Attachment 9 - PCRA.pdf
PDF 378 KB Posted
- Attached to
- Z2DA--Replace Dual Duct Boxes on Second Floor - 539-21-201 Federal contract opportunity
- Solicitation number
- 36C25026B0042
About this file
This is a template document for the VHA Pre-Construction Risk Assessment (PCRA), version 1.1 dated May 21, 2024, used by the Department of Veterans Affairs to evaluate safety risks associated with construction, renovation, and maintenance activities at VA facilities.
The PCRA template establishes a three-tiered activity classification system with corresponding control measures. Inspection/Upkeep activities are limited to single-shift work not exceeding 10 hours with no dust, vapor, or fume generation; they require weekly site visits, immediate restoration of ceiling tiles and access panels, and a site-specific safety plan. Small-Scale Construction activities extend beyond one shift but not exceeding six months and include selective demolition, plumbing installations, electrical work, HVAC modifications, and fire system alterations; these require hazard communication inventories, ILSM (Interim Life Safety Measures) assessments per The Joint Commission standards, hot work permits, LOTO (Lock Out Tag Out) procedures, daily contractor inspections, and trained staff. Large-Scale Construction exceeds six months duration and encompasses excavation, confined space entry, crane operations, elevated work, welding, major building demolition, installation of major building systems, and mechanical equipment installation; these require additional activity hazard analyses and control plans addressing excavation safety, dust control, pollution prevention, dig-safe verification, crane lift plans, fall protection, and confined entry procedures. The template mandates that all activities include communication and coordination plans with affected adjacent areas (vacant, non-continuously occupied, or continuously occupied), documented in Table 2 with identified points of contact. An Infection Control Risk Assessment (ICRA) must be evaluated separately for infection-related risks, and a fillable permit form must be posted at the project site identifying the unique permit number, project manager contact information, activity classification, applicable control measures, and required signatures from the Project Manager, Safety Officer, Infection Prevention and Control representative, and Construction Safety Committee Chair.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch RFI 6 life safety plan.pdf | ||
| Atch RFI 4 Lead Paint Report.pdf | ||
| Atch RFI 7 ACM SURVEY REPORT.pdf | ||
| 36C25026B0042 0002.docx | DOCX document | |
| 36C25026B0042_1.pdf | ||
| 36C25026B0042 0001.docx | DOCX document | |
| Attachment 4 - Drawings.pdf | ||
| Attachment 3 - Specs.pdf | ||
| Attachment 2 - VHA Directive 1192.01.pdf | ||
| Attachment 12 - Tridium Niagara Redacted.pdf | ||
| Attachment 8 - ICRA.pdf | ||
| Attachment 1 - OH20260082 01022026.pdf | ||
| Attachment 11 -Honeywell Siemens JCI Redacted.pdf | ||
| Attachment 10 - FX Controls Redacted.pdf | ||
| Attachment 6 - EMR Form.docx | DOCX document | |
| Attachment 5 - VAAR 852.219-75.docx | DOCX document | |
| Attachment 7 - Request for Information.docx | DOCX document | |
| 36C25026B0042_1.docx | DOCX document |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VHA Pre-Construction Risk Assessment (PCRA)
VHA-PCRA-2024-1.1 (May 21, 2024) Page 1 of 5
PCRA Introductory Information and Instructions
Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.
Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.
Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.
Facilities may customize this template to incorporate site-specific information and requirements.
NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.
PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.
Activity Location:
Activity Name, Number, and/or Brief Description:
Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.
Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).
As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.
Activity Type determined from Table 1:
Activity Type and Description Control Measures Inspection/upkeep generally defined as follows:
• Work can be completed in a single shift, not to exceed 10 hours.
• Patients, employees and/or visitors may be in the area depending on the activity.
• Work that does not create dust or debris.
• Work that does not create vapors or fumes.
• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
2. Site visits of construction area are required weekly by member of multi-disciplinary team.
Site visits will be documented on standard checklist.
3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the
VHA-PCRA-2024-1.1 (May 21, 2024) Page 2 of 5 exposure time (not to exceed an hour for each tile) within the shift.
• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.
• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.
shop involved must work with Safety to ensure proper precautions are in place.
4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.
5. Communication and coordination plan for all affected areas
Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:
• Prolonged work that may take longer than a single shift but not exceeding six months.
• Patients and employees are not to be in the area until activity is completed.
• Work that creates some noise and vibration due to power tool use.
• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.
o cause penetrations in fire or smoke barrier
• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:
o LOTO o The use of compressed gas cylinders
• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.
• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:
o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead
• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.
• Architectural, structural, or any other work that may cause vapors or fumes such as:
o Roofing work o Flooring work o Painting or other large-scale use of such substances.
All control measures in the row above and the following:
1. Hazard communication chemical inventory required to be provided by the contractor and approved.
2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly
3. Hot Work or burn permits in place and staff trained
4. LOTO procedures in place and staff trained on their use
5. Site visits will be reviewed using the criteria in standardized guide.
6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.
Large-scale construction, renovation, or maintenance generally defined as follows:
• Work exceeding 6 months in duration.
• Patients and employees are not to be in the area until activity is completed.
All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):
1. Excavation safety plan in place ☐
2. Dust control plan in place ☐
VHA-PCRA-2024-1.1 (May 21, 2024) Page 3 of 5
• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration
• Confined space entry required (permit required or not)
• Requires crane work o General crane work o Lift over buildings
• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control
• Welding, cutting or use of torches requiring burn permits
• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.
o cause breaches to fire or smoke barrier
• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators
• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:
o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.
• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.
• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors
• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.
3. Pollution prevention plan in place ☐
4. Dig safe paper work in place ☐
5. Crane lift plan in place ☐
a. Crane placement
b. Crane swing
c. Crane load evaluation
6. Fall protection plan in place and staff trained ☐
7. Confined entry plan in place and staff trained ☐
Table 2. Affected Adjacent Area Assessment In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:
• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):
o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.
VHACINHendek Oval
VHACINHendek Oval
VHACINHendek Highlight
VHA-PCRA-2024-1.1 (May 21, 2024) Page 4 of 5
• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):
o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).
• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):
o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).
Area Service(s)/Type(s) of Area(s)
(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*
Point of Contact
(POC)
POC Contact Information
Construction plan communicated to POC?
Activity Area**
Area Above
Area Below
Adjacent Area 1
Adjacent Area 2
Adjacent Area 3
Adjacent Area 4
* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.
** List the area(s) in which the construction/renovation/maintenance activity will occur.
Infection Control Risk Assessment (ICRA)
Consult with Infection Prevention and Control regarding the assessment of potential patient infection risks associated with the activity and the need for control measures. For example, activities such as a boiler plant project and/or facility steam shutdown, if properly planned, should have minimal to no patient infection risk impacts and likely not to require an ICRA. See VHA Directive 7715 and the VHA ICRA Template for more information.
Is an ICRA required for the Activity? Yes ☐ No ☐ x
Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area
Unique permit number:
Location and brief description of construction/renovation/maintenance Project manager Project start date Contact phone number Completion date Contractor or lead shop Permit expiration date
Activity Type Inspection/Upkeep, Small-scale, or Large-scale)
Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)
Inspection/Upkeep
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.
3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.
4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.
5. Communication and coordination plan for all affected areas
Small-scale
All control measures in the row above and the following:
1. Hazard communication chemical inventory required to be provided by the contractor and approved.
2. ILSMs in place and staff trained on situation
3. Hot Work or burn permits in place and staff trained
4. LOTO procedures in place and staff trained on their use
5. Site visits will be reviewed using the criteria in standardized guide.
6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.
Large-scale
All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):
1. Excavation safety plan in place ☐
2. Dust control plan in place ☐
3. Pollution prevention plan in place ☐
4. Dig safe paperwork in place ☐
5. Crane lift plan in place ☐
a. Crane placement
b. Crane swing
c. Crane load evaluation
6. Fall protection plan in place and staff trained ☐
7. Confined entry plan in place and staff trained ☐
*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.
VHA-PCRA-2024-1.1 (May 21, 2024)
Additional requirements:
Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☐ No ☐ Infection Prevention and Control signature:
Date:
Project Manager signature Date
Safety Officer signature Date
Chair, Construction Safety Committee signature
Date
VHACINAppleC Typewritten Text Actively Chief of Engineering, to be appointed ELT member.
VHACINAppleC Typewritten Text
COR
VHACINAppleC Typewritten Text Tom Elder
VHACINAppleC Typewritten Text Directive 7715 Part 3(a)(5)(a): "VHA-PCRA must be performed with input from a member of the VA medical facility Infection Prevention and Control staff and with the VA medical facility Water Safety Committee, as needed. See VHA Directive 1061(1), Prevention of Health Care-Associated Legionella Disease and Scald Injury from Water Systems, dated February 16, 2021"
VHACINAppleC Typewritten Text No guidance on how yes/no is determined, no likely only applies for truly outdoor work with no patient impact.
| PERMIT See the last page of this document for a fillable permit form to be used for posting at the activity site: 2nd Floor Radiology |
| andor Brief Description: Project 539-21-201, Replace Dual Duct Boxes on 2nd Floor, will replace the dual duct boxes on the second floor with fan coil units. |
| As the activity progresses a full reevaluation of remaining activity type and risk is required prior to changing: Large Scale |
| Excavation safety plan in place: Off |
| Dust control plan in place: Off |
| Dig safe paper work in place: Off |
| Crane lift plan in place: Off |
| Fall protection plan in place and staff trained: Off |
| undefined: Off |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcActivity Area: 2nd Flr Radiology |
| Point of Contact POCActivity Area: Abby Niswonger |
| POC Contact InformationActivity Area: Abby.Niswonger@va.gov |
| Construction plan communicated to POCActivity Area: Yes |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Above: OR Admin area |
| Point of Contact POCArea Above: Shelly Mann |
| POC Contact InformationArea Above: Shelley Mann@va.gov |
| Construction plan communicated to POCArea Above: Yes |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Below: Under construction- ED |
| Point of Contact POCArea Below: Diane Imhoff |
| POC Contact InformationArea Below: Diane.Imhoff@va.gov |
| Construction plan communicated to POCArea Below: Yes |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 1: Nuclear Medicine |
| Point of Contact POCAdjacent Area 1: Michael Grannen |
| POC Contact InformationAdjacent Area 1: Michael.Grannen@va.gov |
| Construction plan communicated to POCAdjacent Area 1: Yes |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 2: Imaging Tower |
| Point of Contact POCAdjacent Area 2: Abby Niswonger |
| POC Contact InformationAdjacent Area 2: Abby.Niswonger@va.gov |
| Construction plan communicated to POCAdjacent Area 2: Yes |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 3: MICU Lockers |
| Point of Contact POCAdjacent Area 3: Jeffrey Kuhn |
| POC Contact InformationAdjacent Area 3: Jeffrey.Kuhn@va.gov |
| Construction plan communicated to POCAdjacent Area 3: Yes |
| ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 4: Logistics Supply |
| Point of Contact POCAdjacent Area 4: Chris Ashcraft |
| POC Contact InformationAdjacent Area 4: Christopher.Ashcraft@va.gov |
| Construction plan communicated to POCAdjacent Area 4: Yes |
| Is an ICRA required for the Activity: Off |
| Activity Type InspectionUpkeep Smallscale or Largescale: Large Scale |
| 1 Excavation safety plan in place: Off |
| 2 Dust control plan in place: On |
| 3 Pollution prevention plan in place: Off |
| 4 Dig safe paperwork in place: Off |
| 5 Crane lift plan in place: Off |
| 6 Fall protection plan in place and staff trained: Off |
| 7 Confined entry plan in place and staff trained: Off |
| Additional requirements: ICRA has already been approved. |
| Is an Infection Control Risk Assessment ICRA required for the Activity: Yes_2 |
| Pollution prevention plan in place: Off |
| Unique permit number: 539-21-201 Replace Dual Duct Boxes on the Second Floor |
| Project manager: Kevin Henderson |
| Contact phone number: 513 487-6698 |
| Project Start Date_af_date: 06/02/2025 |
| Completion Date_af_date: 12/12/2028 |
| Permit Expiration Date_af_date: 12/12/2028 |
| Contractor or lead shop: TBD |
| Location and brief description of Construction/Renovation/Maintenance: This will replace dual duct boxes in Radiology. |
| Check Box6: Off |
| Check Box7: Off |
| Check Box8: Yes |
| Date10_af_date: |
| Project Manager Date Signed_af_date: |
| Safety Officer Date Signed_af_date: |
| CCS Date Signed_af_date: |
File details come from the government source that posted it. Updated .