This document is a ground floor plumbing plan for a temporary trailer at the Northport VA Medical Center, part of a project to renovate the Sterile Processing Department (Building No. 200). The plan details a comprehensive plumbing configuration for mobile water solutions, including utility and critical water connections, with specific requirements for water treatment and piping. Key specifications include:

The plumbing design involves a Mobile Water Solutions Unit with multiple water connections (2" and 1.5" cold water, 4" fire connection), a Reduced Pressure Zone (RPZ) backflow preventer, and connections to existing sanitary lines. The contractor must coordinate pipe sizing, provide piping insulation with aluminum jacketing and heat tracing, and ensure water treatment meets AAMI TIR34 standards. The plan notes that plumbing fixtures in the storage trailer will not be connected, and signage will indicate non-functional status. The project is in the 100% Construction Documents phase, with the most recent revision made on 09/03/2025, and is located in Northport, VA.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2" CW

2" CW (60 GPM) CONNECTION TO MOBILE

WATER SOLUTIONS UNIT. ALL CW & HW

PIPING BETWEEN TRAILERS WILL BE

PROVIDED BY THE CONTRACTOR.

TIE INTO EXISTING

SANITARY. SEE CIVIL

FOR CONTINUATION.

4" SAN

TIE INTO EXISTING

SANITARY. SEE CIVIL

FOR CONTINUATION.

MOBILE WATER SOLUTIONS UNIT

4" FCO

RPZ

F

E

D

C

1 1/2" CW

STORAGE

CO-49

EX RISER 16-25

EX 2" HW

EX 1/2" HWR

EX 2 1/2" CW

2" CW

1 1/2" CW

TEMP

SPS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10 www.abovegroupinc.com COA/CA Lic. No. 31120

FULLY SPRINKLERED305 East Dr., Suite H, Melbourne, Florida 32904

PH: 321.345.9026

VA Project No.

AG Project No.

A u to d e s k D o c s /0

N o rt h p o rt

S P

S /0

N o rt h p o rt

S P

S

R

M E

P F

P F

A T

.r v t

/3

/2

:4

:0

P M

P-100

GROUND FLOOR PLAN -

TEMPORARY TRAILER - PLUMBING

RENOVATE STERILE

PROCESSING DEPARTMENT,

BUILDING NO. 200

NORTHPORT VA

0123025

06/18/2025 ADL CNB

100% CONSTRUCTION

DOCUMENTS

632-12-106

CODED NOTES:

UTIILITY AND CRITICAL WATER FROM MWSU TO TEMPORARY TRAILER. COORDINATE PIPE SIZING WITH THE MANUFACTURER. PROVIDE PIPING INSULATION WITH ALUMINUM JACKETING AND HEAT TRACING

TAPE ON EXPOSED PIPING.

VENDOR WILL PROVIDE ALL REQUIRED WATER TREATMENT AND HEATING. THE BASIS OF DESIGN INCLUDES A SEPARATE TRAILER FOR WATER TREATMENT WITH A REVERSE OSMOSIS FILTER SYSTEM.

ENSURE WATER IS TREATED ACCORDING TO THE STANDARDS OF AAMI TIR34 FOR UTILITY AND CRITICAL WATER. REFER TO SPECIFICTION 01 52 13 FOR ADDITIONAL DETAILS. THE PLUMBING CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND COORDINATING PLUMBING UTILITY PIPING BETWEEN THE TRAILERS.

PROVIDE HOT BOX FOR FREEZE PROTECTION FOR RPZ.

PLUMBING FIXTURES IN THE STORAGE TRAILER WILL NOT BE CONNECTED. PROVIDE SIGNAGE ON

FIXTURES TO INDICATE THEY ARE NOT IN SERVICE.

1/8" = 1'-0"

1 GROUND FLOOR PLAN - TEMPORARY TRAILER - PLUMBING

N 0 4' 8' 16' 24'

1/8" = 1'-0"

N.T.S.

KEY PLAN TEMP SPS

DRAWING NOTES:

1. EXISTING PLUMBING SYSTEMS DRAWN ON PLAN ARE BASED ON LIMITED EXISTING DOCUMENTATION AND FIELD VERIFICATION. THE CONTRACTOR SHALL CONFIRM SIZE OF ALL EXISTING PIPING LOCATED WITHIN AND ADJACENT TO THE PROJECT SCOPE BOUNDARY PRIOR TO FABRICATION OF ANY NEW

DUCTWORK OR PIPING SHOWN ON PLAN. CONTRACTOR SHALL MAKE ENGINEER AWARE OF ANY

DEVIATIONS OF THE EXISTING DUCTWORK OR PIPING AS SHOWN ON PLAN.

2. CONCRETE AND CMU WALLS AND CONCRETE PADS/SLABS ON GRADE INSTALLED FOR

CONTINUATION OF MEDICAL CENTER OPERATIONAL REQUIREMENTS ARE TEMPORARY AND SHALL BE

REMOVED AND THE AREAS AFFECTED RESTORED TO PRIOR ORIGINAL CONDITIONS UPON

FUNCTIONAL COMPLETION OF THE NEW SPECIAL PROCESSES SERVICES SPACES AND/OR THE

APPROVAL OF THE PROJECT COR.

3. THE PLANS PROVIDED ARE INTENDED TO SHOW THE KEY ELEMENTS AND SCOPE OF WORK. THE

CONTRACTOR SHALL SUBMIT SITE SPECIFIC SHOP DRAWINGS FOR PLUMBING BASED ON THE

TRAILER RENTED.

Revisions Date

1 ADDENDUM 1 09/03/2025

Sheets
P-100 - GROUND FLOOR PLAN - TEMPORARY TRAILER - PLUMBING