water pollution if discharged, locate storage facilities in an area that prevents spillage into waterways or Wetlands.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 15
Develop a site-specific Dust Control Plan and submit it to the Engineer 10 calendar days before the pre-work meeting. This area intermittently experiences high velocity winds that can transport dust and sand. Include the following details:
Measures that will be taken to prevent dust and sand from settling heavily in the riparian areas adjacent to the south drain ditch tributary to Dry Creek, and the OR 11 highway to the west.
Measures that will be taken to ensure the operation will meet Oregon DEQ air quality permit requirements outlined in the General Air Contaminant Discharge Permits for portable crushers and asphalt batch plants #AQGP-007 and #AQGP-008 and all other applicable laws and regulations.
Name and contact information for the Contractor’s on-site person responsible for ensuring processing, crushing and batching activities are in compliance with the permits and the Dust Control Plan.
Construction
00235.40 General - All vehicles and Equipment, prior to entering the site for the first time, and each subsequent time if the vehicle has left the Roadway outside the construction Project limits, shall be steam cleaned of all debris (soil, dirt, plant parts, and vegetative matter) before being brought back to the site. Notify the Engineer before moving each vehicle onto the site.
Certify, in writing, that the Equipment has been steam cleaned.
00235.41 Restrictions and Protection of Resources - Comply with the following for all operations within the material source:
• Protect cultural resources according to 00290.50.
• Protect migratory birds according to 00290.36(a).
• Do not utilize, contaminate, or disperse material from existing stockpiles. If existing stockpiles interfere with the Contractor’s operations, move the stockpiles to other locations within the material source area as directed, at no additional cost to the Agency.
• Limit mineral and Aggregate extraction, crushing, processing, and Equipment operation activities including drilling activities to one-half hour before sunrise to one-half hour after sunset, Monday through Saturday unless modifications to these hours are requested in writing and approved by the Engineer. Do not conduct any operation on Sundays or legal holidays, as defined in ORS 279C.540.
00235.42 Source Setup - Before proceeding with Work in the material source, the following apply:
(a) Access:
• Routine road maintenance activities such as grading and watering of the access roads do not need review or approval. Maintain or develop drain dips, water bars, road crowning, in-slopes and out-slopes during road maintenance.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 16
• If necessary, realign and regrade the bench access road as shown. Construct the road with a width of 12 feet and a reasonably uniform grade, no steeper than 50 percent (1V:2H), for access to the upper bench by tracked vehicles.
• Using overburden or existing, loose and non-stockpiled material or imported or clean soil or a combination of clean soil and rock, construct a safety berm along the top edge of the new excavation or existing slopes as shown. Maintain a 10-foot buffer between the top edge of the excavation or slope and the toe of the safety berm.
Construct the berm 3 feet high, with side slopes of 1V:2H.
(b) Overburden - Before excavating, including drilling and blasting when required, strip and stockpile all soil overburden from within the excavation area and from areas to be developed as new bench access road. Incorporate grass and small shrubs into the stockpiles. Do not remove grass or small shrubs from the overburden. Place stockpiles in the overburden storage area(s). Maintain a minimum 10-foot buffer strip between the toe of the overburden storage area(s) and the excavation area. Smooth and contour overburden storage berms to form side Slopes no steeper than 1V:2H.
00235.43 Blasting - Perform blasting operations according to this Section and Section 00335, except that perimeter controlled blasting as described in 00335.40(a) is not required in the material source.
Restrict blasting to the hours of 9:00 a.m. to 5:00 p.m. Monday through Friday. Do not blast on Saturdays, Sundays, or legal holidays as defined in ORS 279C.540.
00235.44 Source Operations - The following apply during material source operations:
• Construct slopes and floor of the excavation area as shown.
• To control dust, apply water to material source access, internal haul road(s), and crushing and processing operations.
• Stockpile scalpings and reject fines in separate and accessible stockpiles as shown.
• If the Contractor chooses to utilize this material source, maintain the condition of OR11 near the access roads at all times. Provide traffic control related to ingress and egress movements in a manner that allows a safe work zone and safe passage of vehicles.
• Maintain the gates into the source at all times.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 17
00235.45 Source Clean-up - The following apply at the completion of operations:
• Leave no loose material on the site exceeding 1 foot diameter, except as noted below.
Process existing oversize material, and all material loosened in the source by the Contractor that meets quality requirements, with the following exception:
• A maximum of 100 cubic yards of oversize material with a maximum dimension of 2.5 feet may be stockpiled in the material source. Consolidate oversize material as shown.
• Place all excess produced Aggregate remaining at the end of operations in separate and accessible stockpiles on Agency owned or controlled property in areas designated by the Engineer, at no additional cost to the Agency.
• Leave the material source bench access road open. Do not rip or block the road.
• Remove all loose, hanging or potentially dangerous Rock on or above the excavated surface.
• Pile and burn all construction slash and combustible debris resulting from use and development of the source, including the preexisting refuse identified at the pre-work meeting, even if it is from outside the material source project boundary except for grass and small shrubs that are incorporated into the overburden. Comply with all open burning regulations in effect at the time of source occupancy. If burning is not allowed, all construction slash and combustible debris become the property of the Contractor, to be treated as noncombustible and removed from material source.
00235.46 Seeding:
• In addition to other areas with soil cover within the site disturbed by the Contractor's operations, stabilize the overburden storage area, scalpings stockpile, and any stormwater control berms by seeding, mulching, and tackifying, as directed.
• Provide the following seed mixture:
• Broadcast Rate Common name / Scientific Name
1.5 PLS lb/ac indian ricegrass Achnatherum hymenoides
2.0 PLS lb/ac squirreltail Elymus elymoides
1.4 PLS lb/ac slender wheatgrass Elymus trachycaulus ssp. trachycaulus
1.7 PLS lb/ac Idaho fescue Festuca idahoenis
1.7 PLS lb/ac basin wildrye Leymus cinereus
1.1 PLS lb/ac Sandberg bluegrass Poa secunda
5.1 PLS lb/ac bluebunch wheatgrass Pseudoroegneria spicata ssp. spicata
• Provide straw mulch according to 01030.15(b).
• Apply a commercial straw mulch tackifier according to the manufacturer’s directions and at the recommended rate.
• Apply seed and mulch according to Section 01030.
• If conditions allow and the Contractor chooses, the area may be stabilized by applying seed using a range drill with a roller attachment. All areas seeded with the range drill and roller do not need to be subsequently covered with mulch and tackifier.
• All variations to these requirements require written approval by the Engineer.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 18
00235.47 Source Vacating - Before vacating the material source the following apply:
• Remove all structures, noncombustible debris, and equipment from the material source, even if it was pre-existing, except for grass and small shrubs incorporated into the overburden.
• Remove solid waste and hazardous material from the site and dispose of properly.
These include, but are not limited to, bag-house sludge or fines, lime, excess liquid asphalt, rejected and excess asphalt mixture, plant cleanings, materials placed in sumps, tires, pipes, belts, screens and truck cleanings. Provide documentary evidence of proper disposal and verify the amount of material removed.
• If a spill or dumping has occurred or if a spill or dumping is suspected to have occurred, the Contractor shall clean up the contaminated materials according to Section 00290.
After clean up, the Engineer may, sample and test materials at the spill or dumping locations to verify the clean up has been completed. If the Engineer’s verification testing demonstrates remaining contamination, the Contractor shall perform additional clean up until the requirements of Section 00290 including 00290.20(g) are met
• Attend a post-work meeting at the material source to evaluate material source rehabilitation work with the Engineer and attendees listed under 00235.05.
Measurement
00235.80 Measurement - No measurement of quantities will be made for Work performed under this Section.
Payment
00235.90 Payment - No separate or additional payment will be made for Work performed under this Section. Payment will be included in payment made for the appropriate items under which this Work is required.
SECTION 00237 - AGENCY-PROVIDED STAGING AREAS
Section 00237, which is not a Standard Specification, is included in this Project by Special
00237.00 Scope - This Work consists of utilizing Agency provided prospective or mandatory staging areas as the Contractor elects or as required for the construction of the Contract.
Locate staging area(s) in previously improved area(s) that have been paved or compacted and graveled, unless otherwise shown or approved.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 19
00237.01 Prospective Staging Areas - If the Contractor elects not to utilize the listed prospective staging area(s) or elects to use other or additional staging areas, 00290.10 applies.
(a) Prospective Staging Area, Wildhorse Creek Quarry:
• Source Number - OR-30-050-5
• Location - Highway OR335, MP 9.37, approximately 6.5 miles northeast of
Pendleton
• Access - From OR11, MP 6.19, travel north on OR335 to MP 9.37. Source is adjacent east through locked gate.
• Available Area - 1 acre
If used, restore the site to preconstruction condition, as directed, by:
• Removing all imported fabric, rock, and other construction and non-combustible debris
• Removing all solid waste and hazardous materials, including spills, and dispose properly
• Leveling the ground
(b) Prospective Staging Area, Weston Interchange:
• Location - Highway OR11, MP 20.39 (middle), approximately 1 mile north of Weston
• Access - For northbound access, take off-ramp at MP 20.44 and loop back around to the south for approximately 400 feet, entrance is on the west. For southbound access, take off-ramp at MP 20.48 and loop around west then south on OR204 (under OR11) for 0.23 miles, then turn east onto OR204 on-ramp and travel 700 feet to entrance on the west.
• Available Area - 1.5 acres
• Removing all solid waste and hazardous materials, including spills, and dispose properly
(c) Prospective Staging Area, Dry Creek Quarry:
• Source Number - OR-30-019-5
• Location - OR11, MP 22.9, approximately 5 miles northeast of Athena
• Access - Adjacent east of MP 22.9 of OR11
• Available Area - 3 acres, if not used as a Prospective material source.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 20
• Removing all solid waste and hazardous materials, including spills, and dispose properly
00237.05 Pre-Work Meeting - Before occupying a staging area, attend a pre-work meeting at the staging area with the Engineer and the following owners or representatives:
Subsection Source Name Contact Names and phone numbers 00237.01(a) Wildhorse Creek
Quarry ODOT Geologist: Scott Billings (541) 410-6693
00237.01(b) Weston Interchange
ODOT Geologist: Scott Billings (541) 410-6693
00237.01(c) Dry Creek Quarry ODOT Geologist: Scott Billings (541) 410-6693
00237.40 General - All vehicles and Equipment, prior to entering a site for the first time, and each subsequent time if the vehicle has left the Roadway outside the construction Project limits, shall be steam cleaned of all debris (soil, dirt, plant parts, and vegetative matter) before being brought back to the site. Notify the Engineer before moving each vehicle onto a site.
Certify, in writing, that the Equipment has been steam cleaned.
00237.41 Restrictions and Protection of Resources - Comply with the following for all operations within the staging area operations:
• Protect cultural resources according to 00290.50.
• Protect migratory birds according to 00290.36(a).
00237.44 Staging Area Operations - The following apply during staging area operations:
• Develop a site-specific Pollution Control Plan for the staging area(s) according to 00290.30(b), and submit it to the Engineer at or before the pre-work meeting. In addition to the requirements of 00290.30(b) include the following in the Pollution Control Plan:
• For materials capable of causing water pollution if discharged, locate storage facilities in an area that prevents spillage into waterways or Wetlands.
• Provide, operate, and maintain wildland firefighting equipment appropriate for the current fire levels on-site at all times during all staging operations.
• To control dust, apply water to staging area access road(s) and staging operations.
• For staging area Wildhorse Creek Quarry (00237.01(a)) and Dry Creek Quarry
(00237.01(c)), maintain the livestock gates into the site at all times.
00237.47 Staging Area Vacating - Before vacating the staging area(s) the following apply:
• Remove all structures, construction debris and trash, and equipment from the staging area, even if it was pre-existing.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 21
• Remove solid waste and hazardous material from the site and dispose of properly.
Provide documentary evidence of proper disposal and verify the amount of material removed.
• If a spill or dumping has occurred or if a spill or dumping is suspected to have occurred, the Contractor shall clean up the contaminated materials according to Section 00290.
After clean up, the Engineer may sample and test materials at the spill or dumping locations to verify the clean up has been completed. If the Engineer’s verification testing demonstrates remaining contamination, the Contractor shall perform additional clean up until the requirements of Section 00290 including 00290.20(g) are met.
• Attend a post-work meeting at each staging area to evaluate staging area rehabilitation work with the Engineer.
Measurement
00237.80 Measurement - No measurement of quantities will be made for Work performed under this Section.
Payment
00237.90 Payment - No separate or additional payment will be made for Work performed under this Section.
SECTION 00280 - EROSION AND SEDIMENT CONTROL
Comply with Section 00280 of the Standard Specifications modified as follows:
00280.00 Scope - Replace the paragraph that begins "This Work also consists of providing temporary …" with the following paragraph:
This Work also consists of providing temporary erosion and sediment control (ESC) measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing ESC throughout the Project area according to the Standard Drawings, the erosion and sediment control plan (ESCP), the Specifications, or as directed, until the site is permanently stabilized. Included also is the monitoring of weather, of stormwater and receiving waters, the reporting of monitoring observations, the reporting of corrective actions (when necessary) and the updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the NPDES 1200-CA, 1200-CN, OR 1200-C permit if applicable.
Delete the paragraph that begins “When contaminants, pollutants or hazardous materials…”.
Add the following paragraph to the end of this subsection:
The Agency's NPDES 1200-CA permit is not applicable to the Project. Before beginning Work on the Project, obtain a NPDES 1200-CA permit from the applicable local jurisdiction or a NPDES 1200-C permit that is applicable to the Project.
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 22
Add the following paragraph to the end of this subsection:
The Agency’s NPDES 1200-CA permit is not applicable to this Project. Comply with all applicable conditions of this Section.
00280.02 Definitions - Delete the definition Wet Season Work
00280.04 Erosion and Sediment Control Plan on Agency Controlled Lands - Replace the bullet that begins “Information required under 1200-CA…” with the following bullet:
• Information required under 1200-CA permit, if applicable.
00280.06 Erosion and Sediment Control Manager - Delete this subsection.
00280.16(k) Active Treatment System – Add the following sentence to the end of this subsection:
Obtain approval of the active treatment system from DEQ prior to use.
00280.41(c) Wet Season Work and Temporary Work Suspension - Replace this subsection with the following subsection:
00280.41(c) Temporary Work Interruption - Update the ESCP and schedule for Work proposed between October 1 and May 31 to ensure that all appropriate controls, including ESC during Work interruption, are implemented and maintained. Submit the updated ESCP and schedule to the Agency and receive approval before beginning any Work between October 1 and May 31.
Between October 1 and May 31, limit excavation and bare ground activities to only those required for immediate operations. Stabilize stockpiles at the end of each workday by diverting flows, placing covers, or installing Sediment barriers.
00280.41(f) Hauling Material – Replace this subsection, except for the subsection number and title, with the following:
Cover loads carrying soil or sediment which may generate dust. Haul saturated loads in water tight beds or drain saturated loads prior to leaving the Project Site.
00280.41(g) Underground Injection Controls (UIC) – Replace this subsection, except for the subsection number and title, with the following:
Do not allow storm water from work area to enter Underground Injection Control (UIC) inlets, UIC catch basins or UIC wells.
00280.62 Inspecting and Monitoring – Delete the paragraph that begins “Inspect the Project Site…”.
00280.62(a) Inspection - Replace the paragraph that begins "Perform site inspection, complete…" with the following paragraph:
SPS_M25003, OR11: MP 4 to Weston Intchge. Chip Seal Project, Contract, September 2025 23
Inspect the Project Site and all ESC devices for Effective Function and potential erosion or sediment movement and complete all applicable parts of the ODOT Erosion Control Monitoring Form, and submit the form to the Agency as follows:
00280.64(a) Corrective Action Timelines – Delete the bullet that begins “If completion of corrective action is not feasible…”
Delete the bullet that begins “Provide a schedule for clean-up and corrective actions…”
Delete the bullet that begins “Provide all corrective action documentation and photographs…”
00280.91 Payment – Replace the paragraph that begins “Emergency Materials that are incorporated…” with the following paragraph:
Materials listed in 00280.48 that are incorporated into the Project will be paid for under the appropriate items listed in the Contract Schedule of Items.
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications modified as follows:
00290.10 Staging and Disposal Sites – Replace the paragraph that begins “Locate staging areas…” with the following paragraph:
Locate staging areas and disposal sites in previously improved or disturbed sites, including existing Roadways, pullouts, turnouts, parking lots, and storage yards that have been compacted, and graveled or paved,…